S.R. 44 Corridor Management Plan
S.R. 44 Corridor Management Plan
Begin at
Samsula Dr
~7.4 miles
End at
Myrtle Ave
Project Overview
S.R. 44 Corridor Management Plan
• Study Limits – Samsula Drive to Myrtle Avenue
• Evolution of the Need for Planning Study
• Development Activity
• Proactive versus Reactive
• Avoid costly fragmented approach
• More effectively direct monies
S.R. 44 Corridor Management Plan
Study Focus Areas
S.R. 44 Corridor Management Plan
• Access Management Plan
• Operational Needs (Short and Long Term)
• Multi-Modal Evaluation
• Safety Assessment
S.R. 44 Corridor Management Plan
S.R. 44 Corridor Management Plan
Recommendations Overview
• Final Access Management Plan
• Near-Term Intersection Improvements
• Long-Term Intersection Improvements
• Multimodal Improvement Recommendations
• Potential Future Connections
S.R. 44 Corridor Management Plan
Recommendations Overview
• Final Access Management Plan
• Near-Term Intersection Improvements
• Long-Term Intersection Improvements
• Multimodal Improvement Recommendations
• Potential Future Connections
S.R. 44 Corridor Management Plan
Final Access Management Plan
• Maintain four-lane section throughout the length
of the study area
• Identify Potential Future Signal Locations
S.R. 44 Corridor Management Plan
Final Access Management Plan
• Median Modifications
• West corridor: new median cuts to be allowed to
provide access to planned development
• East corridor: modify or close existing median cuts to
better meet FDOT spacing standards, improving
safety and improve traffic flow on SR 44
• Timing / Process for Implementation
S.R. 44 Corridor Management Plan
S.R. 44 Corridor Management Plan
Ex: New median cut to provide access to planned development
Ex: Modify / close existing median cuts to better meet FDOT spacing
standards
S.R. 44 Corridor Management Plan
S.R. 44 Corridor Management Plan
Final Access Management Plan • Additional Consideration based on Public Feedback
• Corbin Park Road
• Commercial Access west and east of Eddie Road
• Chisholm Street
S.R. 44 Corridor Management Plan
Recommendations Overview
• Final Access Management Plan
• Near-Term Intersection Improvements
• Long-Term Intersection Improvements
• Multimodal Improvement Recommendations
• Potential Future Connections
Near-Term Intersection Improvements • New Signal Location(s)
• Sugar Mill Drive (Late 2013)
• Airport Road (Potential Future Signal)
• Signal Coordination: Shoppes at Coronado to Colony Park Rd
• To be completed by Volusia County (Late 2013)
• SR 44 at Mission Drive / Wallace Road
• Exclusive Eastbound Right-Turn Lane
• SR 44 at I-95 Interchange
• Southbound Ramp Improvements
S.R. 44 Corridor Management Plan
Near-Term Intersection Improvements • Right-Turn Lane at Mission Drive / Wallace Road
S.R. 44 Corridor Management Plan
S.R. 44 Corridor Management Plan
Recommendations Overview
• Final Access Management Plan
• Near-Term Intersection Improvements
• Long-Term Intersection Improvements
• Multimodal Improvement Recommendations
• Potential Future Connections
Long-Term Intersection Improvements
• Intersection Turn Lane Improvements
S.R. 44 Corridor Management Plan
Long-Term Intersection Improvements
• I-95 Interchange Loop Ramp Extension
S.R. 44 Corridor Management Plan
S.R. 44 Corridor Management Plan
Recommendations Overview
• Final Access Management Plan
• Near-Term Intersection Improvements
• Long-Term Intersection Improvements
• Multimodal Improvement Recommendations
• Potential Future Connections
Multimodal Improvements
S.R. 44 Corridor Management Plan
• Rural Section (West of Jungle Rd) – Bicycle Lane Markings Recently Completed
• Urban Section (East of Jungle Rd) – Options to Add Bicycle Lanes
• Median and Lane Width Adjustment to Add Bike Lanes within Existing Curb Line
• Conceptual, to be further evaluated in Design
• Multi-Use Paths – Currently Under Evaluation by City
S.R. 44 Corridor Management Plan
Recommendations Overview
• Final Access Management Plan
• Near-Term Intersection Improvements
• Long-Term Intersection Improvements
• Multimodal Improvement Recommendations
• Potential Future Connections
Potential Future Connections • Paige Avenue Extension
• Williamson Boulevard Extension Options
• Cross-Access Connections
S.R. 44 Corridor Management Plan
• Add picture
Cross-Access
Project Information
S.R. 44 Corridor Management Plan
S.R. 44 Corridor Management Plan
• FDOT Project Manager - Judy Pizzo, GISP
• Kittelson & Associates Project Manager - Justin Bansen, P.E.
• Project Website:
http://cfgis.org/FDOT-Resources/SR-44-Corridor-
Management-Plan.aspx