s’hamba sonke business plan
DESCRIPTION
NORTH WEST PROVINCE Department: Public Works, Roads &Transport PRESENTATION TO SELECT COMMITTEE ON APPROPRIATIONS 07 September 2011. S’HAMBA SONKE BUSINESS PLAN. - PowerPoint PPT PresentationTRANSCRIPT
NORTH WEST PROVINCEDepartment: Public Works, Roads
&Transport
PRESENTATION TO SELECT COMMITTEE ON APPROPRIATIONS
07 September 2011
S’HAMBA SONKE BUSINESS PLAN
The Province prepared the Business Plan in March 2011, under the impression that S’hamba Sonke Funding of R501 million would be extra funds over and above the previous years Infrastructure Grant to Provinces (IGP).
In this Plan the Department included Carryovers/ongoing projects, Flood Damages Projects and Accruals. Projecting R597 million, R735 million and R828 million for current MTEF.
The plan was later adjusted to reduce the budgets to R501 million, R590 million and R636 million, signed off on 20th April 2011.
The approved plan together with the Gazetted list of projects were published in June 2011.
S’HAMBA SONKE PRMG ALLOCATION
ALLOCATION 2011/12 ALLOCATION R’000
EPWP CONTRACTOR DEVELOPMENT “REPHELELE” – Provincial Road Maintenance
Grant
34,000
Provincial Road Maintenance Grant
467,826
TOTAL PRMG 501,826
National Department of Transport transferred only R57M, received in May 2011. This is less than 25% of the R501M. (We spent the difference from the Provincial allocation)
DESCRIPTION2011/12
2012/13 2013/14
Bojanala 171,354 255,994 287,268
Dr. Ruth Mompati 206,117 202,885 263,277
Ngaka Modiri-Molema
106,865 62,039 16,871
Dr. Kenneth Kaunda
17,490 63,189 30,750
TOTAL MTEF 501,826 584,107 598,166
S’HAMBA SONKE MTEF ALLOCATIONS BY DISTRICTS
PRMG TRANSFERSInstallment Month Received Province
Transfer R’000Actual Amount Received R’000
First Installment
13 May 2011 110,000 (advance)
57,000
Second installment
19 August 2011 33,000 (Roll over)
164,921
Third Installment
11 November 2011
172,742
Fourth Installment
2 February 2012 106,521
National Department of Transport transferred only R57 million in May 2011. This is amount is less than 25% of the R501 million Provincial Cash flow Projections.
R110 million advance came from the Provincial Treasury to make up for the National Treasury Installment transfer shortfall.
PRMG TRANSFERS
BUDGET VS. EXPENDITURE ALLOCATION 2011/12 PROVINCIAL
ROADS MAINTENANCE GRANT (PRMG) R’000
PRMG EXPENDITURE AS AT 31 JULY 2011
R’000
EPWP CONTRACTOR DEVELOPMENT
“REPHELELE” – PRMG
34,000 12,254
PRMG 467,826 89,645
TOTALS 501,826 101,899 (20,3%)
National Department of Transport transferred only R57M, received in May 2011. This is less than 25% of the R501M. (We spent the difference from the Provincial allocation)
PRMG PLAN PROGRESS PROGRESS STATUS NUMBER OF
PROJECTS Committed/cost
estimate AMOUNT Budget AMOUNT
RETENTION 12 R30,931 R30,931
CONSTRUCTION 7 R456,828 R178,869
TENDER STAGE (Advert, Bid Committees etc.)
16 R808,751 R225,586
DESIGN STAGE (Detailed design and tender
specification)
9 R1,041,990 R36,762
PLANNING (Scoping and Preliminary Designs)
23 R1,447,186 R42,161
Emergency Potholes Repairs and Reseal
36 R275,084 R0
Projects on Hold and Suspended
10 R99,200 R70,000
FACTORS CONTRIBUTING TO SPENDING OF THE GRANT
•Capital Projects suspended due to:• insufficient funds in 2009/10 financial year • non-performance of Service Providers (Consultants and Contractors)• budget over commitment
• There’s extra burden of going back to complete incomplete work before starting any new work.
•Approved Projects list for PRMG are not a true reflection of the actual work on the ground.
•Allocation to North West Province is not sufficient to deal speedily with the current backlogs.
FACTORS CONTRIBUTING TO SPENDING OF THE GRANT
Treasury Supply Chain Management Processes
The possible delays in spending the current budget because of the National Treasury Instruction Note affecting bid in excess of R10 million.
Unbundling of projects to allow maximum participation of Emerging Consultants and Constructors maybe construed as avoiding submission of bids over R10 million to Treasury.
FACTORS CONTRIBUTING TO SPENDING OF THE GRANT
The Department makes use of the services of the Capex Programme Manager to complement the current staff shortage.
Filled Positions: 1 Chief Director, 2 Directors, 4 Deputy Directors, 4 Technicians & 1 Assistant Director.
Vacancies: 2 Directors, 11 Deputy Directors,
58 Technicians & 3 Assistant Directors.
Application to HR for filling of critical vacancies is in progress. Current capacity is augmented with the Program Managers and Project Consultants.
– High number of Engineering/Technical staff vacancies.– Approved structure has about 127 posts, only 47 posts
are filled. Excluding Districts’ posts, for implementation
of the maintenance program.
– High staff turnover, vacated funded posts not filled, since
2006.
– Majority of the posts will be advertised before end of September– The structure is also being revised in line with the Mandate of
the Department.
FACTORS CONTRIBUTING TO SPENDING OF THE GRANT
CURRENT TECHNICAL STAFF CAPACITY LEVEL
The Department makes use of the services of the Capex Programme Manager to complement the current staff shortage.
Filled Positions: 1 Chief Director, 2 Directors, 4 Deputy Directors, 4 Technicians & 1 Assistant Director.
Vacancies: 2 Directors, 11 Deputy Directors,
58 Technicians & 3 Assistant Directors.
Application to HR for filling of critical vacancies is in progress. Current capacity is augmented with the Program Managers and Project Consultants.
S’HAMBA SONKE PROGRAMME •The Department initiated a programme War on Potholes in 2009 – using EPWP methods and JET Patchers
•Mahikeng Revitalisation Programme where a budget of R35M was committed to some identified roads within Mahikeng
•The introduction of the S’hamba Sonke Programme came in at the appropriate time when the above programmes were gaining the interest of other Districts within the Province.
•North West DPWRT is planning a massive launch in September which is coupled with handing over of the Mahikeng Roads
PROGRESS ON JOB CREATIONJune 2011
S’hamba Sonke District
Total Number of FTE's Created to Date (1 FTE =230 labour days)
Adult Male
Adult Female
Youth Male
Youth Female
Disabled Total
Bojanala 247.30 72.88 126.18 67.60 1.74 516
Dr Kenneth Kaunda
- - - - - -
Dr Ruth Segomotsi Mompati
71.32 0.92 49.89 1.65 - 124
Ngaka Modiri Molema
77.82 31.32 141.86 79.98 - 331
TOTAL / AVERAGE
396.43 105.12 317.93 149.22 1.74 970
PROGRESS ON JOB CREATIONPROGRAM 5: COMMUNITY BASED PROGRAM
2011/12
ANNUAL
TARGET
1ST QRT
TARGET
1st QRT ACTUAL
NUMBER OF PEOPLE EMPLOYED
10 500 33001100
NUMBER OF EMPLOYMENT DAYS CREATED
74 4000 28 80066 060
NUMBER OF JOBS CREATED10 500 3 300
1 101
NUMBER OF YOUTHS (16-25) EMPLOYED
4 000 2 300440
NUMBER OF WOMEN EMPLOYED
5 200 2 500690
NUMBER OF PLWD110 55
4
SKILLS AND CONTRACTOR DEVELOPMENT
LOCAL MATERIAL AND EQUIPEMENT
LABOUR ABSORPTIVE METHODOLOGIES
LOCAL LABOUR IS EMPLOYED
LABOUR ABSORPTIVE METHODOLOGIES
PLANNED 2011/12 EPWP LEARNERSHIP LABOUR ABSORPTIVE METHODOLOGIES UPRGADING OF ACCESS ROADS( START IN 3RD QRT 2011/12)
Number of Work Opportunities
PROJECT ROAD LENGTH
BUDGET R’000
FTE ESTIMATE CONSTRUCTION
PERIOD D509 between Leeuwdoringstad and Road D1138
5.0 KM 4, 500 19 12 months
D402 between Mokope and Atamelang
6.0 KM 8,265 36 14 months
Upgrading of Road Z554 between Mokgalwaneng and Matlametlong
4.8 KM 7,337 32 12 months
Z422 between Lokaleng and Junction
11.5 KM 7,062 31 24 months
Z469 from junction with road D414 to Disaneng Dam
4.0 KM 6,836 30 10 months
TOTAL 34,000 148
EPWP JOB CREATION
DEPARTMENTAL PROJECTS
NATIONAL YOUTH SERVICE/YOUTH PROGRAMME (NYS)
NATIONAL YOUTH SERVICE/YOUTH PROGRAMME (NYS)
MAFIKENG REVITALIZATION (ORANGE BRIGADE)
ROAD RANGERS
BUILDING MAINTENANCE PROGRAMME
Project Name District Job Creation Comments
Madikwe Traffic office Bojanala 16 446 persons have been employed in these projects. These are all Building Maintenance and Administrative Support Projects. They are implemented by the Departmental Maintenance Teams whereby the Department procures materials, protective clothing and tools. Each person gets paid a daily stipend of R 75, 00.
Garden Maintenance All districts 102Bojanala Revitalisation( car wash, permit board, operating licencing boad, administration) Bojanala 80
Matlametlo Bojanala 15
Bray Road Camp Dr R Mompati 10
Mokgalwaneng Rural Development Bojanala 133
Legal Service Ngaka Modiri 10Molopo Workshop (landscaping & perimeter wall) Ngaka Modiri 30
Molopo Sub-District paving Ngaka Modiri 50 446
SCHOLAR MONITORING PROGRAMME
SCHOLAR MONITORING PROGRAMME
LOBOLOTSE CONTRACTOR DEVELOPMENT PROGRAMME
ITIRELE ROAD MAINTENANCE PROGRAMME
ITIRELE ROAD MAINTENANCE PROGRAMME
THANK YOU