gautrain - minor amendments _01 12 05_ no 6
TRANSCRIPT
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 1/82
Bohlweki Environmental (Pty) LtdPO Box 11784Vorna ValleyMidrandSouth Africa1686Telephone: 27 011 466 3841
Facsimile: 27 011 466 3849e-mail: [email protected]: www.bohlweki.co.za
GAUTENG DEPARTMENT OF PUBLIC TRANSPORT,
ROADS AND WORKS
REGULATION 9(3) APPLICATION FOR THE AMENDMENT
OF THE RECORD OF DECISION, DATED 25 APRIL 2004,
ON THE GAUTRAIN RAPID RAIL LINK PROJECT
MINOR ROUTE AMENDMENTS:
• Tunnelled section between Park Station, Johannesburg and
the proposed Rosebank and Sandton Stations to the point
where the tunnel is below Mushroom Farm Park, and the
tunnel section between the M1 highway and the Marlboro
tunnel portal.
• The above ground sections from Linbro Park to Rhodesfield,from Linbro Park through Midrand to the Highveld Techno-
Park in Centurion and from the Jean Avenue interchange
with the Ben Schoeman highway in Centurion to the Eeufees
Road interchange in Pretoria.
Draft Report for Public Comment
1 December 2005
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 2/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/05i
TABLE OF CONTENTS
PAGE
1. INTRODUCTION 1
2. MINOR AMENDMENTS TO THE GAUTRAIN ROUTE PROPOSED
BY THE PREFERRED BIDDER
2
3. GROUND-BORNE NOISE AND VIBRATION 4
4. AIRBORNE NOISE 11
4.1 General 11
4.2 Findings 11
5. GEOHYDROLOGICAL IMPACTS 17
5.1 Introduction and Terms of Reference 17
5.2 Comments 17
5.2.1 Park Station to Sandton Station 17
5.2.2 Sandton Station to Marlboro Station 18
5.2.3 Changes in Vertical Alignment and Rail Reserve Width along
the Above-Ground Sections of the Route
18
5.3 Conclusion 19
6. ECOLOGICAL RE-EVALUATION 20
6.1 Introduction 20
6.1.1 Objectives of the Flora / Fauna Ecological Study 20
6.1.2 Scope of Study 20
6.1.3 Methods 21
6.1.4 Constraints / Limitations to the Survey 21
6.2 Description of Prevailing Ecological Environment and StudyAreas 21
6.3 Increased Rail Reserve Width 22
6.4 Sensitive Habitats 29
6.5 Effects of Proposed Increased Rail Reserve and Raised /
Lowered Alignment on the Immediate and Surrounding
Environment
30
6.5.1 Loss of Faunal Habitats 30
6.5.2 Erosion and Possible Siltation / Sedimentation 31
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 3/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/05ii
6.5.3 Migratory Routes 32
6.5.4 Buffer Zones or Biological Corridors 32
6.5.5 Artificial Lighting 33
6.5.6 Horticultural Activities 33
6.5.7 Rescue and Recovery Program 34
6.6 Conclusion and Recommendations 35
7. VISUAL IMPACT 37
7.1 Background 37
7.2 Comparative Assessment Aspects 37
7.3 Methodology and Approach 37
7.4 Comparative Assessment of the Minor Vertical Alignment
Changes
39
7.5 Summary 53
7.6 Mitigation Proposals 53
8. HERITAGE ISSUES 54
8.1 Background 54
9. PUBLIC PARTICIPATION PROCESS 55
10. CONCLUSION 58
APPENDICES
Appendix A: Revised Positioning of Noise Mitigation Measures forMinor Route Amendments
Appendix B: Draft Heritage Report to SAHRA on Station and Tunnel
Portal/Shaft properties affected by the Preferred
Bidder Alignment
Appendix C: Advert for Public participation Process
Appendix D: Background Information Document
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 4/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/051
REGULATION 9(3) APPLICATION FOR THE AMENDMENT OF THE GAUTRAIN
RECORD OF DECISION, DATED 25 APRIL 2004: MINOR ROUTE AMENDMENTS
1. INTRODUCTION
A comprehensive Environmental Impact Assessment (EIA) was undertaken for the
Gautrain Rapid Rail Link project during 2002-2003. The EIA documentation was
submitted to the Gauteng Department of Agriculture, Conservation and Environment
(GDACE), who issued a positive Record of Decision (RoD) in September 2003,
authorising an alignment for the Gautrain. The RoD was amended in April 2004,
following the consideration of appeals submitted in respect of the original RoD. The
amended RoD allowed for public input into the further development of the
Environmental Management Plan (EMP) as the design process became more detailed.
The alignment for the Gautrain, however, remained unchanged from that authorised
in the original RoD.
On July 2, 2005, the Gauteng Premier, Mbhazima Shilowa, announced that a
Preferred Bidder (the Bombela Consortium) had been appointed to undertake the
final design, construction and operation of the Gautrain Rapid Rail Link. The
Preferred Bidder has proposed certain minor horizontal and vertical alignment
amendments to the Gautrain route authorised by GDACE for the sections of the rail
line investigated in this report. Other more substantial changes to the approved
alignment (route variants) will be considered as separate applications to GDACE.
The alignment changes have all been developed by Bombela in its bid to optimise the
rail network from a design and operational perspective.
GDACE has requested the project proponent, the Gauteng Department of Public
Transport, Roads and Works, to apply, in terms of Regulation 9(3) of Government
Notice R1183 under the Environment Conservation Act of 1989 (read with conditions
3.4 (a) and 3.4 (b) of the RoD), in order to present the minor changes to the
alignment to GDACE for consideration.
The proposed approach has been confirmed by GDACE, after the submission of information by the applicant on all of the proposed amendments to the alignment,
including the route variants. The information was provided during various briefing
sessions with GDACE followed by the submission of relevant maps/plans.
The plans/maps of the proposed changes were also made available to the public on a
dedicated website and at public places at the end of October 2005 as part of the
public participation process (see Section 9 below). These maps should be referred to
when reading this report.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 5/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/052
2. MINOR AMENDMENTS TO THE GAUTRAIN ROUTE PROPOSED BY THE
PREFERRED BIDDER
The sections of the route that are included in this report covering the minor routeamendments are:
• Park Station, Johannesburg via Rosebank Station to Mushroom Farm Park, just
after the Sandton Station (tunnel section).
• M1/Marlboro Drive interchange to Marlboro tunnel portal (tunnel section).
• Linbro Park to Midrand Station (above ground section).
• Midrand Station to Highveld Techno-Park, Centurion (above ground section).
• Jean Avenue/Ben Schoeman interchange, Centurion to Eeufees Road, Pretoria
(above ground section).
• Linbro Park to Rhodesfield Station, Kempton Park (above ground section).
The minor route amendments, on which the relevant key specialists involved in the
original EIA (noise, vibration, geohydrological, ecological, visual and heritage) have
been requested to focus as part of this report include:
• A deeper tunnel (up to a maximum of 16m) from Park Station, Johannesburg
(0.0 km) to Parktown Ridge (1.800 km). The tunnel is descending for this length
and will already be more than 25m below ground beneath the tunnel portal at
Park Station, north of Smit Street in Braamfontein.
• A shift of the Johannesburg Park Station footprint to the north, but within the
original rail reserve authorised in the RoD alignment (no new buildings or
properties affected). The same buildings identified in the original EIA will be
demolished. The building situated directly above the tunnel portal at Park
Station, however, has been identified as a heritage structure and it will be
necessary to obtain the approval of the South African Heritage Resources Agency
(SAHRA) to demolish the building. This initial part of the tunnel will now be
constructed as cut and cover as opposed to the open cut envisaged in the
original EIA. A new parking facility will be built over the city block to be
demolished between Wolmarans and Smit Streets. The new Gautrain stationposition will prevent disruption at the existing Park Street station during
construction, whilst allowing for the Gautrain system to be extended in future to
the west via the Braamfontein marshalling yards.
• A slightly shallower tunnel alignment (up to a maximum of 20m) between
Parktown Ridge (1.800 km) and the approach to Rosebank Station (5.500 km).
The tunnel remains deep below the surface under Parktown Ridge (in excess of
40m). At its shallowest point (near the Oxford Road/8th Avenue intersection),
the roof of the tunnel will be 6m below Oxford Road.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 6/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/053
• The use of three erven on the north-eastern side of the Oxford Road/Baker
Street intersection for use as an access and parking facility to Rosebank Station
(requiring the demolition of three buildings, two of which are older than 60 years
that will require approval from SAHRA prior to demolition). It is not possible toprovide parking on the western side of Oxford Road (no land available), whilst
due to services in the vicinity below ground, the parking facility could not be
located underground at Rosebank Station.
• A slightly deeper tunnel (up to a maximum of 8m) from Rosebank Station
(5.900km) to the intersection of 3rd /Melville Roads in Hyde Park (7.700km).
• A slightly shallower tunnel alignment (up to a maximum of 12m) from the
intersection of 3rd /Melville Roads in Hyde Park (7.700 km) to Sandton Station
(10.450 km). The tunnel will however remain 40m below ground or deeper
under this section.
• A slightly shallower tunnel alignment (up to 2m) between Sandton Station
(10.450km) and Mushroom Farm Park (11.100km) and between the M1/Marlboro
Drive interchange (up to a maximum of 5m) to the Marlboro tunnel portal
(15.400km). All the tunnel depth amendments proposed above by Bombela
provide for less steep grades and better operational conditions between stations.
• The final footprint of Sandton Station at the surface (access point) on land owned
by the municipality is currently being negotiated with the City of Johannesburg.
The footprint will require the demolition of the low-rise section of the Sandton
Civic Centre.
• Minor amendments to the width of the rail reserve and the vertical alignment on
the above ground sections listed at the top of previous page. These changes
have been proposed by the Preferred Bidder in order to provide flexibility to
optimize the alignment in the final design process, to allow for the movement of
material as a result of cuts and fills during construction, to ensure sufficient
space to accommodate the angles/toes of slopes and embankments and to allow
access for maintenance during the operational phase. No new properties are
affected by these minor amendments on the above ground sections.
The specialist investigations on the minor route amendments follow:
Section 3: Ground-borne noise and vibrationSection 4: Air-borne noise
Section 5: Geohydrological impacts
Section 6: Ecological re-evaluation
Section 7: Visual impacts
Section 8: Heritage issues
In Section 9, the public participation process followed for these environmental
investigations is described whilst conclusions are drawn in Section 10.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 7/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/054
3. GROUND-BORNE NOISE AND VIBRATION
(Professor Wikus van Niekerk, Jongens, Keet and Associates)
The repositioning of the Gautrain tunnel in Johannesburg at different depths to thoseoriginally proposed in the RoD alignment has been investigated. The original
trajectory, and specifically the depth and geology thereof, was used to predict the
expected ground-borne noise and vibration levels. If the tunnels are repositioned
closer to the surface, the potential to increase the ground-borne noise and vibration
levels to above the limit values proposed in the original EIA does exist. It was
confirmed, however, that no significant change to the ground-borne vibration and
noise levels predicted in the original EIA would occur where the Preferred Bidder’s
alignment is deeper in tunnel.
The alignment proposed by the Preferred Bidder was used to re-evaluate the ground-
borne noise and vibration levels according to the same methodology as that used in
the original impact study. As specific speed-profiles were not available, the original
speed-profile was used, even though it is proposed that the trains will be limited to a
maximum speed of 160 km/h versus the originally proposed top speed of 180 km/h.
This assumption is conservative and therefore the levels may be even lower. (The
reduction from 180 to 160 km/h will result in an overall lowering of the vibration
level by approximately 1 dB(V)).
It was further assumed that there will only be a small deviation from the lateral
alignment of the tunnels and hence the same geological data, as used in the original
impact assessment, was used to recalculate the shallower profile.
The results of the recalculation are compared with the original predictions in Figures
3.1 and 3.2 below.
Figure 3.1 Predicted ground-borne vibration levels in the Johannesburg tunnel
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 8/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/055
Figure 3.2 Predicted ground-borne noise levels in the Johannesburg tunnel
From Figure 3.1 it is clear that a reduced depth will have a very small effect on the
predicted ground-borne vibration levels. In the section from approximately 1 800 to
5 500 metres (from beneath Parktown Ridge north to the Oxford Road/Worcestor
Road intersection), there is a slight increase in the predicted vibration level. This
increase is less than 5 dB(V) and in an area where the predicted vibration levels are
less than 90 dB(V), the level where a human will probably not be able to tell when
vibration is present. The other section where it is proposed to reduce the depth of
the tunnel, from approximately 7 700 to 10 450 metres (from the 3rd Road/Mellville
Road intersection in Hyde Park to the Sandton Station), the tunnel is mostly deeper
than 40 m and therefore the effect on the predicted vibration level is negligible.
The same effect can be seen in Figure 3.2. In the section from approximately 1 800
to 5 500 metres the original alignment was deep enough to enter solid rock most of
the time. With the new Preferred Bidder alignment, the tunnel is much closer to the
interface between solid and weathered rock and hence the newly proposed alignment
results in lower noise levels where the tunnel does not enter the solid rock layer.
(This is due to a penalty in the prediction method, where it is proposed than in solid
rock higher frequency vibrations will be transmitted more effectively than in
weathered rock).
The surface section of the line is dominated by air-borne noise, which is dealt with
separately (see Section 4 below). As far as the effect of the change in the level on
the rest of the line with regard to ground-borne noise and vibration is concerned,
there will only be insignificant changes in the predicted levels.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 9/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April2004:Minor Route Amendments
Bohlweki Environmental 01/12/056
In Tables 3.1 and 3.2, a complete assessment of the effect of the change in levels
along the entire line is provided. It can therefore be concluded that the repositioning
of the Gautrain tunnel alignment closer to the surface will have a very small effect on
the ground-borne noise and vibration levels at the surface. As the slight increase alsooccurs in areas where the predicted ground-borne vibration levels are already well
below the perception level of 90 dB(V), the new vertical alignment will not affect the
conclusions of the original ground-borne noise and vibration impact assessment.
Reference:
Bohlweki Environmental (2002). EIA for the Proposed Gautrain Rapid Rail Link
between Johannesburg, Pretoria and Johannesburg International Airport. Volume 3,
Part 3, Chapter 12: Noise and Vibration Study.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 10/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendments
Bohlweki Environmental 7
TABLE 3.1: JOHANNESBURG TO HATFIELD LINE: EFFECT OF THE BOMBELA (BIDDE
LONGITUDINAL SECTION ALIGNMENT ON THE GROUND-BORNE NOISE AND
AS CALCULATED FOR THE RECORD OF DECISION (RoD) LONGITUDINAL SECT
BIDDER Alignment Effect of Change of
Kilometre RoD Alignment X-Section and Relative Level of BID Ground Borne Vibratio
Distance X-Section Long Section to that of RoD what was calcula
0,000: Park Station
0,000 to 0,500 Cut & Cover BID approx 10m lower No significant change
0,500 to 1,800 Tunnel BID approx same level No significant change
1,800 to 4,800 Tunnel BID up to 27m shallower A possible increase of less
4,800 to 5,200 Tunnel BID approx same level No significant change
5,200 to 6,200 Cut & Cover BID approx same level No significant change
6,000: Rosebank Station
6,200 to 8,000 Tunnel BID approx same level No significant change
8,000 to 9,200 Tunnel BID up to 18m shallower No significant change9,200 to 10,500 Tunnel BID approx same level No significant change
10,500: Sandton Station
9,200 to 10,600 Tunnel BID approx same level No significant change
Excludes the section from Mushroom Farm (km 10,650) to the crossing of the M1 Freeway (km 13,800)
13,800 to 15,200 Tunnel BID approx same level No significant change
Excludes the section from the Marlboro tunnel portal (km 15,200) to a point just east of the N3 Freewa
16,600: Marlboro Station
17,100: RoD overpass of National Road N3 (BID underpass)
17,200 to 17,600 Fill Cut: BID average of 16m lower No significant change
17,600 to 18,000 Cut Cut: BID varies from 14m lower to 0m No significant change
18,000 to 18,100 Cut Cut: BID varies from 0m to 2m higher No significant change18,100 to 18,600 Fill Fill: BID average of 2m higher No significant change
18,600 to 19,000 Cut Cut: BID varying from 2m higher to 0m No significant change
19,000 to 19,700 Cut Cut: BID average of 2m lower No significant change
19,700 to 21,600 Fill Fill: BID approximately same level No significant change
21,600 to 22,400 Cut Cut: BID approximately same level No significant change
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 11/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendments
Bohlweki Environmental 8
BIDDER Alignment Effect of Change of
Kilometre RoD Alignment X-Section and Relative Level of BID Ground Borne Vibra
Distance X-Section Long Section to that of RoD
with what was calc22,400 to 23,500 Fill Fill: BID average of 5m higher No significant change
23,500 to 24,000 Structure(viaduct) Structure/Fill: BID average of 2m higher No significant change24,100: Allandale Road Overpass
24,000 to 25,100 Structure Structure: BID 2m higher No significant change
25,100 to 24,300 Fill Fill: BID average of 2m higher No significant change
24,300 to 25,300 Cut Cut: BID average of 2m higher No significant change
25,300 to 25,900 Cut Cut: BID average of 2m lower No significant change
25,900 to 26,200 Cut Cut: BID average of 3m higher No significant change
26,200 to 26,700 Cut Fill: BID average 5m higher (fill average 1m
high)
No significant change
26,700 to 26,900 Cut Cut: BID varies from 5m higher to 0m No significant change
26,900 to 27,700 Cut Cut: BID average of 3m lower No significant change
26,800: Midrand Station
27,700 to 28,800 Fill Fill: BID average of 0,5m lower No significant change
29,100: New Road Underpass
28,800 to 30,100 Cut Cut: BID average of 3m lower No significant change
30,100 to 30,750 Cut Cut: BID varies from 0m to 7m higher No significant change
30,750 to 31,000 Cut Fill: BID average of 8m higher (fill average1m high)
No significant change
31,000 to 31,700 Cut Cut: BID average of 7m higher (cut av 2mdeep)
No significant change
31,700 to 32,000 Fill Fill: BID varies from 6m higher to 0m No significant change
32,200: Olifantsfontein Road (PWV 5) overpass
32,000 to 32,800 Structure(viaduct)
Structure/Fill: BID average of 4m lower No significant change
32,800 to 33,200 Fill Fill: BID average of 2m lower No significant change
33,500: Road K27/R562 underpass
33,200 to 34,400 Cut Cut: BID approximately same level No significant change
35,100: Samrand Road overpass
34,400 to 35,800 Fill Fill: BID average 2m higher No significant change
35,800 to 36,400 Cut Cut: BID approximately same level No significant change
36,400 to 37,100 Fill Fill: BID approximately same level No significant change
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 12/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendments
Bohlweki Environmental 9
BIDDER AlignmentEffect of Change of L
Kilometre RoD Alignment X-Section and Relative Level of BID Ground Borne Vibrat
Distance X-Section Long Section to that of ROD with what was calcu37,100 to 38,250Cut Cut: BID average 6m higher No significant change
38,250 to 38,900Cut At grade: BID average 5m higher No significant change
38,900 to 39,800Cut Cut: BID approximately same level No significant change
39,800 to 41,800Fill Fill: BID average of 2m higher No significant change
41,800 to 42,000Cut Fill: BID average of 2m higher (fill average1m high)
No significant change
42,000 to 42,200Cut Cut: BID average of 5m lower No significant change
Excludes section through central Centurion from just south of crossing of N1 Freeway (km 42,200) t
Freeway crossing (km 47,800)
43,300: National Road N1
underpass45,300: Centurion Station
47,200: National Road N14 (R28) underpass
47,800 to 48,200Fill Cut: BID average of 8m lower No significant change
48,200 to 50,600Fill Fill: BID average of 6m lower No significant change
50,300: Snake Valley Road
overpass
50,600 to 51,200Fill Fill; BID average of 1m higher No significant change
51,200 to 52,800Cut Cut: BID average of 2m higher No significant change
Excludes section from just south of Eeufees Road (km 52,800) to Hatfield
Station
53,700: Eeufees Road overpass
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 13/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendments
Bohlweki Environmental 10
TABLE 3.2: SANDTON TO JIA LINE: EFFECT OF THE BOMBELA (BIDDER) CHANGES IN LEVEL OALIGNMENT ON THE GROUND-BORNE NOISE AND VIBRATION ENVIRONMENT RECORD OF DECISION (RoD) LONGITUDINAL SECTION ALIGNMENT
BIDDER Alignment Effect of Change
Kilometre RoD Alignment X-Section and Relative Level of BID Ground Borne Vi
Distance X-Section Long Section to that of RoD with what was cThis line starts (kilometre 0,000) approximately 300 metres west of MarlboroStation)
Excludes section from km 0,000 to point just east of National Road N3 (km 1,000)
0,800: National Road N3 Freeway
1,000 to 1,600 Fill Cut: BID average of 16m lower Slight decrease of le
1,600 to 2,150 Cut Cut: BID varies from 14m lower to 0m No significant chang
2,150 to 2,900 Cut Cut: BID average of 1,5m higher No significant chang
2,900 to 4,000 Fill Fill: BID average of 2m higher No significant chang
4,000 to 4,200 Cut Fill: BID average of 2m higher No significant change4,200 to 4,600 Fill Fill: BID average of 2m higher No significant chang
4,600 to 4,780 Cut Cut: BID varies from 2m higher to 0m No significant chang
4,780 to 5,850 Fill Fill: BID varies from 0m to 6m lower to 0m No significant chang
5,850 to 6,050 Fill Fill: BID varies from 0m to 5m higher No significant chang
6,050 to 6,300 Cut Fill: BID average of 9m higher No significant change
6,300 to 6,950 Cut Cut: BID average 8m higher No significant chang
6,950 to 7,600 Fill Fill: BID varies from 4m higher to 0m No significant chang
7,800: Modderfontein Road overpass
7,600 to 8,600 Fill Fill: BID at approximately same level No significant chang
8,600 to 9,350 Cut Cut: BID at approximately same level No significant change
9,350 to 10,650 Fill Fill: BID average of 2m higher No significant chang10,145: Zuurfontein Road overpass
10,650 to 10,900 Cut Cut: BID varies from 1m higher to 0m No significant chang
10,900 to 11,800 Cut Cut: BID average of 2m lower No significant chang
11,800 to 12,400 Cut Cut: Bid average of 3m higher No significant chang
Excludes section from km 12,400 to Rhodesfield Station and JIA Station
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 14/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:MinorRoute Amendments
Bohlweki Environmental 11 1/12/05
4. AIRBORNE NOISE
(Derek Cosijn, Jongens, Keet and Associates)
4.1 General
In this Section, the changes in the airborne noise due to minor changes in the proposed
alignment by the Bombela Consortium (Preferred Bidder alignment) are compared to the
original RoD noise condition. The main changes proposed that may have an impact on
airborne noise have been those in the vertical alignment (longitudinal section). All the
calculation parameters used in the EIA have been kept the same even though it is likely that
some will change in the final analysis (namely the speed profile of the train will reduce and
the height of the cooling fan noise will be lower on the proposed train). Both the
aforementioned factors will reduce the train generated noise profile along certain sections of
the alignment. Thus, the conservative approach adopted in the EIA on calculating potential
noise impacts has been retained.
The detailed analysis of the implications of the changes in alignment proposed by the
Bombela Consortium as related to airborne noise are given in Table 4.1 and Table 4.2.
4.2 Findings
i) In places, the Preferred Bidder alignment introduces level (height) changes to the
RoD vertical alignment. This will alter the noise condition along the relevant section
of the route, in some cases improving the original situation and in other casesworsening it.
ii) Along no section where the noise condition deteriorated, due to level changes, was it
found that the Preferred Bidder noise levels reached were of an order higher than
levels reached in similar situations (namely at similar cross section profiles) for the
RoD alignment.
iii) Where the Preferred Bidder alignment increases the noise level, it is generally stated
as being “not a problem” (or “insignificant”) as the final changed noise level still lies
within the range that can be mitigated (as determined during the EIA).
iv) In general, the Preferred Bidder horizontal alignment indicates a wider rail reserve
on the surface (although no new properties are affected). This, as such, will not
result in any noise increases unless there is to be a significant lateral shift of the
alignment. No such shifts are presently indicated.
v) The additional rail reserve to the west required for a wider maintenance depot and
railway workshops could have noise implications for this area and should be checked
in terms of the proposed mitigation measures through the EMP process, when more
detailed design information is available on the exact location of noise generating
facilities on the maintenance depot site.
vi) In Appendix A, the positioning of the proposed noise mitigation measures to limit
noise impact have been revised to take account of changes in height levels in the
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 15/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:MinorRoute Amendments
Bohlweki Environmental 12 1/12/05
Preferred Bidder alignment. The areas for these revised mitigation measures should
be incorporated into the EMP.
Reference:
Bohlweki Environmental (2002). EIA for the Proposed Gautrain Rapid Rail Link between
Johannesburg, Pretoria and Johannesburg International Airport. Volume 3, Part 3, Chapter
12: Noise and Vibration Study.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 16/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amend
Bohlweki Environmental 13 1/12/05
TABLE 4.1: JOHANNESBURG TO HATFIELD LINE: EFFECT OF THE BOMBELA (BIDDER) CHA
LONGITUDINAL SECTION ALIGNMENT ON THE AIRBORNE NOISE ENVIRONMEN
FOR THE RECORD OF DECISION (RoD) LONGITUDINAL SECTION ALIGNMENT
Kilometre DistanceRoD Alignment
X-Section
BIDDER Alignment
X-Section and Relative Level of BID
Long Section to that of RoD
Effect o
Section)
Calcula
0,000 to 15,000 Tunnel No airborne
Along the tunnel portion of the route, excludes the section from beneath Mushroom Farm (km 1Freeway (km 13,800).
Surface section: Excludes the section from the Marlboro tunnel portal (km 15,200) to a point j17,200)
16,600: Marlboro Station
17,100: RoD overpass of National Road N3 (BID underpass)
17,200 to 17,600 Fill Cut: BID average of 16m lower BID alignm
17,600 to 18,000 Cut Cut: BID varies from 14m lower to 0m BID alignm
18,000 to 18,100 Cut Cut: BID varies from 0m to 2m higher BID alignma problem.
18,100 to 18,600 Fill Fill: BID average of 2m higher BID alignm
18,600 to 19,000 Cut Cut: BID varying from 2m higher to 0mBID alignm
Not a prob
19,000 to 19,700 Cut Cut: BID average of 2m lower BID alignm
19,700 to 21,600 Fill Fill: BID approximately same level BID alignm
21,600 to 22,400 Cut Cut: BID approximately same level BID alignm
22,400 to 23,500 Fill Fill: BID average of 5m higher BID alignm
23,500 to 24,000Structure
(viaduct)Structure/Fill: BID average of 2m higher BID alignm
24,100: Allandale Road Overpass
24,000 to 24,100 Structure Structure: BID 2m higher BID alignm
24,100 to 24,300 Fill Fill: BID average of 2m higher BID alignm
24,300 to 25,300 Cut Cut: BID average of 2m higher BID alignm
25,300 to 25,900 Cut Cut: BID average of 2m lower BID alignm
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 17/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amend
Bohlweki Environmental 14 1/12/05
Kilometre DistanceRoD Alignment
X-Section
BIDDER Alignment
X-Section and Relative Level of BID
Long Section to that of RoD
Effect o
Section)
Calcula
25,900 to 26,200 Cut Cut: BID average of 3m higher BID alignm
26,200 to 26,700 CutFill: BID average 5m higher (fill average
1m high)
BID alignm
a problem.
26,700 to 26,900 Cut Cut: BID varies from 5m higher to 0mBID alignmNot a prob
26,900 to 27,700 Cut Cut: BID average of 3m lower BID alignm
26,800: Midrand Station
27,700 to 28,800 Fill Fill: BID average of 0,5m lower BID alignm
29,100: New Road Underpass
28,800 to 30,100 Cut Cut: BID average of 3m lower BID alignm
30,100 to 30,750 Cut Cut: BID varies from 0m to 7m higherBID alignmNot a prob
30,750 to 31,000 CutFill: BID average of 8m higher (fill
average 1m high)
BID alignm
Not a prob31,000 to 31,700 Cut
Cut: BID average of 7m higher (cut av
2m deep)
BID alignm
Not a prob
31,700 to 32,000 Fill Fill: BID varies from 6m higher to 0m BID alignm
32,200: Olifantsfontein Road (PWV 5) overpass
32,000 to 32,800Structure
(viaduct)Structure/Fill: BID average of 4m lower BID alignm
32,800 to 33,200 Fill Fill: BID average of 2m lower BID alignm
33,500: Road K27/R562 underpass
33,200 to 34,400 Cut Cut: BID approximately same level BID alignm
35,100: Samrand Road overpass
34,400 to 35,800 Fill Fill: BID average 2m higher BID alignm35,800 to 36,400 Cut Cut: BID approximately same level BID alignm
36,400 to 37,100 Fill Fill: BID approximately same level BID alignm
37,100 to 38,250 Cut Cut: BID average 6m higherkm 37,1 tincrease no
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 18/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amend
Bohlweki Environmental 15 1/12/05
Kilometre DistanceRoD Alignment
X-Section
BIDDER Alignment
X-Section and Relative Level of BID
Long Section to that of RoD
Effect o
Section)
Calcula
Km 37,9 t
noise by 6d
38,250 to 38,900 Cut At grade: BID average 5m higher BID alignmNot a prob
38,900 to 39,800 Cut Cut: BID approximately same level BID alignm
39,800 to 41,800 Fill Fill: BID average of 2m higher BID alignm
41,800 to 42,000 CutFill: BID average of 2m higher (fillaverage 1m high)
BID alignm
42,000 to 42,200 Cut Cut: BID average of 5m lower BID alignm
Excludes section through central Centurion from just south of crossing of N1 Freeway (km 42,200) Freeway crossing (km 47,800)
43,300: National Road N1 underpass
45,300: Centurion Station
47,200: National Road N14 (R28) underpass47,800 to 48,200 Fill Cut: BID average of 8m lower BID alignm
48,200 to 50,600 Fill Fill: BID average of 6m lower BID alignm
50,300: Snake Valley Road overpass
50,600 to 51,200 Fill Fill; BID average of 1m higher BID alignm
51,200 to 52,800 Cut Cut: BID average of 2m higher BID alignm
Excludes section from just south of Eeufees Road (km 52,800) to Hatfield Station
53,700: Eeufees Road overpass
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 19/82
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 20/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 17 1/12/05
5. GEOHYDROLOGICAL IMPACTS
(Reinhard Meyer, CSIR Environmentek)
5.1 Introduction and Terms of Reference
• The CSIR Environmentek was approached by Bohlweki Environmental (Pty)
Ltd, to comment on the potential impact that the minor changes to the route
alignment proposed by the Bombela Consortium may have on the geology
and groundwater conditions that may be expected during construction of the
Gautrain Rapid Rail Link. During a meeting at the offices of Bohlweki
Environmental (Pty) Ltd on 23 September 2005, the proposed minor changes
to the route were identified and discussed. The following Terms of Reference
were agreed upon during this meeting:
• CSIR Environmentek will be required to provide comments on whether the
envisaged minor changes to the route and tunnel alignment for specific
sections of the route would impact upon groundwater, or be impacted upon
by groundwater conditions during construction, and also during the
operational stages of the rail link. In addition, we were also requested to
comment on changes to the geological conditions that can be expected. The
following specific sections of the route were identified for review:
Tunnel section between Park Station and Sandton Station
(approx 10.5 km).
Tunnel section between Sandton Station and Marlboro Station
excluding the tunnel variant section between Mushroom Farm
Park and the M1/Marlboro Drive interchange.
Changes in the vertical alignment and rail reserve width along
the above ground sections of the route.
5.2 Comments
5.2.1 Park Station to Sandton Station
Over the first approximately 4 km of this section (Parktown Ridge – Rosebank
Station), the change in vertical alignment reaches its maximum (just over 20m
shallower). This roughly coincides with the section where tunneling will be into
quartzite, shale, conglomerate and lava of the Witwatersrand and Ventersdorp
Supergroups. Although static groundwater levels are of the order of 10m below
ground surface over this section, the aquifer is believed to be semi-confined as
water strikes during drilling are mostly encountered at greater depths, even
below the proposed new tunnel level. The aquifer is further classified as a minor
aquifer (Bohlweki Environmental, 2002). The potential impacts upon groundwater
conditions due to tunneling, as well as the impacts of groundwater upon the
tunneling operation investigated in the original EIA report, will not change; in
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 21/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 18 1/12/05
fact, due to the shallower route of the tunnel, impacts on groundwater from
tunneling may be less than previously envisaged. Should there be a need to
dewater a tunnel section for construction purposes, water levels will be lowered
during the dewatering period, but are expected to return to original static levels
shortly after completion of construction.
Between chainage ~4km and ~10.5km (Sandton Station), the tunnel will be in
granitic rocks and with the tunnel being shallower than the RoD route over this
section (although still at depths exceeding 40m for much of the route), more
weathered/fractured rock conditions can be expected. Should the static water
level over this section be above the roof of the tunnel, slightly more water
seepage can be expected due to somewhat higher hydraulic conductivities in the
more weathered/fractured sections. The mitigation measures provided in the
original EIA report, however, will suffice to deal with this eventuality.
5.2.2 Sandton Station to Marlboro Station
Over this entire section, the route will be tunneled into granitic rocks. Over most
of this section, the proposed new tunnel route is only 2-3m shallower at
maximum than the RoD design, and no significant changes to the groundwater
conditions are expected. Although the difference increases to nearly 5m
(shallower than RoD route) closer to Marlboro station (approximate chainage
15km), no changes in groundwater conditions are expected. Due to the shallower
depth of the tunnel, slightly more weathered and fractured rock conditions can beexpected compared to the RoD route. The mitigation measures provided in the
original EIA report, however, will suffice to deal with this eventuality.
5.2.3 Changes in Vertical Alignment and Rail Reserve Width along the
Above Ground Sections of the Route
The groundwater specialist study for the original EIA considered the impacts on
groundwater conditions over a 2km wide zone around the centrelines of the
proposed route alignments investigated. Although deviations in the vertical
alignment and rail reserve width are now proposed, none of these transgress the
boundaries of the original investigation. It may be possible that new existing
boreholes are now located within this new proposed rail reserve width, but a
detailed survey of infrastructure inside the entire rail reserve still needs to be
conducted during the land acquisition phase. Any additional existing boreholes
that are located within the newly proposed wider rail reserve should also be
identified during this survey. The mitigation measures provided for boreholes
encountered in the rail reserve in the original EIA report will suffice.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 22/82
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 23/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 20 1/12/05
6. ECOLOGICAL RE-EVALUATION
(Clayton Cook, Ecological Specialist)
6.1 Introduction
A brief ecological survey was undertaken for re-evaluation purposes due to the
proposed widening of certain sections of the rail reserve on the surface, as well as
the raised or lowered elevation of certain sections. The survey focused on the
findings of previous specialist surveys undertaken for the EIA of the proposed
Gautrain rapid rail link route (see Volume 4: Biophysical Environment; parts 1
and 2).
Surveys reviewed included:
• Vegetation survey (J. Van Staden)
• Avifaunal (Bird) survey (C.S. Van Rooyen)
• Mammal and Herpetological survey (C.L. Cook)• Invertebrate survey (P.Roos & G. Henning)
• Surface water and wetlands study (G.Marneweck)
The survey focused on the current status of areas identified by the specialists as
containing sensitive habitats, or habitats containing or likely to contain
threatened species of plant or animal within the proposed alignment corridor of
the Gautrain Rapid Rail Link project.
6.1.1. Objectives of the Flora/Faunal Ecological Study
• To determine potential impacts of the increased rail reserve and the raised
or lowered alignment on the fauna and flora.
• To provide management recommendations to mitigate negative and
enhance positive impacts.
• To identify any further issues not raised by the previous surveys.
6.1.2 Scope of Study
•
A brief survey of the selected sensitive sites recording the current statusof the sites and close examination of the areas affected by the increase in
or changes to the proposed rail reserve
• Literature investigations with which to augment field data where
necessary.
• Investigate feasible and practical management recommendations that
should be implemented to reduce or minimise the impacts, should the
changes to the alignment be approved.
• Documentation of the findings of the study in this report.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 24/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 21 1/12/05
6.1.3 Methods
The brief ecological survey focused on the current status of threatened plant or
animal species occurring, or likely to occur, within the proposed adjusted rail
reserves and raised or lowered rail alignment corridor. Due to the fact that a
considerable portion of the rail alignment is either underground or passing
through already transformed habitats, the survey focused on the remaining
natural environments (open grasslands, hillslope seeps, seasonal drainage lines,
rocky outcrops) and not on transformed environments. Special emphasis was
placed on seasonal wetland areas and their surrounding grasslands, as well as
any other sensitive environments. No actual species lists or intensive field
surveys were conducted. Selected sites were surveyed between 7-9th October,
2005.
As the majority of threatened plant and animal species are extremely seasonaland difficult to observe, the presence of suitable habitat was also used to
determine their possible occurrence along the surface sections of the rail
alignments. Fieldwork was heavily augmented with species lists compiled from
previous specialist surveys conducted for the EIA as well as personal records
(Glen Austin and Midrand; 1991-2005) and published data (literature).
6.1.4 Constraints/Limitations to the Survey
• Being limited to a brief base-line ecological survey – two days prior to first
sufficient seasonal rainfall.• Recent fires have resulted in habitat destruction as well as extreme
difficulty in identifying specialised habitats, vegetation etc.
• The majority of threatened species are extremely secretive and difficult to
observe during intensive field surveys.
• The limitations of historic data and available data-bases. Insufficient
knowledge is available on the specific habitat requirements (migratory,
foraging and breeding) of the majority of threatened species.
• The presence of threatened species on site is assessed mainly on previous
specialised surveys as well as habitat availability and suitability.
•
Certain surveys were conducted during the dry winter months which onlyprovide probable species lists.
6.2 Description of Prevailing Ecological Environment and Study Areas
The majority of remaining natural habitats in the rail corridor fall within the
Vegetation Type classified as Rocky Highveld Grassland (Vegetation Type 34; Low
& Rebelo 1996). The Vegetation Type forms part of the Grassland Biome, and
covers an area of approximately 24 062 km2 within South Africa, approximately
65% of which has been transformed and 1,38% of which is currently conserved.
Within Gauteng, Rocky Highveld Grassland covers an area of approximately 9462km2, approximately 2,07% of which is currently conserved. Remaining
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 25/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 22 1/12/05
grasslands are characterised by frequent burning, grass collection, extensive
littering, alien vegetation invasion and are bisected by numerous human
pathways.
6.3. Increased Rail Reserve Width
The increased width to the rail reserve on the surface sections will vary, but the
average will be about 20-30m. On both sides of the servitude, a further 20-50
metres may have to be cleared of large trees, which will mean that an effective
minimum of 60-70 metres will be cleared of large trees. The removal of trees and
other vegetation might have some impact on species breeding and foraging
directly in the servitude. The clearing will, however, also create new habitat. The
run-off from the tracks could result in enhanced grass growth at the edges, which
will in turn draw rodents and insects. The cleared areas adjacent to the rail tracks
will be attractive hunting areas for certain mammals, bird species (raptors),
amphibians, reptiles, insects etc, as it will enhance prey accessibility or habitat
suitability (open habitat).
The area of the proposed increased rail reserve was only surveyed in the
remaining large open grassland areas along the rail corridor. These sites were
also selected in areas where previously threatened or endangered species have
occurred or are likely to still occur. The remaining natural habitats were surveyed
with a special emphasis on identifying any sensitive habitats still in existence, and
the possible occurrence of threatened or endangered fauna and flora.
The large open grasslands selected for the survey are described and reported on
in the following pages.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 26/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 23 1/12/05
Glen Austin A.H. Ext. 3
East of the Jukskei Quarry (Glen Austin A.H. Ext. 3) 26º 01’ 49”S 28º 07’31”E
Open grassland situated adjacent to the Jukskei Quarry, bordering the suburbs of
Buccleuch and the Glen Austin Agricultural Holdings Extension 3. The open
grassland is surrounded by major road networks, including the N1 and the K101.
Existing impacts on the site include:
• Extensive mining at the quarry site.
• Frequent burning of the grassland area.
• Severe headcurr (headward) erosion occurs on sections of the seasonal
drainage line.• Artificial damming of the Jukskei River upstream into a permanent man-
made dam.
• Reed invasion around the edges of the dam.
• The occurrence of extensive grass harvesting/cutting.
• Heavy vehicular traffic restricts certain animal migration (amphibians,
reptiles and mammals).
• Secondary roads bisect the site – including motorcycle, 4x4 bike and 4x4
vehicle routes.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 27/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 24 1/12/05
Suitable foraging, migratory and breeding habitat exists to the east of theproposed rail alignment on the farm Waterval (26°02’11”S 28°07’57”E) for Giant
Bullfrogs and possible African Grass Owls. Bullfrogs breed in the shallow margins
of seasonal pans and sometimes in dams. Bullfrogs may occasionally also breed
in shallow seasonally inundated margins (temporary flood-plain) of the drainage
line on the farm Waterval.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 28/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 25 1/12/05
Scattered rocks along the seasonal watercourse or drainage channel are
important for vantage and foraging sites for certain bird species (chats, cappedwheatear, marsh owls) as well as scent markers for certain mammals territories
(mongooses, jackal etc).
The proposed increased rail reserve does not impact on the potential bullfrog and
grass owl habitats or sensitive areas along the upper reaches of the seasonal
watercourse. The alignment crosses the watercourse below a severe headward or
headcurr erosion. Ideally this entire area should be rehabilitated preventing
further erosion and habitat deterioration and degradation along the watercourse
(spoil material from the construction activities could be used for this purpose). It
is important that during all phases of the project, access into the adjacentundeveloped open areas (east of the rail reserve) is severely restricted and
impacts minimised.
Glen Austin Extension 3 up to proposed Midrand Station.
East of the Proposed Midrand Station (Grand Central Airport) 26º 01’ 49” S 28º
07’31”E.
The rail corridor follows a path through the Glen Austin Agricultural Holdings and
open grassland. The above-mentioned section passes through old agriculturallands and existing smallholdings that proved to be degraded ecologically by many
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 29/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 26 1/12/05
exotic trees and gardens, in which it is highly unlikely that any specialised fauna
will be found. There are also further residential developments planned for the
area south of Grand Central Airport (President Park).
A restricted grassland area borders the Grand Central Airport and the K101.
Existing impacts on the site include:
• Bordered by major road networks (K101, Dale Street).
• Heavy vehicular traffic restricts certain animal migration (amphibians, reptiles
and mammals).
• Grand Central Airport’s fence and airstrip restricts animal movements
(between foraging and breeding areas).
• Frequent and irregular burning of grasses.
• Extensive grass harvesting and collection of medicinal plants.
• Numerous human pathways bisect the site.
• Evidence of poaching and wood harvesting.• Major littering throughout the site.
The increase in the rail reserve around the proposed Midrand station on either
side of the proposed alignment should not result in increased impacts on the
faunal composition and vegetation. Ideally the rail reserve should run
immediately alongside the road reserves as these areas are mostly transformed
grasslands. The open grassland areas adjacent to the proposed Midrand station
are rapidly developing with residential and commercial developments.
Brakfontein Sample Site
Large area of open grassland and wooded area situated adjacent to South African
Mint and the Highveld Techno-Park. The site is bordered by the National Road 1
(N1) and retailer’s warehouses. Existing impacts on the site include:
• Massive habitat destruction for Eco-Park residential and commercial
developments.
• Artificial damming of wetland areas into dams.
• Severe siltation and sedimentation in the dams.
•
Drainage canals in seepage areas.• Evidence of previous agricultural practises including irrigation.
• Restriction of water entering wetland areas - limited releases from dams.
• The site is bisected by the K54, which restricts frog, reptile and mammal
migration between suitable foraging and breeding areas.
• Hunting and poaching, including use of dogs.
• Frequent and irregular burning of grasses.
• Wood and grass harvesting.
The rail reserve is minimally increased (between 10-20m) and the alignment runs
parallel to the K101 in an area that can be considered as transformed habitat.
Massive residential and commercial developments have transformed the majority
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 30/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 27 1/12/05
of open habitat. The increased rail reserve will have no additional impacts on the
fauna and flora.
Esther Park
With respect to the wetland at Esther Park, the increased rail reserve is situated
deliberately north and away from the seasonal drainage line and Red Data listed
Trachyandra elythrorrhisa populations. The rail reserve’s southern boundary is
unchanged. Strict conservation management is required for the protection of the
above-mentioned plant species.
The seepage area comprising the wetland has been impacted on since theprevious surveys conducted in 2002-2003. Large scale dumping of building rubble
and litter, recent burning of the site, scraping of secondary access roads, and
excavations in the drainage line have recently occurred.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 31/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 28 1/12/05
The upper areas around the two hills and the beginning of the drainage line are
still currently in reasonably good condition and the system is not severely
degraded. The drainage line below the wetland is, however, showing signs of
degradation and erosion gullies have developed.
As long as the southern and eastern side of the wetland are protected during
construction, adequate stormwater control and flow dispersion measures are
implemented along the rail reserve, and a suitably designed stormwater
management system is developed for dealing with the flows coming from the
section of line in cut (above the wetland), then the impacts on the functionality of
the system should be minimal.
Railway Alignment in Centurion
The rail alignment follows a route alongside the existing National Road (N1)
adjacent to the Highveld Techno-Park, through built up commercial and
residential areas towards the proposed Centurion Station.
The rail corridor near the proposed Centurion Station site follows a route through
a built up residential and commercial area, and therefore no detailed investigation
was undertaken. The section of the corridor from the military area to Fountains
Valley, and including Fountains Park, is alongside or within existing road and rail
alignments, and it is not expected that there will be any major additionaldisturbance of the area than already exists. No further studies of this area were
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 32/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 29 1/12/05
undertaken in view of the existing degradation in this section, as well as the
many artificial landscapes introduced by local developments.
The alignment through Centurion should not result in any additional impacts other
than those raised during the EIA process. A raised line could potentially reduce
railway fatalities of certain migrating species such as frogs, reptiles and
mammals. On the other hand, species such as flying insects and birds may be
affected by the increase in the obstruction path of the raised alignment. The
management considerations contained in each specialist report in the original EIA
report should adequately mitigate any further possible impacts.
6.4 Sensitive Habitats
Certain sensitive habitats have been identified, but in these cases, increases in
the rail reserve have been prevented or minimised namely:
Seasonal Watercourses or Drainage Lines with Inundated Grasslands
Seasonal watercourses and inundated grasslands are vital habitats for numerous
animal species including numerous threatened species (Giant Bullfrog, African
Marsh Harrier, Grass Owl, South African Hedgehog, Striped Weasel, White-tailed
Mouse and Rough-haired Golden Mole). The entire Midrand wetland areas and
seepage zones, with their associated vegetation are extremely sensitive to
possible further negative impacts from proposed developments. The proposed
rail alignment avoids all major seasonally inundated areas in the Midrand-
Centurion area.
Wooded Hills and Forested Dolomite Ridges
Wooded hills and forested dolomite ridges are important habitats. Trees are vital
habitats for numerous arboreal animal species. Large numbers of birds have
been recorded in these woody habitats. Trees and shrubs provide vital refuge,
foraging and migratory passages for species migrating to and away from wetland
sites. The scattered rocky outcrops are important habitats for numerous
rupicolous animal species including scorpions, arachnids, geckos, skinks, snakes
and smaller mammals. The impact of the proposed rail alignment on such habitathas been minimized.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 33/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 30 1/12/05
6.5 Effects of Proposed Increased Rail Reserve and Raised/Lowered
Alignment on the Immediate and Surrounding Environment
6.5.1 Loss of Faunal Habitats
The increase in the rail reserve from between 10-50m will result in minimal
additional impacts on the fauna and flora if the appropriate mitigation measures
originally identified by the specialists in the EIA are implemented, as well as
minimising potential impacts in the designated sensitive areas such as rivers with
their associated riparian zones, seasonal watercourses in Midrand and Esther
Park, ridges and hills in Tshwane (Pretoria) etc.
Alteration of the additional vegetation along the proposed increased rail reserves
will directly, and indirectly, impact on the smaller sedentary species (insects,
arachnids, reptiles, amphibians and mammals) adapted to their terrestrial or
ground dwelling habitats. Larger, more agile species (birds and mammals) will
try and re-locate in suitable habitats away from the development. In addition,
heavy construction machinery, vehicles and the anticipated increased human
population density, will most likely directly and indirectly result in the short and
long term alteration of the faunal composition of the site and surrounding areas.
A further indirect, moderate to high, long term, negative impact which is likely to
affect the remaining fauna is uncontrolled hunting (“poaching”) on the site and
surrounding areas. This will naturally have the effect of reducing affected animal
species on the site and surrounding areas. This pressure, however, is likely to
occur irrespective of the rail project, because of the pressure to develop
remaining open areas in the fast growing corridor between Johannesburg andPretoria.
Mitigation and Recommendations
During the construction phase, workers must be limited to areas under
construction and access to neighbouring undeveloped areas (especially open
grasslands and wooded areas) must be strictly regulated, preventing uncontrolled
hunting, poaching and gathering of firewood and medicinal plants. Increased
pressure on an already impacted environment could result in major
environmental degradation if environmentally sensitive practices are not followedand maintained. Construction should be limited, where practical, to the daylight
hours preventing disturbances to the nocturnal activities of certain species and
nearby human populations. This will also minimise disturbances to sensitive and
secretive species. All remaining large indigenous tree species (dead and alive)
should be retained or replaced wherever possible as they form vital habitat for
numerous insectivorous predators, which control deleterious insect
(grasshoppers), bird (queleas) and mammal (rodents) populations. Trees and
stumps are vital habitats for numerous arboreal reptiles (chameleons, snakes,
agamas, geckos and monitors) as they are used for refuge sites as well as
foraging areas. Trees play a vital role in erosion and bank stabilisation by binding
the soils in their root systems. The trees will also provide valuable shaded areas
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 34/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 31 1/12/05
along the alignment and for newly established railway stations. Large rocks or
rocky outcrops should be conserved wherever possible or else the rocks should be
relocated outside the proposed alignment. Weeds and alien vegetation should be
removed and prevented from spreading into newly disturbed areas or areas
cleared of vegetation. Top soil obtained from the bulldozing activity along the
alignment should be appropriately stored and used to rehabilitate disturbed areas
after completion of the project. This will ensure a seed bank representing the
native flora, and will also be suited to the diet of the native mammal and bird
species. Where practical, termite mounds, dead trees, branches, scattered low
rocky outcrops, loose rocks, leaf and organic litter should be left undisturbed as
these special niches provide essential foraging, roosting and nesting sites for
numerous animal species. All temporary stockpile areas, litter and rubble must
be removed on completion of construction.
6.5.2 Erosion and Possible Siltation/Sedimentation
Future soil stockpiling areas must follow environmentally sensitive practices and
be situated a sufficient distance away from seepage zones and rivers. The sandy
soils around such sites are highly erodible, so erosion stabilising mechanisms
must be implemented. It is vital that preventative measures are undertaken to
prevent further headcount erosion and sedimentation on highly impacted
seasonal watercourses as well as bank erosion of rivers and streams. Continual
degradation of riparian zones and water quality will result in the eventual collapse
of the aquatic ecosystems.
The opportunity exists to include in the mitigation plan measures to stabilise theheadcuts occurring along certain seasonal watercourses in the Midrand and
Centurion areas in order to prevent the further erosion and thus degradation of
the systems. This was pointed out in the wetland specialist chapter of the EIA
report where it was stated a requirement for mitigation should also include the
stabilisation of the headcuts, since any construction activity in the area, without
careful management, could exacerbate the erosion problem currently evident in
the systems. This issue will need careful attention at the detailed design stage
and will need to be monitored post-construction. However, it should be noted that
the headcuts are not a consequence of the Gautrain project.
Mitigation and Recommendations
Stormwater and runoff should be channelled through natural grassland buffer
areas (at least 20m) reducing the erosional force and the potential risk of
contamination of the water source. Erosion stabilising actions (gabions) must be
implemented to prevent further habitat deterioration and degradation. The
careful position of soil piles, and runoff control, during all phases of development,
and planting of some vegetative cover after completion (groundcover etc.) will
limit the extent of erosion occurring on the site. Sufficient measures must be
implemented to prevent the possible contamination of surface water and
groundwater. Provision of adequate toilet facilities must be implemented to
prevent the possible contamination of surface and ground (borehole) water close
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 35/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 32 1/12/05
to the construction area. Heavy construction machinery must be regularly
serviced and checked for oil and fuel leaks. The timing of clearing activities is of
vital importance. Clearing activities and earth scraping should preferably be
restricted to the dry winter months, where possible, in order to prevent erosion
and siltation. The dry winter months are also the period when the majority of
species are either dormant or finished with their breeding activities.
6.5.3 Migratory Routes
The migratory movements of several animal (frog, reptile, bird and mammal)
species are completely disrupted by numerous road networks, which restrict
natural movements between suitable foraging and breeding areas. This is
especially prevalent for highly mobile species, such as Giant Bullfrogs, which can
migrate up to six kilometres from suitable foraging areas (open grassland) to
favourable breeding areas (seasonal pans or ponds). Fencing off of residential
areas and private property also plays a critical role in impeding the naturalmigration of the majority of animal species. A trade off thus exists between
safety and security on the one hand and movement of animal species on the
other.
Mitigation and Recommendations
The preservation, maintenance and creation of tracts of natural vegetation
(biological corridors) in all stages of ecological succession, interconnected by
corridors or green belts for escape, foraging, breeding and exploratory
movements needs to be considered. The area of the proposed rapid rail linkcorridor should be fenced off, and remain fenced off after the completion of
construction. Fencing or any other barrier should be low impact, preventing
further disturbance of the neighbouring vegetation and disruption of the natural
migratory movements of remaining animals. The fence or barrier should,
however, limit people, livestock and dogs entering the sensitive sites and contain
possible increased poaching and hunting, wood harvesting, vegetation removal
and continual pressure on remaining resources.
6.5.4 Buffer Zones or Biological Corridors
Connecting corridors between fragmented habitats and any other water sources
should be encouraged, where possible, to ensure a flow of genes between target
species, and also so that natural dispersion of species can occur. Ecological
corridors can be any width possible, but must be maintained to prevent blockages
or obstacles to the migrating or dispersing species. This will necessitate some in
depth research and further planning in the area, if implemented. Buffer zones
should be established around sensitive ecological areas to ensure the survival of
fauna and flora species. Reasonable buffer zones should be established between
marsh edges, for instance, and the rail route, and any associated roadways or
building operations envisaged in the future. The ideal buffer zone for
invertebrates and certain fauna species would be 200 m to 500 m, or wider. A
water buffer zone, such as a canal or stream, can also be considered as a buffer.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 36/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 33 1/12/05
6.5.5 Artificial Lighting
Artificial lighting will most likely result in a moderate to high negative short,
medium and long-term impact on all nocturnal animal species. Numerous species
will be attracted towards the light sources and this will result in the disruption of
natural cycles, such as the reproductive cycle and foraging behaviour. The lights
may destabilise insect populations, which may alter the prey base, diet and
ultimately the well-being of nocturnal insectivorous fauna. The lights may attract
certain nocturnal species to the area, which would not normally occur there,
leading to competition between sensitive and the more common species.
Mitigation and Recommendations
Artificial lighting should be directed away from the open grasslands and sensitive
habitats in order to minimise the potential negative effects of the lights on the
natural nocturnal activities of animals. Where lighting is required for safety orsecurity reasons, this should be targeted at the areas requiring attention.
6.5.6 Horticultural Activities
Landscape architects, and the developer, have an opportunity to conserve certain
faunal biodiversity present on the sites. Vegetation has been reported to be the
single most important habitat component for all species of animals. Linked to
this, is the preservation, maintenance and creation of tracts of natural and
ornamental vegetation in all stages of ecological succession, interconnected by
corridors or green belts for escape, foraging, breeding and exploratorymovements. Urban settings are all too frequently characterised by exotic trees,
planted at the same time, at the same size and are spaced at regular centred
settings. The resulting pattern and structure is one of limited vegetation
diversity, trees of uniform size, even age stands and little or no understorey
planting. Only a few species of animals (urban exploiters) will occupy these
limited niches, leading to decreased faunal biodiversity. Remaining indigenous
bulbous geophytes and aloe species should be retained or replanted where
possible. Gardens or landscaped areas around stations or within the rail corridor,
should be planted with indigenous (preferably using local plants cleared from the
area) plants and trees, which are water wise and require minimal horticulturalpractices.
Mitigation and Recommendation
Horticultural activities resulting in fertiliser, herbicide and pesticide runoff,
increases in alien vegetation and weedy species, and dumping of refuse and
building material must be prevented or strictly managed. Landscaping should be
environmentally sensitive and should meet the following requirements:
• Limited to building environs.
• Limited irrigation through water-wise gardening (use local plants adapted
to local conditions).
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 37/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 34 1/12/05
• Strict fertiliser, pesticide and herbicide control (limited usage).
• Reduction of weeds and erosion control by minimum tillage gardening
practices (groundcovers and mulching).
• No dumping of any materials in undeveloped open areas and buffer strips
(biological corridors).
• Activities in the surrounding open undeveloped areas must be strictly
regulated.
• Certain exotic weed, reed and tree (Melia azedarach, Acacia mearnsii,
Morus alba etc.) species should be removed to prevent further invasion.
6.5.7 Rescue and Recovery Programme
Prior to construction activities, the areas of the proposed railway alignment aswell as increased rail reserve should be walked with a botanist and a zoologist. All
geophytes and bulbous plants should be relocated away from the proposed route.
If certain sensitive habitats or vegetation (large trees, bulbs etc) have to be
destroyed due to development pressures, a rescue and recovery programme
should be adopted. Animals and plants recovered can be relocated in suitable
habitat adjacent or close to the impacted sites. If any threatened species are
unearthed or discovered during the construction phase, all activities must be
suspended and the relevant authorities informed for appropriate action.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 38/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 35 1/12/05
6.6. Conclusion and Recommendations
It can be safely stated that the study area is one of the most heavily impacted in
South Africa with the result that the natural vegetation cover has largely been
irreversibly altered, primarily by industrialisation and urbanisation. Continual
habitat destruction, alteration and human disturbances will result in the
disappearance of the majority of sensitive or secretive species in peri-urban
Gauteng. Few suitable grasslands and seasonal wetland areas remain in
Gauteng, especially in the Midrand-Centurion area. Increased pressure on an
already impacted environment could result in major environmental degradation if
environmentally sensitive practices are not followed and maintained. Although
the proposed Rapid Rail Link traverses or edges open grassland areas, the
majority are already severely fragmented and in relative stages of transformation
due to increased human pressures and impacts. They do, however, offer critical
habitat for remaining plant and animal species and impacts should be strictly
limited or managed. Increased rail alignments should follow existing impacted
areas or corridors wherever possible and remain as close as possible to the major
road and rail reserves. This will prevent further habitat fragmentation and
possible disruption of migratory routes of remaining species.
Mitigation could be considered in terms of placing the line in cut, where possible,
in the more sensitive areas described in this report and ensuring effective
rehabilitation of the landscape after construction with indigenous grasses, which
will be attractive to remaining fauna. All mitigation measures should be properly
described in the Environmental Management Plan (EMP). These measures should
be meticulously applied, monitored and audited (by an independentenvironmental specialist/s) to ensure proper rehabilitation and demonstrate an
acceptable level of stabilisation.
More comprehensive and intensive specialist surveys would be required in order
to ascertain the status of threatened amphibian (Giant Bullfrog); reptile
(Harlequin Snake); bird (Grass Owl, Marsh Harrier, Lesser Kestrel) and mammal
(Hedgehog, White-tailed Mouse, Rough-haired Golden Mole, Striped Weasel)
species in the Gauteng province. More intensive provincial surveys of mammals,
reptiles and amphibians would also be required to assess whether remaining open
spaces in the corridor between Johannesburg and Pretoria need protection.Nationally co-ordinated Management Plans will need to be implemented to ensure
the survival of these threatened areas and the species they support. Current
IUCN Red Data lists are outdated and should be revised (amphibians and
mammals have been recently updated). If certain sensitive habitats have to be
destroyed due to development pressures, a rescue and recovery programme
should be adopted. Animals recovered can be relocated in suitable habitat
adjacent or close to the impacted sites. The existence of similar alternative
habitat outside the proposed site should be investigated before a final decision is
made. If any threatened species are unearthed or discovered during the
construction phase, all activities must be suspended and the relevant authoritiesinformed for appropriate action.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 39/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 36 1/12/05
References
Low, A.B. and Rebelo, A.G. (1998). Vegetation of South Africa, Lesotho and
Swaziland . D.E.A.&T., Pretoria.
Various specialist surveys conducted for the EIA for Gautrain Rapid Rail link
between Pretoria and Johannesburg International Airport. Volume 4: Biophysical
Environment parts 1 and 2 (October 2002).
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 40/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 37 1/12/05
7. VISUAL IMPACT(Thomas Van Viegen, earthINC)
7.1 BACKGROUND
This section of the report outlines the methodology and approach adopted in the
landscape and visual impact evaluation for the Preferred Bidder’s minor route
amendments where they vary from the RoD approved alignment.
7.2 COMPARATIVE ASSESSMENT ASPECTS
The horizontal and vertical alignment proposed by the Preferred Bidder was
compared with the Record of Decision (RoD) alignment. In the majority of
circumstances the horizontal alignment (though slightly wider at the surface)
remains unchanged. Where the Preferred Bidder’s horizontal alignment does vary
more substantially from the RoD alignment (route variants), this is being
considered through separate Regulation 9(3) amendment applications to be
submitted to GDACE early in 2006.
In most instances the visual influence of the Preferred Bidder’s vertical alignment
is unchanged, with negligible difference when compared to the RoD alignment.
However, as per the evaluation below, there are specific sections of the alignmentwhere there is a marked improvement in the landscape and visual amenity, such
as deeper cut sections, especially in those areas illustrating a sensitive land use
such as residential and institutional land uses.
Similarly, sections of the Preferred Bidder’s alignment have been identified where
the potential impact on the landscape and visual quality of the receiving
environment and community would be more substantial. This is the result of the
Preferred Bidder’s alignment being raised on fill through areas of sensitive landuse. As evaluated, an increase in height of 2 meters above the approved RoD
alignment could have a negative effect on visual (and noise) influence. In most
instances a variation of 2,5 meters or more will have a negative visual influence.
7.3 METHODOLOGY AND APPROACH
The approach to the evaluation has been to consider the RoD alignment and the
Preferred Bidder’s alignment per kilometre chainage. Each section is evaluated in
terms of its potential to influence the landscape and visual amenity. Where the
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 41/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April
2004:Minor Route Amendments
Bohlweki Environmental 38 1/12/05
impact has been positive it has been indicated as such, and where the impact has
been negative it has been similarly highlighted.
The impact has been categorised with respect to “Impact Change” as follows:
Adverse:
Substantial change to the visual amenity. Substantial change is a raised vertical
elevation of 2,5 meters and higher in residential and or sensitive land use areas.
Negligible:
Minimal or insignificant change to the visual influence. The visual influence in
industrial areas is seen as negligible due to the generally low quality of the
landscape and visual amenity, and the ability of the environment to more easily
absorb the potential impacts.
Beneficial :
Very little (insignificant) to no change or the alignment is now deeper (or
remains) in cut or tunnel.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 42/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 39
7.4 COMPARATIVE ASSESSMENT OF THE MINOR VERTICAL ALIGNMENT CHANGES
Section Park Station – Sandton Station
Kilometre
Chainage
Reference
RoD Alignment Description Preferred Bidder
Alignment Description
Impact Descripti
Comments
1741.77 – 1772.28 The RoD alignment is in
tunnel
Preferred Bidder alignment is
in a deeper tunnel than ROD
alignment
Preferred Bidder Al
in tunnel structure
approved alignmen
16 meters. No adv
impact.
1772.28 – 1663.62 The RoD alignment is still in
tunnel structure
Preferred Bidder’s alignment
is in shallower tunnel than
RoD alignment till cut and
cover section where it meets
the RoD alignment
Preferred Bidder’s
is still in tunnel str
above RoD alignme
20m. No adverse
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 43/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 40
1663.62 – 1663.11 RoD alignment is in cut and
cover
Preferred Bidder alignment is
in higher cut and cover than
RoD alignment
Preferred Bidder’s
is 1 meter shallowe
alignment. No adv
impact
1663.11 – 1578.01 The RoD alignment remains in
tunnel
Preferred Bidder alignment
remains in tunnel
Preferred Bidder’s
varies in depth, sta
deeper (by up to 8
the RoD approved
and at 1606.55 bec
shallower by up to
the RoD alignment
before the Sandton
No adverse impact
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 44/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 41
Section Sandton Station – Midrand Station
Kilometre
Chainage
Reference
RoD Alignment
Description
Preferred Bidder
Alignment Description
Impact Descripti
Comments
10450.00-10660.00 Cut and cover to Sandton
Station
2m shallower than ROD
alignment
No adverse impact
10660.00-11075.00
and
14360.00-15260.00
Alignment in tunnel Preferred Bidder alignment
shallower by 2m than
approved RoD alignment, but
remaining in tunnel
Preferred Bidder al
remains in tunnel.
impact.
11075.00-14360.00
(Sandton Variant
Alignment)
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 45/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 42
15260.00-15390.00 RoD alignment is in a cut and
cover section at the interface
between the tunnel and
above ground alignment
The Preferred Bidder
alignment is at a shallower
level than the RoD alignment
Preferred Bidder al
meters above appr
alignment. No adv
as no visual differe
RoD alignment.
15390.00-17160.00
(Marlboro Variant
Alignment)
17160.00-18120.00 RoD alignment aboveground
on viaduct, then entering cut
till 18120.00
Preferred Bidder alignment
completely in cut till 18120.00
An improvement to
amenity compared
alignment.
18120.00-18640.00 RoD alignment on fill Preferred Bidder alignment on
fill that is 2 meters higher
than RoD alignment
The surrounding la
industrial and the r
alignment will not c
the existing visual
value.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 46/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 43
18640.00-19760.00 RoD alignment in cut Preferred Bidder alignment
similarly in cut, but deeper
than the RoD alignment by up
to 2 meters
The Preferred Bidd
is deeper in cut tha
alignment by up to
No adverse impact
19760.00-21600.00 RoD alignment on fill and
bridge structure over water
course
Preferred Bidder alignment
deviates from RoD alignment
by a maximum increased
height of up to 0.5-1 meter
Marginal increase i
alignment height.
impact.
21600.00-22440.00 RoD alignment in cut Preferred Bidder alignment in
cut, below the RoD alignment.
No adverse impact
22440.00-24280.00 The RoD alignment is on fill
and viaduct structure over
prominent road system
Preferred Bidder alignment is
on fill and viaduct structure.
Height above RoD alignment
averages approx. 4.5 meters
A more substantial
change to the RoD
Where the alignme
small holding area,
will be required, to
impact.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 47/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 44
24280.00-26240.00 The RoD alignment is in cut The Preferred Bidder
alignment is in cut and follows
the RoD alignment closely
Negligible visual im
over the extent of
26240.00-26640.00 The RoD alignment is in cut. The Preferred Bidder
alignment is on marginal fill of
0.5 to 1 meter in height
The fill is negligible
but the change of t
alignment now exp
cut to above groun
substantial variatio
26640.00-27760.00 Alignment in cut Alignment in deeper cut No adverse impact
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 48/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 45
Section Midrand Station - Hatfield Station
Kilometre
Chainage
Reference
RoD Alignment Description Preferred Bidder
Alignment Description
Impact Description
Comments
28.104-28.800 RoD alignment on fill Preferred Bidder alignment
on fill approx. 1 meter
below RoD alignment
No additional impact.
28.800-30.750 RoD alignment in cut Preferred Bidder alignment
in cut, but surfacing at
30.750.00
No adverse impact, b
change in the alignme
it surfaces from cut to
level is a substantial v
30.750-31.550 RoD alignment in cut Preferred Bidder alignment
close to natural ground
level and marginal fill of
0.5-1 meter
Visual influence is mo
substantial when com
approved RoD alignm
use in area close to K
largely commercial an
industrial. Negligible
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 49/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 46
31.550-33.250 RoD alignment is on fill and
viaduct
Preferred Bidder alignment
sits on increased fill on the
southern approach to the
viaduct by up to 4 meters.
Viaduct and northern fill is
considerably lower than
RoD alignment by 4-4.5
meters
The impact of the fill
southern approach is
substantial. However
remainder of the Pref
Bidder alignment is lo
height.
33.250-34.450 RoD alignment is in cut Preferred Bidder alignment
is in cut
Alignments are simila
34.450-35.800 RoD alignment is on fill with
bridge structures
Variant alignment is on fill
with an increase in the
vertical alignment of about
2-2.5 meters
Negligible impact.
35.800-37.100 Alignment in cut, fill and
viaduct
Alignment in cut, fill and
viaduct
Alignments are simila
37.100-37.500 Alignment in cut Alignment in cut Alignments are simila
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 50/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 47
37.500-38.900 Alignment in cut Preferred Bidder alignment
exits cut at 38.200 and
follows natural ground level
Visual impact differen
substantial. Land use
not sensitive – overa
impact on landscape
quality is negligible.
38.900-42.600 RoD alignment in cut and fill Preferred Bidder alignment
in cut and fill. Variant
alignment follows RoD
alignment till 40.100 from
where the vertical
alignment gradually
increases to a height of
about 2.5 meters above
RoD alignment
The Preferred Bidder
passes through undev
commercial / industri
Land uses are not sen
the visual quality and
character will not be
42.600-48.000
(Centurion Variant
Alignment)
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 51/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 48
48.00-51.200 RoD alignment traverses the
SANDF property on fill
Preferred Bidder alignment
is on fill at a varying
vertical alignment of
between 0.5 and 8m below
the RoD alignment. The
Preferred Bidder may
choose to utilise a viaduct
structure here if the
dolomitic ground warrants
this
Impact is an improve
51.200-52.800 RoD alignment in substantial
cut
The Preferred Bidder
alignment is in deeper cut,
averaging between 5-10m
deeper which will influence
the footprint of the cutting.
Visual influence of the
cutting will be negligi
52.800-54.000 ROD alignment in fill with
viaduct structure over the
R28 off-ramp at Eeufees Road
Variant alignment largely
follows the RoD alignment
with very little influence
Negligible impact.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 52/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 49
54.000-56.200
(Salvokop Variant
Alignment)
56.400-59.500
(Pretoria Variant
Alignment)
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 53/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 50
Section Marlboro Station – JIA Station
Kilometre
Chainage
Reference
RoD Alignment
Description
Preferred Bidder
Alignment Description
Impact Descripti
Comments
0.00-880.00
(Marlboro Route
Variant)
880,00-10020.00 The RoD alignment follows
the receiving topography
with a series of cut and fill
sections, with bridge
structures at Ardeer Road,
Centenary Way, Antwerp
Road, Pressburg Road, and
Modderfontein Road
The Preferred Bidder
alignment deviates from the
RoD alignment in being in
deeper cut over the initial
sections of the alignment. It
closely follows the vertical
alignment of the RoD
alignment from 2120.00 to
the approach to Ardeer Road,
where it is considerably lower
by up to 6 meters. Between
Antwerp Road and Pressburg
Road, it is in less cut (less
Sections of the var
alignment which ar
more exposed than
alignment are in lo
sensitivity landscap
land uses. The vis
landscape quality i
be negligible.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 54/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 51
landscape impact) and is
raised by 4 meters on
average at the Centenary
Way / Pressburg Road
intersection. It then follows
the RoD alignment to
10020.00
10020.00-10690.0 RoD alignment crosses the
Kelvin rail siding and
Zuurfontein road on a
viaduct, with fill adjacent to
the residential
neighbourhood
The Preferred Bidder
alignment follows the RoD
alignment but with a raised
vertical elevation of 2 meters
The impact in close
of the residential a
be substantial if no
adequately mitigat
10690.00-12400.00 The RoD alignment is in cut Preferred Bidder alignment is
in cut and follows the RoD
alignment. There is a
variation of 1-2 meters
between the two alignments,
in terms of grade difference
The impacts are ne
Screening mitigatio
provided alongside
area on approach t
JIA alignment.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 55/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:Minor Route Amendment
Bohlweki Environmental 52
12400.00-JIA
(JIA Variant
Alignment)
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 56/82
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 57/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:MinorRoute Amendments
Bohlweki Environmental 54 1/12/05
8. HERITAGE ISSUES
(Len van Schalkwyk, Debbie Whelan and Beth Wahl, eThembeni Cultural Heritage)
8.1 Background
As a result of amended station footprints at Park, Rosebank and Sandton Stations
on the Preferred Bidder’s alignment, a number of heritage issues have arisen.
It will be necessary to demolish the Technical College on Smit Street in
Braamfontein (above the Park Station tunnel portal) and 2 houses on Oxford Road
(Rosebank Station) older than 60 years. This requires the necessary
investigations and approval from SAHRA to do so. Included in the heritage
investigations for completeness are the office block in Braamfontiein, another
office building in Rosebank, as well as the low-rise segment of the Sandton Civic
centre at Sandton Station that will also have to be demolished. The additional
tunnel shaft to be sunk at Mushroom Farm Park in Sandton (to prevent traffic
problems in Sandton during construction) has also been checked for heritage
value.
A draft report (Appendix B) has been submitted to SAHRA for consideration by the
SAHRA Committee in December 2005. Further relevant information is being
collected in the meantime to supplement this draft report and assist the SAHRA
Committee in reaching a decision.
The Bombela Consortium is also collecting relevant information for SAHRA in
terms of the ROD requirements for siting tunnel emergency evacuation shafts. It
must be emphasised that in terms of Bombela’s proposal, ventilation shafts will
only be required at the stations where the line is in tunnel. Emergency evacuation
shafts (a small area housing an approximately 4x4x4m structure and an access
drive for emergency vehicles) will be sited about every 1 km above the tunnel.
These shafts are sealed at the foot and top of the shaft (no noise from the tunnel)
and are only opened in an emergency in the tunnel, when emergency personnel
cannot access trapped passengers via the tunnel from the stations.
The proposed sites for the emergency access shafts are:
The eastern corner (road reserve) of Clarendon Place and Yettah Road in Hillbrow.
Adjacent to the access road into the Wilds from Houghton Drive.
A vacant stand north-east of the corner of Riveira and Oxford Roads in Riviera.
A car park of a business on the corner of Oxford Road and 9th Street in Houghton.
The south-eastern corner (road reserve) of Cradock and Bompas Roads in
Dunkeld.
The south-western corner (road reserve) of Melville and 1st Roads in Hyde Park.
The entrance to the Inandas complex on Rivonia Road in Sandton.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 58/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:MinorRoute Amendments
Bohlweki Environmental 55 1/12/05
9. PUBLIC PARTICIPATION PROCESS
A media conference was conducted on 26 October 2005 at the Gautrain Project Office in
order to commence the process of communicating the details regarding all the proposed
amendments to the approved route alignment to the media and to the public.
The following day an advert informing the public of the proposed changes to the alignment
and the process to be followed was published in the Beeld, Sowetan, Pretoria News and
The Star Newspapers. On 2 November the advert was published in the Midrand Reporter
and on 4 November, it was published in the Rekord (Centurion and East), Sandton
Chronicle and the Alex News. The advert provided points of contact to obtain further
information. A copy of the advert is attached for information in Appendix C.
The advert made reference to the website www.gautrain-env.co.za which has been
established to provide further information to all stakeholders. Relevant public documents
are placed on the website and interested and affected parties (I&APs) are able to access
contact information, register as I&APs and provide comments through the website.
A Background Information Document (BID) which describes the proposed changes to the
alignment in more detail was distributed during the second week of November 2005 to all
registered I&APs, together with a comment sheet inviting I&APs to submit details of any
issues and concerns. The aim of this document was to provide a brief outline of the
proposed amendments to the alignment, details regarding the variant alignments,
introduce the Environmental Management Plan (EMP) process, and an explanation on howI&APs can become involved in the process. The document has also been placed on the
website to allow for electronic access, and more comprehensive distribution. A copy of the
BID is attached as Appendix D.
Public consultations have formed an essential component of the environmental
investigations carried out for the minor route amendments. In addition to the advertising
and media release described above, over 20 focus group meetings have been held with all
the key stakeholders and communities with whom the environmental team interacted
during the original EIA on those sections of the route where the minor route amendments
are proposed. The minutes of these meetings will be included in an Addendum to this
report, to be compiled for GDACE, together with any comments received on this draft
report and the environmental team’s responses, once the 14 day comment period has
elapsed. All three Metropolitan Councils (City of Johannesburg, Tshwane and Ekurhuleni)
have also been addressed about the minor route amendments and their comments noted.
In addition, SAHRA has been informed about the heritage issues associated with revised
station footprints and those buildings that will need to be demolished.
Table 9.1 lists the specialist studies and focus group meetings conducted for this report.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 59/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:MinorRoute Amendments
Bohlweki Environmental 56 1/12/05
TABLE 9.1: MINOR ROUTE AMENDMENTS
Special Studies: Focus Group Meetings:
• Noise (Derek Cosjin, Jongens,
Keet and Associates
• Vibration (Prof Wikus van Niekerk,
Stellenbosch University)
• Visual (Thomas van Viegen)
• Geohydrology (Reinie Meyer,
Environmentek, CSIR)
• Fauna and Flora (Clayton Cook)
• Heritage (eThembeni Cultural
Heritage)
Park Station – Rosebank
• Braamfontein Technical College (x2)
• Roedean School
• Local Councillors and Killarney, Houghton, Parkwood and
Saxonwold Community Representatives
Rosebank – Sandton• Local Councillors and Rosebank, Melrose, Dunkeld, Hyde
Park and Inanda Community Representatives
Sandton – Marlboro
• Atholl and RESTOA Community Representative
• Local Councillor and Sandton Community Representatives
• Marlboro Gardens Community Representatives
Marlboro – Midrand
• Triangle Communities Representatives and Mia Group
• President Park and Glen Austin Ext 3 Community
Representative
Midrand – Centurion
• Glen Austin Community Representatives
• Randjesfontein Community Representatives
• Samrand Area Businesses
Centurion – Pretoria
• SANDF
Marlboro– Rhodesfield
• Linbro Park and Thornhill/Lakeside Community
Representatives and Linbro Park Business Park.
• AECI/Heartland Properties
• Local Councillor and Rhodesfield, Cresslawn, Esther Park
Community Representatives
• Rhodesfield Residents (Glenfield and Diana Court
Complexes)
Authorities
• City of Johannesburg, Tshwane and Ekurhuleni Metropolitan
Councils (Environmental Departments), SAHRA and
Gauteng Heritage Agency (meeting and site visit)
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 60/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:MinorRoute Amendments
Bohlweki Environmental 57 1/12/05
It should be noted that a widening of the rail reserve was not supported by the
environmental team in the section of the rail line in Randjesfontein south of Olifansfontein
Road to prevent further loss of bridle trails in this area. Similarly, a widening of the rail
reserve to the south near Esther Park was also not supported to protect the Red Data
plant species in the vicinity.
Traffic studies carried out for the EIA in 2002-03 have been updated by Bombela and
submitted to the three Metropolitan Councils, along with proposals for road closures and
traffic diversions during construction. These will be considered in terms of the Local
Government Ordinance. The City of Johannesburg has requested public comment (until 2
December 2005) on the proposed road closures and traffic diversions that will be required
to commence with initial preparatory works on the tunnel shafts in January 2006.
Feedback will be incorporated into the Initial Works EMP that is currently in the public
domain for comment until 12 December 2005.
The EMP process to further develop the draft EMP contained in the original EIA also
commenced at the end of October. The Bombela environmental team developing the EMP
accompanied the environmental team interacting with I&APs on the minor route
amendments to all the focus group meetings. The EMP process was explained and a
Revision 2 EMP has been issued and comments received for updating and submission to
GDACE for approval on 2 December 2005. The Draft Final EMP will be developed early in
2006.
The engagement with I&APs since late October 2005 on the minor route amendments hasnot led to any groundswell opposition to the proposed changes. Most feedback has been
centred around the commencement of the initial works in January 2006 and how traffic
and noise impacts will be managed during construction though the EMP process.
The areas of most concern raised during consultations on the minor route amendments
revolved around issues of access and the implications of an adjusted vertical alignment or
wider rail reserve on planned or existing developments. Such issues have been raised in
Midrand (Mia Group, Glen Austin and Samrand businesses), in Modderfontein (AECI) and
at Linbro Park. These will be investigated further during the comment period on this
report.
A number of comments were also received around the acquisition of land for the rail
reserve through the Gauteng Transport Infrastructure Act process. Many property owners,
particularly in Ekurhuleni, are wanting certainty about when and how they will be
compensated for the loss of their property.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 61/82
Regulation 9(3) Application for the Amendment of the Gautrain Record of Decision, Dated 25 April 2004:MinorRoute Amendments
Bohlweki Environmental 58 1/12/05
10. CONCLUSION
The minor amendments proposed to the Gautrain route alignment approved in the RoD of
2004 investigated in this report largely entail changes to the station footprints, the vertical
alignment of the route (in the tunnel and above ground sections of the route) and/or a
slightly wider rail reserve (above ground sections of the route only).
The rationale for these changes are mainly the result of design, construction and
operational advantages foreseen by Bombela (in the case of the vertical alignment
changes), the ability to optimise the final design and allow for the movement of cut and fill
material during construction (in the case of a wider rail reserve) or amendments to the
station footprints (Park, Rosebank and Sandton Stations) as a result of current and
potential future operational improvements, unforeseen constraints or after consultations
with the City of Johannesburg.
It should be noted that the minor amendments to the Gautrain route are already
extensively covered by the specialist investigations undertaken for the original EIA, and
thus the information contained in the original EIA report remains important as input to
assessing any change, if any, in impact.
The minor amendments to the original RoD alignment proposed by the Preferred Bidder for
the Gautrain Rapid Rail Link are not anticipated to result in any significant changes to the
vibration, noise, geohydrological, ecological or visual impacts, or to the findings in the
specialist studies contained in the EIA report. The specialists are of the opinion that the
mitigation measures provided in the original studies or updated for this report will be
adequate to address impacts associated with the minor amendments.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 62/82
APPENDIX A:
REVISED POSITIONING OF NOISE MITIGATION
MEASURES FOR MINOR ROUTE AMENDMENTS
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 63/82
GAUTRAIN RAPID RAIL LINK
REVISED NOISE MITIGATING MEASURES
The following “diagrammatic tables” have been prepared to indicate the type and position of possible
appropriate noise mitigating measures that could be implemented along the Johannesburg – Pretoria
(JP) Line and Sandton – Airport (SA) Line railway corridors. These tables should be read as plans.
They are set out so as to indicate increasing kilometre distances from the lower to the upper section of
the page namely from south (Johannesburg) to north (Pretoria) for the JP Line and from west (Sandton)
to east (JIA) for the SA Line. The sections plotted are for the Bidder Alignment. The figures must be
treated as being schematic and not always strictly to scale.
Note that the measures indicated are typical ones and are based on the train details used and the
findings of the noise impact study. Once the final design of the train system is complete, theappropriate detailed mitigating measures will in turn be designed. As the noise impact assessment
used a very conservative approach it is likely that there will be some adjustments to some of the
measures indicated.
For certain sections of the Bidder alignment, where significant changes in the alignment (route variants)
are being re-investigated by the Bidder, the mitigating measures along these sections are not indicated
in this document. These sections are:
i) The section of the JP Line through Centurion from John Vorster Drive to just west of the National
Road (Ben Schoeman) N14 freeway.
ii) The section of the JP Line on the southern approach to Pretoria Station from the crossing of the
National Road N14 freeway to Pretoria Station.
iii) The section of the JP Line from Pretoria Station to Hatfield Station.
iv) The section of the SA Line on the approach to Johannesburg International Airport (from west of
Rhodesfield).
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 64/82
The details of the symbols used in the “table diagrams” are as follows:
Symbol Description
F Cross-section in fill
C Cross-section in cuttingT Cross-section in tunnel
G Cross-section at grade
C/C Cross-section in cut and cover construction
S Track on structure (viaduct)
St Station
Gautrain track on surface (grade, fill and cutting)
Gautrain track in tunnel (T)
Gautrain track on structure
Gautrain track in cut-and-cover construction (C/C)
2,5 metre high wall or earth berm. In cutting sections barrier to be at least 4m high
from track level
4 metre wall or earth berm
-x-x-x-x-x-x- Property boundary
ٱ Mitigating measure
++++++++++ Spoornet railway line
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 65/82
MITIGATING MEASURESSECTION: JP LINE (00km00 to 5km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
SectLeft of the Tracks
L R Right of Tracks
5km00 T
4km80 T
4km60 T
4km40 T
4km20 T
4km00 T
3km80 T
3km60 T
3km40 T
3km20 T
3km00 T
2km80 T
2km60 T
2km40 T
2km20 T
2km00 T
1km80 T
1km60 T
1km40 T
1km20 T
1km00 T
0km80 T
0km60 T
0km40 T
0km20 G
0km00 G St St
__________________ Oxford Road
_________________
________________
TUNNEL ENTRANCE ٱ Treat enhancement effects
with sound absorbent liningfor short distance into tunnel
________________ Eastwold Road/Riviera Road
________________ M1 Freeway
_________________ Carse O Gowrie Road
TUNNEL SECTION: ٱ Measures at ventilation shafts
(only at stations):
• Lining with sound absorbentmaterial
• Damping of fans
• Architectural treatment of outlet structures
PARK STATION
JOHANNESBURG
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting, C/C = Cut & cover
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 66/82
MITIGATING MEASURES
SECTION: JP LINE (5km00 to 10km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
10km00 T
9km80 T
9km60 T
9km40 T
9km20 T
9km00 T
8km80 T
8km60 T
8km40 T
8km20 T
8km00 T
7km80 T
7km60 T
7km40 T7km20 T
7km00 T
6km80 T
6km60 T
6km40 T
6km20 T St St
6km00 T
5km80 T
5km60 T
5km40 T
5km20 T
5km00 T
__________________ Melville Road
▼
▲ Under Melville Road
___________________
Under Oxford Road▼
__________________
__________________
________________ Rivonia Road
TUNNEL SECTION: ٱ Measures at ventilation shafts
(only at stations):
• Lining with sound absorbentmaterial
• Damping of fans
• Architectural treatment of
outlet structures
________________ Bompas Road
_________________
Jellicoe Road
ROSEBANK STATION
_________________ Bolton Road/Glenhove Road
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting, C/C = Cut & cover.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 67/82
MITIGATING MEASURES
SECTION: JP LINE (10km00 to 15km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
15km00 T
14km80 T
14km60 T
14km40 T
14km20 T
14km00 T
13km80 T
13km60 T
13km40 T
13km20 T
13km00 T
12km80 T
12km60 T
12km40 T12km20 T
12km00 T
11km80 T
11km60 T
11km40 T
11km20 T
11km00 T
10km80 T
10km60 T St St
10km40 T
10km20 T
10km00 T
______________________
_____________________
_______________________
______________________ M1 Freeway
______________________ KatherineStreet
TUNNEL SECTION: ٱ Measures at ventilation shafts
(only at stations):
• Lining with sound absorbentmaterial
• Damping of fans• Architectural treatment of
outlet structures
______________________ Grayston Drive
SANDTON STATION
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 68/82
MITIGATING MEASURES
SECTION: JP LINE (15km00 to 20km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
20km00 F
19km80 F
19km60 C
19km40 C
19km20 C
19km00 C
18km80 C
18km60 C
18km40 F
18km20 F
18km00 C
17km80 C
17km60 C
17km40 C 17km20 C
17km00 C
16km80 F
16km60 F St St
16km40 F
16km20 F
16km00 F
15km80 C
15km60 T
15km40 T
15km20 T
15km00 T
▲ MODDERFONTEIN LAND
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
_____________________
MARLBORO GARDENS
▼
ٱ
4m wall
ٱ 2,5m wall
TUNNEL ENTRANCE ٱ Treat enhancement effects with
sound absorbent lining for short distance into tunnel
▲ MODDERFONTEIN LAND
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
_______________________ N3 Freeway
MARLBORO STATION
MARLBORO GARDENS
▼ ٱ 4m wall
TUNNEL SECTION: ٱ Measures at ventilation shafts:
• Lining with sound absorbentmaterial
• Damping of fans
• Architectural treatment of outlet structures
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 69/82
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 70/82
MITIGATING MEASURES
SECTION: JP LINE (25km00 to 30km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
30km00 C
29km80 C
29km60 C
29km40 C
29km20 C
29km00 C
28km80 F
28km60 F
28km40 F
28km20 F
28km00 F
27km80 F St St
27km60 C
27km40 C27km20 C
27km00 C
26km80 C
26km60 F
26km40 F
26km20 C
26km00 C
25km80 C
25km60 C
25km40 C
25km20 C
25km00 C
▲ GLEN AUSTIN AH
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
__________________
▲ GRAND CENTRAL AIRPORT
______________________
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-GLEN AUSTIN AH X3
▼
ٱ No wall on western side
ٱ No wall on western side
ٱ 2,5m wall
▲ GLEN AUSTIN AH
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
____________________ New Road
MIDRAND STATION
▲ GRAND CENTRAL AIRPORT
______________________
Dale Road -x-x-x-x-x-x-x-x-x-x-x-x-x-
GLEN AUSTIN AH X3
▼
ٱ 4m wall or earth berm
ٱ 2,5m wall or earth berm
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 71/82
MITIGATING MEASURES
SECTION: JP LINE (30km00 to 35km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
35km00 F
34km80 F
34km60 F
34km40 C
34km20 C
34km00 C
33km80 C
33km60 C
33km40 C
33km20 F
33km00 F
32km80 F
32km60 F
32km40 F32km20 F
32km00 F
31km80 F
31km60 F
31km40 C
31km20 C
31km00 C
30km80 F
30km60 C
30km40 C
30km20 C
30km00 C
ٱ No measures necessary
__________________
▲ INDUSTRIAL LAND-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
RANDJESFONTEIN AH
▼
ٱ 2,5 wall or earth berm
__________________
ٱ 4m wall or earth berm
ٱ 4m wall
▲ RANDJESFONTEIN AH
__________________ -x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
GLEN AUSTIN AH
▼
ٱ No wall on western side
________________
ٱ No wall on western side
ٱ No measures necessary
_________________ Samrand Road(Oliefenhoutbosch Road)
▲ INDUSTRIAL LAND
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
RANDJESFONTEIN AH
▼
ٱ 2,5m wall or earth berm
__________________ Road R562
ٱ 4m wall or earth berm
ٱ 4m wall
▲ RANDJESFONTEIN AH
___________________ Olifantsfontein Road -x-x-x-x-x-x-x-x-
GLEN AUSTIN AH
▼
ٱ 4m wall
ٱ 4m wall or earth berm____________________ George Road
ٱ 4m wall or earth berm
ٱ 2,5m wall
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 72/82
MITIGATING MEASURES
SECTION: JP LINE (35km00 to 40km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
40km00 F
39km80 C
39km60 C
39km40 C
39km20 F
39km00 F
38km80 C
38km60 C
38km40 C
38km20 C
38km00 C
37km80 C
37km60 C
37km40 C37km20 C
37km00 F
36km80 F
36km60 F
36km40 C
36km20 C
36km00 C
35km80 C
35km60 F
35km40 F
35km20 F
35km00 F
▲ UNDEVELOPED AREAINDUSTRIAL LAND
▼
_________________
▲ INDUSTRIAL LAND
▲ UNDEVELOPED AREA
INDUSTRIAL LAND
▼
____________________
Brakfontein Road
▲ INDUSTRIAL LAND
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 73/82
MITIGATING MEASURES
SECTION: JP LINE (40km00 to 45km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
45km00 S
44km80 F
44km60 F
44km40 F
44km20 S
44km00 S
43km80 S
43km60 S
43km40 S
43km20 S
43km00 C
42km80 C
42km60 C
42km40 C42km20 C
42km00 F
41km80 F
41km60 F
41km40 F
41km20 F
41km00 F
40km80 F
40km60 F
40km40 F
40km20 F
40km00 G
Centurion area being reassessed
by Bidder
________________
_______________ N1 Freeway
Railway line parallel andadjacent to N1 Freeway▼
◄BRAKFONTEIN INTERCHANGE
▲ Railway line parallel andadjacent to N1 Freeway
___________________
John Vorster Drive
___________________ N1 Freeway
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
HIGHVELD TECHNOPARK
▼
▲ HIGHVELD TECHNOPARK
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-UNDEVELOPED LAND
▼
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting; C/C = Cut & cover.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 74/82
MITIGATING MEASURES
SECTION: JP LINE (45km00 to 50km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
50km00 F
49km80 F
49km60 F
49km40 F
49km20 F
49km00 F
48km80 F
48km60 F
48km40 F
48km20 F
48km00 G
47km80 S
47km60 S
47km40 S 47km20 S
47km00 S
46km80 F
46km60 F
46km40 F
46km20 F
46km00 S
45km80 S
45km60 S
45km40 S St St
45km20 S
45km00 S
_______________
▲ MILITARY LAND
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
LYTTELTON AH
▼
◄CLUBVIEW
______________ N14 Freeway
______________
Centurion area being re-assessed byBidder
▲ LYTTELTON AH
______________
CENTURION CBD
______________
______________
________________ Road M10 (K103)
▲ Railway line adjacent
to N14 Freeway-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
LYTTELTON AH
▼
________________ N14 Freeway
________________ Rabie Street
▲ LYTTELTON AH
_________________
Gerhard Street
CENTURION STATION
_________________ West Avenue_________________ Lenchen Street
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting; C/C = Cut & cover.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 75/82
MITIGATING MEASURES
SECTION: JP LINE (50km00 to 55km00) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
55km00 C
54km80 C
54km60 C
54km40 C
54km20 C
54km00 C
53km80 F
53km60 F
53km40 F
53km20 F
53km00 F
52km80 F
52km60 C
52km40 C52km20 C
52km00 C
51km80 C
51km60 F
51km40 C
51km20 F
51km00 F
50km80 F
50km60 F
50km40 S
50km20 F
50km00 F
Southern approach to Pretoria Station
being re-assessed by Bidder
________________ N14 Freeway
PARKLAND (UNDEVELOPED)
▼
▲ PARKLAND (UNDEVELOPED)
________________ -x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
MILITARY LAND
▼
________________
________________ N14 Freeway
PARKLAND (UNDEVELOPED)
▼
▲ PARKLAND (UNDEVELOPED)
_________________ Eeufees Road -x-x-x-x-x-x-x-x-x-x-x-x-x
MILITARY LAND
▼
▲ Railway line adjacent
to N14 Freeway
___________________ Snake Valley Road(Road M24)
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting; C/C = Cut & cover.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 76/82
MITIGATING MEASURES
SECTION: SA LINE (0km00 to 3km60) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
3km60 F
3km40 F
3km20 F
3km00 F
2km80 C
2km60 C
2km40 C
2km20 C
2km00 C
1km80 C
1km60 C
1km40 C
1km20 C
1km00 C 0km80 C
0km60 C
0km40 F St St
0km20 F
0km00 F
▲ MODDERFONTEIN LAND
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
____________
ٱ 2,5m earth berm or wall
LINBRO PARK AH ______________ -x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x
MODDERFONTEIN AH ____________
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
____________
MARLBORO GARDENS
▼
▲ MODDERFONTEIN LAND
-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
_____________
Douglas Road
ٱ 4m earth berm or wall
ٱ 2,5m earth berm or wall
___________ LINBRO PARK AH First Road -x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-x-
___________ MODDERFONTEIN AH
Third Road -x-x-x-x-x-x-x-x-x-x-x-x-x-x-
____________ N3 Freeway
MARLBORO STATION
ٱ 4m wall
MARLBORO GARDENS
▼
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 77/82
MITIGATING MEASURES
SECTION: SA LINE (3km60 to 8km60) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
8km80
8km60 C
8km40 F
8km20 F
8km00 F
7km80 F
7km60 F
7km40 F
7km20 F
7km00 F
6km80 C
6km60 C
6km40 C
6km20 G
6km00 F5km80 F
5km60 F
5km40 F
5km20 F
5km00 F
4km80 F
4km60 F
4km40 F
4km20 F
4km00 F
3km80 F
3km60 F
ٱ 4m earth berm or wall
◄ESTHER PARK
________________
________________
________________
◄MODDERFONTEIN FACTORY AREA
ٱ 4m earth berm or wall
◄MODDERFONTEIN VILLAGE
__________________
Modderfontein Road
__________________ Centenary Road
__________________ INDUSTRIAL ► Centenary Road
ٱ 4m earth berm or wall
THORNHILL►
LAKESIDE►
ٱ 4m earth berm or wall
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 78/82
MITIGATING MEASURES
SECTION: SA LINE (8km60 to 13km80) BIDDER ALIGNMENT
DESCRIPTION OF MITIGATING MEASURE
ExtentKm
Distance
Cross
Sect
Left of the TracksL R
Right of Tracks
13km80 S
13km60 S
13km40 S St St
13km20 S
13km00 S
12km80 S
12km60 F
12km40 F
12km20 C
12km00 C
11km80 C
11km60 C
11km40 C
11km20 C
11km00 C10km80 C
10km60 F
10km40 F
10km20 F
10km00 F
9km80 F
9km60 F
9km40 F
9km20 C
9km00 C
8km80 C
8km60 C
◄RHODESFIELD HIGH SCHOOL
__________________
Railway line +++++++++++++++++++++++
ٱ 4m wall
▲ RHODESFIELD
__________________ INDUSTRIAL ▼
▲ INDUSTRIAL (SPARTAN)
_________________
CRESSLAWN▼
ٱ 4m wall
▲ CRESSLAWN
_________________ INDUSTRIAL (SPARTAN)
▼
Access to JIA being re-assessed by
Bidders
RHODESFIELD STATION
_____________
Anson Street ++++++++++++++++++++++
INDUSTRIAL
▼
______________ Western Road
_______________
Chestnut Street
_________________
Zuurfontein Road
▲ INDUSTRIAL (SPARTAN)
Legend:
• Cross-section : T = Tunnel; F = Fill; S = Structure; G = Grade; C = Cutting.
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 79/82
APPENDIX B:
DRAFT HERITAGE REPORT TO SAHRA ON STATION AND
TUNNEL PORTAL/SHAFT PROPERTIES AFFECTED BY THE
PREFERRED BIDDER ALIGNMENT
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 80/82
APPENDIX C:
ADVERT FOR PUBLIC PARTICIPATION PROCESS
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 81/82
8/7/2019 Gautrain - Minor amendments _01 12 05_ no 6
http://slidepdf.com/reader/full/gautrain-minor-amendments-01-12-05-no-6 82/82