Page 1: Small Modular GTL: Commercialisation and Strategic

Slide 0 © 2011 CompactGTL plc

Real title

Iain BaxterCompactGTL plc

Small Modular GTL: Commercialisation and Strategic Partnerships

XTL World Forum7th – 8th June 2011

Page 2: Small Modular GTL: Commercialisation and Strategic

Slide 1 © 2011 CompactGTL plc

Stranded

Oil !

Page 3: Small Modular GTL: Commercialisation and Strategic

Slide 2 © 2011 CompactGTL plc

Engineering Partners

Client Sponsor

Technology Development

Support Partners

2006: Challenges for CompactGTL

Supply Chain Partners

Market Opportunity

• Strong project economics needed for attractive ROI

• Vision of CompactGTL as a solution provider to Upstream industry

• Partnership model necessary for successful execution

Page 4: Small Modular GTL: Commercialisation and Strategic

Slide 3 © 2011 CompactGTL plc

2011: Vision Realised

Delivering an associated gas solution to enable oilfield development

Client commercial plant studies & pre-FEED’s at 200 bpd tp 2,000 bpd

Volume manufacturing supply chain established

CompactGTL Brazil subsidiary established in Rio de Janeiro

Continuously strengthening team with World-scale GTL experience

Petrobras plant commissioned and now running under test

Page 5: Small Modular GTL: Commercialisation and Strategic

Slide 4 © 2011 CompactGTL plc

Real title

Market Opportunity & The Modular GTL Solution

Page 6: Small Modular GTL: Commercialisation and Strategic

Slide 5 © 2011 CompactGTL plc

Associated gas particularly problematic at < 50 MMscf/d

E&P TRENDSMore development in deepwater

More development remote from gas markets

250 km

Satellite image of gas flaring in Nigeria

0

50

100

150

200

5-10 11-50 51-100 101-150

Offshore

Onshore

Associated gas production [MMscf/day]

Nu

mb

er

of

Fie

lds

Image courtesy of Chris Elvidge, National Geophysical Data Centre, Bouder, CO, USA

Page 7: Small Modular GTL: Commercialisation and Strategic

Slide 6 © 2011 CompactGTL plc

Distinct market for modular GTL

Reinjection

Associated Gas MMscf/d

Dis

tan

ce

to

ma

rke

t fo

r co

nve

rte

d p

rod

uct

[k

m]

150

75

40020050

500

FLNG

CNG

PipelineGas to Wire

ModularGTL

Page 8: Small Modular GTL: Commercialisation and Strategic

Slide 7 © 2011 CompactGTL plc

CompactGTL solution @ 2-50MMscf/d

• Incremental NPV of >$100MM possible

• Early production – Standalone unit

• Increased revenue from syncrude

• Savings in gas re-injection wells or pipelines

• Gas can be booked as reserves

• No separate storage, transportation or market access required for syncrude

Concept Design10MMscfd GTL plant on FPSO

Modular GTL :Convert the associated gas into syncrude

Co-mingle and transport with the natural crude

Image courtesy of SBM Offshore

Page 9: Small Modular GTL: Commercialisation and Strategic

Slide 8 © 2011 CompactGTL plc

Commercial plant conceptual design

• 10 MMscfd gas feed

• 1,000 bbl/d syncrude production

• 2,400 T operating weight

• Configurable for :

• Aframax

• Suezmax

• VLCC

SMR modules

FT modules

Page 10: Small Modular GTL: Commercialisation and Strategic

Slide 9 © 2011 CompactGTL plc

Modular plant design gives scaleability, inherent reliability & operability

• Modules can be removed as production falls

• Modules re-furbished and catalyst replaced onshore

• Modules can go on-line and off-line to accommodate production variability

• Multiple modules provide inherent reliability

Page 11: Small Modular GTL: Commercialisation and Strategic

Slide 10 © 2011 CompactGTL plc

Basis for enhanced oilfield NPV

Facilities Capital Cost PV

Gas Disposal

Crude Revenue

PV

OilfieldNPV

Operations & Tax

PV

Penalties or Delay

Operations & Tax

PV

GTL Opex

OilfieldNPV

Syncrude PV

Crude Revenue

PV

Gas Re-Injection or Pipeline to Market

Facilities Capital Cost PV

GTL Plant

Integrated CompactGTL

Page 12: Small Modular GTL: Commercialisation and Strategic

Slide 11 © 2011 CompactGTL plc

Real title

Commercialisation Route & Key Milestones Achieved

Page 13: Small Modular GTL: Commercialisation and Strategic

Slide 12 © 2011 CompactGTL plc

Commercialisation route

Lab Reactors Commercial PlantBrazil PlantUK Pilot Plant

Commercial Plant Studies

Requirements

Reactor & Catalyst Supplier

Engagement

Prototype Reactor & Catalyst

Evaluation

Requirements

Supplier Selection

Pilot Reactor & Catalyst

Manufacture

Commercial Supply Chain Establishment

Page 14: Small Modular GTL: Commercialisation and Strategic

Slide 13 © 2011 CompactGTL plc

Mini-channel CompactGTL reactors

Catalysts :

• Removable metallic inserts

• Established automotive mass production techniques

Reactors :

• High specific heat transfer

• Established heat exchanger mass production techniques

• High reactor ‘voidage’ using pressed fin plates, minimising metal content, cost & weight

Automated catalyst insertion & removal at point of manufacture

Page 15: Small Modular GTL: Commercialisation and Strategic

Slide 14 © 2011 CompactGTL plc

UK Pilot plant operational for > 2.5 years

Plantcommissioned

July 2008

Installation atWilton, NE

England

• Confirming catalyst & reactor performance from manufacturers

• Integrated operation – ‘gas in to liquids out’

• Operational stability, start-up & shut down procedures

• Variable feed gas composition & CO2 content

• Operator training for larger plants

Page 16: Small Modular GTL: Commercialisation and Strategic

Slide 15 © 2011 CompactGTL plc

Petrobras GTL demonstration plant contract

• Contract confirmed with CompactGTL in July 2008

• Funded by Petrobras

• Capacity of 200,000 scf gas (20 bpd)

• Plant required to demonstrate all aspects needed for commercial application

Page 17: Small Modular GTL: Commercialisation and Strategic

Slide 16 © 2011 CompactGTL plc

Plant constructed in Canada & Japan

Plant constructed by Zeton Inc, Burlington, Canada

SMR & FT Reactors fabricated by Sumitomo Precision Products, Osaka, Japan

Page 18: Small Modular GTL: Commercialisation and Strategic

Slide 17 © 2011 CompactGTL plc

Complete set of GTL reactors despatched by air-freight to Brazil

Page 19: Small Modular GTL: Commercialisation and Strategic

Slide 18 © 2011 CompactGTL plc

Final commissioning December 2010

Plant running and under test

• Gas pre-treatment

• Pre-reforming

• Reforming

• Waste heat recovery

• Process steam generation

• Syngas compression

• Fischer Tropsch synthesis

• FT cooling water system

• Tail gas recycling

World’s first small scale fully integrated

GTL facility !

Image shown courtesy of Petrobras

Page 20: Small Modular GTL: Commercialisation and Strategic

Slide 19 © 2011 CompactGTL plc

Partnership approach critical to success

FPSO Expertise

Catalyst Supplier

Reactor Supplier

FEED Partners

Technology Support

Page 21: Small Modular GTL: Commercialisation and Strategic

Slide 20 © 2011 CompactGTL plc

Real title

Bayer Technology Services

Technology & Engineering Support Partner

Page 22: Small Modular GTL: Commercialisation and Strategic

Slide 21 © 2011 CompactGTL plc

Bayer Technology Services –Technology Solutions for Bayer & External Companies

Design and Manage Investments

Covering the whole Plant Life Cycle

Optimize Facilities and Products

Develop Products and

Processes… a Bayer Group Company

Turnover worldwide(*) 420 EUR mill.

Employees worldwide(**) 2,600(*)2010 (**)Dec 31, 2010

Client industries• Health Care• Crop Science• Material Science/Polymers• Chemicals/Petrochemicals

Page 23: Small Modular GTL: Commercialisation and Strategic

Slide 22 © 2011 CompactGTL plc

Reactor & Process Technology Development Workflow

Lab Reactors Commercial PlantBrazil PlantUK Pilot Plant

Reaction KineticsCFD Modelling

Brazil Plant Option

Selection

Lab Reactor Tests < 10 Channels

Prototype Reactor Tests

50-100 Channels

Multiple Reactor & Catalyst Suppliers

Commercial Plant Design?

Process Modelling Heat & Mass Balances

Page 24: Small Modular GTL: Commercialisation and Strategic

Slide 23 © 2011 CompactGTL plc

Model based reactor design & scale up methodology

Catalyst screening

Reaction modelling

Reactormodelling

Modelvalidation

Reactor design& scale up

Lab reactors for all process steps

Reactor models withdetailed kinetics

Process heat and mass balances

Page 25: Small Modular GTL: Commercialisation and Strategic

Slide 24 © 2011 CompactGTL plc

Real title

Sumitomo Precision Products

SMR & FT Reactor Manufacturing Partner

Page 26: Small Modular GTL: Commercialisation and Strategic

Slide 25 © 2011 CompactGTL plc

Amagasaki Head Office

Overseas Offices

New York

Major Subsidiaries

STS(UK), MET(JPN), SE(JPN)

Page 27: Small Modular GTL: Commercialisation and Strategic

Slide 26 © 2011 CompactGTL plc

Heat Exchangers

- SUMALEX

- LNG Vaporizer

Siphorex (Thermo-siphon semiconductor

device cooling equipment)

Main Heat Exchanger for Air Separation

Heat Exchanger for Helium Liquefaction Plant

LNG VaporizerOpen Rack type (ORV)

Page 28: Small Modular GTL: Commercialisation and Strategic

Slide 27 © 2011 CompactGTL plc

Page 29: Small Modular GTL: Commercialisation and Strategic

Slide 28 © 2011 CompactGTL plc

The Result………

Strong economics where gas infrastructure or re-injection are avoided

UK pilot plant operational for >2.5 years

Manufacturing route & partners established

‘Standalone’ solution for oilfield development

Petrobras plant commissioned and now running under test

With special thanks to Petrobras and all our