skimming vision system project (4) 6th feb 2015
TRANSCRIPT
Sahaviriya Steel Industries UK
Skimming Vision System Project
JOHN DUNNECHATCHAWAT SAE-JUNGPANYA PHADUNGSANTCHAROENCHAI SRISA-NGA NARIT PHONRAKKHET
Content
1. Introduction2. What is Skimming Vision System3. Trial test skimming Vision System4. Estimate Budget5. Time Line
1.Introduction
Current operation Currently no repeatable standardization on shifts Operator undertakes a visual estimation of slag remaining linked to the aim sulphur. An observation for an aim sulphur of 0.004% the operator skims a minimum of 90% . No recording of individual skimming performance. Longer than required treatment times
Aim & Benefits
Yield improvement Standardization Cost saving Spin off safety benefits Pre and post photo giving evidence on the skim to be compared to the sulphur
specification through the process. The operators are mimicking the learning from station 2 onto station1. Time wasted in over skimming.
2.What is Skimming Vision System? Architecture and Network Diagram ( Figure1).
Figure 1
2.What is Skimming Vision System?The Skimming Vision system for hot metal slag skimming uses a high definition thermal camera to take emission intensity signals from defined region of interest on the image ladle surface ( Figure2)
Figure2
2.What is Skimming Vision System?The Screen visually shows the outline of slag and hot metal in ladle during skimming process. It indicates slag coverage in percent and aim hot metal in percent ( Figure3)
Figure 3
Ownership
3.What is Skimming Vision System?While skimming , the slag coverage decreases. If the coverage reaches the aim target, a sign signal on the screen ( Figure4 ). At this point, the operator stops skimming manually
Figure 4
Skimming weight loss issue The result show that after skimming with thermal camera setting 70%
skim off can reduce the iron skimming loss approximately 1.17 t when compare with history data
3. Trial test skimming Vision System
Current skim loss compared to pre- camera
22772280
22842288
22922295
22992302
23052309
23112316
23202324
23282332
23352339
23422348
23522356
23602364
23710
2
4
6
8
10
12
Iron loss per ladleTotal skim loss Average skim lossLinear (Average skim loss)
Extended Trial
22772280
22842288
22922295
22992302
23052309
23112316
23202324
23282332
23352339
23422348
23522356
23602364
23710
2
4
6
8
10
12
Iron loss per ladle
Iron loss per ladle
Performance During Trial
$145.92
$138.04 $138.37
$147.96
$140.71$142.56
Aver. cost saving/heat ($) by Shift
A Shift B Shift C Shift D Shift E Shift All Shift
Benefits Reduce iron loss More accuracy slag skimming Ladle temperature analysis can apply in the future Increased iron units charged to the vessel and reduce the quantity of desulph slag going to HARSCO
The benefit below can changeable depend on cost of HM and the number of iron loss we saved.
3.In summary, Trial test skimming Vision System
Assumption save actual iron loss after install camera
heat produce/day save iron(t) accum saving/day (t) year saving(t) cost saving/y ($)
35 1.2560 43.96 15,605.9 $1,779,078.06
Saving per shift
8 Day Periods :
27/01/2015 - 03/02/2015
2. Accumulate Skimming Vision System of Desulphur Station2 Report
A Shift B Shift C Shift D Shift E Shift All Shift
Heat Produce Recorded 31 27 9 28 30 125
Aver. Iron loss/heat (t) 0.765 0.698 0.800 0.752 0.815 0.745
Aver. cost saving/heat ($) $128.13 $141.92 $176.07 $182.65 $128.20 $141.45
Iron Loss Saving (t) 38.489 35.134 10.811 34.585 35.438 154.456
Cost Saving ($) $4,387.72 $4,005.25 $1,232.48 $3,942.69 $4,039.88 $17,608.013
Saving
History data
Heats skim loss (t) Iron loss (t)50% avg iron loss/ladle (t)
120 800.5 400.25 3.34
Commissioning
126 313 156.5 1.24
Saving iron loss 2.10
$22,432.37
History data
Heats skim loss (t) Iron loss (t) 30% avg iron loss/ladle (t)
120 800.5 240.15 2.00
Commissioning
126 313 93.9 0.75
Saving iron loss 1.256
Cost Saving $18,041.36
4.Estimate Budgetary & Time Schedule
Time Schedule: Mar’15
Work to Progress
System to pick up the quality from the heat number and skimming aim.Look at adapting the CBM to reflect the reduced skimming loss.Construct a professional skimming station control panel to store the computer and monitor.Trial the gull wing skimming heads Install an ultrasonic level sensor in the Coag bulk silo.Audit the system.