solicitors construction law update - devonshires · evonshires solicitors construction law update:...
TRANSCRIPT
evonshiressolicitors
CONSTRUCTION LAW UPDATE: Interim and Final Accounts: The Muddy Waters of Harding v Paice
This article considers the application of notice requirements under s.111(1) of the Housing, Grants, Construction and Regeneration Act 1996. In particular, how the Court of Appeal has interpreted the application in respect of both Interim and Final Accounts in Harding (t/a MJ Harding Contractors) v Paice [2015] EWCA Civ 1231.
It is worth mentioning at the outset, for reasons that will become
clear later, the distinction between Interim and Final Accounts.
Where an employer fails to serve a payless notice in respect of an
interim application, he is “deemed to have agreed” the valuation
put forward by the contractor in the application. Importantly, that
does not stop the Employer recovering any over-payment at
the next interim application or the Final Account (where he can
properly value/revalue the works).
The same principles, however, do not apply where the matter in
question is the Final Account itself. In that scenario the distinction
between the “true value” of the work and the amount applied for
by the Contractor is of greater relevance since there will be no
further opportunity for the Employer to recover any overpayment.
This is a matter which the Court of Appeal has recently touched
upon, with implications for construction professionals and lawyers
alike.
Background
The instant case concerned a contractual relationship between
Harding, a building contractor and Paice, property developers.
During the course of the construction and fit out of two residential
properties in Surrey, the relationship deteriorated and resulted
in Paice terminating the contract owing to an alleged failure to
proceed diligently with the works.
Harding subsequently submitted his own notice of termination
and submitted the account to Paice, valuating the owed
balance at £397,912.48. Paice failed to issue a pay less notice
and the adjudicator accordingly found in favour of Harding. A
subsequent adjudication was sought by Paice to reduce the
value of the contract works to £340,032.60, however, Harding
applied for an injunction restraining the proceedings on the
basis that 1) the adjudicator in first instance had determined the
amount falling properly due and therefore the matter could not
be revisited; and 2) pursuant to paragraph 9(2) of the Scheme
the Adjudicator should resign owing to the overlay in disputed
issues (“the adjudicator must resign where the dispute is the
same or substantially the same as one which has previously been
referred to adjudication, and a decision has been taken in that
adjudication”).
Mr Justice Edwards Stuart dismissed Harding’s application,
maintaining Paice’s entitlement to determine what amount was
“properly due in respect of the account” rather than what had
previously been awarded i.e. the Final Account balance. However,
this did not detract from Paice’s obligation to comply with the
adjudicator’s original decision in the meantime by paying the
sum ordered. The position accords with the key notion that an
Adjudicators’ decision is “interim binding”.
Similarly, Harding’s second ground for an injunction was
You should read this Construction Law Update if:
• You are an Employer / Client under a construction contract;
• You are a Main Contractor to a construction contract;
• You are involved in any current or forthcoming construction projects in the UK.
1
dismissed. It was held that the adjudicator had not made a
decision on the true value of the account and as such it remained
open for determination by a further adjudicator.
Harding Appealed.
The Court of Appeal
Harding appealed on two grounds:
1. Failure to serve a pay less notice is tantamount to the
employer having agreed the value of the relevant payment.
Accordingly, a second Adjudicator would be acting outside
their jurisdiction in reducing the determined amount. Ironically,
the contractor relied upon the dictum of Edward-Stuart J
in ISG Construction Ltd v Seevic College in advancing this
argument.
2. Regardless of whether the adjudicator had determined the
amount properly due, by reference to the absence of a pay
less notice or otherwise, he had been asked that issue so as
to arrive at a decision. It follows that paragraph 9(2) and the
resignation of the adjudicator must be borne out.
Taking the points in reverse order, Lord Justice Jackson dealt
swiftly with the terminology of the word “decision” in paragraph
9(2), endorsing the explanation of the lower court to mean
“decision in relation to that dispute”. The first Adjudicator had
made no decision in relation to the true value of the account, but
rather the principle issue of the pay less notice i.e. his decision
related solely to the failure of the Employer to comply with a
technicality.
In relation to the first ground of appeal, his Lordship suggested
the contractor’s position could be split into two separate issues,
contractual and valuation. The first relating to the employer’s failure
to issue a pay less notice and the other relating to the appropriate
amount due on account. It was held that the first Adjudicator had
only dealt with the former of these two issues, leaving the matter
of valuation open to further scrutiny.
His Lordship held it was unnecessary to consider the case of ISG
v Seevic owing to Edward-Stuart J’s focus in that case centring
on interim payments. Indeed, the passage Harding sought to rely
on states: “in the absence of a payment or pay less notice issued
in time by the employer, the contractor becomes entitled to the
amount stated in the interim application irrespective of the true
value of the works actually carried out”. Accordingly, Jackson LJ
held that the principle could not apply by way of analogy given
the distinguishing characteristics of Interim and Final Accounts.
Interim payments having no relevance in the instant case, it
was unnecessary to consider whether what the judge had said
previously was correct.
Appeal dismissed.
Commentary
The decision of the Court in respect of Harding’s second
submission is certainly welcome. By interpreting the word
“decision” in paragraph 9(2) to mean “decision in relation to that
dispute”, Jackson LJ brings clarity to what would have been a
manifestly unjust position proposed by the contractor. It would
be inequitable to utilise Paragraph 9(2) to preclude further
adjudication of contemporaneous issues, particularly in respect
of Final Accounts where the potential for permanent overpayment
would leave the system open to abuse.
In respect of Harding’s first submission, it follows that failure to
issue a pay less notice, as applicable to Final Accounts, has
only limited consequences. Whilst the full amount awarded in the
adjudication must be paid, the employer has scope to adjudicate
the matter of what is “properly due” at a later date. Whilst this
appeals in principle as a means of avoiding overpayment, in
practice we are left with a convoluted and somewhat clumsy two-
tier dispute process.
The failure of the Court of Appeal to fully examine the case of ISG
v Seevic was perhaps, on reflection, short-sighted. His Lordship
touches upon the notion that failure to serve a pay less notice
on a contractor bears the consequence of having “deemed
to agreed” the interim application, yet fails to explore why this
position should be different for Interim and Final Accounts. One
assumes the distinction arises owing to the logistical ability to vary
subsequent interim valuations when juxtaposed with the finality
of the Final Account. However, this was not fully explored by his
Lordship.
A perhaps more satisfactory outcome would have been for
the court to clarify the position in ISG. It is of course correct to
conclude that the amount sought is owed in the absence of a
pay less notice, however, it may be better to view this simply as
a contractual consequence of a technical failure by the employer
rather than a ‘deemed agreement’. The semantics of the lower
Court does nothing more than muddy the waters.
Of course, if the court were to address this point the matter would
be treated as obiter. For the time being the debate may continue
in respect of interim payments and will likely warrant further
consideration by the Court of Appeal in future.
The tiny print
No action should be taken on the matters covered by this leaflet without taking specific legal advice.
This is one of a series of regular updates from the Construction & Engineering Department. For advice on any of the above issues,
or if you have any suggestions for topics you’d like us to cover next, please do email us at [email protected]. This
is a new initiative so please share this article among your colleagues and contacts and encourage them to subscribe via the same
address.