southern cove orrington remediation site orrington, … · sediment chemical characterization ......
TRANSCRIPT
Mallinckrodt US LLC
June 8, 2016
CORRECTIVE MEASURES IMPLEMENTATION PLAN
Southern CoveOrrington Remediation Site
Orrington, Maine
Prepared by:
Anchor QEA, LLC
9 Water Street, First Floor
Amesbury, MA 01913
CDM Smith, Inc.
25 Industrial Avenue
Chelmsford, MA 01824
i
Table of Contents
Section1. Introduction....................................................................................................................................1‐1
Purpose........................................................................................................................................................................1‐1
SiteDescription........................................................................................................................................................1‐1
ReportOrganization..............................................................................................................................................1‐1
Section2. SummaryofSouthernCovePre‐designActivities...............................................................2‐1
Background................................................................................................................................................................2‐1
Pre‐designActivitiesOverview........................................................................................................................2‐1
BathymetricSurvey...............................................................................................................................................2‐1
HydrodynamicStudy.............................................................................................................................................2‐2
GeotechnicalInvestigation.................................................................................................................................2‐2
DisposalCharacterization...................................................................................................................................2‐3
TreatabilityTesting................................................................................................................................................2‐4
SedimentChemicalCharacterization.............................................................................................................2‐4
IntertidalVegetationSurvey..............................................................................................................................2‐4
Section3. DesignObjectives...........................................................................................................................3‐1
CorrectiveMeasuresImplementationPlanObjectives..........................................................................3‐1
MediaProtectionStandards...............................................................................................................................3‐1
CompliancewiththeOrderMediaProtectionStandards.....................................................................3‐1
SouthernSedimentRemovalArea(SMA‐3..................................................................................................3‐3
SoutherlyStreamSedimentRemovalArea(SMA‐1)...............................................................................3‐5
NorthernSedimentRemovalArea(SMA‐2)................................................................................................3‐6
NorthernSedimentRemovalArea(SMA‐2)–NorthernPortion........................................3‐6 NorthernSedimentRemovalArea(SMA‐2)–SouthernPortion........................................3‐7 NorthernSedimentRemovalArea(SMA‐2)–WesternEdge...............................................3‐7
DefinitionofPreliminarySedimentRemovalAreas...............................................................................3‐7
Section4. SouthernCoveCorrectiveMeasuresImplementationActivities....................................4‐1
OverviewoftheRemedialAction....................................................................................................................4‐1
ExistingConditionsandSitePreparation....................................................................................................4‐1
SiteTrailers/Offices................................................................................................................................4‐1 SiteStaging..................................................................................................................................................4‐1 SedimentProcessingandStockpilingAreas................................................................................4‐1 AccessRoads..............................................................................................................................................4‐2 TemporaryErosionandSedimentControl...................................................................................4‐2
SedimentRemovalandProcessingActivities............................................................................................4‐2
Excavation...................................................................................................................................................4‐2 Dredging.......................................................................................................................................................4‐3 DredgedMaterialProcessing..............................................................................................................4‐3
Table of Contents Corrective Measures Implementation Plan
ii
EnvironmentalControls.......................................................................................................................................4‐4
WaterQualityandFishMonitoring.................................................................................................4‐4 WaterTreatment......................................................................................................................................4‐4
RestorationActivities............................................................................................................................................4‐5
Backfilling....................................................................................................................................................4‐5 PlantingandSeeding..............................................................................................................................4‐5
Section5. Permitting........................................................................................................................................5‐1
Section6. Schedule............................................................................................................................................6‐1
Section7. References........................................................................................................................................7‐1
List of Tables
Table2‐1:FlowVelocitySummary–MaximumsMeasuredNeartheSouthernCoveOvera12‐hourTidalCycleonAugust3,2016.....................................................................................2‐2
Table6‐1:ProposedSouthernCoveSchedule..............................................................................................6‐1
List of Figures
Figure1‐1:SiteMap
Figure1‐2:SedimentSampleLocations
Figure2‐1:SedimentRemovalAreasandDepths
Figure2‐2:ExtentofIntertidalVegetation
Appendices
AppendixA:Pre‐designActivitiesReport
AttachmentA.1:BathymetricReport
AttachmentA.2:AcousticDopplerCurrentProfilerReport
AttachmentA.3:BoringLogs
AttachmentA.4:GeotechnicalData
AttachmentA.5:TreatabilityReport
AttachmentA.6:MercuryDataReport
AttachmentA.7:DataUsabilityAssessment
AppendixB:TurbidityControlEvaluationReportAppendixC:DelineationofSedimentRemovalAreasforBasisofRemedialDesignTechnicalMemorandum
Table of Contents Corrective Measures Implementation Plan
iii
AppendixD:WaterQualityandFishMonitoringPlanAppendixE:DrawingsAppendixF:TechnicalSpecificationsAppendixG:ConstructionQualityAssurancePlanAppendixH:RemediationContractorHealthandSafetyPlan(placeholder,tobeprovidedbycontractor)AppendixI:Schedule(placeholder,tobeprovidedbycontractor)
iv
Acronyms
ADCP AcousticDopplerCurrentProfilerbgs belowgroundsurface
CEO CodeEnforcementOfficerCMI CorrectiveMeasuresImplementationCMS CorrectiveMeasuresStudyCQA ConstructionQualityControlCU CertificationUnitCWA CleanWaterActcy cubicyardDelineationTechnical ProposedDelineationofSedimentRemovalAreasforBasisMemorandum ofRemedialDesignEPA U.S.EnvironmentalProtectionAgency
ft/s footpersecondMaineBEP StateofMaineBoardofEnvironmentalProtectionMallinckrodt MallinckrodtUSLLCMaineDEP MaineDepartmentofEnvironmentalProtectionMEPDES MainePollutantDischargeEliminationSystem
mg/kg milligramsperkilogram
MPS MediaProtectionStandardNTU nephelometricturbidityunit
Order MaineBEPOrderdatedAugust19,2010,andeffectiveApril3,2014,whichincorporates,withmodifications,theComplianceOrderissuedbyMaineDEPdatedNovember24,2008
PERC PenobscotEnergyRecoveryCompany
RCRA ResourceConservationandRecoveryAct
RPM RemediationProjectManagerSI SiteInvestigationSIReport SiteInvestigationReportSMA SedimentManagementAreaTCLP ToxicityCharacteristicLeachingProcedureTESC temporaryerosionandsedimentcontrolTSS totalsuspendedsolids
TSSA‐2 TemporarySoilStockpileArea#2
1‐1
Section 1. Introduction
Purpose This Southern Cove Corrective Measures Implementation Plan (CMI Plan) was prepared byAnchorQEA,LLC,andCDMSmith,Inc.,onbehalfofMallinckrodtUSLLC(Mallinckrodt).Thepurposeofthis CMI Plan is to present the corrective measures necessary to remediate sediment within theSouthern Cove of the Penobscot River adjacent to the Orrington Remediation Site located at99IndustrialWay,Orrington,Maine,showninFigure1‐1.TheCMIPlanpresentstheobjectivesofthecorrectivemeasures,resultsofthepre‐designactivities,designdrawings,andtechnicalspecificationstoimplementtheremedialaction.
PlansandengineeringdesignsfortheSouthernCoveremediationweredevelopedinaccordancewiththeStateofMaineBoardofEnvironmentalProtection(MaineBEP)OrderdatedAugust19,2010,andeffectiveApril3, 2014,which incorporates,withmodifications, theComplianceOrder issuedby theMaineDepartmentofEnvironmentalProtection(MaineDEP)datedNovember24,2008(collectivelyreferredhereafterasthe“Order”).TheOrderrequirescorrectivemeasurestoachieveMediaProtectionStandards(MPSs)formercuryinsediment.
Site Description The Southern Cove is located in the Penobscot River bordering the Orrington Remediation Site, asshowninFigure1‐1.Afulldescriptionofthesite,whichincludedaformermanufacturingplantandfive landfills, is included in the Site InvestigationReport (SI Report; CDM 1998) and theCorrectiveMeasuresStudy(CDM2003).TheSouthernCoveliestothesouthofthehistoricalmanufacturingplantarea,ontheeasternsideofthemainchannelofthePenobscotRiver.ThePenobscotRiverissubjecttotidal fluctuations up to 16 feet, and a portion of the cove is tidalmudflats exposed under low tideconditions.
TwooutfallsandtwodrainagesthatcurrentlydischargetotheSouthernCoveareshowninFigure1‐2.Oneof the twooutfalls is thepermittedeffluentpipe fromtheon‐sitegroundwater treatmentplant(GWTP),whichrunsbeneaththebeachatthenorthernsideofthecoveanddischargesintotheriver.Theotheroutfall isthecoolingwaterdischargepipefromthePenobscotEnergyRecoveryCompany(PERC)facility;thepipeisburiedbeneaththebeachandrunsoffshorenearthecentralportionoftheSouthernCove.The twodrainages that flow into the cove are theNorthernDrainageDitch and theSoutherlyStream.
Report Organization Thereportisorganizedasfollows:
Section1:Introduction
Section2:SummaryoftheSouthernCovePre‐designActivities
Section3:DesignObjectives
Section4:SouthernCoveCorrectiveMeasuresImplementationActivities
Section5:Permitting
Section6:Schedule
Section7:References
Thefollowingtechnicalappendices(AthroughI)arealsoincludedandreferencedinthesesections:
Section 1 Introduction
1‐2
AppendixA:Pre‐designActivitiesReport
AttachmentA.1:BathymetricReport
AttachmentA.2:AcousticDopplerCurrentProfilerReport
AttachmentA.3:BoringLogs
AttachmentA.4:GeotechnicalData
AttachmentA.5:TreatabilityReport
AttachmentA.6:MercuryDataReport
AttachmentA.7:DataUsabilityAssessment
AppendixB:TurbidityControlEvaluationReport
AppendixC:DelineationofSedimentRemovalAreasforBasisofRemedialDesignTechnicalMemorandum
AppendixD:WaterQualityandFishMonitoringPlan
AppendixE:Drawings
AppendixF:TechnicalSpecifications
AppendixG:ConstructionQualityAssurancePlan
AppendixH:RemediationContractorHealthandSafetyPlan(placeholder,tobeprovidedbycontractor)
AppendixI:Schedule(placeholder,tobeprovidedbycontractor)
2‐1
Section 2. Summary of Southern Cove Pre‐design Activities
Background The Orrington Remediation Site, including the Southern Cove, was investigated during the SiteInvestigation(SI;CDM1998)andCMS(CDM2003).Atotalof250sedimentsampleswerecollectedfrom the SouthernCove and analyzed formercury,with some samples also analyzed for additionalphysicalparameters.ThemajorityofthesesampleswerecollectedandreportedaspartoftheSIReportandCMS,whichwerereviewedbyMaineDEPandtheMaineBEPandformedthebasisoftheirfinaldecisionsontheremedialactionsrequiredfortheSouthernCoveintheOrder.
AdditionaldatawerecollectedfromtheSouthernCoveduringthepre‐designfieldactivitiesconductedin2015and2016.Afullreportofthepre‐designmethodsandresultsisincludedinAppendixA.Resultsarealsobrieflysummarizedinthefollowingsubsections.
Pre‐design Activities Overview Pre‐design field work was completed in accordance with the Maine DEP‐approved Southern CovePre‐design Work Plan (AnchorQEA and CDM 2015). Subsequent work plan modifications wererequestedduringthefieldactivitiesandapprovedbyMaineDEP, includinge‐mails fromMaineDEPdatedMay21,2015regardingdrillingequipmentandoceanographicsurveytimeintervals,andJune12, 2015 regarding sampling sediment for chloropicrin. In addition, a work plan addendum wasapprovedbye‐mailfromMaineDEPonSeptember4,2015.
Fieldworkwascompletedduringlatespringandfall2015.WorkwascompletedinaccordancewiththeQualityAssuranceProjectPlan (CDM Smith 2014a), theProjectHealth and SafetyPlan (CDM Smith2014b), and theHealthandSafetyPlan (AnchorQEA2014) prepared specifically for remedial datacollectionactivitiesintheSouthernCove.
Field data collection and laboratory analyses conducted as part of the pre‐design field activitiesincluded:
Bathymetricsurvey
Hydrodynamicstudy(includingAcousticDopplerCurrentProfiler[ADCP]surveyandtidegaging)
Geotechnicalinvestigations
Disposalcharacterization
Treatabilitytesting
Sedimentchemicalcharacterization
Intertidalvegetationsurvey
Areportofpre‐designworkisincludedinAppendixAandsummariesareprovidedinsubsequentsections.
Bathymetric Survey AbathymetricsurveyoftheSouthernCoveuptothemaximumhightidelinewasconductedin2015andisdepictedinthePre‐designActivitiesReport(AppendixA;Figure2‐1).
Section 2 Summary of Southern Cove Pre‐design Activities
2‐2
Hydrodynamic Study Ahydrodynamicstudywasconductedtoevaluatetherangeofexpectedtidalfluctuationandcurrentvelocities,and toprovidedata forhydrodynamicanalyses tosupport thedesignof turbiditycontrolmeasures.AtemporarytidalgagewasinstalledintheSouthernCovetomeasurewaterlevelsovertidalcyclesbetweenJune15and20,2015.Tidalfluctuationswereapproximately15feet.
WaterflowvelocitiesacrossthePenobscotRiverchanneladjacenttotheSouthernCoveweremeasuredduring an ADCP survey in June 2015. Flow velocities measured at the surface and the average ofvelocitiesmeasuredat0.25‐footdepth intervals throughthewatercolumnwereevaluated.Velocitydatawere collectedhourly over the studyperiod.Table2‐1 lists themaximumsurface anddepth‐averagedvelocitiesfortheupstream,middle,anddownstreamlocationsduringthefloodandebbtidesmeasuredinthevicinityoftheSouthernCovesedimentremovalareas.
Table 2‐1: Flow Velocity Summary – Maximums Measured Near the Southern Cove Over a 12‐hour Tidal Cycle on August 3, 2016
ADCP Transect
Flood Tide Ebb Tide
Surface Velocity (ft/s)
Depth‐averaged Velocity (ft/s)
Surface Velocity (ft/s)
Depth‐averaged Velocity (ft/s)
Upstream Transect 3.5 2.6 3.2 2.7 Middle Transect 2.9 2.3 3.5 2.8
Downstream Transect 2.8 2.1 3.2 3.1
Note: ft/s = feet per second
Basedonreviewofcollectedfielddataandpublishedtidalandcurrentdata,ahydrodynamicevaluation,includingmodelingoffloodandebbconditionsandflowrates,wascompletedandresultsareincludedinAppendixB.The resultswereused to evaluate loadings from flows in the riveronpotential siltcurtain designs/orientations. Based on this analysis, a mobile turbidity curtain system is beingrecommended rather than larger, stationery silt curtains, which may not be stable in high flowconditions.
Geotechnical Investigation Geotechnicaldatawerecollectedtosupportengineeringdesignwiththefollowingobjectives.SamplelocationsareshowninFigure1‐2.
Collectstandardpenetrationtestdatatoevaluatethedepthtocompetentstrataandtodeterminethetypeanddesignoffootingsifrequiredforasiltcurtain
Sampledatawerecollectedoutsidethesedimentremovalareas,nearoratthebreakbetweentheSouthernCoveandtheedgeofthePenobscotRiverChannelatSD‐SC‐01,‐02,and‐03
CollectstandardpenetrationtestandgrainsizedatatosupportdesignofanequipmentaccessroadacrosstheintertidalareaoftheSouthernCove,ifneeded
SampledatawerecollectedwithintheintertidalareaatlocationsSD‐SC‐04,‐05,and‐06
Characterizephysicalpropertiesofsedimenttoberemovedandstratigraphytosupportengineeringforthesedimentremovaldesign
Section 2 Summary of Southern Cove Pre‐design Activities
2‐3
Datawerecollectedfromalllocationssampledduringthepre‐designinvestigation
Subsurface sampling conditions were difficult, with frequent refusals encountered. Both vibracore(4‐inchdiameter)andsplit‐spoon(2‐or3‐inchdiameter)sampling techniqueswereemployed,andbothsampling techniquesmetwithrefusalbetween1and2 feetatmanyof thesampling locations.DetailsonthetechniquesusedatspecificsamplinglocationsareavailableintheboringlogsincludedinthePre‐designActivitiesReportinAppendixA.
Overall,basedonfieldobservationsandgeotechnicalanalyses,materialwithinthesedimentremovalareasisgenerallycharacterizedaswellgraded,rangingfromcobblestoclay,withmediumtocoarsesand as the dominant grain sizes. Sediment is finest in the southern sections of the cove where adiscontinuoussoftsiltlayeroccurswithinthetop1to2feetbelowthemudline.Thissurfacesiltlayerisgenerallyabsenttowardthenorth(SD‐SC‐07)andtowardthePenobscotRiverChannel(SD‐SC‐01and‐02).
Generally, deposits coarsen with depth. The extent of cobbles and coarse gravel in the materialthroughoutthecoveisunclearbecausebothvibracoreandsplit‐spoonsubsurfacesamplingequipmentencounteredrefusalatseverallocations,whichwasmostlikelyoncobbles,althoughsamplescouldnotbecollected.Thus,thegeotechnicalsampleresultsmaynotreflectsomeofthecoarsermaterial(coarsegravelandcobbles)insomeareas.
Althoughrefusalwasmetatseverallocations,bedrockwasnotconfirmedinanyoftheexplorationsintheSouthernCove,norisitexpectedtobepresentintheremovalareas.Bedrockmapsdevelopedforthe upland portion of the site during the SI (CDM2003) indicate a phyllite bedrockwith elevationvaryingsteeply.ThebedrocksurfaceappearstooutcropwheretheSoutherlyStreamdischargestotheSouthern Cove, but maps indicate it may be 90 feet below ground surface along the beach at thenorthernendoftheSouthernCove.
Disposal Characterization Sedimentfromwithinthehorizontalandverticalextentsofthesedimentremovalareaswassampledfordisposal characterization.Methods and results aredetailed in thePre‐designActivitiesReport inAppendixA,andanoverviewofthestudiesisprovidedbelow.
MercuryintheSouthernCoveisassumedtobeprimarilyfromhistoricalwastewaterdischargesfromthe plant. Based on chemical data, the sediment is not a characteristic waste as defined by theU.S.EnvironmentalProtectionAgency(EPA)ResourceConservationandRecoveryAct(RCRA)ToxicityCharacteristicLeachingProcedure(TCLP)methods.Disposalcharacterizationconsistedofanalysesfora suite of chemical and physical characteristics typically required bywaste disposal facilities. Fourcomposite samples (SD‐SC‐07 through ‐10)were collected fromwithin theextentof each sedimentremovalareatocharacterizematerialforhandlinganddisposalrequirements.SamplinglocationsareshowninFigure1‐2.SampleswereanalyzedusingEPATCLPmethodsforvolatileorganiccompounds,semivolatile organic compounds,metals, pesticides, and select herbicides (i.e., 2,4,5‐TP and 2,4‐D).Sampleswerealsoanalyzedforasuiteofadditionalchemicalandphysicalcharacteristicsthatcouldberequired by disposal facilities. The results were either non‐detect or below the disposal facility
Section 2 Summary of Southern Cove Pre‐design Activities
2‐4
requirements; thus, the material is not characteristically hazardous in accordance with RCRArequirementsandcanbecharacterizedassolid,non‐hazardous,waste.
Treatability Testing Sediment samples collected fordisposal characterizationwere also subject to treatability testing todeterminefeasiblepost‐removaldewateringmethodsfortheproject.DetailsofthestudyareincludedinAttachmentA.5tothePre‐designActivitiesReportinAppendixA.
The treatability testing evaluated the rate that sediments would dewater, the need for addingamendmentstoachievelowmoisturerequirements(i.e.,theabilitytopassthe“paintfilter”test),andthechemicalcompositionofthedewateringelutriateincomparisontotheon‐siteGWTPrequirements.Ingeneral,thematerialdrainedwell,andtheadditionofseveraltypesofamendmentswassuccessfulinachievingthelowmoisturerequirementsfortransportanddisposal.Dewateringelutriategenerallymetrequirements tobeacceptedbytheon‐siteGWTP,althoughsomefilteringmaybenecessarytoreducetheleveloftotalsuspendedsolids(TSS)priortodeliverytotheon‐siteGWTP.
Sediment Chemical Characterization Inadditiontosedimentsamplescollectedfortreatabilitytestinganddisposalcharacterization,sampleswerecollectedduringPDactivitiestocompletedelineationofmercury insediments,andtosupportdelineationofremovalareasthatwillmeetMPSrequirementsoutlinedintheOrder.Afulldescriptionof samples collected, objectives and results in presented in the Pre‐design Activities Report(AppendixA) and Proposed Delineation of Sediment Removal Areas for Basis of Remedial Design(DelineationTechnicalMemorandum;AppendixC).ResultsarealsodiscussedinSection4.
Intertidal Vegetation Survey Theextentofwetlandcommunitieswithintheprojectareaweredelineatedduringa fieldsurvey inMay2015.Atthetimeofthesurvey,theplantswithinthewetlandhadnotreachedfullgrowthfortheseasonbuthadgrownenoughfortheextentandspeciespresenttobeidentified.
Threeseparatewetlandcommunitieswereidentifiedcovering2.1acres,asshowninFigure2‐2.Thethreecommunitieswerecomposedofthefollowing:
Ahighmarshcommunityofbeakedspikerushgrowingneartheshorelineonathickbaseofpeat(0.15acre)
Multiple,sparsebedsofcommonthree‐squaregrowinginsoft,unconsolidatedmud(1.9acres)
Asmallbedofdenselygrowinghardstembulrushembeddedwithinthesparsecommonthree‐square,whichappearedtobegrowingpartlyonasmallchunkofpeatmataswellassoftmud(0.03acre)
OnlyoneofthespeciesidentifiedislistedasaMainerare,threatened,orendangeredplant.BeakedspikerushisidentifiedasthreatenedinMaine,asofSeptember2015,andwasidentifiedinthehighmarshcommunityattheOrringtonRemediationSite(MENaturalAreasProgram2015).
3‐1
Section 3. Design Objectives
Corrective Measures Implementation Plan Objectives TheprimaryobjectivesoftheremedyfortheSouthernCovearetoremovesedimentsthatareabovetheMPSasrequiredintheOrder,andtorestoremudlineelevationsandvegetationtopre‐remediationconditions.
Media Protection Standards TheMPSs identified in the Order require that sediment be removedwheremercury levels exceed2.2milligramsperkilogram,averagedovera0.25‐acrearea.Irrespectiveofconcentrations,sedimentwithinthetwohotspotareasidentifiedforthreeseparatedepthintervalsmustalsoberemoved.ThehotspotsaredefinedintheOrderbyboththemapandalistofsamplelocationsincludedasa“narrativeMPS”thatmustbeencompassedinthesedimentremovalareas.
Compliance with the Order Media Protection Standards TheOrder‐definedsedimentremovalareasandtheproposedsedimentremovalareasaredepictedinFigure2‐1andDrawingC‐4. The proposed sediment removal areas include the areas and depthsrequiredbytheOrder.ThebasisoftheproposedsedimentremovalareasandcompliancewiththeMPSisfurtherdescribedinthefollowingsubsections.
MallinckrodtsubmittedadraftDelineationTechnicalMemorandum(AppendixC)onOctober29,2015.Followingthatsubmittal,MallinckrodtpresentedanoverviewofthetechnicalmemorandumtoMaineDEPonFebruary18,2016,andreceivedcommentsfromMaineDEPbye‐mailonFebruary26,2016.MallinckrodtpresentedresponsestoMaineDEPcommentsduringawebinaronMarch15,2016.Basedon feedback received fromMaineDEP in itswritten comments, and comments received during theMarch15webinar,MallinckrodtsubmittedresponsestoMaineDEPcommentsandafinalDelineationTechnicalMemorandumtoMaineDEPonMarch25,2016,whichisincludedasAppendixC.Thereaderis directed to figures in the Delineation TechnicalMemorandum (AppendixC) that showmercuryconcentrations at various depths within the Southern Cove and are referenced in the followingparagraphs.
Inane‐mailtoMallinckrodtdatedApril4,2016,MaineDEPconcurredwiththeareastoberemovedwiththefollowingprovisions:
1. Theresultsfromtheadditionalsamplesshownbelowwillbereviewedtodetermineiftheyincreasethescopeoftheremovalarea.
Section 3 Design Objectives
3‐2
NorthernSedimentRemovalArea(SMA‐2) SouthernSedimentRemovalArea(SMA‐3)ProposedAdditionalRemovalAreaDelineationSamples
2. TheremovaldepthofthenorthernportionofNorthernSedimentRemovalArea(SMA‐2)willneedtobedeterminedinthefieldduringremovaloperations(seeSection7.3.1oftheDelineationTechnicalMemorandum[AppendixC]).
MallinckrodtconductedthisadditionalsamplinginMay2016,andsubsequentlyidentifiedtheneedforadditionalsamplecollectiontocompletedelineation.Tokeeptheprojectconstructiononschedule,thisdraftCMIPlanissubmittedbasedonpreliminarysedimentremovalareas,withtheunderstandingthatthefinalsedimentremovalareaswillbeadjustedbasedonnewsampledatatobegeneratedinJune2016.
Basedonrecentsamplingandreviewofhistoricaldata,threeproposedsedimentremovalareas/prismshavebeenidentifiedtomeettherequirementsintheOrder.ThehorizontalandverticalextentsoftheproposedremovalprismsareshownonAppendixCFigure9,alongwiththeremovalareasanddepthintervalsrequiredbytheMPSintheOrder.OnesectionoftheremovalareaidentifiedintheOrderwasexcludedfromtheproposedsedimentremovalareasbasedondatacollectedsincetheOrderwasissued,as described in Section 5.3.2. The Order included a vegetated wetland hummock east of SMA‐3(SouthernSedimentRemovalArea)wherenosampledatawereavailablefromtheSIandCMS.Samplescollected aspart of thepre‐design investigation fromSD‐SC‐22 (0 to0.2 and0.8 to1 foot) showedmercurylevelsbelow2.2milligramsperkilogram(mg/kg)atthislocation(seeimagebelow);therefore,itwasexcludedfromtheproposedsedimentremovalareas.
Section 3 Design Objectives
3‐3
SMA‐3 (Southern Sediment Removal Area) (0.8 to 1 foot) – Mercury MPS Compliance at SD‐SC‐22
The rationale for delineation of the horizontal and vertical extents of the three proposed sedimentremovalareasisexplainedinthefollowingsections.
Southern Sediment Removal Area (SMA‐3) ThehorizontalextentoftheproposedSouthernSedimentRemovalArea(SMA‐3)includesallsamplelocationsintheareaexceeding2.2mg/kginanysampleddepthintervals,asdepictedonAppendixCFigure7.Oneexceptionoutsidetheremovalareaisaconcentrationof2.6mg/kgmercurydetectedatSD‐10‐C1from0to0.2foot(seeimagebelow).However,withconsiderationofsamplesfromthesamedepthintervalwithina0.25‐acreareathatincludesSD‐10‐C1,theaveragemercuryconcentrationofthe0.25‐acrearea is2.1mg/kg,which is less than theMPS (seeAppendixCFigure2).Therefore, thissamplelocationisnotincludedintheproposedSouthernSedimentRemovalArea(SMA‐3).
Section 3 Design Objectives
3‐4
SouthernSedimentRemovalArea(SMA‐3)(0to0.2foot)–MercuryMPSCompliancewithin0.25acreatSD‐10‐C1
Forverticaldelineation inSouthernSedimentRemovalArea(SMA‐3),datadepictedonAppendixCFigures2and3showmercuryconcentrationsexceedingtheMPSinthetop1footofsediment.Alldatafromsedimentsamplescollectedbelow1‐footdepthshowmercuryconcentrationsbelow2.2mg/kg(Appendix C Figures 4, 5, and 6) with the exception of sample SD‐10‐B4, which had 5.7mg/kgmercuryat1.5‐ to2‐footdepth(AppendixCFigure5).However,adjacentsampleshad less than1mg/kgmercuryatthesamedepthintervalforanaverageconcentrationof1.6mg/kgovera0.25‐acreareawithinthe1.5‐to2‐footdepthinterval.Basedontheseresults,theproposeddepthforSouthernSedimentRemovalArea(SMA‐3)dredgeprismis1foot.
Based on comments received from Maine DEP on the draft Delineation Technical Memorandum(AppendixC),Mallinckrodtcollectedthe followingsamples inMay2016,andwillcollectadditionalsamplesinJune2016tocompletedelineation:
NorthandEastofRSD‐15AandRSD‐15B:Threeadditionalsampleswillbecollectedtocompletedelineation—onenorthofSouthernSedimentRemovalArea(SMA‐3)andtwototheeast,asshownintheimagebelow.Sampleswillbecollectedfrom0‐to0.2‐footand0.8‐to1‐footdepthintervals.
Section 3 Design Objectives
3‐5
Delineation at RSD‐15A and RSD‐15B – Southern Sediment Removal Area (SMA‐3)
Southerly Stream Sediment Removal Area (SMA‐1) The horizontal extent of the proposed Southerly Stream Sediment Removal Area (SMA‐1) wasestablishedbasedonmercuryconcentrationsgreaterthan2.2mg/kgandapplyingthenarrativeMPSofanaveragemercuryconcentrationoflessthan2.2mg/kgovera0.25‐acreareatosamplelocationsoutside the proposed removal area, as shown on Appendix C Figures 2 and 3. The averageconcentrationwascalculatedbasedonsamplesfromsimilardepthintervals.Theproposeddepthofthisremovalareais0.8foot(AppendixCFigure9)basedonconcentrationsmeetingtheMPSinsamplesfromthe0.8‐to1‐footdepthinterval.
SoutherlyStreamSedimentRemovalArea(SMA‐1)(0.8to1foot)–MercuryMPSCompliance
Section 3 Design Objectives
3‐6
Northern Sediment Removal Area (SMA‐2) ThehorizontalextentofNorthernSedimentRemovalArea(SMA‐2)iswelldefinedbysampledataandencompassesalldatapointsthatexceed2.2mg/kginthisvicinity.Thisremovalareahasbeendividedintothreesubsectionsbasedondifferencesinthedepthofmercurycontamination,asdiscussedinthefollowingsectionsandshownonAppendixCFigure9.
Northern Sediment Removal Area (SMA‐2) – Northern Portion
The highest and deepest mercury concentrations are found in the northern portion of NorthernSedimentRemovalArea (SMA‐2),which is close toaMainePollutantDischargeEliminationSystem(MEPDES)discharge.Theelevatedconcentrationsofmercuryarelocalizedanddecreaserapidlyinthehorizontaldirectionout fromRSC‐024, the locationwiththehighestconcentration,especially to thewestwithincreasingwaterdepthtowardthemainriverchannel.Theproposedremovaldepthis3feetintheareaofhighestmercuryconcentrations,correspondingtothedeepestmeasuredinterval,withmercurygreaterthan2.2mg/kg(sampleSD‐SC‐07from30to36inches).However,becausethepre‐design investigation sampling equipment could not penetrate to deeper depths, it is unclear if thecontaminationextendsdeeperthan3feetinthisarea.AdditionalsamplingwillbecompletedinJune2016toestablishthedredgedepthinthisarea.
Based on comments received from Maine DEP on the draft Delineation Technical Memorandum(AppendixC),MallinckrodtcollectedthefollowingsamplesinMay2016,andallresultswerelessthan2.2mg/kgmercury (thedatawillbepresentedalongwith theadditional June2016sampledata tofinalizethesedimentremovalareas):
NorthandEastofRSC‐11G:SedimentsamplesfromtwoadditionallocationseastofSMA‐2(NorthernSedimentRemovalArea)asshownintheimagebelow.Fromeachlocation,sampleswillbecollectedfromtwodepthintervalsbetweensurfaceand2feet.
Section 3 Design Objectives
3‐7
RSD‐11G – Northern Sediment Removal Area (SMA‐2)
Northern Sediment Removal Area (SMA‐2) – Southern Portion
MercuryconcentrationsinthesouthernportionofSMA‐2(NorthernSedimentRemovalArea)arelowerthantothenorth,butstillexceedtheMPSinthetop2feet.Thedeepersample(SD‐SC‐08)indicatesamuchlowermercuryconcentrationof0.06mg/kgat3feetdepth. Therefore, theproposedremovaldepthinthisareais3feetbasedonsampleresults.
Northern Sediment Removal Area (SMA‐2) – Western Edge
Mercury concentrations show a rapid decrease in concentration and contaminant depth along thewesternedgeofNorthernSedimentRemovalArea(SMA‐2)andtowardthemainriverchannelwherewaterdepths increase.Thus, theremovaldepthofthewesternedgeofNorthernSedimentRemovalArea(SMA‐2)isproposedat1foottomeettheMPS.
Definition of Preliminary Sediment Removal Areas Basedonpre‐designsamplingandreviewofhistoricaldatadescribedherein,threesedimentremovalareashavebeenidentifiedandaredescribedintheDelineationTechnicalMemorandum(AppendixC).TheseareasareshownonFigure2‐1andDrawingC‐4,alongwiththeremovalareasanddepthintervalsrequiredbytheMPSdefinedintheOrder.Asdescribedabove,additionalsampleswerecollectedinMay2016atMaineDEP’srequest.Basedonthosesampleresultsandtheinabilityofequipmenttopenetrate
Section 3 Design Objectives
3‐8
torequireddepths,MallinckrodtwillcollectadditionalsamplestocompletedelineationinJune2016.FinalsedimentremovalareaswillbepresentedinthenextversionoftheCMIPlan.
4‐1
Section 4. Southern Cove Corrective Measures Implementation Activities
Overview of the Remedial Action The Southern Cove remedial action will involve removal of sediment to comply with the MPS, asdescribed in previous sections, and restoration of the removal areas to pre‐construction elevation.DetailsofthecorrectiveactionimplementationareprovidedinthedesigndrawingsinAppendixE,theTechnicalSpecificationsinAppendixF,andthefollowingsections,whichareorganizedasfollows:
Section4.2–ExistingConditionsandSitePreparation
Section4.3–SedimentRemovalandProcessingActivities
Section4.4–EnvironmentalControls
Section4.5–RestorationActivities
TheConstructionQualityAssurancePlanispresentedinAppendixG.
Existing Conditions and Site Preparation Prior to beginning sediment removal activities, support areas for staff and equipment, access tosediment removal areas, and sedimentmanagementand stockpilingwill be established.Temporaryerosion and sediment control measures will also be established. Each of these requirements aredescribedinthefollowingsubsections.
Site Trailers/Offices
Trailers forMallinckrodt, theRemediationProjectManager(RPM), theConstructionQualityControl(CQA)Engineer,andMaineDEP;anon‐sitelaboratory;andrestroomfacilitieswereestablishedduringprevious site work phases. The Remediation Contractor will be responsible for providing its owntrailerstobeinstalledintheRemediationContractorOfficeTrailerComplexshowninDrawingG‐7.
Site Staging
Asmallstagingarea(labeledasNearshoreSupportAreainDrawingG‐4)willbeestablishedaspartofthe Northern Drainage Ditch CMI Plan (submitted to the Maine DEP on February 5, 2016). TheRemediationContractorwillusethisareatooffloaddredged/excavatedsedimentsfortransporttotheSediment Management Area (SMA), and to load clean materials for backfilling. The RemediationContractorwillberesponsibleformaintainingtheconditionofthestagingareapadinaccordancewithDrawingC‐9andtheTechnicalSpecifications(AppendixF,Section015000).
Sediment Processing and Stockpiling Areas
SedimentwillbestockpiledanddewateredattheRemediationSupportArea,whichhasbeenpreviouslyestablishedandisoperatedfortheentireOrringtonRemediationSite(bothsoilandsediment)bytheRPM (see location inDrawingG‐4).Dredgedandexcavated sedimentwill be transported from theNearshore Support Area to the Remediation Support Area in sealed containers or trucks. Prior totransferringthesedimentonshore,theRemediationContractorwillremoveanyaccumulatedoverlyingwater(seeSection4.3.2).Sedimentwillbedewateredbymixingadditives(e.g.,cementorotherdrysitesoils) directly into the sediment on a processing pad as shown in Drawing G‐3. Any necessaryenhancements to theprocessingpadwillbedeterminedafter theRemediationContractorhasbeen
Section 4 Southern Cove Corrective Measures Implementation Activities
4‐2
selected;however,ataminimum,thepadwillmeettherequirementsshowninDrawingC‐3.Stockpilesof dewatered sediment will be managed in accordance with Drawing C‐3 and the TechnicalSpecifications(AppendixF,Section015719).
Clean stockpile areas for import backfill have been previously established andwill bemanaged tominimizedust.
Access Roads
TheaccessroadbetweentheNearshoreSupportAreaandtheexistingRemediationSupportArea(seeDrawingG‐4)willbeestablishedaspartoftheNorthernDrainageDitchCMIPlan.Materialtransferredalongthisaccessroadwillbecontainedwithinsealedcontainersortrucks;therefore,housekeepingoftheroadisexpectedtobeminimal.Thisroadwillremaininplaceafterconstructioniscomplete.
ToaccessSoutherlyStreamSedimentRemovalArea(SMA‐1),theRemediationContractorwillneedtoestablish access along the shoreline. The exact method of access will be determined after theRemediationContractorhasbeenretained;however,itisexpectedthattheRemediationContractorwilluseexistingtideflatssupplementedbymarshorcranemats,wherenecessary,thatareresilienttothehightideandminimizedisturbanceof thearea. Ifcontaminatedmaterialsaretransferredalongthisaccessroad,theywillbecontainedwithinsealedandcoveredcontainers;therefore,housekeepingoftheroadisexpectedtobeminimal.TheRemediationContractormayelecttobuildadditionalaccessroadsusingsimilarmethodsthroughtheSouthernCovetoaccessthesedimentremovalareas.Alloftheseroadswillberemoved,andthearearestored,afterconstructioniscomplete.
Temporary Erosion and Sediment Control
It isnotexpectedthatactivities immediatelyadjacenttotheSouthernCovewillsignificantlydisturbuplandsoilsandrequiretemporaryerosionandsedimentcontrols(TESCs)perMaineDEPStormwaterConstructionGeneralPermitconditions.However,asshowninDrawingC‐1,siltfenceswillbeinstalledbetweentheNearshoreStagingAreaandtheriverasaprecautiontocontainanyaccidentalspillsduringsediment transfer. Existing TESCs around the Remediation Support Area will be maintained andsupplemented, as necessary, in accordance with the Technical Specifications (Appendix F,Section015719).
Sediment Removal and Processing Activities Thissectiondescribes theremovalof sediment fromthe threesedimentmanagementareas (SMAs)shown inDrawingC‐4, the controls that will be used tominimizewater quality impacts, and theanticipatedprocessesnecessarytopreparetheremovedsedimentforoff‐sitetransportanddisposal.ThenatureandextentofsedimentcontaminationandtherationalefortheremovaldepthsforeachSMAarediscussedinSections2.8and3.3.
Excavation
The existing bathymetry surrounding Southerly Stream Sediment Removal Area (SMA‐1) is veryshallowandwaterlevelsathightidelimittraditionalfloatingdredgingequipmentaccess.Therefore,itis expected that the Remediation Contractor will remove the sediment within Southerly StreamSedimentRemovalArea(SMA‐1)usingtraditionalland‐basedexcavationequipmentduringlowtide.Theapproximatevolumeofsedimenttargetedforremovalfromthisareais230cubicyards(cy),andexcavationswilllikelyoccuroverseveraltidalcycles.
TheareaofworkthatcanbecompletedwithinatidalcyclewillbedesignatedasaCertificationUnit(CU).Tominimizethepotentialforrecontaminationbetweentidalcycles,eachCUwillbeimmediatelybackfilledafterverificationthatthedesignremovaltargets, intermsofdepthandextent,havebeenachievedandverifiedbytheCQAEngineer.CUverificationwillbebasedontraditionalsurveymethods
Section 4 Southern Cove Corrective Measures Implementation Activities
4‐3
toverifythattherequiredremovaldepthhasbeenachievedthroughouttheexcavation.TheTechnicalSpecifications (Appendix F, Sections022100 and 352023) include minimum requirements forsurveyaccuracyandperformance.
Dredging
SedimentremovalwithinNorthernSedimentRemovalArea(SMA‐2)andSouthernSedimentRemovalArea(SMA‐3)willoccurpredominatelyusingtraditionalmechanicaldredgingequipment.TherequiredremovalareasanddepthsareshowninDrawingC‐4andthesequenceofworkwillgenerallyoccurfromupstreamtodownstream.Theapproximatevolumeofsedimenttargetedforremovalfromtheseareasis4,390and2,000cy,respectively.TheTechnicalSpecifications(AppendixF,Sections022100and352023)includedetailedrequirementsforpositioningcontroltoensurethattheRemediationContractor removes the sediment with the most practicably achievable precision. The TechnicalSpecificationsalsoincludebestmanagementpracticesthatmustbefollowedtominimizethepotentialtogenerateexcessiveturbidityduringdredgingandrecontaminationofpreviouslydredgedareas.
DredgingwilloccurwithinamobileturbiditycurtainsystemasshowninDrawingC‐2.EachpositionofthesystemwilldefineadredgingCU.PriortomovingthesystemtothenextCU,theRemediationContractorwillsurveythedredgedareainaccordancewiththeTechnicalSpecifications(AppendixF,Section352023)andtheCQAEngineerwillverifythattherequiredremovaldepthhasbeenachieved.Onceapproved,theRemediationContractorwillplaceaninitialbackfilllayerandthenmoveontothenextCU.The intent of the initial backfill layer is to stabilize any thin veneerof disturbed sedimentremainingonthepost‐dredgesurfacetominimizethepotentialforsubsequentwaterqualityimpacts.
TheRemediation Contractorwill place the dredged sediment either into a storage barge (scow) ortransport containers located on a flat‐deck barge. Overlyingwater that accumulates in the scoworcontainers will be filtered in accordance with the Technical Specifications (AppendixF,Section015719) before discharge to the river. The overlying water must be removed prior toinitiating transfer of the sediment onto land tominimize the potential for sloshing or spills duringtransferandtransport.SedimentwillfirstbetransferredonlandattheNearshoreSupportAreaandthentransportedviatheaccessroadtoTSSA‐2forprocessing.
TheeasternportionofNorthernSedimentRemovalArea(SMA‐2)containstwoindustrialoutfallsthatrequirespecialconsiderationduringdredgingandexcavation.Theareasimmediatelyadjacenttotheindustrial outfalls will be dredged using careful procedures, and potentially special dredgingequipment,topreventdamagetotheoutfall.Theseareaswillbedredgedinsmall‐areaintervalsandimmediatelybackfilledwithcleanbackfilltopreventunderminingoftheoutfalls.
ThenorthernportionofNorthernSedimentRemovalArea(SMA‐2)containsanareaofhardsubgradeinthevicinityofstandardpenetrationtest(SPT)boringlocationSD‐SC‐07.DuringtheSPT,extremelyhardmaterialwasencounteredat3.3feetbelowgroundsurface(bgs)andanN‐valueof177wasreported.TheRemediationContractorwillattempttodredgetheCUsurroundingSD‐SC‐07toadepthof3.5feetbgs(i.e.,toadepthdeeperthantherefusalintervalencounteredduringtheSPT)asshowninDrawingC‐4.Ifrefusaloccurspriortoreaching3.5feetbgs,dredginginthisCUwillbeconsideredcomplete.DepthverificationandinitialbackfilllayerplacementwillproceedconsistentwithotherCUs.
Dredged Material Processing
Priortofinaloff‐sitetransporttothedisposalfacility,thedredgedmaterialwillrequiredewateringandverificationusingthepaintfiltertest.BasedontheresultsoftheTreatabilityStudy(AttachmentA.5ofthePre‐designActivitiesReportinAppendixA),blendingthesedimentswithotherexcavatedon‐sitesoils(inaccordancewiththeSoilUsePlanapprovedbyMaineDEP)isexpectedtobesufficienttoreducethemoisturecontentofthedredgedsedimentstolevelsacceptablefortransportanddisposal.Inthe
Section 4 Southern Cove Corrective Measures Implementation Activities
4‐4
event that on‐site material is not available at the time of dewatering, another economical, well‐performingagentfromtheTreatabilityStudywillbeused.
Environmental Controls Monitoring of the environment will occur throughout the construction period. The RemediationContractorwillprepareanenvironmentalpollutionprotectionplanthatwillincludegeneralcontrolsregardingspillprevention,dustandodors,noise,light,TESCs,fuelstorage,equipmentdecontamination,wastemanagement,andotherenvironmentalconsiderations.TheRPMwillberesponsibleforairandwater quality monitoring and fish observations in accordance with permit requirements. ThismonitoringisdescribedinthePerimeterAirMonitoringPlan(CDMSmith2015)andtheWaterQualityandFishMonitoringPlan(AppendixD).
Asdiscussedintheprevioussection,dredgingwilloccurwithinamobileturbiditycurtainsystemasshown inDrawingC‐2.AppendixBdescribes the site conditions and engineering evaluations thatwereusedtoselectamobilesysteminlieuoftheuseofastationaryturbiditybarrierenclosingtheentireSouthernCoveworkareas.TheRemediationContractorwillberesponsibleforthefinaldesign,operation,andmaintenanceofthesystem.
Duringtransferofsedimentonshore,theRemediationContractorwillestablishtemporarycontrolsasshowninDrawingC‐9tocontainanypotentialspillsthatmayoccurduringtransferandtransporttoTSSA‐2.
Water Quality and Fish Monitoring
WaterqualityandfishmonitoringrequirementswillbefinalizedbasedonthepermitsissuedbytheU.S.ArmyCorpsofEngineers.Mallinckrodt’sproposedapproachisdescribedintheWaterQualityandFishMonitoringPlan(AppendixD).
Waterqualitywillbemonitoredduringallin‐waterworkeitherbyhandfromasmallutilityboat,orusingtwoanchoredbuoys.MonitoringpointswillbelocatedinthePenobscotRivernorthandsouthofthe Southern Cove. The upstream and downstream location will be determined based on tidalconditionsandflowdirection.Thewaterqualitymonitoringcriteriathatwilltriggercorrectiveactionsare35nephelometricturbidityunits(NTUs)higheratthedownstreambuoycomparedtotheupstreammeasurement.
Priortocommencingsedimentremovalwithamobileturbiditycurtainsystem,thecontaineddredgeareawillbecheckedforthepresenceofAtlanticsalmonorAtlanticorshortnosedsturgeon,whicharelistedspeciesundertheEndangeredSpeciesAct.Ifthesespeciesareidentified,thefishwillbeclearedfromtheareapriortocommencingdredging.
Water Treatment
Watergeneratedduringsedimentdewateringwillbesentthroughtheon‐siteGWTPanddischargedunderthecurrentMEPDESpermit(#ME0000639).Storagetanksonsitemaybeusedfortemporarystorageasneeded.Waterwillbe tested toverify that itmeets influent requirements for theon‐siteGWTP.
TheSouthernCoveCMIhasbeendesignedtominimizethevolumeofwaterdirectedthroughtheon‐siteGWTP.OverlyingwaterfromsedimentwillbedecantedonthebargeanddischargedtotheriveratthepointofdredgingpriortotransporttoTSSA‐2.Itisanticipatedthatpre‐filteringofthedecantedwaterprior to discharge into the rivermay be required tomeetwater quality standards required in theproject’sCleanWaterAct(CWA)Section401WaterQualityCertification.
The sediment dewateringmethodwill include a stabilization process that generates limited excesswater.Anydewateringeffluentgeneratedduringdewateringactivitieswillbetransferredtotheon‐site
Section 4 Southern Cove Corrective Measures Implementation Activities
4‐5
GWTPforprocessingpriortodischargeinaccordancewithMEPDESpermitlimits.Asacontingency,existingstoragetanksmaybeusedtotemporarilystoredewateringeffluentsothatGWTPcapacityisnotexceeded.Dewateringeffluentwillbetestedtodetermineifitmeetsinfluentcriteriaoftheon‐siteGWTP.BasedonresultsoftheTreatabilityStudy,itispossiblethatthewaterwillexceedTSScriteriaandrequirepre‐treatmentpriortobeingdeliveredtotheGWTP.
Restoration Activities
Backfilling
Eachareaexcavatedordredgedwillbebackfilledtopre‐constructiongrades.Thebackfillmaterialwillconsistofimportedcleangravelysand,similarinsizedistributiontomaterialscurrentlyfoundwithintheSouthernCove.
As stated inSection4.3.1,backfillingofSoutherlyStreamSedimentRemovalArea (SMA‐1)CUswilloccurduringthesametidalcycleinwhichdredgingoccurs.InNorthernSedimentRemovalArea(SMA‐2)andSouthernSedimentRemovalArea(SMA‐3),eachverifiedCUwillbebackfilledwithan initialbackfillliftpriortorepositioningthemobileturbiditycurtainsystemtoanadjacentCU,asdiscussedinSection4.3.2.AfterallCUsaredredged,theremainingbackfillmaterialwillbeplacedtoreturntheareasto pre‐construction grades. The placement of the final layer of backfill will generally occur fromupstreamtodownstreamlocations.Post‐constructionsurveyswillbeusedtoconfirmthattheareashavebeenreturnedtopre‐constructiongradeswithinacceptabletolerances.
The preliminary limits of areas requiring revegetation are shown inDrawingC‐10. In addition togravely sandbackfill, these areaswill receive a 6‐inch layer of habitat‐amendedbackfill to supportsubsequentplantingandseeding.
Planting and Seeding
TheplantingandseedingplanshowninDrawingC‐10willbefinalizedbasedonobservationsmadeduringdredgingactivities.TheRPMwillverifytheextentsandtypesofwetlandvegetationimpactedbyconstructionoperations.
Depending on the completion date of backfilling activities, planting and seeding activities may bedelayeduntil thefollowingspringonce ice isthawedandtemperaturessupportplantestablishmentandseedgermination.
5‐1
Section 5. Permitting
ThefollowingpermitsareneededfortheSouthernCoveCMIactivities:
ShorelandProtectionActPermit.ApermitapplicationwassubmittedonApril5,2016,totheOrringtonCodeEnforcementOfficerforworkwithin250feetfromthePenobscotRiverfortheentireOrringtonRemediationSite.WithrespecttotheSouthernCoveCMI,thispermitcoversconstructionandmaintenanceofstagingareasandaccessroadsnecessarytoperformsedimentremoval.
MaineIndividualPermit.TheMaineIndividualPermitincludestheCWASection401WaterQualityCertification,CWASection404,andSection10oftheRiversandHarborsActof1899.The following required consultation is also completed by theU.S. ArmyCorps of Engineersbeforegrantingthepermit:
Section106oftheNationalHistoricPreservationActandwithlocalTribes
Section7consultationswithNationalOceanicandAtmosphericAdministration,NationalMarineFisheriesService,andU.S.FishandWildlifeServiceforEndangeredSpeciesActandEssentialFishHabitat
MaineNaturalResourcesProtectionAct.Permit‐by‐rulewasgrantedbytheMaineDEPfortheentireOrringtonRemediationSite,includingtheSouthernCove.
FollowinginitialreviewoftheCMIPlanbyMaineDEP,MallinckrodtwillsubmittheMaineIndividualPermitapplication,whichshouldoccurinfall2016.ThissubmissionwillincludethedraftCMIPlan(revisedtoaddressMaineDEP’sinitialcomments)andthedraftRemediationContractorWorkPlans.
6‐1
Section 6. Schedule
TheanticipatedschedulefortheSouthernCoveispresentedinTable6‐1.ThisscheduleiscontingentonMaineDEPapproval.
Table 6‐1: Proposed Southern Cove Schedule
Activity Anticipated Start Date
Anticipated End Date
Submit Southern Cove CMI Plan to Maine DEP -- June 8, 2016 Maine DEP Preliminary Review of CMI Plan June 8, 2016 August 12, 2016
Meet with Maine DEP -- June 15, 2016 Revise CMI Plan with Remediation Contractor
Work Plans and Submittals July 11, 2016 November 16, 2016
Meet with Maine DEP -- January/February 2017 Finalize CMI Plan January 23, 2017 March 14, 2017
Final Maine DEP Approval -- April 25, 2017 Remediation Contractor Mobilization -- Mid-June 2017
7‐1
Section 7. References
AnchorQEA,LLC,2014.HealthandSafetyPlan.SouthernCove,OrringtonRemediationSite.PreparedforCDMSmith,Inc.December2014.
Anchor QEA, LLC, and CDM Smith, Inc., 2015. Southern Cove Pre‐design Work Plan. OrringtonRemediationSite,Orrington,Maine.PreparedforMallinckrodtUSLLC.June2015.
CDM(CampDresser&McKeeInc.),1998.SiteInvestigationReportVolumeI.HoltraChemManufacturingSite,Orrington,Maine.December22,1998;RevisedAugust15,2001.
CDM,2003.CorrectiveMeasuresStudy.Mallinckrodt Inc.,HoltraChemManufacturingSite,Orrington,Maine.May27,2003;RevisedSeptember19,2003.
CDM Smith, 2014a. Quality Assurance Project Plan. Orrington Remediation Site, Orrington, Maine.RevisionNo.01.December15,2014.
CDM Smith, 2014b. Project Health and Safety Plan. Orrington Remediation Site, Orrington, Maine.October9,2014.
CDMSmith,2015.PerimeterAirMonitoringPlan(PAMP),OrringtonRemediationSite,Orrington,Maine.June25,2015.
MaineBEP(MaineBoardofEnvironmentalProtection),2010.AppealofDesignationofUncontrolledHazardousSubstanceSiteandOrder,FindingsofFactandOrderonAppealintheMatterofUnitedStatesSurgicalCorporationandMallinckrodtLLCConcerningaChlor‐alkaliManufacturingFacilityin Orrington, Penobscot County, Maine Proceeding Under 38 M.R.S.A. § 1365, UncontrolledHazardousSubstanceSitesLaw;August19,effectivedateApril3,2014.
MaineDEP(MaineDepartmentofEnvironmentalProtection),2008.ComplianceOrder:DesignationofUncontrolled Hazardous Substance Site and Order in the Matter of United States SurgicalCorporation, Mallinckrodt LLC Concerning a Chloralkali Manufacturing Facility in Orrington,PenobscotCounty,MaineFormerlyOwnedandOperatedbyMallinckrodtInc.,ProceedingUnder38M.R.S.A.§1365,UncontrolledHazardousSubstanceSitesLaw;November24.
MaineNaturalAreasProgram,2015.DepartmentofAgriculture,ConservationandForestry.ElementsofDiversityRare,ThreatenedandEndangeredPlants.September2015.
FIGURES
SMA 1
SMA 2
SMA 3
Southern Cove
PlantArea
Norther
n Drai
nage
DitchSo
utherl
y Stre
am
Landfill1
Landfill2
Landfill3
Landfill4
Landfill5Landfill
Ridge Area
Figure 1-1Site Map
Corrective Measures Implementation PlanSouthern Cove, Orrington Remediation Site
0 200 400Feet
Q:\
Job
s\H
oltr
aC
he
m_
00
00
\Ma
ps
\CM
I_P
lan
\Vic
inity
_M
ap
.mxd
n
ko
chie
4
/20
/20
16
1
2:5
7:4
3 P
M
[
ProjectLocation
T(
T(
T(
T(
T(
T(
"J
"J"J"J
"J
"J
"J"J"J
"J
"J"J"J"J
"J
"J"J"J
"J"J"J
"J"J"J
"J"J"J"J
"J
"J
"J
"J
"J
"J
"J"J"J
"J
"J"J
"J
"J
"J
!R
!R
!R
!R
"J
"J
"J
"J
"J
"J
"J
!R
!R
!R
!R
!R
"J
"J"J"J
"J"J"J
"J"J
"J"J"J
"J"J"J
"J
"J
"J
"J
"J
"J
"J
"J
"J"J"J"J"J
"J
"J
"J"J"J
"J
"J
"J"J
"J
"J
"J
"J
"J
"J
"J
"J
"J
"J
#I
#I
#I
#I
#I
#I#I
#I#I#I#I#I#I
#I#I
#I#I#I#I#I#I
$1$1
$1$1
$1$1
$1$1
$1$1$1$1
$1
$1$1
$1
$1
$1
$1$1
$1
$1 $1
#*
"J
Northern Drainage Ditch
Southerly Stream
RSC-001
RSC-002
RSC-003
RSC-004
RSC-005
RSC-006
RSC-007
RSC-008
RSC-009
RSC-010RSC-011
RSC-012
RSC-013
RSC-014
RSC-015
RSC-016
RSC-017
RSC-018
RSC-019
RSC-020
RSC-021
RSC-022RSC-023
RSC-024
RSC-025
RSC-026
RSD-04A
RSD-04B
RSD-04C
RSD-05A
RSD-05B
RSD-05C
RSD-06A
RSD-06B
RSD-06C
RSD-06E
RSD-07A
RSD-07B
RSD-07C
RSD-07D
RSD-07E
RSD-08A
RSD-08B
RSD-09A
RSD-09B
RSD-10A
RSD-10B
RSD-10C
RSD-11A
RSD-11B
RSD-11C
RSD-11D
RSD-11E
RSD-11F
RSD-11G
RSD-11H
RSD-12ARSD-12B
RSD-12CRSD-12D
RSD-12ERSD-13A
RSD-13BRSD-13C RSD-13D
RSD-13E
RSD-14A
RSD-14BRSD-14CRSD-14D
RSD-15A
RSD-15B
RSD-15CRSD-15D
RSD-15E
RSD-15FRSD-15G
RSD-15H
RSD-16A
RSD-16B
SD10-A1
SD10-A2
SD10-A3
SD10-A4
SD10-A5
SD10-B1SD10-B2
SD10-B3SD10-B4SD10-B5
SD10-C1SD10-C2
SD10-C3SD10-C4SD10-C5
SD-SC-07
SD-SC-08
SD-SC-09
SD-SC-10
SD-SC-11SD-SC-12
SD-SC-13 SD-SC-14
SD-SC-15
SD-SC-16SD-SC-17
SD-SC-18
SD-SC-19
SD-SC-20
SD-SC-22
SD-SC-23
SD-SC-24SD-SC-25
SD-SC-1
SD-SC-2
SD-SC-3
SD-SC-4
SD-SC-5
SD-SC-6
PBR-16A-09V
Sample Locations!R 1995 Sample Location
"J 1997 Sample Location
#I
2001 Sample Location
$1 2015 Sample Location
#*2007-11 Penobscot River StudyPanel Sample Location
T( 2015 Geotechnical Sample Location
Proposed Sediment Removal Area
"J Tide Gauge
MEPDES Outfall
PERC Outfall
Northern Drainage Ditch
Stream
Figure 1-2Sediment Sample Locations
Corrective Measures Implementation PlanSouthern Cove, Orrington Remediation Site
Q:\
Job
s\H
oltr
aC
he
m_
00
00
\Ma
ps
\CM
I_P
lan
\PD
I_S
am
ple
_L
oca
tio
ns
.mxd
n
ko
chie
5
/31
/20
16
9
:35
:39
AM
0 50 100 150 200Feet
[
T(
T(
T(
T(
T(
T(
"J
"J"J"J
"J
"J
"J"J"J
"J
"J"J"J"J
"J
"J"J"J
"J"J"J
"J"J"J
"J"J"J"J
"J
"J
"J
"J
"J
"J
"J"J"J
"J
"J"J
"J
"J
"J
!R
!R
!R
!R
"J
"J
"J
"J
"J
"J
"J
!R
!R
!R
!R
!R
"J
"J"J"J
"J"J"J
"J"J
"J"J"J
"J"J"J
"J
"J
"J
"J
"J
"J
"J
"J
"J"J"J"J"J
"J
"J
"J"J"J
"J
"J
"J"J
"J
"J
"J
"J
"J
"J
"J
"J
"J
"J
#I
#I
#I
#I
#I
#I#I
#I#I#I#I#I#I
#I#I
#I#I#I#I#I#I
$1$1
$1$1
$1$1
$1$1
$1$1$1$1
$1
$1$1
$1
$1
$1
$1$1
$1
$1 $1
$8
$8
$8
$8
$8
RSC-001
RSC-002
RSC-003
RSC-004
RSC-005
RSC-006
RSC-007
RSC-008
RSC-009
RSC-010RSC-011
RSC-012
RSC-013
RSC-014
RSC-015
RSC-016
RSC-017
RSC-018
RSC-019
RSC-020
RSC-021
RSC-022RSC-023
RSC-024
RSC-025
RSC-026
RSD-04A
RSD-04B
RSD-04C
RSD-05A
RSD-05B
RSD-05C
RSD-06A
RSD-06B
RSD-06C
RSD-06E
RSD-07A
RSD-07B
RSD-07C
RSD-07D
RSD-07E
RSD-08A
RSD-08B
RSD-09A
RSD-09B
RSD-10A
RSD-10B
RSD-10C
RSD-11A
RSD-11B
RSD-11C
RSD-11D
RSD-11E
RSD-11F
RSD-11G
RSD-11H
RSD-12ARSD-12B
RSD-12C RSD-12DRSD-12E
RSD-13A
RSD-13BRSD-13C RSD-13D
RSD-13E
RSD-14A
RSD-14BRSD-14CRSD-14D
RSD-15A
RSD-15B
RSD-15CRSD-15D
RSD-15E
RSD-15FRSD-15G
RSD-15H
RSD-16A
RSD-16B
SD10-A1
SD10-A2
SD10-A3
SD10-A4
SD10-A5
SD10-B1SD10-B2
SD10-B3SD10-B4SD10-B5
SD10-C1SD10-C2
SD10-C3SD10-C4SD10-C5
SD-SC-07
SD-SC-08
SD-SC-09
SD-SC-10
SD-SC-11SD-SC-12
SD-SC-13 SD-SC-14
SD-SC-15
SD-SC-16SD-SC-17
SD-SC-18
SD-SC-19
SD-SC-20
SD-SC-22
SD-SC-23
SD-SC-24SD-SC-25
SD-SC-1
SD-SC-2
SD-SC-3
SD-SC-4
SD-SC-5
SD-SC-6
SD-SC-23
SD-SC-24
SD-SC-20
SD-SC-25
SD-SC-22
Northern Drainage Ditch
Southerly Stream
Sample Locations!R 1995 Sample Location
"J 1997 Sample Location
#I
2001 Sample Location
$1 2015 Sample Location
T( 2015 Geotechnical Sample Location
Dredge Depth Delineation0.8 feet
1 foot
3 feet
3 feet(Final Dredge Depth To BeAdjusted During Construction)
Proposed Sediment Removal Area
Sediment Removal Arearequired by Order MPS
0 - 0.2 feet
0.8 - 1 feet
> 1 feet
MEPDES Outfall
PERC Outfall
Stream
Figure 2-1Sediment Removal Areas and Depths
Corrective Measures Implementation PlanSouthern Cove, Orrington Remediation Site
Q:\
Job
s\H
oltr
aC
he
m_
00
00
\Ma
ps
\CM
I_P
lan
\Pro
po
sed
_R
em
ov
al_
De
pth
s.m
xd
n
koc
hie
4
/22
/20
16
11
:26
:32
AM
0 50 100 150 200Feet
[Note:Proposed sediment removal areas represent the minimum removal limits; the boundaries may be optimized for efficient construction.
Northern Drainage Ditch
Southerly Stream
Sample Locations!R 1995 Sam ple Location"J 1997 Sam ple Location
#I2001 Sam ple Location$1 2015 Sam ple Location
Proposed Sedim ent Rem oval Area
Mercury Concentrations (mg/kg)! ≤ 2.2! > 2.2
Wetland Community BoundaryHig h Marsh /Sedge BedDense Hardstem Bu lru shSparse Th ree-squ are Sedge
MEPDES Ou tfallPERC Ou tfallNorth ern Drainage DitchStream
Figure 2-2Extent of Intertidal Vegetation
Corrective Measu res Im plem entation PlanSou th ern Cove, Orring ton Rem ediation Site
Q:\Jobs\HoltraChem_0000\Maps\CMI_Plan\Intertidal_Vegetation.mxd nkochie 4/22/2016 11:23:57 AM
0 50 100 150 200Feet[