session 6- payment clauses and procedures
TRANSCRIPT
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 1/40
Financial Clauses
and
Procedures
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 2/40
Measurement and Evaluation
Variations and Adjustments
Contract Price and Payments
CLAUSES 12, 13 & 14
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 3/40
Payment Modalities
Lump Sum
Re-measurement
Cost reimbursement
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 4/40
Lump Sum
Scope of the work and the amount is well
defined.
Contractor agrees to work for a pre-determined
lump sum.
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 5/40
Lump Sum
tem
Nr.
Description Unit Qty Rate Amount
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 6/40
Lump Sum ±
Advantages & Disadvantages ± Cost commitment is
known at the outset
± Relatively easycontractor selection
± Fully defined scope
± Contractor assumes
greatest risks
± Time required for
producing full scope
± Changes difficult andpotentially costly
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 7/40
Re- measurement
The scope of the work is generally well defined
but the amount of work is indefinite.
Sufficiently detailed scope of work to allow
contractor to calculate unit rates.
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 8/40
Measure & Pay
tem
Nr.
Description Unit Qty Rate Amount
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 9/40
Measure & Pay
Advantages & Disadvantages Scope need not be asaccurate
Cost per unit of productionpredetermined
Flexibility- scope &quantity can bevaried.
Final cost not clearly
known
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 10/40
Cost Reimbursement
Contractor is paid all what he spends plus OH & Profit.
Minimal pre-determined scope definition.
Clear and explicit definition of what constitutesreimbursable costs.
Co-operative atmosphere and a competent and
trustworthy contractor.
Close audit and quality supervision and direction by the
Client.
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 11/40
Cost Reimbursement
Item
Nr.
Schedule UnitRate
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 12/40
Cost Reimbursement
Advantages & Disadvantages Useful when the
scope cannot be
specified in advance
Minimal pre-
determined scope
definition permitsearly start
Final cost unknown
Buyer retains risk
Reduces ability to
compare contractor¶s
bids
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 13/40
Contract Price and Payment
Sub Clause 14.1 ± Contract Price may be
represented through Bill of Quantities (re-measured) or Schedules
Sub Clause 14.2 ± Anticipates that advance
payment will be made and procedures provided
15 sub clauses relate to this vital sector
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 14/40
Measurement and Evaluation
(Clauses 12.1 and 12.2)
Measurements is undertaken by the Engineer,
giving notice to the Contractor¶s Representative
to attend etc.
Measurement shall be net actual quantities
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 15/40
Evaluation by Engineer
(Clauses 12.3 and 12.4)
T
he rates specified in the Contract will apply unlessthere are no appropriate rates for a new item of work
New Rates may be determined where items a) and
b) of Sub Clause 12.3 apply
Sub Clause 12.4 provides for possiblecompensation to Contractor relating to omissions
of work
Sub Clause 12.3 Provides the basis for the Engineer to
determine the value of each item of work
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 16/40
Variation
± Increasing, decreasing or omitting any
part of the contract work
± Changing the character or quality of
material or work
± Changing the source of subcontract
work
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 17/40
Variations and Adjustments
(Clause13) Engineer has right to vary under Sub Clause
13.1 and with details of types of issues covered
Opportunity for Contractor to submit ³Value
Engineering´ change. Risk of development with
Contractor and any savings are split 50:50
Sub Clause 13.3 sets out procedure required to
be followed if Engineer requests proposal prior
to instructing Variation
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 18/40
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 19/40
Provisional Sums (Clause 13.5)
Include the provisional sum of
Dhr. 120 (one hundred and
twenty Dirhams) for connectingend of drain to be the soakage
pit.
Prov. Sum 120 00
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 20/40
Prime Cost Sum
Include the prime cost sum of
Dhr. 800 (eight hundred
Dirhams) for patent partitions tobe executed by nominated sub-
contractors.
Add for profit
General attendance
PC Sum
%
Item
800 00
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 21/40
Include the prime cost sum of
Dhr. 55 (fifty-five Dirhams) for
ironmongery to be supplied bynominated supplier.
Add for profit
PC Sum
%
Prime Cost Sum (Contd«)
55 00
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 22/40
Prime cost sum for patent partitions
Add for profit (10%)
General attendance
Emirates Interior Ltd., A/C No. 2134
Profit (10%)
General attendance
Total
Less omission
Net addition C/F to Grand Summary
800.00
80.00
120.00
1000.00
850.00
85.00
120.00
1055.00
(1000.00)
55.00
Omissions Additions
Adjustment of PC & Provisional Sums
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 23/40
Daywork (Clause 13.6)
Day-work means payment for actual hours
spent carrying out an operation as against
payments made based on prices given in the
tender.
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 24/40
Daywork Records
The minimum information recorded should
include:
± Hours worked by those engaged in daywork
± Hours machines were hired
± Material used by the Contractor for daywork
purposes
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 25/40
Who Orders Daywork?
Daywork is only carried out in special situations.
Engineer will usually only request daywork in an
emergency when there is insufficient time to raise avariation quotation request. The same emergency may
give the Contractor insufficient time to assess and cost
a variation quotation.
Another instance would be where tradesmen for a
particular trade has to be brought back to do work in
that trade when the work in that trade is completed.
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 26/40
Price Fluctuations (Clause 13.8)
Often construction projects, particularly, largeprojects are undertaken over a long period of time.It is more than likely that the price of material usedin a job and the rates of pay of the workmen will
increase and even in some instances fall duringthe life of the contract.
Rise and Fall is the adjustment made to thecontract price to offset or compensate for any risesand falls that occur during the period of contract.
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 27/40
Adjustments for Changes in Cost
Extensive details provided for the use of
formulae for cost variations during the contract
period. Optional, determined by employer prior
to Tender
Base rate reference is 28 days prior to date of
tender submission
Factors provided in Appendix to Tender for each
project
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 28/40
Payment Methods
± Payment on completion
± Stage payments
± Progress payments
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 29/40
Progress Payments
The value of progress payments are determined on
the actual value of work done
This method is based on actual measurement of
work done or value of percentages of work done
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 30/40
Contractual Implications
(Clauses 14.3 - 14.6)
The conditions of contract stipulates:
When progress payments are to be made.
The method of presentation by the Contractor of hisclaim for progress payments (the information to beprovided)
Method for fixing the estimate of the contract valueof work executed including variations, unfixedmaterials on site, etc.,
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 31/40
Interim Payments (Cont.)
Sub Clause 14.3 ± Contractor to submit a
Statement for application for interim payment.
Note cross reference to Sub Clause 4.21, plus
requirement for 6 copies.
Sub Clause 14.6 ± Sets out procedure for issue
of interim Payment Certificate by the Engineer -see also chart 2
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 32/40
Payment (Clauses 14.7 & 14.8)
Sub Clause 14.7 ± Payment duties of Employersplus under 14.8 the financial charges to be paid if Employer is late in payment
(3% above discount rate of Central Bank of countryof the currency of payment)
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 33/40
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 34/40
Final Accounts
Sub Clauses 14.10/14.11/14.12/14.13
These deal with the Statement on completion,
application for Final Payment Certificate,discharge and issue of Final Payment Certificate
Sub Clause 14.15 Currencies of Payment
This clause sets out the procedures if the
payments are to be made in more than one
currency
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 35/40
Final Accounts (Cont.)
Sub Clause 14.10 requires Contractors within
84 days of Taking Over Certificate too submit
a statement showing:
- Value of all work done
- Further sums considered due
- Estimate of any other amounts
considered due
Engineer shall certify in accordance with
Sub Clause 14.6
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 36/40
Final Accounts (Cont.)
Sub Clause 4.11 requires Contractor to submit
Final Statement within 56 days of receiving
Performance Certificate.
Sub Clause 4.12 Contractor to submit written
discharge with Final Settlement.
Sub clause 14.13 requires Engineer to issue
within 28 days Final payment Certificate.
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 37/40
Exercise 1
Read Clauses 12, 13 & 14 of the Red Book and answer
following questions.
Yes No May
be
Does the Contractor undertake the measurement of
the Works in Red Book?
Should the method of measurement be stated in the
Bill of Quantities
Can the Engineer demand the Contractor to give the
breakdown of his rates?
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 38/40
Yes No May
be
Can the Daywork Schedule be used to agree
new rates
Can the Contract Price be fixed?
Can the Engineer correct previous payment
certificates?
Have Provisional Sums to be spent within the
contract?
Exercise 1 (Cont.)
8/8/2019 Session 6- Payment Clauses and Procedures
http://slidepdf.com/reader/full/session-6-payment-clauses-and-procedures 39/40
Exercise 2 (Group)
A contract agreement was signed based on the FIDIC 1999Red Book on 1st February, with Commencement Datestated as 1st March. On 4th April the Contractor submittedan application for an interim payment.
On 18th April, the Engineer replied that he did not intend toissue an Interim Payment Certificate.
On what grounds can the Engineer refuse to issue an InterimPayment Certificate?