Shaft Sinking with Electronic detonators at the Gautrain Rapid Rail Link Project
Presentation by:C.G. Goncalves DetNet South Africa (Pty) Ltd
Paper by: C.G. Goncalves DetNet South Africa (Pty) LtdS.J. Tose AEL
![Page 2: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/2.jpg)
Outline
• Location• Project Overview• Project Requirements• Geology• Explosives and Initiating Systems• Drilling and Blasting Overview
– Drilling– Charging– Timing
• Blast Results and Benefits• Conclusion
![Page 3: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/3.jpg)
![Page 4: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/4.jpg)
Gautrain Project Overview
• One of the largest civil engineering projects in South Africa’s history
• Construction is being carried out by the Bombela consortium of Bouygues, Murray and Roberts, Bombardier and Strategic Partners Group
• Phase 1 is planned for completion in time for the 2010 FIFA Soccer World Cup
![Page 5: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/5.jpg)
Gautrain Blasting Project Requirements
• A Blasting system that maximises advance and optimises blasting cycles
• An explosives services provider that was able to manage all the requirements associated with transporting, handling, storing and using explosives
• An initiation system and blast design that would minimize air blast and ground vibrations due to environmental constraints
![Page 6: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/6.jpg)
Gautrain Geology
• The underground line encounters two different geological formations namely;– Witwatersand formation
(from Park to E2 shaft)heterogeneous ground composed alternatively of quartzite, siltstone, shales in various degrees of weathering, with water circulation
– Granite formation(from E2 shaft to Marlboro Portal)Granite with all degrees of weathering from soft to sound rock, with some intrusion of diorite (diabase)
![Page 7: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/7.jpg)
Shaft Sinking
AEL’s products for Shaft Sinking.
Products Used:
• Explosives – Pumpable Underground Bulk Emulsion – R100G
• Explosives – Magnum 365 Cartridges (32 x 200mm)
• Initiation System – QuickShot™ Electronic detonators
![Page 8: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/8.jpg)
Explosives
AEL Underground Bulk Systems (UBS)
• State of the art pumpable emulsion formulation
• The system consists of a non explosive base emulsion, which is only sensitised whilst charging
• The ability to store non-explosive base emulsion
• The system optimises safety and security, while dramatically speeding up the charging process
![Page 9: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/9.jpg)
Explosives
AEL Underground Bulk Systems
• Critical diameter - 22mm• The emulsion is cap sensitive and no booster is
required. • Water resistant• High VOD - 4500 m/s in 45mm diameter• Shelf life - 6 to 8 weeks• Repumpability - 6 stages
![Page 10: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/10.jpg)
• R100G – Gassed Emulsion
Explosives
![Page 11: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/11.jpg)
Explosives
• UBS – UV 80 Bulk Charging unit with palfinger crane
• Two charging hoses for efficient charging
![Page 12: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/12.jpg)
Initiating System
QuickShot™ Features:
• Pre programmed (125ms)• Full functionality testing • Daisy chain connection, connected in order of firing • Can fire up to 1200 detonators• Millisecond accurate delays • Inherently safe • Fast to connect up • Automatic delay allocation
![Page 13: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/13.jpg)
Robust, watertight, easy to connect connectors
![Page 14: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/14.jpg)
Fly lead Return Plug
QuickShot
• Easy daisy chain connection
QuickShot
![Page 15: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/15.jpg)
QuickShot splitter
QuickShot pause marker
QuickShot delay marker
![Page 16: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/16.jpg)
Shaft Sinking – Drill and BlastSH E1 SH E2
SH E3 SH E4“Deep”shaft (72m)
“Deep”shaft (45m)
“Shallow”shaft (25m) “Shallow”
shaft (17m)
1270m 1085m 1025m 990m 1020m
RosebankStation
SandtonStation
940m 960m 1150m 1040m
“Deep”shaft (53m)
“Deep”shaft (77m)
“Deep”shaft (67m)
SH E5 SH E6 SH E7
ParkStation
RosebankStation
• Shaft E6 being constructed using the raise boring method. (Shaft diameter of 6.1m)
• Six circular emergency shafts and rectangular station-access shafts employed the traditional top-down (blind sink) shaft sinking method
![Page 17: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/17.jpg)
Rectangular Shafts – Sandton Station
![Page 18: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/18.jpg)
Drilling
• The hole diameters used are either 45 or 48 mm in size.
• Drilling was closely monitored and was identified as one of the critical factors to determine whether a blast has been successful in achieving the required results.
![Page 19: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/19.jpg)
Sleeving for Hole Lining
![Page 20: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/20.jpg)
Sandton South Shaft
![Page 21: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/21.jpg)
Using Cut to Create Free Face
![Page 22: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/22.jpg)
Connecting up a round – Rectangular Shaft
1 4 m s
1 4 m s
14ms
2 8 m s
2 8 m s
2 8 m s
Fly lead one to control box on surface
Fly lead two to control box on surface
Fly lead three to control box on surface
- 14ms Pause Marker
- 28ms Delay Marker
- Splitter
![Page 23: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/23.jpg)
Sandton North Shaft - Connecting up detonators
![Page 24: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/24.jpg)
Sandton North Shaft – Covering the Blast
![Page 25: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/25.jpg)
Emergency Shafts - Circular
![Page 26: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/26.jpg)
E5 Emergency Shaft
• Magnum Explosives Cartridges often used due to space constraints
![Page 27: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/27.jpg)
Connecting up a round – Circular Shaft
Fly lead to control box on surface
First detonator
Delay marker
Fly lead to control box on surface
First Detonator
Delay Marker
![Page 28: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/28.jpg)
Results
• An average advance of 95% - 100 % of drilled length was achieved
• Increased speed of charging and timing operations allowed two blasts per day
• Vibration and Airblast levels within USBM limits
![Page 29: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/29.jpg)
Vibration Limits
AEL vibration levels taken from the USBM
Blasting Situation Recommended Maximum Level (mm/s)
Heavily reinforced concrete structures 120
Property owned by the concern performing blasting operations where minor plaster cracks are acceptable
84
Commercial property in reasonable repair where public concern is not an important consideration
25
Private property if public concern is to be taken into account or if blasting is conducted on a regular and frequent basis
10
![Page 30: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/30.jpg)
31 E
D≥
Vibration Control – an example
• In one case, a sensitive structure was measured at 60m from blasting activity at the base of a construction shaft
• Using the empirical formula;
• And solving for E (mass per delay), the maximum safe mass was calculated to be 3.7kg/delay
• This was achieved using shorter holes and electronic timing to ensure not only single hole firing but also to ensure a minimum of 9ms between each hole.
• No limits were exceeded
![Page 31: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/31.jpg)
AEL Guide for Airblast control
95% confidence could be given that adoption of the recommended measures, in the absence of unforeseen events, e.g. failure along a geological feature, would result in the required control of the airblast i.e. < 134 db.
AEL Guide for Airblast criteria
Level Description
100 dB (2.0 Pa) Barely noticeable
110 dB (6.3 Pa) Readily acceptable
128 dB (50.2 Pa)
Currently accepted by South African authorities as being a
reasonable level for public concern. (No more than 10% of
measurements should exceed this value.)
134 dB (100.2 Pa)
Currently accepted by South African authorities that damage will not
occur below this level. (No measurements should exceed this value
outside of the mining boundaries.)
![Page 32: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/32.jpg)
Recommended measures to limit Environmental Impact
– Adequate stemming – Sequential firing– Charge per delay– Avoid adverse environmental conditions – Time blasts to coincide with peak ambient noise levels.– Use a blast cover. e.g. sand and/or blasting mats– Larger, less frequent blasting
![Page 33: Shaft Sinking with Electronic detonators at the Gautrain](https://reader030.vdocuments.site/reader030/viewer/2022012413/616dc47ece1aa32b4f3c13d7/html5/thumbnails/33.jpg)
Conclusions
• Shafts completed within 33 months and on schedule
• The success of the project was due to a combination of knowledge, application and the use of the correct products to match the robust and challenging conditions.