simulation-powered building energy management and control system

Upload: victor-nava

Post on 07-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    1/41

    SIMULATION-POWERED BUILDING ENERGY MANAGEMENT AND CONTROL

    SYSTEM

    Sung Hong ParkB.A., University of California, Berkeley, 2005

    THESIS

    Submitted in partial satisfaction ofthe requirements for the degree of

    MASTER OF SCIENCE

    in

    MECHANICAL ENGINEERING

    at

    CALIFORNIA STATE UNIVERSITY, SACRAMENTO

    FALL2010

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    2/41

    ii

    2010

    Sung Hong ParkALL RIGHTS RESERVED

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    3/41

    iii

    SIMULATION-POWERED BUILDING ENERGY MANAGEMENT AND CONTROLSYSTEM

    A Thesis

    by

    Sung Hong Park

    Approved by:

    __________________________________, Committee ChairDr. Dongmei Zhou

    __________________________________, Second ReaderDr. Akihiko Kumagai

    ____________________________Date

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    4/41

    iv

    Student: Sung Hong Park

    I certify that this student has met the requirements for format contained in the University format

    manual, and that this thesis is suitable for shelving in the Library and credit is to be awarded for

    the thesis.

    __________________________, Graduate Coordinator ___________________

    Dr. Kenneth S. Sprott Date

    Department of Mechanical Engineering

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    5/41

    v

    Abstract

    of

    SIMULATION-POWERED BUILDING ENERGY MANAGEMENT AND CONTROL

    SYSTEM

    by

    Sung Hong Park

    As efficiency of the equipment improves, there is a need for more sophisticated control

    over all equipment to achieve a global optimization. The idea of a simulation-powered building

    energy management and control system (SPEMS) to achieve such optimization has interested the

    building retrofit community since the 1980s, but there is still no such system available to

    consumers today.

    In this paper, a 200,000 square foot high-rise office building in San Jose, California, is

    used to demonstrate the SPEMS. For this demonstration, DOE-2.2 building energy simulation

    was used, and the building model was calibrated to the actual electricity meter interval data for

    the year 2007.

    The building simulation showed 2.25% energy reduction and the estimated payback time

    was 11.4 years. This result is significantly different than the 20% energy reduction result by

    Cumali et al. in 1988. The reduction of savings from SPEMS is due to system optimization done

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    6/41

    vi

    through smarter EMCS and higher building efficiency standard set by California Title 24

    Building Code.

    _______________________, Committee ChairDr. Dongmei Zhou

    _______________________Date

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    7/41

    vii

    TABLE OF CONTENTSPage

    List of Tables ................................................................................................................. ix

    List of Figures................................ .......................... .......................... ......................... ....... x

    Chapter

    1. INTRODUCTION .......................... ......................... .......................... ......................... .... 1

    1.1 Let There Be Green Industry ........................................................................ 1

    1.2 Building Energy Efficiency vs. Renewable Energy Sources .............................. 3

    1.3 Further Improvement on Building Energy Efficiency ............... ......................... 5

    2. DOE BUILDING SIMULATION ........................ .......................... ......................... ........ 7

    2.1 DOE-2.2 ........................... ......................... .......................... ......................... .... 7

    2.2 Building Model.............................................. ......................... .......................... 9

    3. SPEMS SIMULATION ............................................... ......................... ......................... 16

    3.1 Simulation Tactics ........................ .......................... ......................... ................ 16

    3.2 Indoor Temperature Set Point Schedule ........................... ......................... ....... 17

    3.2.1 Lunchtime Pre-Cool ....................... .......................... ........................ 17

    3.2.2 Temperature Set-Back ......................... .......................... ................... 20

    3.2.3 The Productive Work Space Temperature and Body Temperature ..... 20

    3.3 Running the Simulation at Optimal Indoor Temperature Set Points .................. 22

    4. COST EFFECTIVENESS STUDY .......................... .......................... .......................... .. 26

    4.1 Implementation Cost .......................... ......................... .......................... ........... 26

    4.2 Cost Effectiveness ......................................... ......................... ......................... 26

    5. CONCLUSION AND THE FUTURE OF BUILDING CONTROL ......................... ....... 28

    5.1 Conclusion ...................................................................................................... 28

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    8/41

    viii

    5.2 Comparison with Other Studies........................................ ......................... ....... 28

    5.3 Sources of Error............................................................................................... 28

    5.4 Future Work of Building Control ........................ .......................... ................... 29

    References ......................................................................................................................... 30

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    9/41

    ix

    LIST OF TABLES

    Page

    1. Table 1: The Office of Energy Efficiency and Renewable Energy (EERE) Budget .. 2

    2. Table 2: Energy Consumption Comparison ... 25

    3. Table 3: Estimated Cost of the Project ... 26

    4. Table 4: Economical Summary .. 27

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    10/41

    x

    LIST OF FIGURES

    Page

    1. Figure 1: EMCS Evolution..... 6

    2. Figure 2: DOE-2.2 Simulation Flow....... 8

    3. Figure 3: Aerial View of Legacy Civic Towers Building... 9

    4. Figure 4: Annual Average Hourly Load Profile.... 11

    5. Figure 5: Annual Average Hourly Load Profile by End-Use ...12

    6. Figure 6: Annual Energy Consumption..... 13

    7. Figure 7: Simulated Building Energy Consumption by End-Use..14

    8. Figure 8: CEUS Large Office Building Energy Consumption by End-Use..15

    9. Figure 9: Weather Independent Internal Load Profile... 17

    10. Figure 10: Cooling Tower Cooling ... 19

    11. Figure 11: 2007 San Jose Outside Wet Bulb Temperature....20

    12. Figure 12: Average Human Body Temperature Profile. 21

    13. Figure 13: Energy Demand from Different Temperature Set Point Schedules.. 22

    14. Figure 14: Energy Demand Profile by Optimal Schedule.. 23

    15. Figure 15: Temperature Set Point Schedule... 24

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    11/41

    1

    Chapter 1

    INTRODUCTION

    1.1 Let There be Green Industry

    The green industry has existed for more than 30 years, since the first oil crisis hit

    the United States. The Department of Energy (DOE) was formed after the first oil crisis

    in 1977 to research renewable energy and to improve energy efficiency. The main focus

    of DOE is to develop alternative energy sources other than fossil fuels, hence majority of

    its budget is allocated in scientific research such as fusion and nuclear physics. While

    DOE focused on the research, the Office of Energy Efficiency and Renewable Energy

    (EERE), an agency under DOE, created the green industry to bring energy efficient

    technologies and renewable energy sources to consumers.

    EERE runs numerous energy efficiency and renewable energy programs and

    historically, put slightly more weight on energy efficiency programs then renewable

    energy programs, until recently, as shown in Table 1.

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    12/41

    2

    Programs2006 Budget 2011 Budget

    $ (thousands) $ (thousands)Biomass and Biorefinery Systems R&D 89,776 220,000

    Building Technologies 68,190 230,698Federal Energy Management Program 18,974 42,272Geothermal Technology 22,762 55,000Hydrogen Technology 153,451 137,000Hydropower 495 40,488Industrial Technologies 55,856 100,000Solar Energy 81,791 302,398Vehicle Technologies 178,351 325,302Weatherization and IntergovernmentalActivities 316,866 385,000Wind Energy 38,333 122,500

    TOTAL 1,024,845 1,960,658Table 1: The Office of Energy Efficiency and Renewable Energy (EERE) Budget [1]

    In 2006, EERE spent approximately 37% on renewable energy research programs

    and 43% on building energy efficiency programs, with more emphasis on the building

    energy efficiency programs. The building energy efficiency programs include: building

    technologies, industrial technologies, weatherization, and intergovernmental activities.

    The building technology program focuses on improving the overall energy

    efficiency of new and existing buildings through research, partnerships, and developing

    tools for various industries. In past years, EERE focused to improve heating, ventilating,

    and air conditioning (HVAC) systems, lighting technology, building design, and other

    building technologies. The industrial technology program encourages industries in the

    U.S. to reduce their energy consumption by running incentive programs to implement

    energy efficient equipment and practices. The weatherization and intergovernmental

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    13/41

    3

    programs are incentive programs designed to encourage implementing energy efficiency

    equipment and practices.

    With the growing concerns about global warming, the general public is now more

    conscious about where the energy they use is coming from and how to conserve to reduce

    their carbon footprint. As a result, renewable energy gains more support and has fueled

    the solar, hydrogen, and wind energy industries. Public demand for renewable energy

    was reflected in the 2011 EERE budget allocation: 37% for energy efficiency and 45%

    for renewable energy. Emphasis has now shifted toward renewable energy.

    1.2 Building Energy Efficiency vs. Renewable Energy Sources

    Improving building energy efficiency and researching renewable energy are both

    effective ways to reduce carbon footprints, but improving building energy efficiency is

    money better spent to reduce our carbon footprint. Lets compare two different ways to

    reduce building electric bill. The first way is to install photovoltaic panels and generate

    20% of building electric bill at the facility. The other method is to install more efficient

    light bulbs to reduce electric demand permanently.

    Photovoltaic panels are the iconic green energy of today and it is a good example

    to address the problems in renewable energy. For an example, if a facility operation

    manager installs photovoltaic (PV) panels to supply 25% of a 14-story office building in

    San Jose, it takes 29 years to break even without tax incentives and additional 6.7 years to

    break even pollutant created during PV panel production. The available solar radiance in

    San Jose is 5.48 kWh/m2/day and that would require 36,339 square feet of photovoltaic

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    14/41

    4

    panels at an average efficiency of 20%. The estimated project cost would be $2.5 million,

    without government incentives [2]. Based on PG&Es Billing Schedule E19S summer

    peak electricity price of 0.15217 dollar per kWh, it would take 29 years without tax

    incentives, ($7,295.41 per month of savings equals 349 months) to break even. If one

    considers that the expected lifetime of photovoltaic system is 25 to 30 years, the building

    would hardly break even on this investment. Another consideration: in the process of

    manufacturing photovoltaic panels, energy has been inputted, this is called embodied

    energy. The payback time for manufacturing photovoltaic panels is 6.7 years [3].

    Including the payback period for embodied energy, photovoltaic panels end up producing

    more of a carbon footprint than if they were not used.

    Building energy efficiency, on the other hand, has better monetary return rate.

    For an example, upgrading lighting equipment is a common retrofit project among many

    businesses. Title 24 requires 1.0 W/square foot for use in office spaces. If a T8 32W

    bulb is used, which is the industry standard for office lighting for 200,000 square feet of

    office space, it would require 6,250 32W 4-foot T8 bulbs ($2.49) to keep the entire space

    at 90 lumens, and a color-rendering index (CRI) of 85. If T5 fixtures were installed

    instead, it would need 6,250 28W 4-foot T5 bulbs ($9.75), effectively reducing 120,000

    kWh per year at a cost of $61,000. It would only take 3 years to break even. The

    payback for the embodied energy of fluorescent light bulbs is only approximately 50

    hours.

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    15/41

    5

    1.3 Further Improvement on Building Energy Efficiency

    Building energy efficiency improvement is a much better monetary and

    environmental return today. For many years, different industries focused on improving

    individual component efficiency. In the last decade, with cheaper and higher processing

    power available, the building energy management control system (EMCS) was developed

    to optimize the whole system efficiency. The first generation of EMCS was focused on

    optimizing performance of the individual HVAC component. Now, EMCS involves the

    broader picture of the HVAC system and optimizes the system based on readings from

    individual components. The modern EMCS can now run an HVAC system based on

    occupancy and equipment schedules, and optimize the system based on those factors.

    SPEMS is the next generation of EMCS, and the idea for this system has

    interested the industry for over 20 years, to further savings from buildings. For the last

    20 years, as shown in Figure 1, EMCS have evolved from traditional component control

    to equipment optimization and HVAC system optimization [4]. The next improvement

    for EMCS is global optimization using computer simulations.

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    16/41

    6

    Figure 1: EMCS Evolution

    In 1988, Cumali et al. implemented simulation-powered building management

    and control systems to actual buildings, and the result showed a 20% energy reduction

    from three large office buildings [5]. The result demonstrated attractive savings, but still,

    no EMCS with building simulation capability is available on the market today.

    In the past 20 years, significant progress has been made in building energy

    efficiency and it is questionable that the same rate of savings could be achieved from a

    modern building. Building codes have become more rigorous: the building must be more

    insulated, EMCS and sensors together achieve HVAC system optimization, system

    component efficiency has been improved, and internal building load has been reduced

    from efficient plug loads. Using DOE 2.2 building energy simulation of calibrated

    building in San Jose, electrical energy savings from the simulation-powered energy

    management and control system (SPEMS) were explored and compared with electrical

    energy savings from study done by Cumali et al.

    Traditional

    Application

    Equipment

    Optimization

    System

    Optimization

    Global

    Optimization

    Sophistication

    Savings

    EMCS Evolution

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    17/41

    7

    Chapter 2

    DOE BUILDING SIMULATION

    2.1 DOE-2.2

    For more than 30 years, building designers and research communities have used

    building energy simulation to create energy efficient buildings, assess energy savings

    from implementing energy efficient measures, and estimate the size of HVAC equipment.

    The DOE building simulation software is the most well-known software in the industry

    for its accuracy and usefulness in designing and retrofitting buildings. The DOE building

    simulation software was developed by James J. Hirsch in collaboration with Lawrence

    Berkeley National Laboratory. From numerous revisions, the current software version is

    DOE-2.2.

    DOE-2.2 software is composed of four subprograms as shown in Figure 2. The

    BDL Processor subprogram takes user input files and accesses a library to generate the

    BDL file. The simulation process uses the BDL file and the local weather data to run the

    LOADS subprogram to simulate the building heat load, then the SYSTEMS subprogram

    simulates the HVAC system load, and finally, the ECONOMICS subprogram calculates

    the hourly energy consumption and its cost [6].

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    18/41

    8

    Figure 2: DOE-2.2 Simulation Flow Chart

    The user input file is composed of the year of building simulation run,

    construction materials, various equipment schedules, building design, HVAC system, and

    building zoning pattern. It has intuitive names of variables more easily readable by a

    human.

    The main purpose of the BDL Processor subprogram is to translate a human-

    readable user input file to a machine-readable BDL file and access a library of material

    properties and various equipment performance curves. The user can simply define the

    construction material, such as Polyurethane insulation, in the user input file, and the BDL

    Processor inserts the thermal properties of Polyurethane from the library to the BDL file.

    It works the same way for equipment components; the user can simply define a chiller

    type in the user input file and the BDL Processor accesses the proper compressor

    performance curve and includes it in the BDL file.

    As previously mentioned, the DOE-2.2 simulates the building using three

    subprograms: LOADS, SYSTEMS, and ECONOMICS. The LOADS subprogram uses a

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    19/41

    9

    BDL file and weather data to calculate the hourly heating and cooling load for a user-

    defined building model based on the weather data provided. The SYSTEMS subprogram

    calculates the HVAC system performance to meet the user-defined heating and cooling

    set point. The ECONOMICS subprogram then calculates the energy consumption and its

    cost based on the LOADS and SYSTEMS results. When the building simulation process

    is complete, DOE-2.2 generates an Output Report.

    2.2 Building Model

    To demonstrate the savings from SPEMS, a DOE-2.2 building model of a real

    building in San Jose was created. The building is Legacy Civic Towers in San Jose, as

    shown in Figure 3. It is a 14-story building with a basement, totaling 200,674 square feet.

    Figure 3: Aerial View of Legacy Civic Towers Building [7]

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    20/41

    10

    The building is open from 6 a.m.to 6 p.m., Monday through Friday. For the last

    two years, the average building occupancy rate was at 60% of its maximum capacity.

    The buildings HVAC system runs at a standard variable air volume with a hot water

    reheat system. One 500-Ton York chiller and one 250-Ton Trane chiller supply cools the

    chilled water loop, while two gas furnaces heat the hot water loop.

    This building was chosen because it is a good representation of a typical high-rise

    office building in the San Jose area. The facility was built in 1997, during the dot-com

    economic boom era and has participated in multiple PG&E commercial retrofit programs

    to keep the building efficiency up to date.

    Based on the whole facility survey done by ADM Associates, Inc., in 2009, the

    DOE-2.2 building model was created. The whole facility survey includes detailed

    information on building construction, HVAC equipment, plug-in equipment,

    miscellaneous equipment, facility operating schedules, and EMCS operating setup.

    In order to reflect the actual building using a computer model, the model must be

    calibrated based on the actual building energy consumption. By running the DOE-2.2

    simulation of the building model using the year 2007 weather data from National Oceanic

    and Atmospheric Administration (NOAA) and comparing it against the 2007 15-min kW

    interval data from PG&E, the model was calibrated to match within 10% of the actual

    billing data. The calibration involved adjusting occupancy rate, plug-in equipment load,

    and miscellaneous loads.

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    21/41

    11

    Figure 4: Annual Average Hourly Load Profile

    The Figure 4 shows the difference between annual average hourly electric

    demand profile from the electric interval data and the simulation result. The hourly

    profile calibration calibrates building power demand for every hour. The simulation

    hourly profile has an average of a 106% match to the actual building hourly profile. The

    building electric demand is allocated to represent the actual building electric demand as

    shown in Figure 5, below.

    0.00

    50.00

    100.00

    150.00

    200.00

    250.00

    300.00

    350.00400.00

    450.00

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    kW

    Hour

    Annual Average Hourly Load Profile

    Billing Data

    Simulation

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    22/41

    12

    Figure 5: Annual Average Hourly Load Profile by End-Use

    The building electric demand is broken up into seven different end-use categories:

    space cool, heat rejection, ventilation, pumps, exterior use, plug loads, and lighting. The

    space cool is the energy demand from chillers; heat rejection is the energy used by

    cooling tower; ventilation is the energy demand from air handling units and exhaust fans;

    pumps are the energy consumed by various hydro pumps associated the HVAC system

    and domestic hot water; exterior use is the buildings exterior lighting; plug loads are

    miscellaneous equipment connected to building via electrical outlet; and lighting is the

    demand from lighting fixtures.

    This building houses a server room that is running 24 hours a day, seven days a

    week, therefore at night, the building still demands approximately 160 kW. The majority

    of that demand is from the mainframe computers and cooling associated with them. The

    0

    50

    100

    150

    200

    250

    300

    350

    400

    450

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    kW

    Hour

    Annual Average Hourly Load Profile by End-Use

    Space Cool

    Heat

    Rejection

    Ventilation

    Pumps

    Exterior Use

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    23/41

    13

    plot also shows slowly increasing demand at 6 a.m.as employees come to work and

    slowly decreases at 5 p.m.as employees leave.

    Once the hourly electric demand is calibrated, the next step is to calibrate electric

    energy consumption. The hourly profile gives a daily demand of the electricity, whereas

    the annual electric energy consumption gives the monthly profile of electricity

    consumption. Figure 6 presents the comparison of annual electric energy consumption

    between 2007 Bills and simulation results. On average, the simulation electric energy

    consumption agrees to the actual electric bills by 101%.

    Figure 6: Annual Energy Consumption

    -

    50,000

    100,000

    150,000

    200,000

    250,000

    1 2 3 4 5 6 7 8 9 10 11 12

    kW

    h

    Month

    Annual Energy Consumption

    2007 Bills

    Simulation Result

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    24/41

    14

    Figure 7: Simulated Building Energy Consumption by End-Use

    The buildings annual electric energy consumption by end-use is shown in Figure

    7 above. For this particular building, the plug load is the largest part of the annual

    electric consumption, at 37%. HVAC equipment, a combination of space cool, heat

    rejection, ventilation, and pumps, is the second largest, at 36%. The lighting fixtures take

    up 25% and the exterior lights make up the last 2%. This ratio is comparable to Itrons

    California Commercial End-Use Survey (CEUS) result of large office buildings in

    California shown in Figure 8.

    Space Cool

    10%

    Heat Rejection

    0%

    Ventilation

    12%

    Pumps

    14%

    Exterior Use

    2%

    Plug Loads

    37%

    Lights

    25%

    Energy Consumption by End-Use

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    25/41

    15

    Figure 8: CEUS Large Office Building Energy Consumption by End-Use [8]

    The difference in plug loads by comparing results in Figure 7 and Figure 8 comes

    from the mainframe computer hosted at the Legacy Partners building. The mainframe

    server computers run 24 hours a day, seven days a week, and therefore take up large

    portions of the total consumption. The general office building in CEUS does not include

    facilities with mainframe servers; rather it categorizes separately as high-tech facility.

    HVAC

    42%

    Exterior Use

    3%

    Plug Loads

    30%

    Lighting

    25%

    CEUS End-Use Consumption

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    26/41

    16

    Chapter 3

    SPEMS SIMULATION

    3.1 Simulation Tactics

    The simulation of the simulation-powered energy management and control system

    (SPEMS) is a challenge because there is no function available in DOE-2.2 to simulate

    such EMCS. SPEMS is designed to create numerous temperature schedules and run

    DOE-2.2 simulation, and uses the temperature schedule that saves the most electricity. In

    order to demonstrate the savings from the SPEMS, a simplified approach was taken to

    mimic how SPEMS would control indoor temperature. 20 indoor temperature set point

    schedules were created based on three factors: Outside weather condition, internal loads,

    and the productive workspace temperature. Multiple DOE-2.2 runs were made and the

    schedule with the highest savings for every month was chosen to run.

    The reason for using the indoor temperature set point is that, in the DOE-2.2

    simulation, indoor temperature set point controls the supply of cool air and directly

    controls the HVAC system run-time. The indoor temperature depends on human

    occupancy, plug loads, lighting loads, sunlight, and the latent heat from walls and

    windows. The indoor cooling load varies by time of day. Sunlight and latent heat from

    the walls and windows depend on the weather and it affects the performance of chillers.

    DOE-2.2 runs system optimization at a given condition, and one can lower the

    temperature set point to draw more cooling load inside and indirectly control the chillers

    at any given time. Conversely, one can increase the indoor temperature to rest the

    chillers.

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    27/41

    17

    3.2 Indoor Temperature Set Point Schedule

    The indoor temperature set point schedules were created based on three energy

    savings strategies. The first, is to pre-cool running chillers during lunchtime (Noon to 1

    a.m.) to reduce chiller runtime during the peak time. The second is to start temperature

    set back as occupancy rates drop in the building. The last strategy is to slowly lower the

    temperature set point in the morning until body temperatures reach the optimal level of

    98.6F.

    3.2.1 Lunchtime Pre-Cool

    The lunchtime pre-cool is a strategy to run chillers during lunchtime when there is

    less internal load and when the cooling tower efficiency is higher. During that time, the

    building occupancy drops as employees leave to have lunch. The following plot in

    Figure 9 shows the change in occupancy rate and plug load demand.

    Figure 9: Weather Independent Internal Load Profile

    0%

    20%

    40%

    60%

    80%

    100%

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    %ON

    Hour

    Occupancy

    Lighting

    Equipment

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    28/41

    18

    The lighting equipment tends to be powered on during the business hour in an

    open office configuration because it is ineffective to install occupancy sensors on every

    lighting fixture in an open office space. Therefore, EMCS controls the light in that type

    of office.

    As occupancy rates fall, equipment demand falls due to office equipment going

    into idle mode. For example, personal computers consume less energy when it lowers the

    CPU clock speed to use less CPU and power down monitors when no one is using them.

    Copy machines goes to a sleep mode when they are not used for more than an hour. An

    automatic system like this can bring the plug load down during lunch.

    Outside wet bulb temperature is closely related to cooling tower efficiency and it

    is better to run the tower when the wet bulb temperature is lower. As outside wet bulb

    temperature increases, the cooling capacity on a cooling tower falls, as it becomes

    difficult to remove the heat using the evaporation of water. Figure 10 shows how the

    outside wet bulb temperature affects the cooling capacity of the cooling tower. As the

    wet bulb temperature increases, cooling capacity drops.

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    29/41

    19

    Figure 10: Cooling Tower Cooling Capacity [9]

    Based on the 2007 NOAA San Jose weather record, an average wet bulb

    temperature plot was created as shown in Figure 11. Three average hourly wet bulb

    profiles are displayed: January, July, and the annual average. The outdoor wet bulb

    temperature peaks at 1 p.m., so by reducing the cooling tower run-time during this hour,

    the building can potentially save energy. The January profile is an example of a winter

    wet bulb temperature profile, and the July profile is an example of a summer wet bulb

    temperature profile.

    757

    704

    631

    558

    400

    450

    500

    550

    600

    650

    700

    750

    800

    66 68 70 72

    Coo

    lingCapacityinGPM

    Outside Wet Bulb Temperature

    Cooling Tower Cooling Capacity

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    30/41

    20

    Figure 11: 2007 San Jose Outside Wet Bulb Temperature

    3.2.2 Temperature Set-Back

    Starting at 5 p.m., employees begin to leave work, and the temperature set back

    strategy should begin to reduce chiller run-time. As shown in Figure 9, occupancy,

    lighting, and equipment loads fall after 5 p.m. For example, when the SPEMS predicts

    lower demand ahead, it forces the chillers to run at their highest efficiency even if it is a

    lower cooling supply. If at 4:30 p.m. the internal set point temperature is at 74F and the

    chiller needs to run at 90% load to meet that cooling load, SPEMS can decide to run the

    chiller at 85% load because the chiller efficiency is higher at that load, but it produces

    enough cooled air to keep the internal temperature at 75F.

    3.2.3 The Productive Work Space Temperature and Body Temperature

    The indoor temperature set point and body temperature together are an important

    factor for keeping employees productive and comfortable. In many studies of

    30

    40

    50

    60

    70

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    F

    Hour

    Outside Wet Bulb Temperature

    July

    Average

    January

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    31/41

    21

    productivity at work, researchers found an inverted U-shape relationship centered

    between 72F (22C) and 77F (25C) [10]. As the indoor temperature deviates from

    that range, productivity falls by 2% per every degree Celsius. Hence, the temperature

    between 72F to 77F is the range of temperature and SPEMS can fluctuate without

    sacrificing productivity.

    Thermal comfort is another factor related to work productivity. The comfortable

    temperature is relative to the temperature difference between body and ambient. Body

    temperature varies throughout the day; it is lowest at 4 a.m. and highest between 4 p.m. to

    6 p.m. as shown in Figure 12.

    Figure 12: Average Human Body Temperature Profile [11]

    Optimal body temperature is 98.6F. The body feels different depending on if

    body temperature is below or above optimal temperature. In the morning, the body

    97.2

    97.4

    97.6

    97.8

    98.0

    98.2

    98.4

    98.698.8

    99.0

    99.2

    99.4

    99.6

    99.8

    100.0

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Bo

    dyTemperature

    (F)

    Hour

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    32/41

    22

    temperature is below the optimal temperature, therefore, the person prefers a warmer

    ambient temperature until their body temperature reaches the optimal level. Warmer

    ambient temperature minimizes body heat loss so it helps body to reach the optimal level.

    In the afternoon, the body temperature is well above optimal levels, so the cooler ambient

    temperature feels better as it helps the body to regulate its temperature.

    3.3 Running the Simulation at Optimal Indoor Temperature Set Points

    Based on the three energy saving strategies described in the previous section, 20

    temperature schedules were created and compared against the baseline. Based on

    independent DOE-2.2 runs of different temperature schedules, SPEMS chooses the

    optimal temperature schedule to run the building.

    Figure 13: Energy Demand from Different Temperature Set Point Schedules

    Figure 13 shows hourly demand for a 2007 peak day average. The peak day was

    defined by California Public Utilities Commission (CPUC), the hottest three consecutive

    100

    200

    300

    400

    500

    600

    700

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    kW

    Hour

    Energy Demand from Different Temperature Set Point Schedule

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    33/41

    23

    weekdays in 2007, which are July 17 to July 19. As shown above, 20 different

    temperature schedules create different demand profiles. Even with the same temperature

    schedule, depending on the weather, demand can be different.

    Figure 14 compares the peak day average profile to the baseline schedule, the

    75F constant temperature set point schedule, and the July optimal schedule.

    Figure 14: Energy Demand Profile by Optimal Schedule

    In the morning, the optimal schedule demands less energy because lower

    temperature set points provide comfortable temperatures until body temperature reaches

    its optimal 98.6F. The cooling load continues to increase throughout the morning to

    cool the building until noon. From noon to 2 p.m., the energy demand stays constant as

    the pre-cool pays off by slowly increasing the temperature set point. At 4 p.m., SPEMS

    anticipates the lower cooling demand after 5 p.m. and starts the set back process.

    100

    200

    300

    400

    500

    600

    700

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    kW

    Hour

    Energy Demand Profile by Optimal Schedule

    Baseline75F

    Optimum

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    34/41

    24

    The average indoor temperature set point for the July optimal schedule during

    business hours is 74.8F but the average indoor temperature between 11 a.m. and 4 p.m.

    is 72.5F. The plot in Figure 15 shows the difference between the baseline and optimal

    temperature set point schedules.

    Figure 15: Temperature Set Point Schedule

    The result of running SPEMS on the building mode is presented in Table 2. The

    annual energy savings from the SPEMS is 52,254.36 kWh, which is a 2.25% energy

    reduction. The building is in PG&E rate schedule E19S, which charges $0.15217 per

    kWh during the summer. The monetary annual savings is $7,951.55.

    65

    70

    75

    80

    85

    90

    1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

    Temp

    (F)

    Hour

    Temperature Setpoint

    Optimum Schedule

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    35/41

    25

    Month Baseline(kWh)

    SPEMS(kWh)

    Savings(kWh)

    % Reduction

    Jan 178,360.69 175,152.61 3,208.08 1.80%Feb 161,804.56 159,092.47 2,712.08 1.68%

    Mar 190,674.90 186,478.07 4,196.83 2.20%

    Apr 185,931.65 180,807.08 5,124.57 2.76%

    May 204,114.26 197,789.72 6,324.54 3.10%

    Jun 205,737.04 200,071.64 5,665.40 2.75%

    Jul 220,771.72 215,409.32 5,362.39 2.43%

    Aug 227,791.59 221,881.21 5,910.38 2.59%

    Seo 198,779.49 195,799.50 2,979.99 1.50%

    Oct 196,154.30 191,964.31 4,189.99 2.14%

    Nov 177,464.92 172,974.90 4,490.02 2.53%

    Dec 175,102.85 173,012.75 2,090.09 1.19%

    TOTAL 2,322,687.96 2,270,433.59 52,254.36 2.25%

    Table 2: Energy Consumption Comparison

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    36/41

    26

    Chapter 4

    COST EFFECTIVENESS STUDY

    4.1 Implementation Cost

    The estimated cost of implementing SPEMS is $90,480.00 for a 200,000 square

    foot office building. The cost breakdown is listed in Since there are no EMCS with

    building simulation available to the consumer today, a control engineer must integrate the

    building simulation to the existing EMCS. More sensors are required to be installed on-

    site to provide more feedback to SPEMS. In order to create a building model, a full

    building audit is needed. On top of the cost of implementing the SPEMS, there is also

    cost involved to commission the project, creating a report and a user manual, and training

    employees.

    Components Material ($) Hours Rate ($/hour) T&M Cost ($)

    Integration with BAS/EMS 5,000.00 80 120 14,600.00Sensor Installation 15,000.00 240 60 29,400.00Building Audit 1,000.00 80 120 10,600.00Computer Modeling 160 120 19,200.00Commissioning 80 120 9,600.00Report/manual 1,000.00 40 80 4,200.00Training 24 120 2,880.00

    Total Cost ($) 90,480.00

    Table 3: Estimated Cost of the Project

    4.2 Cost Effectiveness

    Table 4 provides the economical summary and indicates that SPEMS

    implementation requires 11.4 years to break even, based on annual energy savings. The

    Database for Energy Efficiency Resources (DEER) estimates the expected useful life of

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    37/41

    27

    typical HVAC equipment at 15 years and the SPEMS can break even before its predicted

    lifetime.

    Cost $90,480

    Energy Savings 52 MWhAnnual Cost Savings $7,952

    Simple Payback Time 11.4 year

    Table 4: Economical Summary

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    38/41

    28

    Chapter 5

    CONCLUSION AND THE FUTURE OF BUILDING CONTROL

    5.1 Conclusion

    The payback period for SPEMS is 11.4 years which makes it difficult to sell to

    customers because a payback period over 10 years is considered to be too long. Because

    of the sophistication of the SPEMS implementation, cost is high as shown in Chapter 4.

    In order to market proliferate SPEMS, the payback period needs to be less than 3 years,

    and otherwise facility managers find it difficult to justify the project cost.

    5.2 Comparison with Other Studies

    Unfortunately, SPEMS showed only a 2.25% energy reduction from the Legacy

    Civic Towers building. In 1988, Cumali et al. implemented simulation-powered EMCS

    on three large office buildings and they were able to achieve a 20% energy reduction.

    The major source of this discrepancy between these two numbers is from the building

    code of higher efficiency standard enforced by local governments. A modern building,

    like Legacy Civic Towers, has better insulation, better glazing, more efficient office

    equipment, and more efficient HVAC components. Along with these technological

    improvements, EMCS can optimize the system, so savings from global optimization have

    diminished compared to Cumalis experiment in 1988.

    5.3 Sources of Error

    In this analysis, the SPEMS were simplified and it may not demonstrate its full

    capability. The proper way to simulate the SPEMS, temperature schedule and energy

    consumption should be a multi-variable function, and SPEMS should run numerous

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    39/41

    29

    DOE-2.2 simulationsiteratively to find the optimal temperature schedule. SPEMS should

    create a new optimized schedule on a daily basis.In this paper, for simplicity, monthly

    optimized schedules were created.

    5.4 Future Work of Building Control

    It was difficult to create a DOE-2.2 simulation of SPEMS as envisioned by author

    of this paper. The SPEMS of the future should be able to communicate with local

    weather stations and the utility companys server. Employees in the building would have

    a radio frequency identification (RFID) card so the SPEMS can monitor building

    occupancy level. Based on the building occupancy, SPEMS could shut down lights and

    plug loads in vacant rooms, also estimating the cooling load required for the next hour.

    SPEMS also would monitor indoor CO2 levels to control the percent of outside air intake

    and air recirculation to minimize the quantity of air to be conditioned. The local weather

    data could be automatically downloaded by SPEMS and used on its DOE-2.2 simulation

    runs. The building could have photovoltaic panels, and based on an hourly electric rate,

    SPEMS can decide whether to store, sell, or use the electricity being generated. If all

    these capabilities were simulated, the savings could be large enough to be worth

    implementing SPEMS on all buildings.

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    40/41

    30

    REFERENCES

    1. Office of Chief Financial Officer.Department of Energy FY 2011 Congrational BudgetRequest. Washington DC: Depart of Energy, 2010, 25.

    2. Cooler Planet. Cooler Planet. http://solar.coolerplanet.com/Articles/solar-calculator.aspx(accessed June 23, 2010).

    3. Corkish, Richard. "Can Solar Cells Ever Recapture the Energy Invested in theirManufacture?" Solar Progress (Photovoltaics Special Research Center), 1997: 16-17.

    4. Thielman, Davis. "System Optimization - The Global Approach to HVAC Control." FirstSymposium. 1984.

    5. Cumali, Z. "Global Optimization of HVAC System Operations in Real Time."ASHRAETransaction 94(1), 1988: 729-1744.

    6. Simulation Research Group.DOE-2 Home. http://gundog.lbl.gov/dirsoft/d2whatis.html(accessed June 23, 2010).

    7. Microsoft.Bing Maps. http://www.bing.com/maps/ (accessed July 30, 2010).8. Itron, Inc. California Commerical End-Use Survey. Consultant Report, Itron, Inc, 2006,

    158.

    9. Evapco. "LSTB/LPT Forced Draft Cooling Towers." Evapco, 22.

    10.Encyclopaedia Britannica.Animal Heat. Vol. 2, inEncyclopaedia Britannica, 11thEdition, 49. 1911.

    11.Seppanen, Olli, William J. Fisk, and David Faulkner. Control of Temperature for Healthand Productivity in Offices. Institute of Heating Ventilating and Air Conditioning,

  • 8/3/2019 Simulation-powered Building Energy Management and Control System

    41/41

    31

    Helsinki Univsersity of Technology, Berkeley: Lawrence Berkeley National Laboratory,

    2004, 2.