ID Task Name Duration Start Finish

1 Identify kitting opportunities 3 days? Mon 23/11/15 Wed 25/11/15

2 Verify eBoM's 1 day? Mon 23/11/15 Mon 23/11/15

3 Check routings 1 day? Tue 24/11/15 Tue 24/11/15

4 Identify mBoM 1 day? Wed 25/11/15 Wed 25/11/15

5

6 Standard work 2 days? Thu 26/11/15 Fri 27/11/15

7 Identify correct team centre model 1 day? Thu 26/11/15 Thu 26/11/15

8 Create standard work document 1 day? Fri 27/11/15 Fri 27/11/15

9

10

11

12 Analyse the data to assess the work content in stores 5 days? Mon 30/11/15 Fri 04/12/15

13 Time studies 5 days? Mon 30/11/15 Fri 04/12/15

14

15

16 Routing the BOM ( Bill of materials) to the correct station or operation5 days? Mon 07/12/15 Fri 11/12/15

17 Audit pilot process introduction 5 days? Mon 07/12/15 Fri 11/12/15

18

19

20 Assess the possible changes to SAP viewer 3 days? Mon 14/12/15 Wed 16/12/15

21

22

23 Differenciation part numbers when material has been kitted25 days? Thu 17/12/15 Wed 20/01/16

24 Investigate identification of loose parts vs. assemblies 1 day? Thu 17/12/15 Thu 17/12/15

25

26 Identify kitting processes 5 days Fri 18/12/15 Thu 24/12/15

27 Scheduling requirements 5 days Fri 18/12/15 Thu 24/12/15

28 Generating picking lists 5 days Mon 04/01/16 Fri 08/01/16

29 Stock shortage process 5 days Mon 04/01/16 Fri 08/01/16

30

31 Select efficient and effective solution 4 days Mon 11/01/16 Thu 14/01/16

32 Team review meeting 1 day? Fri 15/01/16 Fri 15/01/16

33 Test the proposed solution 1 day? Mon 18/01/16 Mon 18/01/16

34 Analyse Results 1 day? Tue 19/01/16 Tue 19/01/16

35 Hold review meeting 1 day? Wed 20/01/16 Wed 20/01/16

36

37

38

39

40 Implimentation Phase 35 days? Mon 01/02/16 Fri 18/03/16

41 Documentation and training for employees 1 day? Mon 01/02/16 Mon 01/02/16

42 Identify training needs 2 days Mon 01/02/16 Tue 02/02/16

43 Create training material 10 days Wed 03/02/16 Tue 16/02/16

44 Deliver training 5 days Wed 17/02/16 Tue 23/02/16

45 Create Kitting area in stores 5 days Mon 01/02/16 Fri 05/02/16

46 Create trackside locations for kits 1 day? Tue 01/03/16 Tue 01/03/16

47 Audit new process 5 days Mon 14/03/16 Fri 18/03/16

T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S Nov '15 16 Nov '15 23 Nov '15 30 Nov '15 07 Dec '15 14 Dec '15 21 Dec '15 28 Dec '15 04 Jan '16 11 Jan '16 18 Jan '16 25 Jan '16 01 Feb '16 08 Feb '16 15 Feb '16 22 Feb '16 29 Feb '16 07 Mar '16 14 Mar '16

Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline

Page 1

Project: Gant chart finalDate: Mon 23/11/15