Page 1: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

SHAPING THE NATURAL GAS MARKET OF CYPRUS

NATURAL GAS PUBLIC COMPANY (DEFA)

Dr. Symeon Kassianides Chairman Natural Gas Public Company New York – 11/29/2017

Page 2: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

1. Current Status

2. Gas Imports – Previous Attempts/Processes

3. Latest Developments

1. LNG Supply Options Study

2. CEF Synergy – “CYnergy” Project

3. New LNG Project (LNG Procurement and Infrastructure Development)

4. NG Pipeline Network

4. Way Forward

SHAPING THE NATURAL GAS MARKET OF CYPRUS

2

Page 3: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

• Cyprus has an energy isolated market (no interconnected capacity)

• High Dependency on Liquid Fuels (Power Gen)

• 3 Main Conventional Power Stations Owned by EAC, Total 1478MW

• Dual fuel (LF & NG) generation capacity 830MW at VPS

• Increasing Renewable Penetration (Solar, Wind)

• NG Market Regulation under CERA

• Cyprus Law - Harmonised with EU Directive 2009/73/EC

• Derogations may apply due to Isolation & Emergent Market

• Possible monopolistic operation for early years

1. CURRENT STATUS

3

Page 4: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

• 3 Previous Attempts

• The first was for a Long Term LNG Supply & On-Shore Regas Terminal

• Following Leviathan And Aphrodite Discoveries, 2 additional Interim Gas Supply Processes for the period up to indigenous gas arrival

• The unsuccessful conclusion reasons of the processes were analysed, indicating the main issues that must be dealt with for the future – Duration

– Quantities

– High Demand in Flexibility

– Prevailing market conditions at the time

4

2. GAS IMPORTS – PREVIOUS ATTEMPTS / PROCESSES

Page 5: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.1. DEFA’s LNG Supply Options Study – Target: NG supply by 2020, due to environmental constraints relating to emission

limits

– DEFA analysed and compared all options for LNG Supply

– Optimum way forward (accounting for cost, time, flexibility) is through floating storage and regas facilities

5

3. LATEST DEVELOPMENTS

Page 6: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.2. CEF Synergy – “CYnergy” Project – Holistic Approach for NG Market development and penetration of use of NG to

Energy and Transport sectors

– Total Proposal Cost ≈€7,5m – CEF EU Co-financing ≈€4,5m (60%)

– Implementation of CYnergy proposal is aligned with NG supply target date – by 2020

– All CYnergy resources have been mobilised and successfully submitted a CEF Energy Proposal for Infrastructure Development of the PCI “CyprusGas2EU” and the timely completion of the project

6

3. LATEST DEVELOPMENTS

Page 7: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.3. New LNG Project (LNG Procurement and Infrastructure Development) – 2 Separate processes

• LNG Procurement, Public Tender to be announced by Q1 2018

• Infrastructure Development, Public Tender to be announced by Q1-Q2 2018

– LNG Project infrastructure requirements have been included in the new CEF Energy Call proposal submission by MECIT, MTCW, DEFA, CPA aiming to secure a grant for the PCI CyprusGas2EU

7

3. LATEST DEVELOPMENTS

Page 8: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.3. New LNG Project - Infrastructure Requirements – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for

the FSRU

– Floating Storage and Regasification Unit (FSRU) – Gas export system and Loading Arm (inclusive of; meters, Gas compressors, filters, heaters, venting system, quick connection, export arm pipelines), permanently berthed in Vassilikos bay

– Jetty borne Gas Pipeline (inclusive of; gas pipelines, valves) connecting the FSRU to the receiving point onshore

– Onshore Gas Pipeline (inclusive of; pipeline, inline valves, cathodic protection systems, civil works), connecting the receiving point onshore to the downstream delivery point

– Pipeline Storage Array (inclusive of; inlet and outlet manifolds, inline valves, protection systems, civil works), able to store Natural Gas in gaseous form in the required operational pressure ranges adjacent to Vassilikos power station

– Onshore Above Ground Installation (AGI) – Metering Station

8

3. LATEST DEVELOPMENTS

Page 9: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.3. New LNG Project – Project Layout

9

3. LATEST DEVELOPMENTS

Page 10: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.3. New LNG Project – Preliminary Cost Estimate – Consultation with all Cypriot Operating

Financial Institutions

– 10 LoIs have been received

– GoC Decision for Electricity Authority of Cyprus (EAC) participation in the infrastructure SPV, up to 30%

– EAC provided a LoI

10

3. LATEST DEVELOPMENTS

Total

(in EUR)

FSRU & Metering Station 150.664.052

Offshore Pipeline 11.589.542

Local Buffer & Onshore Pipeline 11.589.542

Jetty/Tresle Structure 54.199.346

Breasting & Mooring Dolphins 16.209.150

Loading/Unloading Platforms 16.715.686

Breakwater Extension 41.839.869

Jetty Structure for the Emergency Shelter

1.013.072

Shelter Breasting & Mooring Dolphins 6.179.739

Dredging 20.000.000

Leeside Breakwater 10.000.000

Total Investment Cost 340.000.000

Page 11: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.4. NG Pipeline Network – DEFA appointed GNFe for Engineering Consultancy Services for the NG Pipeline

Network Development in 2010

– Feasibility Study completed in 2012

• Revised in 2016-2017

11

3. LATEST DEVELOPMENTS

Page 12: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.4. NG Pipeline Network – Various Studies are

included in the Feasibility Study

• Gas Demand

• Route Selection

• Network Sizing

• Preliminary EIA & Risk Assessment

• Economic & Financial Analysis

12

3. LATEST DEVELOPMENTS

Page 13: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

3.4. NG Pipeline Network – Phase A’ – Power Gen

– Route Selection

13

3. LATEST DEVELOPMENTS

Page 14: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

• LNG Procurement, Public Tender to be announced by Q1 2018

• Infrastructure Development, Public Tender to be announced by Q1-Q2 2018

• Open Season Process in early 2018, for the determination of demand by all users, committed quantities of NG and spatial allocation users

• FEED for the Pipeline Network (following completion of Open Season and generation expansion plan study of EAC)

16

4. WAY FORWARD

Page 15: SHAPING THE NATURAL GAS MARKET OF CYPRUS€¦ · – Marine Works: Jetty for FSRU berthing and LNG transfer activities and an emergency shelter for the FSRU – Floating Storage and

17