Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project. SMACC Fifth report [20 min ] 28/06/2013. Activities since last LSC (14/06/2013) Status of SMACC-QA (R Ostojic’s presentation) Activities for the next 2 weeks Considerations on progress and planning Conclusions. - PowerPoint PPT PresentationTRANSCRIPT
SMACC Fifth report[20 min ]
28/06/2013
Jean-Philippe Tock (TE-MSC)
On behalf of the SMACC project
Activities since last LSC (14/06/2013)Status of SMACC-QA (R Ostojic’s presentation)
Activities for the next 2 weeks
Considerations on progress and planning
Conclusions
JPh Tock4/26
SMACC Main activities for the next 2 weeks Sector 56 :
Continuation of on-going activities (Arcs and DFBAs with restart of broaching)
Restart welding at a substantial speed
Complete electrical measurements on the quadrupole diodes
Sector 67
Complete the opening of the M-lines
Complete the opening of the quadrupole diode containers & start electrical measurements
Perform ElQC on present splices
Sector 78
Continue installation of DN200
Start opening of IC (> 50 % have already W-bellows opened to allow DN200 installation)
Sector 12
Disconnect cryodipoles to be replaced (Rate : 1-2 per week)
(Objective: All 18 cryomagnets disconnected for end of August 2013)
Other sectors:
Special interventions/investigations
Welding restarted in 56, see next slide
Also started in 81 for advanced info on existing splices
Opening of diode containers also in 78
> 70% (#123) are installed
142 ICs are completely opened + 50 W bellows opened
All (#6) are disconnected, starting in S23 (#2)
From last LSC (14.06.2013)
Was presented last LSC by L Grand-Clement
JPh Tock5/26
SMACC Progress report Activities since last LSC
Opened interconnections in 8 sectors, almost equivalent to 4 sectors
Some team members will reinforce ELQC and DN200 activities
JPh Tock6/26
SMACC Progress report Activities since last LSC
ELQC measurements
See R Ostojic’s presentation
Critical NC LHC-QN-QBBI.A21L6-M2-Int-cable
Investigations are on-going (not top priority)
Less critical outlier in S45: Magnetistaion
results shows that there is no significant Ic
degradation. (Detailed report at a further LSC)
Conservative measure:
Investigate other outliers (Open IC,
open M, (enhanced) ELQC but NO
splices desoldering [Limited spare
availability] (Not top priority)
JPh Tock7/26
SMACC Progress report Activities since last LSC
Quadrupole diodes
S56 & 67 opened, 23/51 opened S78
One component (Inconel threaded piece) is expected to be delivered next week
[Delay for starting the actual consolidation, progress on opening diodes containers]
NC corrected, validated by electrical tests
Courtesy L Grand-Clement
JPh Tock8/26
SMACC Progress report Activities since last LSC
M insulation installation
68 ICs equipped (See issue with interference with M lines) [Was 52 2 weeks ago]
ELQC procedure updated
See Ranko’s presentation
M-welding
18 ICs released beginning of the week. (6 where only M3 has to be welded):
Now 4 remains / 10 were welded this week, not yet controlled
10 more could potentially be released if accepted to come back for diode containers
rewelding and the equivalent of 7 more ICs could be released if individuals lines are
welded: Not the optimum use of welding resources but better than not working
JPh Tock9/26
SMACC Progress report Activities since last LSC
DFBA Consolidation
Broaching incident reproduced in workshop conditions
Courtesy R Principe
LSC 31.05.2013 In workshop, at 318 bars (Now pressure limited at 150 bars)
Damaged splices have been desoldered and are under resoldering
Broaching to restart next week; on the critical path for DFBA consolidation, not (yet) for SMACC
JPh Tock10/26
SMACC Progress report Activities since last LSC
DFBA Consolidation : RCS.A56B2 (DFBAK and 11 other ones)
MP3 recommendation presented by M Modena at last LSC
Proposal was presented and approved by MP3 this week
Courtesy A Perin
PEEK protection (optional, 2 halves)
Spacer to avoid overheating (concept)
PEEK protection (2 halves)
Perimetral glass-epoxy foil protection (0.5 mm thickn.)
- function: protection againts wear and insulation if damage- smooth insulating surfaces- minimal thickness to avoid deforming the busbars (≤ 2 mm)- strong and very resistant to wear- avoid overheating (being validated)
JPh Tock11/26
SMACC Progress report : Dashboards
Forecast 4 LSCs ago
Concern : Busbar position and consequent interference between M lines and insulation boxNevertheless, 193 ICs are now equipped with shunts (> 90% of a sector)
Welds not yet entered because not controlled
JPh Tock12/26
SMACC Progress report : Dashboards
Start shunt installation in sector 67.Is it good news?
JPh Tock13/26
SMACC summary status Updated 26-Jun-13
19-Apr-13 212 13-May-13 17-Jun-13 193 19-Jul-13 05-Jul-13 13 08-Aug-13 19-Jul-13 0 15-Aug-13 30-Aug-13 0 27-Sep-13 17-Sep-13 0 25-Oct-13-11 212 -6 -54 212 -41474 -58 212 -41494 -41474 212 -41501 212 212
08-Apr-13 100% 07-May-13 24-Apr-13 91% 08-May-13 6% 0%
16-May-13 211 06-Jun-13 22-Jul-13 13 23-Aug-13 13-Aug-13 0 17-Sep-13 27-Aug-13 0 24-Sep-13 30-Sep-13 0 27-Oct-13 15-Oct-13 0 22-Nov-13-20 211 10 -31 211 -41509 -41499 211 -41534 -41513 211 -41541 -41547 211 -41574 -41562 211 -41600
26-Apr-13 100% 16-Jun-13 21-Jun-13 6%
07-Jun-13 142 27-Jun-13 26-Aug-13 30-Sep-13 18-Sep-13 22-Oct-13 02-Oct-13 29-Oct-13 28-Oct-13 22-Nov-13 12-Nov-13 20-Dec-13-24 212 -41452 -41512 212 -41547 -41535 212 -41569 -41549 212 -41576 -41575 212 -41600 -41590 212 -41628
14-May-13 67%
28-Jun-13 44 18-Jul-13 01-Oct-13 04-Nov-13 23-Oct-13 26-Nov-13 06-Nov-13 03-Dec-13 27-Jan-14 21-Feb-14 11-Feb-14 21-Mar-14-38 212 -41473 -41548 212 -41582 -41570 212 -41604 -41584 212 -41611 -41666 212 -41691 -41681 212 -41719
21-May-13 21%
19-Jul-13 50 08-Aug-13 05-Nov-13 09-Dec-13 27-Nov-13 14-Jan-14 11-Dec-13 21-Jan-14 24-Feb-14 21-Mar-14 11-Mar-14 22-Apr-14-53 212 -41494 -41583 212 -41617 -41605 212 -41653 -41619 212 -41660 -41694 212 -41719 -41709 212 -41751
27-May-13 24%
09-Aug-13 45 29-Aug-13 10-Dec-13 27-Jan-14 20-Jan-14 21-Feb-14 31-Jan-14 27-Feb-14 24-Mar-14 22-Apr-14 08-Apr-14 21-May-14-67 212 -41515 -41618 212 -41666 -41659 212 -41691 -41670 212 -41697 -41722 212 -41751 -41737 212 -41780
03-Jun-13 21%06-Feb-0025-Nov-13 37 13-Dec-13 29-Jan-14 04-Mar-14 24-Feb-14 28-Mar-14 07-Mar-14 03-Apr-14 24-Apr-14 22-May-14 07-May-14 20-Jun-14
-188 212 -41621 -41668 212 -41702 -41694 212 -41726 -41705 212 -41732 -41753 212 -41781 -41766 212 -4181021-May-13 17%
06-Jan-14 30 24-Jan-14 05-Mar-14 08-Apr-14 31-Mar-14 07-May-14 11-Apr-14 13-May-14 22-May-14 20-Jun-14 06-Jun-14 18-Jul-14-255 212 -41663 -41703 212 -41737 -41729 212 -41766 -41740 212 -41772 -41781 212 -41810 -41796 212 -41838
26-Apr-13 14%
19-Apr-13 771 24-Jan-14 17-Jun-13 206 08-Apr-14 05-Jul-13 13 07-May-14 19-Jul-13 0 13-May-14 30-Aug-13 0 20-Jun-14 17-Sep-13 0 18-Jul-14-11 1695 -41663 -54 1695 -41737 -58 1695 -41766 -41474 1695 -41772 -41516 1695 -41810 -41534 1695 -41838
08-Apr-13 45% 24-Apr-13 12% 08-May-13 1% 0% 0% 0%
S34
S45
LHC
S67
S78
S81
S12
S23
ICs Opening
S56
Sleeves Welding M lines Leak Test ICs closure Ins Vac LtestShunts Installation
Planned Start Done Planned End
Delay on Start Total Delay on End
Actual Start % Actual End
On going activity
Ahead of schedule
Late
SMACC Some dashboards
Working on a simplified view
JPh Tock14/26
SMACC Some considerations on progress and planning
Progress:Baseline: 4.4 %Achieved: 8.4 %
Advance: 15 days
JPh Tock15/26
SMACC Some dashboards
JPh Tock16/26
SMACC Some considerations on progress and planning
Progress:Baseline: 14.6 %Achieved: 11.4 %
Delay 10 days
JPh Tock17/26
SMACC Some considerations on progress and planning
Progress:Baseline: 12.3 %Achieved: 6.6 %
Delay 29 days
JPh Tock18/26
SMACC Some considerations on progress and planning
Progress:Baseline: 54 %Achieved: 20 %
Delay 42 days
JPh Tock19/26
SMACC Some considerations on progress and planning
Progress:Baseline: 8.4 %Achieved: 8.9 %
Advance: 1.5 days
JPh Tock20/26
SMACC Some considerations on progress and planning
First sign of the «last 10-20% effect» Non-conformities are left behind to keep
good train progress SIT should become free later to solve
these issues In first sectors, margin wrt pressure test,
Coactivity ! Not in the last ones ! One local NC blocks 1 subsector
(214 m / 16 ICs)
JPh Tock21/26
SMACC Some considerations on progress and planning
Main 13 kA Splices: Started a week in advance, now 2 weeks
Special Interventions: 10 days delay: late release of some sectors (45)
DFBA: 1 month delay: Issue with broaching procedure
DN200: > 1 month delay: late release of sector 78 / Start up difficulties
SMACC: 1.5 days advance (but we started one week in advance)
Only completed activities are accounted for, not the on-going ones Weighting factors are based on initial estimates Achieving baseline rates per activity has to be demonstrated
Sequential processFocus on quality first, then production rates
Mind the last 10 % effect (Minimum consequence on first sectors)
JPh Tock22/26
SMACC Main activities for the next 2 weeksSector 56 :Continuation of on-going activities (Arcs and DFBAs with restart of broaching)Continue welding of M lines at an increased rateInvestigate the overheated cable (21L6)
Sector 67Continuation of on-going activities (Arcs and DFBAs with restart of broaching)Perform ElQC on present splices
Sector 78(Almost) complete installation of DN200Complete opening of ICReconnect the disconnected cryodipoles (#2)
Sector 81Open M lines and perform advanced ELQC on about 20 ICs
Sector 23, (34 or 45 depending on access constraints)Disconnect cryodipoles to be replaced (Rate : 1-2 per week)(Objective: All 18 cryomagnets disconnected for end of August 2013)
Other sectors:Special interventions/investigations
JPh Tock23/26
ConclusionsStrategy under implementation for the higher number of splices
to redo (Teams reinforced)Solution ready for DFBA splices broachingMain concerns :
Interference between insulation box and M lines caused by non-nominal busbars position and impact on welding activities
Overheated cables and high R@ 1.9K investigation to define repair procedureCould require replacement of a magnet
Still within schedule, margin decreasedFocus on quality then production ratesLong way to go … on good tracks with a motivated team
25.06.2013 : Completion of the M lines opening in the second sector (S67)
Courtesy JM Hubert / A Aijaz
24.06.2013 : Thermal shields preparation in 183 : OK for 2 sectors
Courtesy G Barlow