solid ground floors
TRANSCRIPT
Building Methods & Construction Technology
Solid Ground Floors
Ground FloorsThere are two main types of ground floors:
• Solid floors. • Hollow floors.
Concrete ground floors consist of the following components, in order:
• Hardcore • Blinding• DP membrane • Site concrete• Insulation • A floor finish
Section Through a Solid Ground Floor.
Ground levelFloor finish Insulation
Site concrete
Blinding
DP membraneHardcore
Components and Sequence of Building a Solid Ground Floor
Hardcore and blindingHardcore is used to provide a firm and
solid base on which to place the concrete slab.
Blinding is usually building sand spread on top of the hardcore to provide an even bed and to prevent any puncturing of the DPC membrane by sharp pieces of hardcore.
The damp-proof membrane sheeting should be laid on top of the blinding and should lapped onto the horizontal DPC of the brickwork to form a continuous membrane.
Ground level DP Membrane laid onto blinding and lapped into the internal brickwork
Blinding sand
Hardcore
Compaction of hardcoreHardcore should be laid in 100mm layers maximum, and each layer should be well compacted and consolidated. This should prevent any unacceptable settlement beneath the finished solid floor. The main item of small plant which is used to compact hardcore is a Plate Compactor.
Insulation
Insulation should always be laid above the DPM membrane preferably under the floor slab, or alternatively under the floor finish. If it is not it could cause the insulation to become damp which will impair its performance.
The Building Regulations require ground floors to be insulated to prevent heat loss. There are several types of insulation available such as expanded polystyrene and rigid foam insulation.
Insulation positioned below
the floor finish
Insulation positioned below
the floor slab
Ground level
Ground level
Floor finish
Floor finish Insulation
Insulation
Site concrete
Site concrete
DPM
DPM
Blinding
BlindingHardcore
Hardcore
Oversite concreteThe concrete placed in between the ground floor walls is known as ‘oversite concrete’. The brickwork or blockwork on the internal walls acts as shuttering for the concrete. Oversite concrete should be at least 100mm thick.