shaft sinking installation - application and … · web viewfor friction winders or drum winders...

46
Application and assessment for shaft sinking installation and approval of shaft sinking operations Statutory requirements for winding systems and shaft sinking are contained in Parts 11 and 12 of the Mines Safety and Inspection Regulations 1995 (MSIR) and any Australian Standards (AS) referenced therein. Regulations 12.3 and 12.4 of the MSIR require notification to, and approval from, the senior inspector of mines before sinking any new shaft or extending any existing shaft. Proposed shaft sinks using a mobile crane may be approved for use by the senior inspector of mines for shaft depths up to 50 m (refer regulation 12.5). If the proposed shaft sink uses a temporary winding system, approval is required from the State mining engineer under regulations 11.3 and 11.4 of the MSIR for the installation and use of the temporary winding system. If modifications or repairs are required to the temporary winding system used in the shaft sink then notification and approval of the repairs are required under regulations 11.6 and 11.7 respectively. This form may be used to obtain such approvals for any shaft sinking proposals (including modifications or repairs) that include the use of mobile cranes and/or temporary winding installations. Note: Applications for approval of permanent winding installations (including modifications or repairs) must be submitted using the separate application form available. This form assists mine managers or other responsible persons to prepare the application. Departmental officers will also use the form for assessment and approval. Approval typically includes several stages: Stage 1A – Shaft pre-sink Assessment of proposal for sinking of the shaft collar and installation of collar equipment (i.e. the shaft pre-sink). If the pre-sink operations only involve the use of a registered mobile crane to hoist broken rock (i.e. no temporary winding equipment) then a structural/mechanical design review is generally not required. If temporary winding equipment is required for the pre-sink or for further shaft sinking beyond 50m depth, then design approval of the temporary winding system is required. Stage 1B – Design approval of temporary winding system The initial approval of the temporary winding system design is largely a desktop assessment of the various components of the winding system based on design drawings, engineers’ calculations and other documentation. Any approval of the design will be contingent on submission and acceptance of the manufacturing, inspection and test records as well as final site inspection/testing. Application for shaft sinking installation and approval of shaft sinking operations Page 1 of 46

Upload: others

Post on 22-Feb-2020

31 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Application and assessment for shaft sinking installation and approval of shaft sinking operationsStatutory requirements for winding systems and shaft sinking are contained in Parts 11 and 12 of the Mines Safety and Inspection Regulations 1995 (MSIR) and any Australian Standards (AS) referenced therein.

Regulations 12.3 and 12.4 of the MSIR require notification to, and approval from, the senior inspector of mines before sinking any new shaft or extending any existing shaft. Proposed shaft sinks using a mobile crane may be approved for use by the senior inspector of mines for shaft depths up to 50 m (refer regulation 12.5). If the proposed shaft sink uses a temporary winding system, approval is required from the State mining engineer under regulations 11.3 and 11.4 of the MSIR for the installation and use of the temporary winding system. If modifications or repairs are required to the temporary winding system used in the shaft sink then notification and approval of the repairs are required under regulations 11.6 and 11.7 respectively.

This form may be used to obtain such approvals for any shaft sinking proposals (including modifications or repairs) that include the use of mobile cranes and/or temporary winding installations.

Note: Applications for approval of permanent winding installations (including modifications or repairs) must be submitted using the separate application form available.

This form assists mine managers or other responsible persons to prepare the application. Departmental officers will also use the form for assessment and approval. Approval typically includes several stages:

Stage 1A – Shaft pre-sinkAssessment of proposal for sinking of the shaft collar and installation of collar equipment (i.e. the shaft pre-sink). If the pre-sink operations only involve the use of a registered mobile crane to hoist broken rock (i.e. no temporary winding equipment) then a structural/mechanical design review is generally not required.

If temporary winding equipment is required for the pre-sink or for further shaft sinking beyond 50m depth, then design approval of the temporary winding system is required.

Stage 1B – Design approval of temporary winding systemThe initial approval of the temporary winding system design is largely a desktop assessment of the various components of the winding system based on design drawings, engineers’ calculations and other documentation.

Any approval of the design will be contingent on submission and acceptance of the manufacturing, inspection and test records as well as final site inspection/testing.

Stage 2 – Manufacturing, inspection and testing recordsAll material certificates, rope certificates, fabrication records, manufacturer’s data report (MDR), non-destructive testing (NDT) records, load test certificates and other compliance documents are required to be available for inspection. If available at the time, copies of this documentation may be included with the initial design submission (Stage 1), or may be submitted later, but before stage 3 final site inspection/testing.

This application form may initially be submitted with some or all of the stage 2 information incomplete. Such items should be marked “to be advised” for the stage 1 submission. The form may be updated and resubmitted when all the stage 2 information is available.

Application for shaft sinking installation and approval of shaft sinking operations Page 1 of 33

Page 2: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Stage 3 – Final site inspection/testingOn completion of the installation of the temporary winding system, the proponent is required to contact the Mines Safety Directorate to arrange site inspection and witnessing of the site performance testing. Final approval to use the temporary winding system is granted on the basis of a satisfactory site assessment by an inspector of mines [MSIR r. 11.5] who makes an appropriate entry in the winder record book.

Note on independent design verification

Although the regulations in Part 11 of the MSIR do not require design verification for an application to be accepted, design verification is highly recommended for the following reasons:

it demonstrates appropriate engineering due diligence by the applicant

it reduces the need for a detailed check by departmental officers (i.e. approval times are reduced)

less potential for errors and defects to be discovered by departmental officers (i.e. less questions, delays and re-work).

Pursuant to MSIR regulation 11.3(2), Departmental officers may choose to request an independent design verification if significant design issues are observed (i.e. potential delays and rework).

Design verification (or validation) should be undertaken by a competent person who was not involved with the design. This may include, but is not necessarily limited to, third party independent verifiers.

List of abbreviationsMSIR Mines Safety and Inspection Regulations 1995

r. Regulation of the MSIR

rr. Regulations of the MSIR

AS Australian Standard

HRWL High Risk Work Licence

MDR Manufacturer’s data report

NDT Non-destructive testing

OEM Original equipment manager

RMP Risk management plan

SG Site group

SRS Safety Regulation System

WLL Working load limit

Depending on the nature of the operation only the relevant part(s) of the application need to be completed. It is essential the items completed are addressed in sufficient detail for the application to be properly assessed. Additional information may be requested if required.

Application for shaft sinking installation and approval of shaft sinking operations Page 2 of 33

Page 3: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part A – Applicant and contractor details

Details required Application details

Applicant’s name

Applicant’s position

Applicant’s employer/company name

Applicant’s postal address

Applicant’s phone/mobile

Applicant’s email address

Name of mining operation (from SRS)

Name of principal employer

SRS site operation (SG) reference ID(s)

Name of shaft or rise

Name of shaft sinking principal contractor

Contractor’s postal address

Project contacts – names, roles, phone numbers, email address

Application for shaft sinking installation and approval of shaft sinking operations Page 3 of 33

Page 4: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part B – Scope and nature of proposal

Details required Provide comments and advise location within relevant attachments

Type of approval (tick as many as are applicable) New shaft sink Extension (deepening/stripping) existing shaft/rise Crane to be used for shaft sink Temporary winding system to be used for shaft sink Repair of temporary shaft sink winder system Modification or alteration of temporary winder system

General arrangement drawings showing: Plan(s) showing location of shaft (whole mine

and shaft site) Depths, diameter, cross-section of shaft and

collar Mechanical/Structural general layout of

temporary headframe and winding equipment (plan and elevations).

Drawings to be at approved for construction revision status.(List all drawing titles and drawing numbers with correct revision status)

Provide details on the shaft sink development cycle and stages to be followed

Will sink require boring or stripping?

Proposed commencement date

Expected period of shaft sinking operation.Provide schedule/dates for major stages

Application for shaft sinking installation and approval of shaft sinking operations Page 4 of 33

Page 5: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

C1 – Headframe structure [rr. 11.3, 11.27, 11.67 and 12.3, and AS 3785.5, 1657, 3990, 4100 and 1170]

Drawings showing: Structural design details of headframe

structure, including all dimensions, member sizes and materials.

All structural connection details, including bolting and welding details.

Drawings to be at approved for construction revision status.(List all drawing titles and drawing numbers with correct revision status)

Name of structural designer

Name of structural fabricator

Name of structural installation contractor

Date of manufacture

Date of installation

Is the headframe new, relocated or refurbished?If relocated or refurbished, where was it previously used?

Design calculations to load combinations required by AS 3785.5 – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice.Calculation report to include basis of design and design criteria, including all load cases considered and demonstrate that the design shown on the referenced drawings is compliant, safe and fit for purpose.(List document number and revision status for calculation report)

Name of design verifier

Ladder access on head frame complies with AS 1657 – ladder cage included if required

Any platforms supported off headframe – top and/or intermediate– comply with AS 1657?

Any fall restraint anchors required off ladder or platforms – comply with AS 1891?

Handrails and gates comply with AS 1657?

Non-destructive testing (NDT) reports: Main stays, raker legs, connecting plate bolts,

pins, welds, etc. (i.e. all structural components in load path)

(List all certificate numbers with component mark numbers, dates and revisions)

Overwind prevention (describe)

Travel limit switches and other safety devices –

Application for shaft sinking installation and approval of shaft sinking operations Page 5 of 33

Page 6: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

type, locations in headframe and function description.Preferably include information on single drawing showing: Conveyance at highest normal position and

tolerance on this position Headframe overwind distance – for drum

winder, the travel distance from highest normal position to where the conveyance enters catch plate. For friction winder, the travel distance from highest normal position to where conveyance enters arrestors

Arrestor travel (friction winders only) Location of crash beams (if applicable) Extent of jack catches Position of lip of ore bin for skips Conveyance at lowest position in shaft (and

any intermediate positions) and the decking tolerance on these positions (e.g. showing lip of the skip and lip of the loading flask)

For friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind arrestor, arrestor travel distance, location of crash beams, and location of tail loop

For rope guide systems – location of top/bottom fixed guides, location of guide rope top/bottom anchors, location of cheese weights (including tolerance for thermal, elastic and permanent rope stretch)

Headframe identification number: Owners’ plant identification number (if

available) Manufacturer’s serial number Any other unique identifying tag numbers

C2 – Headframe foundation [rr. 11.3 and 12.3, and AS 3785.5, 1657, 2626, 3990 and 4100]

Foundation drawings showing: All holding down bolt details Design details of all concrete footings, slabs

and foundations, including dimensions, reinforcement details and concrete specification

Any civil and earthwork details and founding ground conditions required for footings, slabs, foundations or free standing skid bases

Drawings to be at approved for construction revision status(List all drawing titles and drawing numbers with correct revision status)

Name of civil/concrete designer

Name of civil/concrete works contractor

Date of installation

Application for shaft sinking installation and approval of shaft sinking operations Page 6 of 33

Page 7: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Design calculations to load combinations required by AS 3785.5 – preferably verified by competent engineer and signed-off to confirm compliance with relevant Australian Standards and sound engineering practiceCalculation report to include basis of design and design criteria, including all load cases considered and demonstrate that the design shown on the referenced drawings is compliant, safe and fit for purpose(List document number and revision for calculation report)

Name of design verifier

Geotechnical report: Prepared by Document number, date and revision

Allowable bearing pressure for foundation design

C3 – Sheave wheels [rr. 11.3 and 11.65, and AS 3785.7, 1418.1, 3990 and 4100]

Design detailed drawings of all sheave wheels including all dimensions, materials of construction, machining and welding details, heat treatments, etc.Drawings to be at approved for construction revision status, or manufacturer’s certified (as-built) sheave wheel drawings (if available).(List all drawing titles and drawing numbers with correct revision status)

Name of designer of sheave

Name of manufacturer/supplier

Date of manufacture

Is the sheave wheel new, relocated or refurbished?If relocated or refurbished, where was it previously used?

Design calculations to load combinations required by AS 3785.7 – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of design verifier

Component test certificates and NDT reports: List all certificate numbers with component

mark numbers, dates and revisions

Manufacturers statement of compliance to AS 3785.7

Ratio sheave PCD to rope diameter

Depth of rope groove is at least twice rope diameter?

Application for shaft sinking installation and approval of shaft sinking operations Page 7 of 33

Page 8: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Markings as per AS 3785.7, Section 9: Part number or serial number

C4 – Sheave shaft [r. 11.3 and AS 1403, 3990 and 4100]

Design detailed drawing of sheave shaft including all dimensions, materials of construction, machining and welding details, heat treatments, etc.Drawings to be at approved for construction revision status or manufacturers certified (as-built) drawings if available(List all drawing titles and drawing numbers with correct revision status)

Name of designer of shaft

Name of manufacturer

Date of manufacture

Is sheave shaft a stationary or rotating design?

Is the sheave shaft new, relocated or refurbished?If relocated or refurbished, where was it previously used?

Design calculations (fatigue and static design) as per AS 3785.7 and AS 1403 – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice.Design to include static and fatigue analysis

Name of design verifier

Component test certificates and NDT reports: List all certificate numbers with component

mark numbers, dates and revisions

Markings as per AS3785.7, Section 9: Part number or serial number

C5 – Conveyances – cage [rr. 11.3, 11.52, 11.53, 11.54, 11.55, 11.69, and AS 3785.4, 3990 and 4100]

Design detailed drawing of cage including all dimensions, materials of construction, machining and welding details, etc.Drawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of conveyance designer

Design calculations to AS 3785.4 – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of design verifier

Name of manufacturer

Application for shaft sinking installation and approval of shaft sinking operations Page 8 of 33

Page 9: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Date of manufacture

Floor area (m2)

Rating (WLL in kg)

Capacity (number of persons)

Floor area (m2) per person (must be no less than 0.2)

Weight of conveyance (empty)

Gripper mechanism adequately described on drawings? If guides and grippers not fitted, slack rope detection required.

Gates: height / type / fastened / open inwards and adequately described on drawings?

Wall coverings – adequately described on drawings?

Ventilation – adequately described on drawings?

Number of decks: one or two?

Lower deck ladder and trapdoor – adequately described on drawings?

Overhead protection/top cover – adequately described on drawings?

Height of cage floor to roof (2 metres, AS 3785.4)

Chairing devices – describe

Is the conveyance new, relocated or refurbished?If relocated or refurbished, where was it previously used?

NDT reports for main load bearing components: List all certificate numbers with component mark numbers, dates and revisions

Proof loaded to 2 x normal static load: Test load Name of testing authority Test Cert No. and date

Markings as per AS 3785.4: Manufacturers serial number

C6 – Conveyances – gig [AS 3785.4, 3990 and 4100]

Design detailed drawing of gig including all dimensions, materials of construction, machining and welding details, etc.Drawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Application for shaft sinking installation and approval of shaft sinking operations Page 9 of 33

Page 10: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Name of designer

Name of manufacturer

Date of manufacture

Design calculations to AS 3785.4 – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of design verifier

Rating (WLL in kg)

Empty weight

Capacity (number of persons)

Floor area (m2) (must be no less than 0.2 per person)

Gates: height / type / fastened / open inwards and adequately described on drawings?

Wall coverings – to prevent body parts protruding from gig - adequately described on drawings?

Wall bars rounded off top and bottom?

Number of decks: one or two?

Lower deck ladder and trapdoor – adequately described on drawings?

Overhead protection/top cover – adequately described on drawings?

Clearance to safety appliance top cover

Is the gig new, relocated or refurbished?If relocated or refurbished, where was it previously used?

NDT reports for main load bearing components: List all certificate numbers with component

mark numbers, dates and revisions

Proof loaded to 2 x maximum static load (empty weight plus rated capacity): Test load Name of testing authority Test Cert No. and date

Markings as per AS 3785.4: Manufacturers Serial Number

C7 – Conveyances – skip [rr. 11.3, 11.56 and 11.69, and AS3785.4, 3990 and 4100]

Application for shaft sinking installation and approval of shaft sinking operations Page 10 of 33

Page 11: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Design detailed drawing of skip including all dimensions, materials of construction, machining and welding details, etc.Drawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer

Name of manufacturer

Date of manufacture

Design calculations to AS 3785.4 – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of design verifier

Is the skip configured to carry people as per r. 11.56(1)? If yes, what is floor area (m2)? Is the removable platform adequately described on drawings?

Rating (m3 and kg)

Capacity (number of persons)

Floor area (m2) per person (must be no less than 0.2)

Weight of skip (empty)

Overhead protection/top cover fitted? Is it adequately described on drawings?

Height of floor to roof (2 metres AS 3785.4)

Gripper mechanism adequately described on drawings? If grippers not fitted, slack rope detection required

Chairing devices fitted – describe

Is the skip new, relocated or refurbished?If relocated or refurbished, where was it previously used?

NDT reports for main load bearing components: List all certificate numbers with component mark numbers, dates and revisions

Proof loaded to 2 x normal static load: Test load Name of testing authority Test Cert No. and date

Markings as per AS3785.4: Manufacturer’s serial number

C8 – Conveyances – kibble [r. 12.10 and AS3637.6, 3785.4, 3990 and 4100]

Application for shaft sinking installation and approval of shaft sinking operations Page 11 of 33

Page 12: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Design detailed drawing of kibble including all dimensions, materials of construction, machining and welding details, etc.Drawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer

Name of manufacturer

Date of manufacture

Design calculations to AS 3785.4 – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of design verifier

Rating (m3 and kg)

Weight – empty

Overhead protection (usually part of monkey or crosshead arrangement)

Is the kibble new, relocated or refurbished?If relocated or refurbished, where was it used previously?

Chain angle not > 60 degrees?

Robust construction/shape to prevent it from catching on any obstruction during travel in shaft?

Suspended by bridle or means of at least 3 chains equally spaced around perimeter of top?

Chains used for suspension of kibble:(a) Identical dimensions/ strength(b) Sufficient length to ensure included angle at

apex of suspension of any 2 chains does not exceed 60°

(c) Designed, manufactured and tested to comply with AS 3637.6?

NDT reports for main load bearing components: List all certificate numbers with component mark numbers, dates and revisions

Proof loaded to 2 x max static load (dead weight plus live load): Test load Name of testing authority Test Cert No. and date

Markings as per AS3785.4: Manufacturer’s serial number

C9 – Conveyances – stage [r. 12.19 and AS 3785.4, 3990 nad 4100]

Application for shaft sinking installation and approval of shaft sinking operations Page 12 of 33

Page 13: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Design detailed drawing of shaft sinking stage including all dimensions, materials of construction, machining and welding details, etc.Drawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer

Name of manufacturer

Date of manufacture

Design calculations – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice.

Name of design verifier

Able to support travel gig?

Maximum working load of stage

Maximum load allowed to be suspended off stage (e.g. shuttering)

Empty weight

Floor area (m2)

Maximum number of people allowed on stage

Floor area (m2) per person (must be no less than 0.2)

Gates: height / type / fastened / open inwards and adequately described on drawings?

Wall bars (rounded off top and bottom) – adequately described on drawings?

Number of decks: one/two/three?

Top deck trapdoor included?

Upper, lower and top deck ladders and trapdoors – adequately described on drawings?

Height of floor to roof (2 metres, AS 3785.4)

Overhead protection for persons on top deck – adequately described on drawings?

Is the stage new, relocated or refurbished?If relocated or refurbished, where was it previously used?

Compressed air supply – adequately described on drawings?

Water supply – adequately described on drawings?

Application for shaft sinking installation and approval of shaft sinking operations Page 13 of 33

Page 14: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Electricity supply – adequately described on drawings?

NDT reports for all major load bearing components: List all certificate numbers with component

mark numbers, dates and revisions

Proof loaded to 2 x maximum static load (empty weight plus rated capacity): Test load Name of testing authority Test Cert No. and date

Markings: Manufacturer’s Serial Number

C10 – Monkey [r. 12.9 and AS3785.4, 3990 and 4100]

Design detailed drawing of monkey including all dimensions, materials of construction, machining and welding details, etc.Drawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer

Name of manufacturer

Date of manufacture

Design calculations – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of design verifier

Rated capacity (kg)

Aspect ratio (height/width) preferably aspect ratio 1.5:1 (minimum ratio is 1)

Design approved by senior inspector of mines (for shaft depth over 50 m)?

Overhead protection – adequately described on drawings?

Is the monkey new, relocated or refurbished?If relocated or refurbished, where was it previously used?

NDT reports for major load bearing components: List all certificate numbers with component mark numbers, dates and revisions.

Markings: Manufacturer’s serial number

Application for shaft sinking installation and approval of shaft sinking operations Page 14 of 33

Page 15: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

C11 – Winding ropes [rr. 11.3, 11.38, 11.39, 11.40, 11.41, 11.44, 11.45, 11.61, 11.62, 11.63 and 12.7, and AS 3569 and 3637.3]

Name of rope manufacturer(s)(List all ropes used for stage winder and all other hoists and winders)

Name of rope supplier(s)

Purchase date(s)

Are the ropes new or previously used? Where were they used and for how long?

Are the various rope specifications adequately referenced on the drawings?

Manufacturer’s rope test certificate(s) with the following information: Date of manufacture Date of destructive test Nominal diameter and lay length Construction Wire grade and finish Rope mass per metre Minimum guaranteed robe break load Actual rope break load from destructive test Load-strain curve from destructive testList all certificate numbers with dates

Minimum guaranteed rope break load (RBL) – list for each diameter and type of rope

Actual rope break load (from destructive test results) – list for each diameter and type of rope

Rope factors of safety calculations for each type of conveyance to be used. Preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of designer

Name of verifier

Most recent destructive test reports for each type and size of rope (if not new): List all certificate numbers with dates

Most recent non-destructive test reports for each type and size of rope (if not new): List all certificate numbers with dates

C12 – Winding engine [rr. 11.3, 11.14, 11.15, 11.16, 11.20 and 11.25]

How many winding engines are included (e.g. stage winder, cage winder, etc.)? List here

Engine types (e.g. pneumatic, electric/hydraulic). List for details for each engine

Application for shaft sinking installation and approval of shaft sinking operations Page 15 of 33

Page 16: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Original equipment manager (OEM) drawings of winding engine(s) including all interface dimensions, weights and foundation loadsDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of manufacturer(s)

Engine/motor model number(s)

Date(s) of manufacture

Name of supplier(s)

Purchase date(s)

Calculations for winding engine selection, including duty cycle calculations, capacity to lift maximum unbalanced load, etc. – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of designer (for engine sizing/selection)

Name of design verifier

Rated power output (kW) @ rpm Note: Must be >25 kW to be a winder. If < 25 kW it is a hoist

Power available (kW) @ rpm

Maximum line pull (kN) at rated power

Maximum line pull (kN) when motor stalled

Maximum line speed (m/s)

Winder(s) to be used with what rope diameter?How many layers on drum(s)? Is/are the drum(s) grooved? Parallel or spiral grooves?What are the fleet angles?

Depth indicator – type and location adequately described on drawings?

Speed indicator – type and location adequately described on drawings?

Other gauges and indicators – adequately described on the drawings?

Electric power source required (i.e. Volts, Amps, 3-Ph or 1-Ph)

Hydraulic working pressure(s) – drive and brake circuits, if applicable

Drive to drum direct, through gearbox, through chains, or other?

Application for shaft sinking installation and approval of shaft sinking operations Page 16 of 33

Page 17: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Overall drive ratio (engine to drum shaft)

NDT reports for major load bearing components: List all certificate numbers with component mark numbers, dates and revisions

Is the engine new, relocated or refurbished?If relocated or refurbished, where was it previously used?

Identification No: Manufacturers’ serial number

C13 – Hoist [rr. 11.3, 11.11 11.22 and 11.48]

How many hoists are included (e.g. stage, skip)? List here

Hoist type(s) (e.g. pneumatic, electric/hydraulic)

OEM drawings of hoist(s) including all interface dimensions, weights and foundation loadsDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of manufacturer(s)

Hoist model(s) and serial number(s)

Date(s) of manufacture

Name of supplier(s)

Purchase date(s)

Calculations for hoist sizing/selection, including duty cycle calculations, capacity to lift maximum unbalanced load, etc – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of designer (for sizing and selection)

Name of design verifier

Power source: pneumatic / electric / hydraulic: Compressed air supply required (volume and

pressure) Electric power required (kW, voltage, amps, 3-

Ph or 1-Ph) Hydraulic working pressure

Power available (kW) @ rpm

Maximum line pull (kN) @ rpm

Maximum line pull (kN) when motor stalled

Maximum line speed (m/s)

Application for shaft sinking installation and approval of shaft sinking operations Page 17 of 33

Page 18: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Hoist to be used with what rope diameter?How many layers on drum? Is/are the drum grooved? Parallel or spiral grooves?What are the fleet angles?

NDT reports for major load bearing components: List all certificate numbers with component mark numbers, dates and revisions

Is the hoist new, relocated or refurbished?If relocated or refurbished, where was it previously used?

Identification No: Manufacturer’s serial number

C14 – Winding engine / hoist brakes [rr. 11.3, 11.6, 11.18 and 11.66]

Brake type(s) and where they are applied (e.g. shoe/calliper, disc)

OEM drawing of winder/hoist brakes including all dimensions and componentsDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of manufacturer

Name of supplier

Design calculations for brake sizing/ selection – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of designer (for sizing/selection)

Name of design verifier

Double drum - brakes on each drum?

Single drum - single brake / double brake?

Are multiple braking systems independent?

Method of operation - manual, power, automatic?

Power or pressure failure – are brakes fail safe (i.e. automatically applied)

Designed to support 2 x max static load (winders) or 1.5 x max static load (hoists)?

NDT reports for brake components(List all certificate numbers with component mark numbers, dates and revisions)

C15 – Winding engine foundation [rr. 11.3 and 11.14]

Application for shaft sinking installation and approval of shaft sinking operations Page 18 of 33

Page 19: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Foundation drawings showing:

All holding down bolt details Design details of all concrete footings, slabs

and foundations, including dimensions, reinforcement details and concrete specification

Any civil and earthwork details and founding ground conditions required for footings, slabs, foundations or free standing skid bases

Drawings to be at approved for construction revision status, or manufacturers certified (as-built).(List all drawing titles and drawing numbers with correct revision status)

Name of civil/concrete designer

Name of civil/concrete contractor

Installation date

Design calculations to 1.2 minimum breaking strength of rope and other load cases required by AS3785 – preferably verified by competent engineer and signed-off to confirm compliance with relevant Australian Standards and sound engineering practiceCalculation report to describe basis of design and design criteria, including all load cases considered and demonstrate that the design shown on the referenced drawings is compliant, safe and fit for purpose(List document number and revision for calculation report)

Name of design verifier

Geotechnical report: Prepared by Document number, date and revision

Allowable bearing pressure used for foundation design.

C16 – Winding engine – rope drum and shaft [rr. 11.3, 11.64 and 11.65, and AS 1418.1]

OEM drawings of rope drum and shaft including all dimensions, material specs, thicknesses, weld detailsDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer

Name of manufacturer

Name of supplier

Date of manufacture

Application for shaft sinking installation and approval of shaft sinking operations Page 19 of 33

Page 20: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Design calculations – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice. Must include static and fatigue design(List document number and revision for calculation report)

Name of design verifier

Drum flanges or horns?

Flange above rope > 2 times rope diameter or 100 mm

Rope drum diameter

Rope drum material – grade of steel

Rope drum: Grooved (parallel or spiral) or plain? With or without sleeves?

Rope drum: Rope capacity (m). How many layers of rope on drum at top of

wind? How many idle coils or layers of rope left at

bottom of wind? What is the fleet angle?

Drum shaft basic diameter

Drum shaft material – grade of steel

Drum shaft – designed for infinite fatigue life?

Shaft material certificate: Certificate No. / date / revision

Shaft NDT reports(List all certificate numbers with component mark numbers, dates and revisions)

Drum NDT reports (welds)(List all certificate numbers with component mark numbers, dates and revisions)

Attachment of winding engine to drum (fixed / clutched) – adequately described on drawings?

Methods of securing rope to drum – adequately described on drawings?

Is the hoist drum and shaft new, relocated or refurbished?If relocated or refurbished, where was it previously used?

Identification No: Manufacturer’s serial number

Application for shaft sinking installation and approval of shaft sinking operations Page 20 of 33

Page 21: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

C17 – Rope capping [rr. 11.3 and 11.43 and AS 3637.3]

Type of rope capping: white metal filled wire rope sockets / resin filled rope sockets/ capel, other

Drawing or data sheet for rope capping methodDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing or data sheet titles and drawing numbers with correct revision status)

Name of designer (for sizing/selection of rope capping)

Name of manufacturer

Name of supplier

Date fitted to rope: (6 months maximum)

Design calculations for sizing/selection of rope capping – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice(List document number and revision for calculation report)

Name of design verifier

Rope capping manufacturer’s test certificates Proof load tests for capel or socket

Senior inspector of mines approval of rope capping method and compounds used

NDT reports of rope socket, capels, pins, etc(List all certificate numbers with component mark numbers, dates and revisions)

Identification No: Stamped to show SWL / owner’s identification

/ date installed

C18 – Guide ropes [rr. 11.3, 11.43, 11.45, 11.47 and 12.7, and AS 3637.3, 3785.6]

Name of rope manufacturer

Name of rope supplier

Purchase date

Are the ropes new or previously used? Where were they used and for how long?

Application for shaft sinking installation and approval of shaft sinking operations Page 21 of 33

Page 22: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Manufacturer’s rope test certificate, including: Date of manufacture Date of destructive test Nominal diameter and lay length Construction Wire grade and finish Rope mass per metre Minimum guaranteed rope break load Actual rope break load from destructive test Load strain curve from destructive test Is rope specification adequately referenced on

the drawings?

Is rope specification adequately referenced on the drawings?

Factor of safety calculations – preferably verified by competent engineer and signed-off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of designer

Name of verifier

Tension required at bottom end of guide ropes?

Hoist ropes also used as guide ropes?

Most recent destructive test reports for rope (if not new)(List all certificate numbers with dates)

Most recent non-destructive test reports for rope (if not new)(List all certificate numbers with dates)

C19 – Speed control [rr. 11.17, 11.20, 11.22, 11.23, 11.24, 11.25, 11.27 and 11.28]

Functional description of winder controls – speed controls and overwind prevention controls adequately describedFunctional description to be at approved for construction status or final as-built(List all document numbers with correct revision status)

Auto in constant engagement – will it prevent over-wind and over-speed?

Maximum hoisting speeds: Hoisting ore? Hoisting people?

Speed restricted, confirm: Top and bottom of shaft (2 m/s)?

Application for shaft sinking installation and approval of shaft sinking operations Page 22 of 33

Page 23: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Acceleration rates, confirm: Normal (1.5 m/s2)? Emergency (2 - 5 m/s2)?

Overwind preventer in headframe – describe

Confirm back-out device: confirm manual only and permits withdrawal only

Control selection: Confirm if manual / automatic selector is fitted

C20 – Rope detaching appliances (drum winders only) [r. 11.67 and AS 3637.2]

Type of device (e.g. King, Merod, Humble)

Design detailed drawings of detaching gear including all components, dimensions, material specs, thicknesses, weld detailsDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer (for sizing/selection)

Name of manufacturer

Name of supplier

Date of manufacture

Is the detaching gear new or previously used? Where was it used and for how long?

Calculations for sizing/selection of detaching gear – preferably verified by competent engineer and signed off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of verifier

Manufacturer’s certificates – materials certs, compliance statements, proof load certs, NDT certs, etc. (List all certificate numbers with component mark numbers, dates and revisions)

Distance between detaching device on head frame and matching point of conveyance

Rated load capacity

Design load

Factor of safety [r. 12.7]

Most recent NDT reports of detaching gear (if not new)(List all certificate numbers with component mark numbers, dates and revisions)

Application for shaft sinking installation and approval of shaft sinking operations Page 23 of 33

Page 24: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Identification No: Manufacturer’s serial number

C21 – Chains and links [rr. 11.50, 12.7 and 11.58, and AS 3637.1, 3637.6]

Detailed drawings of all chain assemblies including all components, dimensions, material specs, thicknesses Drawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer

Name of manufacturer

Name of supplier

Date of manufacture

Purchase date

Are all the chains and links new or previously used? Where was it used and for how long?

Factor of safety calculations for chains and links – preferably verified by competent engineer and signed-off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of verifier

Rated capacity

Design load

Factor of safety used for design

Manufacturer’s certificates – materials certs, compliance statements, proof load certs, etc. (List all certificate numbers with component mark numbers, dates and revisions)(Mn steel to comply with AS 3637)

Most recent NDT reports for chain assemblies and links (if not new)(List all certificate numbers with component mark numbers, dates and revisions)

Identification No: Manufacturer’s serial number

C22 – Shackles [r. 11.58 and AS 3637.1, 3637.6]

Drawings or data sheets of all shackles including all dimensions, material specs, thicknessesDrawings or data sheets to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Application for shaft sinking installation and approval of shaft sinking operations Page 24 of 33

Page 25: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Name of designer

Name of manufacturer

Name of supplier

Date of manufacture

Purchase date

Are the shackles new or previously used? Where was it used and for how long?

Factor of safety calculations for shackles – preferably verified by competent engineer and signed-off to confirm compliance with relevant Australian Standards and sound engineering practice

Name of verifier

Rated capacity

Design load

Factor of safety for design

Manufacturer’s certificates – materials certs, compliance statements, proof load certs, etc. (List all certificate numbers with component mark numbers, dates and revisions)

Most recent NDT reports for shackles (if not new)(List all certificate numbers with component mark numbers, dates and revisions)

Identification No: Manufacturer’s serial number

C23 – Rope attachment pins [r. 11.58 and AS 3637.1, 3637.6]

Drawings or data sheets of all pins including all dimensions, material specs, thicknessesDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Name of designer

Name of manufacturer

Name of supplier

Date of manufacture

Are the pins new or previously used? Where was it used and for how long?

Factor of safety calculations for pins – preferably verified by competent engineer and signed-off to confirm compliance with relevant Australian Standards and sound engineering practice

Application for shaft sinking installation and approval of shaft sinking operations Page 25 of 33

Page 26: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Name of verifier

Rated capacity

Design load

Factor of safety for design

Manufacturer’s certificates – materials certs, compliance statements, proof load certs, etc. (List all certificate numbers with component mark numbers, dates and revisions)

Most recent NDT reports for pins (if not new)(List all certificate numbers with component mark numbers, dates and revisions)

Identification No: Manufacturer’s serial number

C24 – Rope clamps [r. 11.58 and AS 3637.1, 3569]

Supplier

Manufacturer

Type

Size

Design/manufacturing standard

Manufacturer’s certificates

Number used

Thimble type: heavy duty / solid

Adequately described on drawings?

C25 – Drawbar [rr. 11.58, 12.7 and AS 3637.1]

Design detailed drawings of drawbar including all dimensions, material specs, and thicknessesDrawings to be at approved for construction revision status, or manufacturers certified (as-built)(List all drawing titles and drawing numbers with correct revision status)

Designer

Manufacturer

Supplier

Date of manufacture

Is the drawbar new or previously used? Where was it used and for how long?

Factor of safety calculations for drawbar – preferably verified by competent engineer and signed-off to confirm compliance with relevant Australian Standards and sound engineering practice.

Application for shaft sinking installation and approval of shaft sinking operations Page 26 of 33

Page 27: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part C – Design of shaft sinking installation (where appropriate)

Details required Provide comments and advise location within relevant attachments

Name of verifier

Rated capacity

Design load

Factor of safety for design.

Manufacturer’s certificates – materials certs, compliance statements, proof load certs, etc. (List all certificate numbers with component mark numbers, dates and revisions)

Most recent NDT reports for drawbar (if not new)(List all certificate numbers with component mark numbers, dates and revisions)

Identification No: Manufacturer’s serial number

Application for shaft sinking installation and approval of shaft sinking operations Page 27 of 33

Page 28: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part D – Mining engineering and safety

Details required Provide comments and advise location within relevant attachments

D1 – Safety procedures [r. 12.3(1)(e)]

Risk management plan (RMP) and report No.Include completed risk assessments for shaft and/or crane sinks.

RMP prepared by: name / address

Shaft layout: cross-section on drawings submitted:Drawing: No. / date / revision

All persons authorised / trained / assessed as competent by manager in writing to transmit signals from shaft floor to stage hand positioned on sinking stage, as well as ensuring: Kibble correctly attached to winding rope Kibble properly loaded No broken rock projects above rim Tools, equipment, other materials not carried

together with broken rock, and secured if they project above rim

Nothing capable of causing injury adhering to outside of kibble

When kibble hoisted it is first raised sufficiently to hang free then steadied

D2 – Use of crane [r. 12.5]

Provide details of the crane to be used to hoist broken rock from the initial surface excavation or shaft

Confirm depth crane to be used to hoist broken rock (not exceeding 50 m)

Confirm crane not to be used when shaft perimeter traversed by dividers or any other structure obstructing free passage of shaft conveyance

Confirm any load lifted by crane not exceed 50% of rated capacity of crane (AS 1418)

Confirm crane used is a slewing type located in a fixed position during hoisting and dumping operations

Crane driver appointed to hoist broken rock from initial surface excavation required to have appropriate High Risk Work Licence (HRWL) for that class of crane. List HRWL numbers.Provide details of other training and assessment to comply with regulation 4.13

Crane load should not be able to free fall. Confirm free fall prevention device is fitted and will be enabled

If crane used to hoist broken rock – describe effective method of signalling to allow communication with crane driver

Application for shaft sinking installation and approval of shaft sinking operations Page 28 of 33

Page 29: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part D – Mining engineering and safety

Details required Provide comments and advise location within relevant attachments

Provide detail and confirm persons not raised or lowered from shaft excavation unless: Travels in an approved conveyance Wears safety harness with fall arrest/restraint

attached to an approved anchor point Is within sight of a person stationed in a place

to communicate with the crane driver

Confirm a person must not remain in the shaft excavation while crane is used to hoist broken rock by means of a grab

Provide details on crane drivers’ proposed hours of work and fatigue management measures

Inspection/NDT results for crane rope

Crane rope factors of safety and load calculations

Inspection/NDT results for crane hoist brakes

Crane hoisting speed

D3 – Crane pad foundation

Foundation drawings showing: Design details of all concrete pads, slabs and

foundations, including dimensions, reinforcement details and concrete specification

Any civil and earthwork details and founding ground conditions required

(List all drawing titles and drawing numbers with correct revision status)

Name of civil/concrete designer

Name of design verifier

Name of civil/concrete installation contractor

Installation date

Geotechnical report – document number/ revision/date – provide copy of report

Allowable soil bearing pressure

D4 – Shaft ground condition – assessment

Provide details of any logged bore holes drilled in proximity of shaft location

Provide information on geology in the shaft

Geotechnical assessment made for the project – document number/revision/date - provide copy of report

Ground control management plan (GCMP) – provide copy of GCMP – document number/revision/date - provide copy of report

Application for shaft sinking installation and approval of shaft sinking operations Page 29 of 33

Page 30: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part D – Mining engineering and safety

Details required Provide comments and advise location within relevant attachments

Based on geotechnical report, are following conditions expected – running/free flowing ground; squeezing ground; excessive water in flow; high stressProvide details including control measures

Provide stability analysis for any pillars associated with the shaft sink, e.g. break-through situations

Are specialised sinking techniques, e.g. freezing, pressure grouting, considered for sinkingIf yes, provide details

D5 – Water

Provide details on the assessment made of the 1 in 100 years highest flood level in the area

Submit a map/plan for the site showing contours and surface drainage flows

Provide details on the assessment made of ground water inflows and control measures

D6 – Ventilation

Provide details of ventilation requirements and planned system of ventilation

Provide details on the assessment of atmospheric contaminants and control measures

D7 – Second means of egress

Provide details on the secondary means of egress.

D8 – Alternative means of travel [r. 12.6]

If no alternative winding plant available for raising/lowering persons in emergency (e.g. power failure / winding plant failure): Substantial ladder way securely supported at intervals of not more than 5 metres to be installed from surface to bottom of shaft

If sinking stage used provide details on the provision made to permit travel from shaft bottom to that stage

D9 – Firing [r. 12.13]

Provide details on blasting practices and confirm that firing in shaft sinking is electrically initiated from surface or other safe location, unless otherwise authorised in writing by senior inspector of mines

D10. Pentices [r. 12.14]

Provide details on the protection provided where the shaft is sunk below the level being worked (i.e. it is protected below that level by a securely constructed pentice).

D11 – Protection [r. 12.16]

Application for shaft sinking installation and approval of shaft sinking operations Page 30 of 33

Page 31: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part D – Mining engineering and safety

Details required Provide comments and advise location within relevant attachments

Provide details on provisions to prevent spillage falling down the shaft during dumping operations

Are doors for covering sinking compartment provided and maintained at collar of each shaft while sinking operations are in progress? Provide details.

Confirm unless suitable alternative protection provided to prevent spillage falling down shaft, doors are kept closed at all times when (a) persons, tools, material loaded into or from

kibble / skip at collar of shaft; or (b) kibble / skip being dumped

Provide details of assessment and control measures to minimise risk of harm to persons from falling objects when a crane is used in shaft sinking operations.

D12 – Warning of obstruction [r. 12.17]

Are doors or other shaft protective devices which when moved into shaft haulage way or travel area, interfere with free passage of conveyance, equipped so position positively indicated to winding engine driver?

Confirm slack rope detection device provides visual and audible signals

Confirm emergency brake system and how it is applied

D13 – Signals [r. 12.18]

Confirm signals, other than code of signals, will not be used in shaft sinking without approval in writing of the senior inspector of mines

D14 – Hoisting and lowering of shaft sinking stage [r. 12.19]

Confirm that, except in an emergency, the following procedure are followed when a shaft sinking stage suspended by a stage winder is in use:(a) stage winding only when all other winding

operations in shaft have stopped(b) when stage to be moved, drivers of other

winders advised and stage not moved until their winds are completed and conveyances parked clear of projected stage movement

(c) when stage movement complete drivers of other winders notified and re-establish their stage position marks

D15 – Interlocking [r. 12.12]

Application for shaft sinking installation and approval of shaft sinking operations Page 31 of 33

Page 32: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part D – Mining engineering and safety

Details required Provide comments and advise location within relevant attachments

Provide details and confirm interlocking is provided with winding engine control system so that:(a) when winding taking place, tipping chutes

clear of kibble path(b) during ascending wind, shaft top doors open

when kibble is in zone extending from safe stopping distance below doors until above doors

(c) before discharging kibble into tipping chute, all shaft top doors closed

D16 – Timber bearer sets [r. 12.15]

Confirm if shaft sunk below the level being worked, shaft protected below that level by a securely constructed pentice

Confirm if timber is used to line the shaft bearer sets or other means of support are provided between the working levels or at distances of not more than 60 metres apart

D17 – Indicators and gauges

Provide details on equipment used to measure and detect the following: Ammeter on drive motor

Winding speed

Shaft door obstruction warning

Application for shaft sinking installation and approval of shaft sinking operations Page 32 of 33

Page 33: Shaft sinking installation - application and … · Web viewFor friction winders or drum winders with arrestors – under-wind distance from normal position to entry of the under-wind

Part E – Exemptions likely to be sought to the MSIR

State any exemptions from specific requirements of the MSIR you intend applying for in relation to this submissionAre you the holder of any current specific exemptions that are relevant to this submission?

Application for shaft sinking installation and approval of shaft sinking operations Page 33 of 33