some updates on development of new energy system in …¼‐grid demonstration project in...
TRANSCRIPT
Some updates on development of new energy system in the framework of energy system in the framework of
the Smart Community initiatives
December 2nd 2011December 2nd, 2011
Hidekazu TakakuraSmart Community Department
NEDO, Japan
What is NEDO
As Japan's public management organization promoting research and development as well as the dissemination of industrial, energy and environmental technologies, NEDO has a crucial mission to carry out.environmental technologies, NEDO has a crucial mission to carry out.
• Enhancement of Japan's industrial competitiveness• Addressing energy and global environmental problems
FoundationOriginally established as a semi governmental organization on October 1 1980;Originally established as a semi-governmental organization on October 1, 1980;reorganized as an Incorporated Administrative Agency on October 1, 2003.
Ch i M K F kChairman Mr. Kazuo FurukawaMinister in charge The Minister of Economy, Trade
and Industry (METI)and Industry (METI)Location Kawasaki city , Kanagawa Pref., JapanPersonnel About 1,000
1
EXPERIENCES INRENEWABLES INTEGRATIONRENEWABLES INTEGRATION
2
Japanese Experiencei R bl I i
FY2006 FY2007 FY2008FY2005 FY2009 and
in Renewables Integration
Up to FY2005 FY2006 FY2007 FY2008FY2005 FY2009 and onward
Up to FY2005
Technology development of renewable energies (PV, WT, etc.) (New Sunshine Project, Large-scale wind power technology development, Advanced photovoltaic technology
development, Future technology development, and Ultra-high efficiency photovoltaic technology development)
Demonstrative Project on Grid interconnection of Research and Development of
Single renewable energy grid-connection technology development (such as the
p )
Grid-connected SystemOperation and grid-connection of high penetration renewable energy or energy storage and
EMS application technology to reduce fluctuation of renewable energy output
Demonstrative Project on Grid-interconnection of Clustered Photovoltaic Power Generation Systems (FY2002-FY2007)
Research and Development of Islanding Testing Technology for Clustered Photovoltaic Power Generation Systems (FY2008-FY2009)
Demonstrative Project of Regional Power Grids
Wind Power Stabilization Technology Development Project(FY2003-FY2007)
p (Rokko Island project)
Demonstrative Project of Regional Power Grids with Various New Energies(FY2003-FY2007)
Demonstrative Project on New Power Network Systems(FY2004-FY2007)
Verification of Grid Stabilization with Large-scale PV Power Generation Systems(FY2006-FY2010)
Development of an Electric Energy Storage System for Grid-connection with New Energy Resources (FY2006-FY2010)
3Promoting Continuous Efforts to Develop Smart Community Technologies
Grid‐interconnection of Clustered PVPower Generation Systems : FY2002 ‐ FY2007
Ota City Demonstration Site
Number of PV equipped houses: 553Development of a new inverter to detect islanding Number of PV‐equipped houses: 553Total PV capacity: 2,129 kWAverage capacity per house: 3.85 kW
p gDevelopment of battery storage operation and network voltage controlDevelopment of simulation technologies
4
Verification of Grid Stabilizationwith Large‐scale PV Power Generation Systems (FY2006 ‐ FY2010)
Wakkanai site
Tokyo
Wakkanai site 5 MW: Most PV cells are crystalline
Hokuto site5 MW: Most PV cells are crystalline.NaS battery: 1500 kW‐7.2hrs
Hokuto site 1.8 MW: 27 types of PVs
Technology development to reduce voltage fluctuation with batteryD l f i i bl f
5
Development of a new inverter suitable for mega‐solar plantTesting various types of PV modules
5
66
77
μ‐grid demonstration project in Sendai(FY2004‐2007)D t ti P j t P S l S tDemonstrative Project on Power Supply System
by Service Level
High Quality ANo Interruption. Compensating voltage at a wave level.
High Quality BHigh Quality BRemoving interruption within 15 ms
Standard Quality CInterruption is usually removed within 1 minute.
DCDCNo Interruption. DC supply.
Great East Japan Earthquake: 2:46 pm on March 11.
8
Sendai system recovered before noon of March 12. And supply electricity to Hospital and High Quality A load (UPS). Utility system recovered at March 14.
ON GOING ACTIVITIES
9
Japan’s Smart Community and smart grid Goal
More convenient, reliable and greener systemby means of IT through coordination and cooperationBetween energy suppliers and demand side users Between energy suppliers and demand side users.
Mega Solar Construct an energy system which is mutually beneficial for main grid operator and regional
Main Grid
Zero Emission Buildings
Wind Power
be e c a o a g d ope ato a d eg o aenergy management provider. Connect BEMS with regional
EMS.
Energy Management SystemGEGE
Storage Battery
Na‐S Battery
Enable better use of heat in addition to electricity.
Regional Energy
CogenerationSolar PowerWind Power
BatteryBiogas
Regional Energy Management Provider
GEGE
Information Network
New‐generation Gas Station
Solar Power EVs and PHEVs
Home Storage
Wasted Heat
Smart Meter:Visualization of home
energy use and demand control
Smart House
Home Storage BatteryUtilize IT for
peak cuts.
Construct charging stations for EVs.
10
Japan Smart Community Alliance
JSCA carries out various work for the development of roadmaps orp pdissemination of information to achieve international standardization andstrengthen collaboration among a wide range of relevant people andorganizations.
Utilities Developers
InstitutionsManufacturers
Members: 646 (As of November, 2011 )
Established: April, 2010p ,
JSCA is a public‐private organization, consists of a broad range of Japaneseorganizations and companies, including electric power, gas, automobile,information and communications electric machinery construction andinformation and communications, electric machinery, construction andtrading industries as well as the public sector and academia. NEDO is apermanent secretary of JSCA.
International Smart Community Activities
12
Project in the United States, New Mexico • Reliable power supply under high penetration of PhotovoltaicReliable power supply under high penetration of Photovoltaic
by using CEMS, DER, NaS etc,.• 2009-2013
Partners; The State of New Mexico, The County of Los Alamos, LANL, Mesa del Sol, PNM, UNM, SNL
Entrusted parties; Toshiba, Kyocera, Shimizu, Itochu, Cyber Defense, etc., 19 companies as total
[Los Alamos]• Utility-Scale PV + NaS• Schedule by Predicting PV generation
[Albuquerque]• Commercial building + DER with BEMS• Absorb fluctuation from Utility Scale PV
Entrusted parties; Toshiba, Kyocera, Shimizu, Itochu, Cyber Defense, etc., 19 companies as total
• Schedule by Predicting PV generation• Optimize by DR and NaS• HEMS demo
Absorb fluctuation from Utility Scale PV
13
Project in the United States, Hawaii• Reliable power supply under high penetration of Wind PowerReliable power supply under high penetration of Wind Power
by managing EV charging etc.,• 2011-2015
Partners; The State of Hawaii,HECO, MECO, HNEI, The County of Maui, The Maui Economic Development Board etc.,
Entrusted parties; Hitachi, Mizuho Corporation, Cyber Defense
[Whole Maui island]• Manage EV charge
Shift to midnightStop charging when unexpected downStop charging when unexpected down ramp occurs etc.,
[Kihei District][Kihei District]• DLC thru μ-DMS• Optimize usage of low Volt transformer• Optimize PV generation by Smart PCS
14
Project in Spain, Malaga• Avoiding congestion of distribution lineAvoiding congestion of distribution line
under high penetration of EV quick chargersby navigating EV users to optimal places
• 2011-20152011 2015• Currently under Feasibility Study
15
Project in France, Lyon• 3 Tasks are under consideration3 Tasks are under consideration
ZEB demoEnergy use monitoring and management for PV and EVsE dit i AMIEnergy audit program using AMI
• 2011-2015• Currently under Feasibility Study
16
Concluding remarks
Establishment of smart communities is required to improve the quality of life
both in Japan and around the world.
It is important to develop and demonstrate smart community-related technologies in a real environment, deploying current smart grid technologies developed through previous development and demonstration activities. g p p
Public-private sector cooperation across various industries is necessary to establish smart communitiesestablish smart communities.
To realize smart communities around the world, it is crucial to facilitate international deployment activities and strengthen collaboration with overseasinternational deployment activities and strengthen collaboration with overseas organizations. JSCA will play a significant role in this.
NEDO will contribute to develop sustainable world through building smartNEDO will contribute to develop sustainable world through building smart communities.
17
Thank you !Thank you ! http://www.nedo.go.jp/