seminar piping costing
DESCRIPTION
Seminar on costTRANSCRIPT
![Page 1: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/1.jpg)
SEMINAR ONSEMINAR ON
PIPING COSTINGPIPING COSTING
Presented ByPresented By
Rajendra M. Bharate(CEO & Managing Director)
CONCEPTS CLEARANCE COMPANY PVT. LTD., 18/B3, Bandal Complex, Near PMT Depot, Paud Road, Pune – 38
![Page 2: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/2.jpg)
BUSINESS PERFORMANCE PARAMETERSBUSINESS PERFORMANCE PARAMETERS
1) Minimum Cost
2) Quality
3) On time Delivery
4) Profits – Return On Investment ( ROI )
5) Meeting Customer Expectation & Satisfaction
6) Competitive Advantage
7) Information ( All Right Factors )
8) Benchmarking – Adherence World Standards
![Page 3: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/3.jpg)
PARTIES INVOLVED IN PROJECT
1) Owner (Client)
2) Shareholders
3) Financer
4) Licensor
5) Government (Statutory)
6) EPC Contractor (Equipment Vendor)
7) Various Contractors
8) Consultants
9) Detailed Design & Engineering etc..
![Page 4: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/4.jpg)
PROCEDURE FOR TENDERINGPROCEDURE FOR TENDERING
1) Advertisement @ Intention 2) Submission of PQs 3) Evaluation of PQs 4) Issue of Tender to Pre-qualified Bidders (Techno-Com) 5) Submission of Technical Bids 6) Evaluation of Technical Bids 7) Submission of Commercial Bids 8) Evaluation of Commercial Bids 9) Finalization of Contractor & Issue of LOI 10) Contract Agreement
![Page 5: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/5.jpg)
PRE-QUALIFICATION PRE-QUALIFICATION
1) Company Information 2) List of Directors, Management & Organization Chart 3) List of Clientele 4) Types of Work Done & Same Type of Experience 5) Work Completion Certificates 6) Details of Staff & Workforce 7) Details of Construction Equipments 8) Financial Capabilities from the Bankers 9) Memorandum & Articles of Association (Limited Co.) 10) Balance Sheet for Last 3 Years
![Page 6: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/6.jpg)
TENDER / BID / PROPOSAL / QUOTATIONTENDER / BID / PROPOSAL / QUOTATION
Technical Part
1) Technical Terms & Conditions with Deviations
2) Work Methods & Detail Technical Specifications
3) Equipment & Organizational Deployment
4) QA Plans, Planning, Control & Reporting Systems
5) Overall Schedule (Bar Chart)
6) Original Bidding Documents Stamped & Signed
Commercial Part
1) Price Schedule (Schedule of Rates)
2) Commercial Terms & Conditions
3) Rates for Extra Work
![Page 7: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/7.jpg)
TYPES OF GUARANTEESTYPES OF GUARANTEES
1) EMD (Alongwith Tender) (% or Fixed Amount)
2) Advance Payment (10 %)
3) Security Deposit (10 %)
4) Retention Money (5%)
5) Performance Guarantee (10%)
![Page 8: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/8.jpg)
TURNKEY ASPECTTURNKEY ASPECT( LSTK / EPC / EPIC CONTRACTS )( LSTK / EPC / EPIC CONTRACTS )
Concept to Commissioning : Single Point Responsibility
1) Project Management
2) Engineering
3) Procurement
4) Quality Assurance
5) Construction
6) Commissioning
![Page 9: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/9.jpg)
FEW BASIC REQUIREMENTS
1) Types of Projects (Fertilizers, ..) 2) Types of Disciplines (Civil, ..) 3) Types of Works Involved (Piping, ..) 4) Types of Piping (Offsite, ..) 5) Piping Materials (CS, …) 6) Piping Schedules & Weights 7) Pipe Fittings & Valves 8) Fabrication of Pipes from Plates 9) Painting Works (Primer, ..) 10) Insulation Works (Hot, ..) 11) NDT Works (Radiography ..) 12) Testing & Commissioning
![Page 10: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/10.jpg)
Inch-Mtr (IM) & Inch-Dia (ID)
Inch-Mtr – When a Pipe of 1 Inch Dia having a length of 1
Mtr is installed, it is termed as 1 Inch-Mtr. (Ex. 6 Inch Pipe, Length 5 Mtr = 6 x 5 = 30 IM)
Inch-Dia – When a Pipe of 1 Inch Dia Size is welded having 1
joint, it is termed as 1 Inch-Dia. (Ex. 10 Inch Pipe, 4 Joints = 10 x 4 = 40 ID)
![Page 11: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/11.jpg)
ManHour, ManDay & ManMonth
ManHour –
When 1 Worker works for 1 Hour, it is said 1 MH of work. (Ex. 2 Workers worked 8 Hrs = 2 x 8 = 16 MH)
ManDay –
When 1 Worker works for 1 Day, it is said 1 MD of work
(Ex. 3 Workers worked 7 Days = 3 x 7 = 21 MD)
ManMonth –
When 1 Worker works for 1 Mth, it is said 1 MM of work
(Ex. 8 Workers worked for 5 Mths = 8 x 5 = 40 MM)
![Page 12: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/12.jpg)
Piping Rates Quotation Basis
1) Per Mtr
2) Per Inch-Mtr
3) Per Inch-Dia
4) Per MT
5) Lumpsum
![Page 13: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/13.jpg)
Piping Welding Productivity
Normal Figures as per the Average working of any Company, certain Norms are as below –
a) Shop Floor – 50 - 60 ID / Day / Welder
(Marking, Cutting, Grinding, Tacking etc..)
b) Erection at Site – 25 - 30 ID / Day / Welder
(Laying, Fit-up, Welding, Testing etc..)
![Page 14: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/14.jpg)
Piping Fabrication from Plates
Normally, above 30 Inch Size Pipes are Prefabricated out of Plates by Rolling & Welding.
Plate Bending Machine is very much important aspect in this Fabrication. It is Specified as Thk (mm) x Width (Mtr)
![Page 15: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/15.jpg)
Related Piping Works
• Pipe Supports Fabrication & Erection
• Mitres Fabrication (Tee, Reducer, Elbow ..)
• Insulation (Hot & Cold)
• Sand Blasting (SA 2 ½)
• Painting (Primer, Intermediate, Final)
• Hydro Testing
• Chemical Cleaning etc..
![Page 16: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/16.jpg)
Various NDT Requirements
• Visual Inspection
• Radiography (X Ray, Gamma Ray)
• DP / MP Testing
• Vacuum Box Testing
• Ultrasonic testing (UT) etc..
![Page 17: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/17.jpg)
Various Piping Materials
• CS – API 5L, A 106 Gr B (IBR, Non IBR)• LTCS – A333 Gr 6• AS – A335 Gr P1, P11, P22 • SS – 304, 304 L, 316, 316 L, 347 H• GI – IS 1239• HDPE / Plastic• C.I. / Cement Pipes• Cement Lined
![Page 18: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/18.jpg)
PIPING ERECTION TYPESPIPING ERECTION TYPES
a) Unit Piping – Involved within the plant mostly coming on Equipments & has more
number of welding joints is referred as Unit Piping. b) Offsite / Rack / Yard Piping – Involved within the plant mostly on Racks & across the plant, but has
less number of welding joints is referred as Offsite Piping. c) Cross country Piping – Out of plant mostly coming across the cities & has naturally less
number of welding joints is referred as Cross-country Piping. (Oil, Gas, Water)
d) Under Ground Piping – Involved under the ground / buried may be within or outside the plant
& has less number of welding joints is referred as Underground Piping
![Page 19: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/19.jpg)
Ratio of Inch-Mtr to Inch-Dia (Appr.)
• Unit Piping – 1.5 to 2.0
• Offsite / Rack / Yard Piping – 3.5 to 4.0
• Cross-Country Piping – 10.0 to 12.0
• Under-Ground Piping – 4.0 to 6.0
![Page 20: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/20.jpg)
IM & ID Calculations from Isometrics
• Piping Material wise Grouping
• Sizewize Grouping
• Number of Fittings
• Valves (Welded / Bolted)
![Page 21: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/21.jpg)
Piping Gangs
a) Piping Prefabrication – Pipe Fabricator, Gas Cutter, Tack Welder,
Grinder, Helper
b) Piping Erection – Pipe Fitter, Tack Welder, Rigger, Helper
c) Piping Welding – Qualified Welder, Rigger, Helper
![Page 22: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/22.jpg)
Weighted Inch-Dia
Piping involves various types of Schedules. To estimate Man-hours, Consumables etc.. for each Schedule, it is really a tough task. Hence, all welding Inch-Dia are converted to a 40 Schedule as a base. On this basis costing is done, which becomes easier. This is called Weighed Inch-Dia.
Example – Size Sch Thk Actual ID Wighted ID 6” Dia 40 6 mm 100”D 100”D 6” Dia 120 18 mm 100”D 300”D
![Page 23: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/23.jpg)
Material wise Piping Consumables
(Sch 40 as a base) (Rs / Inch-Dia)
• C.S. – 30• CSLT – 35• AS – 80• SS – 125• G.I. – 10• PVC / HDPE – 5
![Page 24: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/24.jpg)
Material wise Piping Rates (Only Factors)
(Considering CS as a base)
• C.S. – 1.00• CSLT – 1.25• AS – 2.50• SS – 3.50• G.I. – 0.60• PVC / HDPE – 0.40
![Page 25: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/25.jpg)
Direct Cost
Direct Labor
Direct Supervision
Consumables
R & M of Tools / Tackles & Vehicles
Rental Charges of Equipments
Power & Water consumption
![Page 26: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/26.jpg)
Indirect Cost
Administrative Staff Indirect Labor Accommodation Tools / Tackles & Vehicles Depreciation Insurance Preparatory Expenses Travel Bank Guarantees General Expenses Guarantee Obligation
![Page 27: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/27.jpg)
Total Price
Direct Expenses +
Indirect Expenses +
Material Supplies +
Subcontracting Charges +
Taxes & Duties +
Agents Commission +
Overheads +
Profits
![Page 28: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/28.jpg)
Section A ( Fill in the Blanks) ( 5 Marks )
1) 6 Inch Size pipe having 15 Mtr length laid on a rack will have how many total InchMtr of work --
2) 12 Inch size pipe 5 Joints to welded will be having total -------- Inch dia of work.
3) For Unit piping installed to be in Plant will have Inh-mtr to Inch-dia ratio approximately ------
4) Pipe Fabrication from Plates is done at site normally above ------- Inch Size Pipe.
5) Fabrication of Larger diameter Piping Fittings like Tees, Elbow, Mitre, Reducer etc.. is done on basis of Per -- rate. (Please mention unit)
![Page 29: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/29.jpg)
Section B ( State True or False ) ( 5 Marks )
1) 6 Inch Sch 40 CS piping of 2000 Mtr is to be erected as Offsite Piping & the same quantity is to be erected as Unit Piping in one Refinery Plant. Then Offsite piping will have Less number of joints than Unit piping.
2) SS rate will be More than CS of the same schedule. 3) Various Schedules of Piping Inch-dia work is converted
to single unit of inch-dia of work for easy calculation purpose. This concept is called ‘Weighted Inch-dia’.
4) One welder gang in ‘Erection Site’ will give an average of 25-30 ID Productivity in a working shift of 8 hours.
5) The Piping, which is involved across cities & has less number of welding joints, is referred Cross-country Piping
![Page 30: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/30.jpg)
Section C ( Write Answers in Short ) ( 5 Marks )
1) 5 Welders work for one daily shift of 8 hours per day for 10 days. Calculate total man-hours worked by them.
2) Total work done on one piping job was of 5,200 Manhours. Assuming one ManMonth (MM) of 208 Manhours, find total ManMonths spent on piping job.
3) One piping project has got total workers strength of 100 during its peak period. Find out the total Direct Supervision strength (Engineers & Supervisors) as per the normal experience of few standard norms.
4) Write the Elements of Direct Cost. 5) Write the Elements of Indirect Cost.
![Page 31: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/31.jpg)
Section D ( Full Descriptive Question ) ( 10 Marks )
Shriniwas Constructions Limited, Lucknow (UP)
In one of the Fertilizer Plant near Shahajanpur (UP) some Piping Work is to be done. Quantity is finalized by the Petroleum Company Design department & handed over to Contracts Section for Estimation to find out the Total Cost involved. They floated the Tender & ultimately ‘Shriniwas Construction Limited, Lucknow (UP)’ was Selected as a Final Contractor to Award the Contract being the Lowest Tender.
![Page 32: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/32.jpg)
Question –
1) Estimate the Total Cost in Rupees, which will be required to carry out the work, as the Contracts Department has to get ‘Top Management Approval’.
2) ‘Shriniwas Construction Ltd., Lucknow’ has offered 10 % discount on Total Pricing. Hence, also calculate the Discount & Final Tender Price in Rupees Separately to inform to the Top Management.
![Page 33: Seminar Piping Costing](https://reader036.vdocuments.site/reader036/viewer/2022081421/552c834d4a7959c87c8b47aa/html5/thumbnails/33.jpg)
Tender for Ammonia Fertilizer, Shahajanpur (UP)
20010LtrsEnamel Paint Supply10
20005Days25 T Crane Supply 9
50100MhrsCommissioning Labor8
50?---Radiography (10%)7
75200MhrsExtra Labor Work6
50100M2Painting5
10050M2Insulation4
2,50010MTPipe Support3
1002,000IDPiping Welding2
503,000IMPiping Laying1
AmountRateQtyUnitItemSr