HH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab HH-PF-02 External Masonry Cavity Wall, Partial-Fill - Suspended In-Situ Concrete Floor, Insulation Below Slab HH-PF-04 External Masonry Cavity Wall, Partial-Fill - Independent Lintel HH-PF-03 External Masonry Cavity Wall, Partial-Fill - Concrete Ground Bearing Floor, Insulation Below Slab HH-PF-05 External Masonry Cavity Wall, Partial-Fill - Steel Lintel, Perforated Base Plate, (Insulated Soffit) HH-PF-06 External Masonry Cavity Wall, Partial-Fill - Sill HH-PF-07 External Masonry Cavity Wall, Partial-Fill - Jamb HH-PF-08 External Masonry Cavity Wall, Partial-Fill - Intermediate Timber Floor Within A Dwelling HH-PF-09 External Masonry Cavity Wall, Partial-Fill - Precast Concrete Separating Floor Between Dwellings HH-PF-10 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Gable, Insulation At Ceiling Level, Ventilated Loft HH-PF-11 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Gable, Insulation At Rafter Level, Unventilated Rafter Void HH-PF-12 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Eaves, Insulation At Ceiling Level, Ventilated Loft HH-PF-13 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Eaves, Insulation At Rafter Level, Unventilated Rafter Void HH-PF-14 External Masonry Cavity Wall, Partial-Fill - Normal Corner HH-PF-15 External Masonry Cavity Wall, Partial-Fill - Inverted Corner HH-PF-16 External Masonry Cavity Wall, Partial-Fill - Party Wall Between Dwellings HH-PW-17 Party Wall Masonry, Full Fill - Suspended Beam And Block Floor, Insulation Above Slab HH-PW-18 Party Wall Masonry, Full Fill - Suspended Concrete Floor, Insulation Below Slab HH-PW-19 Party Wall Masonry, Full Fill - In-Situ Concrete Ground Bearing Floor, Insulation Below Slab HH-PW-20 Party Wall Masonry, Full Fill - Roof, Insulation At Ceiling Level, Ventilated Loft HH-PW-21 Party Wall Masonry, Full Fill - Roof, Insulation At Rafter Level, Unventilated Rafter Void Detail Ref. Detail Title HH-PF-23 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Eaves - Insulation At Rafter Level, Unventilated Rafter Void HH-PF-22 External Masonry Cavity Wall, Partial-Fill - Steel Lintel, Open Back (no continuous base plate) DRAWN BY TITLE DATE SCALE CHECKED BY REV.NO. DWG No. Standard Junction Details (partial Fill) INDEX AHR SJB Nov 2012 A N.T.S. REV. DESCRIPTION. DATE. BY. H+H UK Limited Fax +44 (0)1732 887013 Kent, TN15 9HZ. Ightham, Sevenoaks Tel +44 (0)1732 880580 Celcon House Technical Services Dept. E-mail [email protected] These details have been produced for guidance only. It is the responsibility of the building designer to ensure that the details shown are compatible with the overall building design and will satisfy the relevant parts of the Building Regulations applicable before they are adopted into the project design. A 11/2014 SJB HH-PF-22 & HH-PF-23 ADDED

Upload: nguyendien

Post on 20-Mar-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

HH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab

HH-PF-02 External Masonry Cavity Wall, Partial-Fill - Suspended In-Situ Concrete Floor, Insulation Below Slab

HH-PF-04 External Masonry Cavity Wall, Partial-Fill - Independent Lintel

HH-PF-03 External Masonry Cavity Wall, Partial-Fill - Concrete Ground Bearing Floor, Insulation Below Slab

HH-PF-05 External Masonry Cavity Wall, Partial-Fill - Steel Lintel, Perforated Base Plate, (Insulated Soffit)

HH-PF-06 External Masonry Cavity Wall, Partial-Fill - Sill

HH-PF-07 External Masonry Cavity Wall, Partial-Fill - Jamb

HH-PF-08 External Masonry Cavity Wall, Partial-Fill - Intermediate Timber Floor Within A Dwelling

HH-PF-09 External Masonry Cavity Wall, Partial-Fill - Precast Concrete Separating Floor Between Dwellings

HH-PF-10 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Gable, Insulation At Ceiling Level, Ventilated Loft

HH-PF-11 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Gable, Insulation At Rafter Level, Unventilated Rafter Void

HH-PF-12 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Eaves, Insulation At Ceiling Level, Ventilated Loft

HH-PF-13 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Eaves, Insulation At Rafter Level, Unventilated Rafter Void

HH-PF-14 External Masonry Cavity Wall, Partial-Fill - Normal Corner

HH-PF-15 External Masonry Cavity Wall, Partial-Fill - Inverted Corner

HH-PF-16 External Masonry Cavity Wall, Partial-Fill - Party Wall Between Dwellings

HH-PW-17 Party Wall Masonry, Full Fill - Suspended Beam And Block Floor, Insulation Above Slab

HH-PW-18 Party Wall Masonry, Full Fill - Suspended Concrete Floor, Insulation Below Slab

HH-PW-19 Party Wall Masonry, Full Fill - In-Situ Concrete Ground Bearing Floor, Insulation Below Slab

HH-PW-20 Party Wall Masonry, Full Fill - Roof, Insulation At Ceiling Level, Ventilated Loft

HH-PW-21 Party Wall Masonry, Full Fill - Roof, Insulation At Rafter Level, Unventilated Rafter Void

Detail Ref. Detail Title

HH-PF-23 External Masonry Cavity Wall, Partial-Fill - Pitched Roof, Eaves - Insulation At Rafter Level, Unventilated Rafter Void

HH-PF-22 External Masonry Cavity Wall, Partial-Fill - Steel Lintel, Open Back (no continuous base plate)

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

Standard Junction Details(partial Fill)

INDEX

AHRSJB

Nov 2012 AN.T.S.

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

A 11/2014 SJBHH-PF-22 & HH-PF-23 ADDED

Page 2: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

ventilated void

wall cavity insulation tocontinue at least 215mm

from top of beam

partial-fill cavitywall insulation

floor insulation to tightly abutwall blockworkdpc

clear cavity

perimeter insulation toprovide minimum resistanceof 0.8m²K/W

Celcon blocks to inner leaf,above and below dpc

dpm

precast beam and block floorwith Celcon Standard infill blocks

Celcon infill blocks built into wallsto have the same compressivestrength as wall blocks

base course incorporatingdpm and dpc

max. 75mm screed thickness

Celcon foundation blocks

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,

Partial Fill - Suspended Beam And Block

Floor, Insulation Above Slab

HH-PF-01

AHRSJB

Nov 2012 1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBMAX. SCREED THICKNESS NOTEADDED.

For Ψ values applicable to this detail,see Constructive Details CD0001orLABC Registered ConstructionDetails E5MCPF16 - 21.

B 11/2014 SJBLABC REFERENCE ADDED

Page 3: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

dpmdpcwall cavity insulation to

continue at least 215mmbelow underside of slab

partial-fill cavitywall insulation

clear cavity

floor insulation to tightly abutwall blockwork

Celcon blocks to inner leaf,above and below dpc

base course incorporatinglapped dpm and dpc

Celcon foundation blocks

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,

Partial Fill - Suspended In-Situ Concrete

Floor, Insulation Below Slab

HH-PF-02

AHRSJB

Nov 2012 1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBMAX. FLOOR THICKNESS NOTEADDED

B 11/2014 SJB

For Ψ values applicable to this detail,see Constructive Details CD0002orLABC Registered ConstructionDetails E5MCPF28 - 33.

MAX. FLOOR THICKNESS NOTEREMOVED. LABC REFERENCEADDED.

Page 4: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

dpm

dpc

Celcon blocks to inner leaf,above and below dpc

partial-fill cavitywall insulation

clear cavity

base course incorporatinglapped dpm and dpcwall insulation to continue

at least 215mm belowunderside of slab perimeter insulation to provide

minimum resistance of 0.8m²K/W

floor insulation to tightly abutwall blockwork

Celcon foundation blocks

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,

Partial Fill - Concrete Ground Bearing

Floor, Insulation Below Slab

HH-PF-03

AHRSJB

Nov 2012 1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBMAX. FLOOR THICKNESS NOTEADDED

B 11/2014 SJB

For Ψ values applicable to this detail,see Constructive Details CD0003orLABC Registered ConstructionDetails E5MCPF22 - 27.

MAX. FLOOR THICKNESS NOTEREMOVED. LABC REFERENCEADDED.

Page 5: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

minimum frameoverlap 30mm

PVC-U cavity closerfully insulated

internal lintel

Celcon blocks to inner leaf

partial-fill cavitywall insulation

external lintel

clear cavity

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,Partial Fill - Independent Lintel

HH-PF-04

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

A 11/2014 SJBLABC NOTE ADDED

For Ψ values applicable to this detail,see Constructive Details CD0004orLABC Registered ConstructionDetails E2MCPF4 - 6.

Page 6: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

minimum frameoverlap 30mm

soffit insulation with min.resistance of 0.6m²K/W

insulated steel lintel with perforatedbase plate (equivalent conductivity30W/mK or less)

Celcon blocks to inner leaf

partial-fill cavitywall insulation

clear cavity

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-05

AHRSJB

Nov 2012 A1:100 @ A4

External Masonry Cavity Wall,

Partial Fill - Steel Lintel, Perforated

Base Plate, (Insulated Soffit)

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

A

For Ψ values applicable to this detail,see Constructive Details CD0005orLABC Registered ConstructionDetails E1MCPF4 - 6.

11/2014 SJBMAX. LINTEL HEIGHT NOTEREMOVED. LINTEL BASEPLATEADDED. LABC REFERENCE ADDED

Page 7: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

minimum frameoverlap 30mm

partial-fill cavitywall insulation

clear cavityAircrete blocks to inner leaf

insulated steel lintel, no continuousbase plate. max. steel thickness 3.0mm

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-22

AHRSJB

Nov 2014 01:100 @ A4

External Masonry Cavity Wall,

Partial Fill - Steel Lintel, Open back

(no continuous base plate)

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see LABC Registered ConstructionDetails E2MCPF7 - 9.

Page 8: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

minimum frameoverlap 30mm

clear cavity

PVC-U cavity closer,fully insulated

Celcon blocks to inner leaf

partial-fill cavitywall insulation

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,

Partial Fill - Sill

HH-PF-06

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0006orLABC Registered ConstructionDetails E3MCPF4 - 6.

A 11/2014 SJBLABC NOTE ADDED

Page 9: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

minimum frameoverlap 30mm

clear cavity

partial-fill cavitywall insulation Celcon blocks to inner leaf

PVC-U cavity closer,fully insulated

300mm max.

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,Partial Fill - Jamb

HH-PF-07

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0007orLABC Registered ConstructionDetails E4MCPF4 - 6.

A 11/2014 SJBLABC NOTE ADDED

Page 10: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

timber floor joists may be built intoinner block leaf or supported onjoist hangers

Celcon blocks to inner leaf

clear cavity partial-fill cavitywall insulation

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,

Partial Fill - Intermediate Timber FloorWithin A Dwelling

HH-PF-08

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0008orLABC Registered ConstructionDetails E6MCPF4 - 6.

A 11/2014 SJBLABC NOTE ADDED

Page 11: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

clear cavity

proprietary fire stop precast concreteplank floor

ceiling void

Celcon blocks to inner leaf

concrete screed

resilient layer to RobustDetails specification

partial-fill cavitywall insulation

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,

Partial Fill - Precast Concrete Separating

Floor Between Dwellings

HH-PF-09

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0009orLABC Registered ConstructionDetails E7MCPF4 - 6.

A 11/2014 SJBPROPRIETARY FIRE STOP NOTEREVISED. LABC NOTE ADDED.

Page 12: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

clear cavity

minimum 200mmwall insulation above

ceiling insulation

ceiling insulation

pack compressible insulationbetween last truss and wall

Celcon blocks to inner leaf

partial-fill cavitywall insulation

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,

Partial Fill - Pitched Roof, Gable -

Insulation At Ceiling Level, Ventilated Loft

HH-PF-10

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0010orLABC Registered ConstructionDetails E12MCPF4 - 6.

A 11/2014 SJBLABC NOTE ADDED

Page 13: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

partial-fill cavitywall insulation

fill this void with insulationhaving a maximum conductivity

of 0.040W/mK

clear cavity

100mm minimum

breathable roofmembrane

pack compressible insulationbetween last rafter and wall

insulation under rafters(optional)

min. 150mm rafters void fullyfilled with insulation withmax. λ = 0.040W/mK

Celcon blocks to inner leaf

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-11

AHRSJB

Nov 2012 1:100 @ A4

External Masonry Cavity Wall,Partial Fill - Pitched Roof, Gable - Insulation

At Rafter Level, Unventilated Rafter Void

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBRAFTERS INSULATION THICKNESSNOTE ADDED

For Ψ values applicable to this detail,see Constructive Details CD0011orLABC Registered ConstructionDetails E13MCPF4 - 6.

B 11/2014 SJBLABC NOTE ADDED

Page 14: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

ceiling insulationbetween and overroof trusses

ventilated loft

partial-fill cavitywall insulation

clear cavity

Celcon blocks to inner leaf

proprietary ventilatorbetween rafters

min. 50mm insulationbetween wall plate

and vent

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-12

AHRSJB

Nov 2012 1:100 @ A4

External Masonry Cavity Wall,Partial Fill - Pitched Roof, Eaves - Insulation

At Ceiling Level, Ventilated Loft

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBWALL PLATE INSULATION COVERNOTE MOVED

For Ψ values applicable to this detail,see Constructive Details CD0012orLABC Registered ConstructionDetails E10MCPF4 - 6.

B 11/2014 SJBLABC NOTE ADDED

Page 15: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

insulation to entirely filleaves gap betweenwall insulation and

ceiling insulation

clear cavity

partial-fill cavitywall insulation

Celcon blocks to inner leaf

150mm min. rafters with insulationof max. λ = 0.040W/mk between,to sloping ceiling section

breathable roofmembrane

insulation underrafters (optional)

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-13

AHRSJB

Nov 2012 1:100 @ A4

External Masonry Cavity Wall,Partial Fill - Pitched Roof, Eaves - Insulation

At Rafter Level, Unventilated Rafter Void

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

A

A 11/2013 SJBRAFTERS INSULATION NOWSHOWN AS 150mm.

For Ψ values applicable to this detail,see Constructive Details CD0013.

Page 16: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

150mm rafters with insulationof λ = 0.044W/mk between,to sloping ceiling section

proprietary fire stop (if required),max λ ≤ 0.044W/mK

clear cavity

breathable roofmembrane

50mm insulation under

rafters, max λ = 0.022W/mK

Aircrete blocks to inner leaf

partial-fill cavitywall insulation

insulation to entirely filleaves gap betweenwall insulation and

ceiling insulation

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-23

AHRSJB

Nov 2014 1:100 @ A4

External Masonry Cavity Wall,Partial Fill - Pitched Roof, Eaves - Insulation

At Rafter Level, Unventilated Rafter Void

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

0

For Ψ values applicable to this detail,see LABC Registered ConstructionDetails E11MCPF4 - 6.

Page 17: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

clear cavity

Celcon blocksto inner leaf

Partial-fillwall insulation

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-14

AHRSJB

Nov 2012 A1:100 @ A4

External Masonry Cavity Wall,Partial Fill - Normal Corner

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0014orLABC Registered ConstructionDetails E16MCPF4 - 6.

A 11/2014 SJBLABC NOTE ADDED

Page 18: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

partial-fillcavity insulation

clear cavity

Celcon blocksto inner leaf

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

HH-PF-15

AHRSJB

Nov 2012 A1:100 @ A4

External Masonry Cavity Wall,Partial Fill - Inverted Corner

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0015orLABC Registered ConstructionDetails E17MCPF4 - 6.

A 11/2014 SJBLABC NOTE ADDED

Page 19: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

partial-fill cavitywall insulation

clear cavity

Celcon blocks toinner leaf

8mm parge coat may be omitted(subject to Robust Detail requirements)

2 x 100mm leaves to separatingwalls above dpc:Celcon Standard (3.6N/mm²)Celcon High Strength (7.3N/mm³)Celcon Super Strength (8.7N/mm²)

cavity width min. 75mmup to 100mm max.

(subject tp Robust Detailrequirements)

full fill mineral wool cavity wallinsulation, density up to 40kg/m³

proprietary insulated fire stopif required

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

External Masonry Cavity Wall,Partial Fill - Party Wall Between Dwellings

HH-PF-16

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0016orLABC Registered ConstructionDetails E18MCPF7 - 10.

A 11/2014 SJBPROPRIETARY FIRE STOP NOTEREVISED. LABC NOTE ADDED.

Page 20: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

ventilated void

floor insulation to tightly abutwall blockwork

insulation to continueat least 215mm below

top of beams

full fill mineral wool cavity wall

insulation, density up to 40kg/m³

precast beam and blockfloor with Celcon Standardinfill blocks

Celcon infill block built into wallsto have the same compressivestrength as wall blocks

dpmdpm

2 x 100mm leaves to separatingwall above and below dpc:Celcon Standard (3.6N/mm²)Celcon High Strength (7.3N/mm²)Celcon Super Strength (8.7N/mm²)

cavity width min. 75mmup to 100mm max.

(subject to Robust Detailrequirements)

8mm parge coat may beomitted (subject to Robust

Detail requirements)

minimum 225mm

max. 75mm screed thickness

perimeter insulation toprovide minimum resistanceof 0.8m²K/W

Celcon foundation blocks

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

Party Wall Masonry, Full Fill -

Suspended Beam And Block Floor,

Insulation Above Slab

HH-PW-17

AHRSJB

Nov 2012 1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBMAX. SCREED THICKNESS NOTEADDED

For Ψ values applicable to this detail,see Constructive Details CD0017orLABC Registered ConstructionDetails P1PCFF1 - 2.

B 11/2014 SJBLABC NOTE ADDED.

Page 21: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

dpmfloor insulation to tightly abutwall blockwork

insulation to continueat least 215mm belowunderside of slab

cavity width min. 75mmup to 100mm max.

(subject to Robust Detailrequirements)

8mm parge coat may beomitted (subject to Robust

Detail requirements)

2 x 100mm leaves to separatingwall above and below dpc:Celcon Standard (3.6N/mm²)Celcon High Strength (7.3N/mm²)Celcon Super Strength (8.7N/mm²)

base course incorporatinglapped dpm and dpc

full fill mineral wool cavity wallinsulation, density up to 40kg/m³

dpm

Celcon foundation blocks

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

Party Wall Masonry, Full Fill -

Suspended Concrete Floor,

Insulation Below Slab

HH-PW-18

AHRSJB

Nov 2012 1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBMAX. SCREED THICKNESS NOTEADDED

For Ψ values applicable to this detail,see Constructive Details CD0018orLABC Registered ConstructionDetails P1PCFF3 - 4.

B 11/2014 SJBMAX. FLOOR THICKNESS NOTEREMOVED. LABC REFERENCEADDED.

Page 22: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

dpm

floor insulation to tightly abutwall blockworkdpm

wall insulation to continueat least 215mm below

underside of slab

base course incorporatinglapped dpm and dpc

perimeter insulation to provideminimum resistance of 0.8m²K/W

cavity width min. 75mmup to 100mm max.

(subject to Robust Detailrequirements)

2 x 100mm leaves to separatingwall above and below dpc:Celcon Standard (3.6N/mm²)Celcon High Strength (7.3N/mm²)Celcon Super Strength (8.7N/mm²)

full fill mineral wool cavity wall

insulation, density up to 40kg/m³

8mm parge coat may beomitted (subject to Robust

Detail requirements)

Celcon foundation blocks

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

Party Wall Masonry, Full Fill -

In-situ Concrete Ground Bearing Floor,

Insulation Below Slab

HH-PW-19

AHRSJB

Nov 2012 1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBMAX. FLOOR THICKNESS NOTEADDED

For Ψ values applicable to this detail,see Constructive Details CD0019orLABC Registered ConstructionDetails P1PCFF5 - 6.

B 11/2014 SJBMAX. FLOOR THICKNESS NOTEREMOVED. LABC REFERENCEADDED.

Page 23: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

minimum 200mmwall insulation above

ceiling insulation

8mm parge coat may beomitted (subject to Robust

Detail requirements)

ceiling insulation

pack compressible insulationbetween last rafter and wall

full fill mineral woolcavity wall insulation,density up to40kg/m³

cavity width min. 75mmup to 100mm max.

(subject to Robust Detailrequirements)

2 x 100mm leaves to separatingwall above dpc:Celcon Standard (3.6N/mm²)Celcon High Strength (7.3N/mm²)Celcon Super Strength (8.7N/mm²)

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

Party Wall Masonry, Full Fill -

Roof, Insulated At Ceiling Level,

Ventilated Loft

HH-PW-20

AHRSJB

Nov 2012 A1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

For Ψ values applicable to this detail,see Constructive Details CD0020orLABC Registered ConstructionDetails P4PCFF1 - 2.

A 11/2014 SJBLABC NOTE ADDED

Page 24: see Constructive Details CD0001 LABC Registered · PDF fileHH-PF-01 External Masonry Cavity Wall, Partial-Fill - Suspended Beam And Block Floor, Insulation Above Slab ... base course

breathable roofmembrane

minimum 100mminsulation

full fill mineral wool cavity wallinsulation, density up to 40kg/m³

2 x 100mm leaves to separating wall:Celcon Standard (3.6N/mm²)

Celcon High Strength (7.3N/mm²)Celcon Super Strength (8.7N/mm²)

cavity width min. 75mm up to 100mm max.(subject to Robust Detail requirements)

pack compressible insulationbetween last rafter and wall

insulation under rafters(optional)

min. 150mm rafters void fullyfilled with insulation

DRAWN BY

TITLE

DATE SCALE

CHECKED BY

REV.NO.

DWG No.

Party Wall Masonry, Full Fill -

Roof, Insulated At Rafter Level,

Unventilated Rafter Void

HH-PW-21

AHRSJB

Nov 2012 1:100 @ A4

REV. DESCRIPTION.DATE. BY.

H+H UK Limited

Fax +44 (0)1732 887013

Kent, TN15 9HZ.Ightham, Sevenoaks

Tel +44 (0)1732 880580

Celcon HouseTechnical Services Dept.

E-mail [email protected]

These details have been produced for guidance only. It is theresponsibility of the building designer to ensure that the detailsshown are compatible with the overall building design and willsatisfy the relevant parts of the Building Regulations applicablebefore they are adopted into the project design.

B

A 11/2013 SJBRAFTERS INSULATION THICKNESSNOTE ADDED

For Ψ values applicable to this detail,see Constructive Details CD0021orLABC Registered ConstructionDetails P5PCFF1 - 2.

B 11/2014 SJBLABC NOTE ADDED