smacc tenth report [15 min ] 13/09/2013
DESCRIPTION
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project. SMACC Tenth report [15 min ] 13/09/2013. Activities since last LSC (30/08/2013) By Activities By sectors SIT DFBA Dashboards Brief ElQC update Activities for the next 2 weeks Conclusions. - PowerPoint PPT PresentationTRANSCRIPT
SMACC Tenth report[15 min]
13/09/2013
Jean-Philippe Tock (TE-MSC)
On behalf of the SMACC project
Activities since last LSC (30/08/2013) By Activities
By sectors
SIT
DFBA
Dashboards Brief ElQC update Activities for the next 2 weeks Conclusions
JPh Tock4/28
Sector 56 : Work on non-conformities
Sector 67 Installation of insulation boxes and injection Rewelding of M sleeves
Leak test of M lines Reclosure of interconnections DFBA consolidation
Sector 78 Desoldering and resoldering of splices Installation of shunts DFBA consolidation
Sector 81 ElQC of existing splices
Other sectors: S12: Opening of M lines S23: Opening of interconnections and installation of DN200 S12, 23, 34 & 45 : Reconnection of replacing magnets Advanced opening for outliers and CSCM segments Inspection of connection cryostats
On-going, > 1/3 of the sector equipped
SMACC Main activities for the next 2 weeks
Jeune Genevois
…
Good progress
In progress, critical activity
Started, 14 ICs reclosed
Desoldering completed, starting in 81
On-going
On-going, > ¼ completed, see further
> 80% open, DN200 installation completed
On-going, 52 ICs reclosed, leak test of beam lines completed succesfully
On-going
From last LSC (30.08.2013)
In progress, > 1/3 of sector reweldedStarted, 2/14 vac subsectors validated
On-going
JPh Tock5/28
SMACC Progress report by activity
Opened interconnections in 8 sectors, > 6 sectors-eq are opened
Back on schedule
JPh Tock6/28
SMACC Progress report by activity
M line cutting : > 4.5 sectors equivalent (S12 well advanced) Replacing team leader at CERN since beginning of August
Courtesy JM Hubert
JPh Tock7/28
SMACC Progress report by activity
Courtesy H Prin
Desoldering : Completed in S56 & 67 & 78 Resoldering completed in S56 & 67 & at 75 % in S78
Desoldering: Nominal was 53/week; Now we need 95/weekIncreasing is seen (Effect of new staff and tooling) W36 included Jeune GenevoisW37 not completed (preliminary: 85)
Resoldering : Improving, not yet there1 person of the team prepares intervention on overheated cable in 56 with a staff
59
JPh Tock8/28
SMACC Progress report by activity
Shunts are installed in > 2 sectors-eq.
50 ICs behind schedule (About one week at nominal rate) Delay effect of the reinforcement of resoldering teams Non-consecutive interconnections About 8 000 shunts installed (30% of the LHC) «Last 10% effect» in 2 sectors
JPh Tock9/28
SMACC Progress report by activity
Installation of insulation box: Good progess in 67 ( 50 %)
Courtesy H Prin / M Duret
2 phases : Minimum required: 45 ICs/ week (9 per day)Installation (time consuming, continuous) & Injection (By batch of ≈ 15 ICs)
Installation completed in 56 and 55 % of 67 Injection completed in 56 and 45 % of 67 : Inject every 2 days by batch of 15 (37.5/wk) Bottleneck is still the installation of the electrical insulation
Work sequence is optimised Resources are redirected
2 FSUs and 3 COAS (PAEC) in October
THE critical activity
JPh Tock10/28
SMACC Progress report by activity
Quadrupole diodes > 5 sectors are opened / 2 sectors are almost consolidated (1 diode to be exchanged because of too high
internal resistance) Globally almost on schedule BUT One diode has to be replaced because of too high diode to heatsink resistance (Q31R6) Some components were delivered, allowing to barely complete S67; some pieces have to be reworked at
CERN Not critical YET Alternative supply still under investigation to check that it can meet the requirement
OK for the material certificate, price to be renegotiated, manufacturing method still to be confirmed (Delivery time of at least 2 months)
Courtesy L Grand-Clement / F Savary
JPh Tock11/28
SMACC Progress report by activity
M Welding : 290 ICs welded, ≈ 1.35 sec-eq:
Courtesy S Atieh
Reduced team, extrapolating: nominal rates seem achievable
Limited by release rate, not by the team capacity (Presently 30/week)
In-line with forecast of last LSC
Delay wrt baseline Required rate to end according to baseline :
45 IC/week Team sized for 53-60 Margin for the «last 10%» has been eaten Situation to be monitored for a possible
reaction in October.
JPh Tock12/28
SMACC Progress report by activity
M sleeves leak testing : All possible subsectors (200 ICs) are leak tested
All possible subsectors of S56 (11/14) are released and leak tested
Starts in S67 : 3 subsectors released. 2 are leak tested
In-line with forecast of last LSC
Delay wrt baseline Required rate to end according to
baseline : 3.1 subsec/week Foreseen for 3-3.5 subsec/week Margin for the «last 10%» has
been eaten Situation to be monitored for a
possible reaction
Courtesy P Cruikshank / L Mourier
JPh Tock13/28
SMACC Progress report by activity
Reclosure of interconnections : On-going in 67 (priority) and 56,
52 ICs are reclosed in 56 and 14 in 67 Stopped in 56 during beam lines leak test;
contraint relaxed this week by VSC S56 will be delayed (Overheated cable,
DFBAK bellows)
JPh Tock14/28
SMACC Progress report by activity
Final leak test: 1st one STARTED
16 consecutive interconnections closed in 56 Final leak test started Results in 2 weeks, on schedule
JPh Tock15/28
SMACC Progress report by sector
Main activities are on non-conformities Was temporarily stopped for beam lines leak testing Reclosure as a an activity to smooth work load (priority given to S67) Repair of overheated cable will start next week, with a completion by end of
October One PIM to be exchanged for protruding RF fingers (QQBI.29R5): Re-rewelding
capability will be limited – specific procedure (was consolidated in 2009)
JPh Tock16/28
SMACC Progress report by sector
All non-problematic ICs are shunted Main activities are installation of insulation system and welding of M lines Leak test of M lines is on-going (2/14 subsectors validated) Reclosure started
JPh Tock17/28
SMACC Progress report by sector
Main activities are: desoldering of splices
(just completed), resoldering of splices, installation of shunts and related QC/QA
JPh Tock18/28
SMACC Progress report SIT
SIT 2 cryomagnets are reconnected, the other ones are under reconnection and it has started for Q5L8 Standard reconnection will be done by the train when it will arrive PIMs: Rewelded in 6 sectors, 2nd RF ball test done successfully in S56 (Only one more to change in 56) 2 Y-line leaks are repaired and validated, only the closure of IC remains, by the train, end of 2013
To start : Interventions on SAM (Tooling under checking in workshop) and IT
Courtesy N Bourcey, S Le Naour
JPh Tock19/28
SMACC Progress report DFBA
DFBA M Bellows: See report by L Tavian Splices consolidation has restarted at a good rate, with reinforced team
Courtesy TE-CRG, TE-MSC and EN-MME
JPh Tock20/28
SMACC DashboardsSMACC summary status Updated 11-Sep-13
19-Apr-13 212 13-May-13 17-Jun-13 210 19-Jul-13 05-Jul-13 206 08-Aug-13 19-Jul-13 168 15-Aug-13 30-Aug-13 48 27-Sep-13 17-Sep-13 0 25-Oct-13-11 212 -6 -54 212 -41474 -58 212 -41494 4 212 -41501 -10 212 212
08-Apr-13 100% 07-May-13 24-Apr-13 99% 08-May-13 97% 23-Jul-13 79% 20-Aug-13 23% 0%
16-May-13 211 06-Jun-13 22-Jul-13 199 23-Aug-13 13-Aug-13 77 17-Sep-13 27-Aug-13 32 24-Sep-13 30-Sep-13 14 27-Oct-13 15-Oct-13 0 22-Nov-13-20 211 10 -31 211 -41509 8 211 -41534 -41513 211 -41541 -27 211 -41574 -41562 211 -41600
26-Apr-13 100% 16-Jun-13 21-Jun-13 94% 21-Aug-13 36% 15% 03-Sep-13 7% 0%
07-Jun-13 212 27-Jun-13 26-Aug-13 76 30-Sep-13 18-Sep-13 0 22-Oct-13 02-Oct-13 0 29-Oct-13 28-Oct-13 0 22-Nov-13 12-Nov-13 0 20-Dec-13-24 212 12 -3 212 -41547 -41535 212 -41569 -41549 212 -41576 -41575 212 -41600 -41590 212 -41628
14-May-13 100% 09-Jul-13 23-Aug-13 36% 0% 0% 0% 0%
28-Jun-13 212 18-Jul-13 01-Oct-13 0 04-Nov-13 23-Oct-13 0 26-Nov-13 06-Nov-13 0 03-Dec-13 27-Jan-14 0 21-Feb-14 11-Feb-14 0 21-Mar-14-38 212 8 -41548 212 -41582 -41570 212 -41604 -41584 212 -41611 -41666 212 -41691 -41681 212 -41719
21-May-13 100% 26-Jul-13 0% 0% 0% 0% 0%
19-Jul-13 212 08-Aug-13 05-Nov-13 0 09-Dec-13 27-Nov-13 0 14-Jan-14 11-Dec-13 0 21-Jan-14 24-Feb-14 0 21-Mar-14 11-Mar-14 0 22-Apr-14-53 212 21 -41583 212 -41617 -41605 212 -41653 -41619 212 -41660 -41694 212 -41719 -41709 212 -41751
27-May-13 100% 29-Aug-13 0% 0% 0% 0% 0%
09-Aug-13 166 29-Aug-13 10-Dec-13 0 27-Jan-14 20-Jan-14 0 21-Feb-14 31-Jan-14 0 27-Feb-14 24-Mar-14 0 22-Apr-14 08-Apr-14 0 21-May-14-67 212 -41515 -41618 212 -41666 -41659 212 -41691 -41670 212 -41697 -41722 212 -41751 -41737 212 -41780
03-Jun-13 78% 0% 0% 0% 0% 0%24-Feb-0025-Nov-13 55 13-Dec-13 29-Jan-14 0 04-Mar-14 24-Feb-14 0 28-Mar-14 07-Mar-14 0 03-Apr-14 24-Apr-14 0 22-May-14 07-May-14 0 20-Jun-14
-188 212 -41621 -41668 212 -41702 -41694 212 -41726 -41705 212 -41732 -41753 212 -41781 -41766 212 -4181021-May-13 26% 0% 0% 0% 0% 0%
06-Jan-14 37 24-Jan-14 05-Mar-14 0 08-Apr-14 31-Mar-14 0 07-May-14 11-Apr-14 0 13-May-14 22-May-14 0 20-Jun-14 06-Jun-14 0 18-Jul-14-255 212 -41663 -41703 212 -41737 -41729 212 -41766 -41740 212 -41772 -41781 212 -41810 -41796 212 -41838
26-Apr-13 17% 0% 0% 0% 0% 0%
19-Apr-13 1317 24-Jan-14 17-Jun-13 485 08-Apr-14 05-Jul-13 283 07-May-14 19-Jul-13 200 13-May-14 30-Aug-13 62 20-Jun-14 17-Sep-13 0 18-Jul-14-11 1695 -41663 -54 1695 -41737 -58 1695 -41766 4 1695 -41772 -10 1695 -41810 -41534 1695 -41838
08-Apr-13 78% 24-Apr-13 29% 08-May-13 17% 23-Jul-13 12% 20-Aug-13 4% 0%
S34
S45
LHC
S67
S78
S81
S12
S23
ICs Opening
S56
Sleeves Welding M lines Leak Test ICs closure Ins Vac LtestShunts Installation
JPh Tock21/28
SMACC Dashboards
Opening is back ahead of schedule despite closure of interconnections
Shunting starts to improve with reinforcement and optimisation of critical activities
Welding: Limited by release rate, confident that nominal rate can be achieved, margin has been eaten up
M leak test : Limited by release rate, confident that nominal rate can be achieved, margin has been eaten up
ReClosure: started ahead of schedule, now in S67 Final leak test started (Results in 2 weeks)
JPh Tock22/28
SMACC Dashboards
Baseline: 26.1 % (22.3 %)Completed: 23.0 % (20.0 %)Delay 10 (9) days Baseline: 47.0 % (41.1 %)
Completed: 33.0 % (29.7 %)Delay 27 (17) days
Baseline: 42.9 % (35.7 %)Completed: 23.0 % (22.3 %)Delay 41 (36) days
Baseline: 100 % (100 %)Completed: 82.4 % (72 %)Delay 64 (52) days
Will be completed by beginnig of November
JPh Tock23/28
SMACC Dashboards
Progress:Baseline: 31.8% (27.2 %)Completed: 25.6% (22.4 %)
Delay 18 (15) days
JPh Tock24/28
SMACC Summary on progress
Main 13 kA Splices: Started a week in advance, now 2 weeks delay (stable)
Special Interventions: 27 days delay, non-conformities start to impact
DFBA: > 1 month delay: should recover for end of the year
Bellows issue could have a large impactDN200:
≈ 2 months delay: not criticalSMACC:
About 3 weeks (stable)
The impact of the summer period on the planning was 3 weeks
Can recover next year when resources are freed by finishing activities
JPh Tock25/28
SMACC ElQC Status
Courtesy C Scheuerlein, S Heck
30 % seems confirmed as more solid number Dedicated presentation in October with half of the LHC measured
Preliminary results of existing splices quality control (7.09.2013).
Sector Sector 56 Sector 67 Sector 78 Sector 81 LHC
Measured [%] 100 100 100 25 40 To redo [%] 28 32 29 31 30
JPh Tock26/28
Sector 56 : Work on non-conformities including repair of overheated cable Reclosure (not in priority)
Sector 67 (Priority sector) Installation of insulation boxes and injection Rewelding of M sleeves Leak test of M lines Reclosure of interconnections DFBA consolidation
Sector 78 Complete resoldering of splices Installation of shunts DFBA consolidation
Sector 81 ElQC of existing splices Start desoldering of splices
Other sectors: S12: Complete opening of M lines S23: Opening of interconnections S12, 23, 34 & 45 : Reconnection of replacing magnets Advanced opening for outliers and CSCM segments Inspection of connection cryostats
SMACC Main activities for the next 2 weeks
JPh Tock27/28
Conclusions New activity: Start of final leak testing (The last one ) About to start to repair the overheated cable in 56 in-situ The ratio of 30 % of splices to redo seems confirmed for 40% of the LHC Reduced ElQA test frequency allows to cope with > 3 sectors in //
Global delay of 3 weeks due to summer period and technical issues under solving ; difficut to recover this year
Margin has been eaten up for some activities (M welding, M leak test)
Issues:Reach nominal rate for arc splices consolidation
(Ramp up with de/re soldering and optimise installation of insulation box)DFBA busbar bellowsComponents for diodes consolidation
So far, not so bad …
JPh Tock28/28
SEQUENCE AND STATUS
OK to open
8 sectors
Open ICs
> 6 sectors
Install DN200
≈ 80%Open M sleeves
≈ 4.5 sectors
ELQC(old splices)
> 3 sectors
Undo / Redo splices
≈ 2.5 sectors
ELQC(new splices)
≈ 2.5 sectorsMachine
Cu
> 2 sectors
ELQCafter Cu mach.
≈ 2 sectors
Install shunts
> 2 sectors
ELQCafter shunt
> 2 sectors
Insulate splices
≈ 1.7 sectors
Weld M
≈ 1.3 sectors
Leak test M
≈ 1 sector
Close IC
≈ 1/4 sector
Final LT
Started
Consolidate Q diodes
≈ 1.7 sectors
Availability of components