section i executive summary index - welcome to...
TRANSCRIPT
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section I/ Executive Summary
15
SECTION – I
EXECUTIVE SUMMARY
INDEX
1.1 IDENTIFICATION OF PROJECT ............................................................................................ 16
1.2 SALIENT FEATURES OF THE PROJECT .............................................................................. 16
1.3 RAW MATERIAL ....................................................................................................................... 17
1.4 PRODUCT .................................................................................................................................... 18
1.5 CONCLUSION ............................................................................................................................. 18
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section I/ Executive Summary
16
EXECUTIVE SUMMARY
1.1 IDENTIFICATION OF PROJECT
“Bharat Petroleum Corporation Limited” a public sector undertaking company of government of
India, deals in refining petroleum crude oil, distribution and marketing of the same in domestic and
international market.
Bharat Petroleum Corporation Limited (BPCL) - LPG plant, Bathinda, is located at plot nos.- A1 and
A2, PSIEC Growth Centre, Mansa Road, Distt.- Bathinda, Punjab, proposing augmentation of LPG
storage by additional 3 nos. of mounded storage vessels of capacity 300 MT each. Presently, the plant
has 3 nos. of A/G storage bullets of 150 MT each with cumulative capacity of 450 MT. Thus, after
augmentation the total LPG storage capacity of the plant will be 1350 MT.
The proposed augmentation of 900 MT mounded storage vessel is planned in existing plant area of 38
acres. No additional land is required for the proposed expansion. The expected capital investment for
the proposed augmentation is 2600 lacs. The proposed storage expansion of LPG bottling plant is
categorized as ‘B ‘in 6 (b) (iv) of Gazette Notification dated Sep 14th, 2006, amendment on
01.12.2009 {isolated storage & handling of hazardous chemical, as per threshold planning quantity
indicated in column 3 of schedule 2 & 3 of MSIHC Rules 1989 amended 2000}
04.04.2011,16.07.2013 and 09.09.2013.
As of now there is no duly constituted SEIAA & SEAC in the state of Punjab, therefore, as per the
provision of Para- 4 of EIA notification 14 September, 2006, “in the absence of a duly constituted
SEIAA & SEAC, category "B" Project shall be treated as a category "A" Project”. Thus, the project
shall be treated as category “A”.
1.2 SALIENT FEATURES OF THE PROJECT
S. No Parameter Description
1. Plant Capacity Existing and proposed plant details are given below.
Particulars Existing Proposed After Augmentation
LPG Storage Capacity A/G Bullets : 3 X 150 MT =
450 MT
Mounded Storage
vessel: 3 X 300 MT =
900 MT
1350 MT
The proposed expansion will also include addition of 1 mechanical carousel station (24 nos.) by replacing
manual filling machine.
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section I/ Executive Summary
17
2. Total area of
the plant
The proposed expansion is planned in existing plant area of 38 acre. No additional land is required
for the proposed expansion.
3. Capital Cost The expected capital investment for the proposed expansion is 2600 lacs.
4
Location
Latitude : 30° 10' 19.83'' N
Longitude : 74° 57' 13.59'' E
5
Total Water
Requirement/
Source
Particulars Existing
KLD
Proposed
KLD
After
Expansion
KLD
Source
Cleaning &
Washing
7 - 7 Source of water is
bore well and
Public water works
Bathinda
Domestic 3 - 3
Total 10 10
Fire water storage is 5400 KL. (Above ground M.S. fire water Tank) in compliance of OISD
guidelines for emergency purpose. The water of the tanks is replaced on half yearly basis.
6
Total waste
water
Generation
and
Management
Waste Water Existing
KLD
Proposed
KLD
After
Expansion
KLD
Management
Washing and
cleaning
waste
0.8 - 0.8 The same is and will be
utilized for plantation after
routing through vapor seal to
collect the vapors of gasses.
Domestic 2.1 - 2.1 The same is and will be
routed through septic tank
followed by soak pit.
Total 2.9 - 2.9
7.
Employment
generation
Category Manpower
Skilled 08 nos.
Un-skilled 70 nos.
Total 78nos.
8.
Power
Supply
Particulars Existing Proposed Total
Power demand 225 kVA (180 KW) - 225 kVA (180 KW)
9 Power
backup
Particulars Existing Proposed Total
DG sets 250 kVA - 250 kVA
125 kVA - 125 kVA
The existing power supply & backup is sufficient for the proposed augmentation.
1.3 RAW MATERIAL
This is not a production unit but a storage facility for Liquefied Petroleum Gas (LPG), its main
function to distribute the LPG in the nearby areas. At present the unit daily receives 450 MT of LPG.
While after augmentation of additional storage the unit will receive daily 1350 MT of LPG from
above said sources.
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section I/ Executive Summary
18
1.4 PRODUCT
The existing unit is a LPG filling plant. The product is LPG (Liquefied Petroleum Gas). The physical
and chemical property of LPG is given as follows:-
S. No. PARAMETER SPECIFICATION
1 Boiling range - 42 to 2 oC
2 Melting/freezing point - 42 oC
3 Vapor density (Air = 1) 1.8
4 Specific Gravity (Water = 1) 0.562 gm/1@ 15oC
5 Physical State Gas @15 oC & 1 atm
6 Vapor pressure 120 psi @ 38 o C
7 Solubility in water at 30 C Immiscible, liquid floats & boils on water
8 PLL Not pertinent
9 Appearance Colorless
10 Odour Ethyl Mercaptan added for odor warning
11 Other Soluble in organic solvent & alcohol.
1.5 CONCLUSION
The proposed expansion of BPCL LPG bottling plant, Bathinda will not only contribute to the growth
of Indian economy but will also strengthens the socioeconomic values / status in the area. All the
latest and environment friendly technology will be adopted. The unit will adopt all measures like;
pollution control equipments, effective EMP & DMP to prevent harm / damage to the environment.
***********
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section II/ Project Brief and Background
Information
19
SECTION II
PROJECT BRIEF AND BACKGROUND INFORMATION
INDEX
2.1 PROJECT BRIEF ................................................................................................................................. 20
2.2 BACKGROUND OF THE PROJECT PROPONENT ......................................................................... 20
2.3 NEED OF THE PROJECT & ITS IMPORTANCE TO THE COUNTRY AND OR REGION .......... 21
2.3 DEMAND-SUPPLY GAP ..................................................................................................................... 21
2.4 IMPORTS VS INDIGENOUS PRODUCTION .................................................................................... 23
2.5 EXPORT POSSIBILITY ....................................................................................................................... 23
2.6 DOMESTIC / EXPORT MARKETS. ................................................................................................... 23
2.7 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT ................ 23
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section II/ Project Brief and Background
Information
20
SECTION II
INTRODUCTION OF THE PROJECT AND BACKGROUND
INFORMATION
2.1 PROJECT BRIEF
“Bharat Petroleum Corporation Limited” a public sector undertaking company of government of
India, deals in refining petroleum crude oil, distribution and marketing of the same in domestic and
international market.
Bharat Petroleum Corporation Limited (BPCL) - LPG plant, Bathinda , is proposing augmentation of
LPG storage by additional 3 nos. of mounded storage vessels of capacity 300 MT each. Presently, the
plant has 3 nos. of A/G storage bullets of 150 MT each with cumulative capacity of 450 MT. The
proposed expansion consists of augmentation of the existing LPG storage capacity of the unit by
addition of 3 nos, of mounded storage vessels of 300 MT capacity each Thus, after augmentation the
total LPG storage capacity of the plant will be 1350 MT. The proposed expansion also includes
addition of a mechanical carousel station (24 nos.).
The proposed augmentation of 900 MT mounded storage vessel is planned in existing plant area of 38
acres. No additional land is required for the proposed expansion. The expected capital investment for
the proposed augmentation is 2600 lacs. The proposed storage expansion of LPG bottling plant
categorized as ‘B ‘in 6 (b) (iv) of Gazette Notification dated Sep 14th, 2006, amendment on
01.12.2009 {isolated storage & handling of hazardous chemical, as per threshold planning quantity
indicated in column 3 of schedule 2 & 3 of MSIHC Rules 1989 amended 2000}
04.04.2011,16.07.2013 and 09.09.2013.
As of now there is no duly constituted SEIAA & SEAC in the state of Punjab, therefore, as per the
provision of Para- 4 of EIA notification 14 September, 2006, “in the absence of a duly constituted
SEIAA & SEAC, category "B" Project shall be treated as a category "A" Project”. Thus, the project
shall be treated as category “A”.
2.2 BACKGROUND OF THE PROJECT PROPONENT
The LPG plant at PSIEC in Bathinda District is owned by Bharat Petroleum Corporation Limited.
Bharat Petroleum Corporation Limited, is public sector company ith a Navratna Status, and a Fortune
500 & Forbes 2000 company.It is one of the seven Navratna status companies of India, apart from
Coal India Limited, NTPC Limited, Oil and Natural Gas Corporation, Steel Authority of India
Limited, Bharat Heavy Electricals Limited and Gas Authority of India Limited.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section II/ Project Brief and Background
Information
21
BPCL and its subsidiaries account for a 49% share in the petroleum products market, 31% share in
refining capacity and 67% downstream sector pipelines capacity in India. TheBPCL Group of
companies owns and operates 4 of India's 22 refineries with a combined refining capacity of over 25
Million metric tonnes per year. BPCL has recorded outstanding results in all the facets of business for
the year 2013-2014. Both in Refining and Marketing excellent results have been delivered which have
contributed to the Company achieving the highest ever net Profit till date of Rs. 4060.88 Crores
surpassing the previous year’s record of Rs. 2642.90 Crores.
2.3 NEED OF THE PROJECT & ITS IMPORTANCE TO THE COUNTRY AND OR REGION
The Govt. of India had ventured into promotion of LPG as a cooking fuel in the Country more than 4
decades before. Starting from a very negligible coverage in the beginning, today all India coverage for
use of domestic LPG is close to 60% of the population. With a view to cut down on pollution and
reduce deforestation, the Govt. of India ventured on a program to increase the use of domestic LPG in
the rural sector by launching Rajiv Gandhi Gramin LPG Vitarak from 2009-10 with a target to
increase the all India coverage on use of LPG as a cooking gas to 75% of the population.
The existing LPG plant is supplying demand of LPG cylinders for domestic and commercial purpose
in the region. To meet the increasing demand of LPG in the region, there is need to expand the
storage and bottling capacity of the existing LPG plant of BPCL.
2.3 DEMAND-SUPPLY GAP
Past Consumption Pattern
The diagram below explains the forces acting upon LPG sector instilling its growth upwardly, and the
inhibitors which deter growth rate of industry. Dynamics in LPG sector is largely affected by both
micro and macroeconomic factors as shown. The growth rates of this industry are highly affected by
economic growth rate of the country as GDP, growth in population, agricultural and commercial
usage, which in turn changes the demand for LPG. Regulatory framework is expected to be an active
enabler for the LPG sector, considering it is a loss making sector to the government; India also
requires huge investments for infrastructural developments in the LPG sector. A National &
International political decision is an uncontrollable factor which affects the demand and supply
scenario of LPG industry. An optimistic view suggests that the drivers foreplay inhibitors and hence
the industry is expected to grow at a significant rate in the coming decade.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section II/ Project Brief and Background
Information
22
Drivers and Inhibitors of LPG
Growth Growth
Drivers Inhibitors
There is a fair degree of correlation between the growth in Oil & Gas products and the growth in the
population and overall economic activities. Thus demand will be in line with population and
economic growth.
Several factors such as household income, location, and availability and prices of alternatives, appear
to affect the choice of or dependence on LPG.
LPG is largely used as a domestic fuel in India for cooking and to a lesser extent, as an industrial and
commercial energy source. LPG consumption in the region has more than doubled over the last
decade.
Future Demand – Supply Projections
LPG will continue to remain a dominant fuel for cooking for households of the region; with
Government of India’s ambitious plans to increase use of LPG and reduction in quota of kerosene. It
Growing
population
Domestic usage
LPG
Commercial
usage
Technological
Advancement
Quality of Life
& Purchasing
Growing service
sector
National &
International
Politics
Limited Funds &
Infrastructure
Regulatory
Framework
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section II/ Project Brief and Background
Information
23
is expected that there will be a shift in fuel usage pattern in rural sector and dependence on
conventional cooking fuels like wood and kerosene will go on reducing consistently.
2.4 IMPORTS VS INDIGENOUS PRODUCTION
The proposed project storage capacity augmentation and does not involves imports.
LPG is used worldwide for cooking and heating, especially in areas without connection to piped
natural gas. LPG is a clean fuel for households and is associated with the need for cylinder refills. The
proposed expansion project aims to fulfill, time and place utility with effective cylinder management
as LPG has to be stored under pressure, with metal cylinders.
2.5 EXPORT POSSIBILITY
There is no export possibility by the proposed capacity augmentation, hence not applicable.
2.6 DOMESTIC / EXPORT MARKETS.
The existing bottling unit aims to cater LPG distribution to nearby area. The proposed storage
expansion is for domestic market.
2.7 EMPLOYMENT GENERATION (DIRECT AND INDIRECT) DUE TO THE PROJECT
The total requirement of manpower for the existing LPG plant is about 78 persons (Skilled Workers-8
& Unskilled Workers-70). For installation of 3 mounded storage vessels (300 MT capacities each)
will require 50 manpower during construction phase.
Manpower
Category Manpower
Skilled Workers 08 nos.
Unskilled Workers 70 nos.
Total 78 nos.
There will be a positive impact on the indirect employment of the region.
Transporters (Trucks and logistics) contract with BPCL for distribution purpose will increase
and this would result in the additional employment by the transporter (in-contract).
Due to gas transportation activity, petty food joints and & others en-route (fruits and
vegetable markets) will be benefitted, to full fill the need of associated people.
*********
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
24
SECTION – III
PROJECT DESCRIPTION
INDEX
3.1 TYPE OF PROJECT ................................................................................................................................25
3.2 LOCATION OF THE PROJECT ..............................................................................................................25
3.3 DETAILS OF ALTERNATIVE SITES CONSIDERED .........................................................................27
3.4 SIZE OR MAGNITUDE OF OPERATION............................................................................................27
3.5 MANUFACTURING PROCESS .............................................................................................................28
3.6 RAW MATERIAL (Quantity and Source), PRODUCT AND MODE OF TRANSPORT ......................30
3.7 SOURCE OPTIMIZATION/RECYCLING AND REUSE ENVISAGED IN THE PROJECT .................31
3.8 AVAILABILITY OF WATER, ENERGY / POWER REQUIREMENT AND SOURCE......................31
3.9 WASTE GENERATION AND MANAGEMENT ..................................................................................32
3.10 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING WHICH GIVE
INFORMATION OF EIA PURPOSE ......................................................................................................32
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
25
SECTION III
PROJECT DESCRIPTION
3.1 TYPE OF PROJECT
The proposed storage expansion of LPG bottling plant is categorized as ‘B’ in 6 (b) (iv) of Gazette
Notification dated Sep 14th, 2006, amendment on 01.12.2009 {isolated storage & handling of
hazardous chemical, as per threshold planning quantity indicated in column 3 of schedule 2 & 3 of
MSIHC Rules 1989 amended 2000} 04.04.2011,16.07.2013 and 09.09.2013. As of now there is no
duly constituted SEIAA & SEAC in the state of Punjab, therefore, as per the provision of Para- 4 of
EIA notification 14 September, 2006, “in the absence of a duly constituted SEIAA & SEAC, category
"B" Project shall be treated as a category "A" Project”. Thus, the project shall be treated as category
“A”.
The proposed project is envisaged for installation of 3 mounded storage vessels (300 MT capacity
each) within existing LPG plant of Bharat Petroleum Corporation Limited (BPCL), PSIEC at
Bathinda, Punjab State. The existing LPG bottling plant has above ground storage of 450 MT LPG (3
bullets of 150 MT capacities each). BPCL has planned to install three mounded storage bullets having
capacity of 300 MT each (3 x 300 MT) at the existing LPG Plant premises having area of 38 acres.
No additional land is required for the proposed expansion. The expected capital investment for the
proposed augmentation is 2600 lacs.
3.2 LOCATION OF THE PROJECT
The existing LPG Plant is located at plot nos. - A1 and A2, PSIEC Growth Centre, Mansa Road,
Distt.- Bathinda, Punjab. The latitude and longitude of the site is 30° 10' 19.83'' N and 74° 57' 13.59''
E.
The site for proposed mounded storage vessel plant is within the BPCL’s existing LPG plant. The
power and water required for installation of three mounded storage vessels and increased capacity of
LPG bottling is already available at the existing plant. Due to its proximity to the SH-17 & NH-7 the
project will enjoy good infrastructure and other facilities such as availability of skilled as well as
unskilled workforce, contractors, transportation facilities, etc.
The plan clearly showing the project site in figure-1and study area of 10 km radius is shown in below
figure-2.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
26
Figure-1 BPCL’s LPG Plant Location
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
27
Figure-2: Project site and Study Area
3.3 DETAILS OF ALTERNATIVE SITES CONSIDERED
No alternative site was examined or chosen, as the proposed expansion is coming up in existing land
area available with BPCL, Bhatinda Plant.
3.4 SIZE OR MAGNITUDE OF OPERATION
There is no production or manufacturing process at existing LPG Plant. The plant is engaged in
storage and bottling of LPG in domestic and commercial cylinders.
The existing LPG bottling plant has above ground storage bullets of 450 MT LPG (3 bullets of 150
MT capacities each). The LPG plant is operated in two shifts i.e. 6am to 2pm & 2pm to 10pm and
general shift (9 AM to 5.30 PM).
Particulars Existing Proposed After Augmentation
LPG Storage
Capacity
A/G Bullets : 3 X 150 MT =
450 MT
Mounded Storage vessel:
3 X 300 MT = 900 MT
1350 MT
The proposed expansion will also include addition of 1 mechanical carousel station (24 nos.) by replacing manual
filling machine.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
28
3.5 MANUFACTURING PROCESS
There are no chemical reactions involved in the process at the Plant. A brief process is depicted
below:
The operations start with the receipt of bulk LPG, bulk LPG is being received through tank lorries in
the plant. The above lorries are decanted in T/L bay by differential pressure method. The product is
transferred from the tank lorry to the storage vessels through pipelines.
From the storage tank (Bullets) the product is pumped to the filling machines by using centrifugal
pumps.
The empty cylinders from the market are received at the unloading finger. These cylinders are
checked as per the visual inspection format for dent, genuineness burnt marks, mechanical damages
by the company staff. Only sound empty cylinders are sent to the carousal & filling machine for
filling.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
29
The cylinder filled is checked for correctness of weight on the check scale, to compact valve tester for
checking of leakage from valve & 'O' Ring. After completing the above checking, the cylinder is
capped by safety cap & then goes to test water bath for body/bung leak checks. The leaky cylinders
are rejected after the test bath and the same goes to evacuation unit for decantation of the product
from the cylinder. After evacuating the product from the cylinder, the above cylinder goes to cold
flaring unit for degassing & then the cold repair is done. Body leak cylinders are rejected for
scrapping after de-gassing.
Similarly the cylinders having variation in weight of the gas filled are also taken out to correction unit
& the weight is adjusted by filling the product or taking out the product as per the requirements.
All sound cylinders after Test Bath are sealed with PVC seal which is sealed through hot Air Sealing
Unit. These cylinders are then loaded to the trucks for dispatching to the markets. A random check is
also done before the dispatch.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
30
3.6 RAW MATERIAL (Quantity and Source), PRODUCT AND MODE OF TRANSPORT
The plant operations are as follows:
1. Receipt of Material
Transfer of LPG from Dahej (Gujarat), Pipavav, Jamnagar Refinery, HMEL
Refinery.
Through bullet trucks
Bullet Trucks unloading
LPG transfer to storage bullets
Storage of LPG in bullets
2. Receipt of empty LPG cylinders &segregation
3. Bottling
Pumping of LPG to filling shed
Bottling of LPG cylinders
Quality check on filled cylinders
Loading into Trucks
4. Dispatch
Loading of packed cylinders in trucks
Supply & distribution to markets (through Authorized dealers)
The LPG cylinders of various capacities i.e. 14.2 kg (domestic purpose), 19 kg (commercial purpose),
35 kg & 47.5 kg (industrial purpose) are bottled at the existing plant and then finally dispatched for
consumers.
Bulk storage of LPG:
Above ground LPG Bullets are provided with 1 No 4 inch nozzle at bottom for product receipt and
with drawl, 3 nos. 3 inch, nozzles are provided at top of the Bullet, 2 nos. for vapour inlet and vapour
withdrawal and one for product return from pump bypass, carousel return and evacuation. Bullet are
designed as per the latest international standards viz BS 5500, ASME SEC III div II. Bulk LPG is
stored in 3 x 150 MT bullet. Each bullet is provided with 2 nos. safety relief valves. Bullets are
provided with 2 gauging systems in the form of a Rochester gauge and slip in dip rod type gauge with
high level switch. All the nozzles on the bullets are provided with remote operated valves for
automatic emergency shutdown. The bullets are also provided with pressure and temperature gauges.
LPG Storage Bullets : 3x 150 MT Bullets
Operating Pressure : 19.33 kg/cm2 at 55
oC
Hydrotest Pressure : 26.76 kg/cm2
Design Temperature : -45 oC +55
oC
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
31
Design Pressure : 21.2 kg/cm2 at top
Corrosion Allowance : 1.5 mm
Product
The existing unit is a LPG filling plant. The product is LPG (Liquefied Petroleum Gas). The physical
and chemical property of LPG is given as follows:-
S. No. PARAMETER SPECIFICATION
1 Boiling range - 42 to 2 oC
2 Melting/freezing point - 42 oC
3 Vapor density (Air = 1) 1.8
4 Specific Gravity (Water = 1) 0.562 gm/1@ 15oC
5 Physical State Gas @15 oC & 1 atm
6 Vapor pressure 120 psi @ 38 o C
7 Solubility in water at 30 C Immiscible, liquid floats & boils on water
8 PLL Not pertinent
9 Appearance Colorless
10 Odour Ethyl Mercaptan added for odor warning
11 Other Soluble in organic solvent & alcohol.
3.7 SOURCE OPTIMIZATION/RECYCLING AND REUSE ENVISAGED IN THE
PROJECT
The BPCL Bathinda plant is LPG storage and Bottling plant and proposing additional augmentation
of storage bullet. Thus, recycle and reuse is not envisaged in the proposed expansion.
3.8 AVAILABILITY OF WATER, ENERGY / POWER REQUIREMENT AND SOURCE
3.8.1 Water Demand
Existing average water consumption of LPG storage and bottling plant is 10 m3 /day. The water is
utilized for cleaning and washing of cylinders to the tune of 7 KLD, while 3 KLD water is required
for domestic purposes. The project proposal is only for installation of 3 nos. of additional mounded
storage vessels to augment the storage capacity. The water consumption due to the proposed augment
will not increase because the total bottling capacity will remain intact after augmentation.
The unit has one 5400 KL (Above ground M.S. fire water Tank) in compliance of OISD guidelines
for emergency purpose. The water of the tanks is replaced on half yearly basis.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
32
3.8.2 Power Demand
The existing power demand of the unit is 225 kVA (180 KW) and is obtained from grid power supply.
The existing plant has D.G. of 125 kVA, and 250 kVA at the site. The existing power supply and
backup is sufficient for the proposed augmentation. No additional D.G. set is required for the
proposed augmentation.
3.9 WASTE GENERATION AND MANAGEMENT
3.9.1 Municipal Solid Waste
Approx. 5 kg municipal waste is generated at existing LPG plant, which is disposed as per Solid
Wastes Management Rule, 2016.
3.9.2 Hazardous Waste
Used oil generated occasionally from maintenance of DG sets and engines is hazardous waste, which
is handed over to authorized used oil recyclers as per MOEF&CC/PSPCB guidelines.
3.9.3 Waste water
Effluent Treatment Plant (ETP) of 25 KLD is already in operation at the existing plant to treat the
effluent generated through washing of cylinders. Sludge generated from ETP is stored in pit and
disposed as per per MOEF&CC/PSPCB guidelines.
3.10 SCHEMATIC REPRESENTATIONS OF THE FEASIBILITY DRAWING WHICH
GIVE INFORMATION OF EIA PURPOSE
As per the EIA notification dated 14th September, 2006, it is mandatory for the proposed activity to
get Environmental Clearance (EC) before setting up any project or expansion/modernization of any
project. The detailed chart delineating the process is given below:
Environmental Impact Assessment (EIA) is a well planned process to predict the environmental
consequences of any kind of development, which is a result of human activities and to suggest
appropriate measures in order to reduce adverse effects and also to augment positive effects. The EIA
procures a rational and ethical approach for sustainable development. However, it is more scientific
process because it not only tells the past, present and the future consequences of on-going
developments, but also predicts the future events which are likely to change due to various reasons.
In terms of the EIA notification of the MoE&F dated 14th September 2006, the generic structure of
EIA documents shall be as under:-
Introduction
Project Description
Analysis of Alternatives (Technology & Site)
Description of the Environment
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section III/ Project Description
33
Anticipated Environmental Impact & mitigation Measures
Environmental Monitoring Program
Additional studies
Project benefits
Environmental Cost benefits Analysis
EMP
Summary & Conclusion
Disclosure of Consultant Engaged
*************
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IV/ Site Analysis
39
SECTION – IV
SITE ANALYSIS
INDEX
4.1 CONNECTIVITY ..................................................................................................................... 40
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP ........................................................ 40
4.3 TOPOGHRAPHY ..................................................................................................................... 40
4.4 EXISTING LAND USE PATTERN ......................................................................................... 41
4.5 EXISTING INFRASTRUCTURE OF SITE ............................................................................ 41
4.6 SOIL CLASSIFICATION ........................................................................................................ 42
4.7 CLIMATE DATA FROM SECONDARY SOURCES ............................................................ 42
4.8 SOCIAL INFRASTRUCTURE AVAILABLE ........................................................................ 42
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IV/ Site Analysis
40
SECTION – IV
SITE ANALYSIS
4.1 CONNECTIVITY
BPCL, Bathinda an LPG storage and bottling plant is situated at located at plot nos.- A1 and A2,
PSIEC Growth Centre, Mansa Road, Distt.- Bathinda, Punjab which has all possible amenities that are
feasible for industrial projects viability.
Particular Details
Airport Bathinda Airport -21.24km towards NW
IGI Airport-274 km towards SE
Nearest National Highway,
State Highway, Major
District road
SH-17: 1.20 km towards NNE
NH-15: 7.47 km towards NNW
NH-64: 5.72 km towards N
SH-41: 10.20 km towards NW
SH-16A: 14.30 km towards ENE
Railway Station Bathinda R.S.- 4.70 km towards NNW
Water Bodies Bid Talab P.F : 7.15km towards WNW
Lower Lisada Nala : 10.47 km towards SSW
Pond : 2.93 km towards NW
Nahar Bathinda Shakha : 6.45 km towards NW
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
Land Form: The proposed expansion is planned in existing plant area of 38.00 acres. No additional
land is required for the proposed expansion.
Land Use: The proposed land use of the project is as under:
Particulars Existing
(Acres)
Proposed
(Acres)
After Expansion
(Acres)
Percentage
(%)
Plant Area, Office Area, and
housing (all covered area) 17.10 - 17.10 45
Paved Area ( Road, Corridor,
Parking and drainage) 3.04 - 3.04 8
Green Belt Area 12.54 - 12.54 33
Open Area 5.32 - 5.32 14
Total Plot Area 38.00 38.00 100
4.3 TOPOGHRAPHY
The district is situated within the Satluj-Ganga plain. The whole of the district is a low-lying flat area.
T he only contour line running across the area is of 220 meters. It runs from the south-east of Sidhani
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IV/ Site Analysis
41
village northward through Kahangarh (Mansa Tehsil) and then north-west to Bareta (Mansa Tehsil).
From here, the line runs north-west and passes just west of Kishangarh (Mansa Tehsil). Then it moves
just south-west of Gidrene (Sirsa District, Haryana) and goes westward through Daska. From here, the
contour takes a south-west bend and goes towards Datewas (Mansa Tahsil, from where it takes a
northwesterly direction and goes through Chak Ni agaon and Gurney Kalan (Mansa Tahsil).
The presence of only one counter indicates the flattish nature of the surface. The slope of the area is
from north-east to south-west as indicated by the direction of the flow of canals and spot heights. The
highest point in the area is Ratta Khera (Hisar District, Haryana) in north-eastern part with a height of
205 meters. The lowest point is at a height (Talwandi Sabo Tehsil). The elevation of the plain thus has
a range of about 25 meters.
4.4 EXISTING LAND USE PATTERN
Particulars Area
(Acres)
Percentage
(%)
Plant Area, Office Area, and housing (all covered area) 17.10 45
Paved Area ( Road, Corridor, Parking and drainage) 3.04 8
Green Belt Area 12.54 33
Open Area 5.32 14
Total Plot Area 38.00 100
4.5 EXISTING INFRASTRUCTURE OF SITE
Physical infrastructure
Physical infrastructure is an important aspect of a city. It determines the quality of life to a large
extent. Physical infrastructure deals with
Water supply
Electricity
Solid waste
Water supply
Existing average water consumption of LPG storage and bottling plant is 10 m3 /day. The water is
utilized for cleaning and washing of cylinders to the tune of 7 KLD, while 3 KLD water is required
for domestic purposes. The project proposal is only for installation of 3 nos. of additional mounded
storage vessels to augment the storage capacity. The water consumption due to the proposed augment
will not increase because the total bottling capacity will remain intact after augmentation.
The unit has one 5400 KL (Above ground M.S. fire water Tank) in compliance of OISD guidelines
for emergency purpose. The water of the tanks is replaced on half yearly basis.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IV/ Site Analysis
42
Electricity
The existing power demand of the unit is 225 kVA (180 KW) and is obtained from grid power supply.
The existing plant has D.G. of 125 kVA, and 250 kVA at the site. The existing power supply and
backup is sufficient for the proposed augmentation. No additional D.G. set is required for the
proposed augmentation.
SOLID WASTE
Municipal Solid Waste
Approx. 5 kg municipal waste is generated at existing LPG plant, which is disposed as per Solid
Wastes Management Rule, 2016.
Hazardous Waste
Used oil generated occasionally from maintenance of DG sets and engines is hazardous waste, which
is handed over to authorized used oil recyclers as per MOEF&CC/PSPCB guidelines.
4.6 SOIL CLASSIFICATION
The area is basically alluvium, situated towards the depression of the rivers Ganges and Indus. The
safe bearing capacity the soil is about 1.0 kg/sq.cm.
4.7 CLIMATE DATA FROM SECONDARY SOURCES
The climate of Bathinda district can be classified as tropical steppe, semi-arid and hot which is mainly
dry with very hot summer and cold winter except during monsoon season when moist air of oceanic
origin penetrates into the district. There are four seasons in a year. The hot weather season starts from
mid March to last week of the June followed by the south- west monsoon, which lasts up to
September. The transition period from September to October forms the post-monsoon season. The
winter season starts in November and remains up to first week of March to last week of the June
followed by the south- west monsoon, which lasts up to September. The transition period from
September to October forms the post monsoon season. The winter season starts late in November and
remains up to first week of March.
4.8 SOCIAL INFRASTRUCTURE AVAILABLE
Habitation of Nacchator Nagar is approx 1.20 km towards NNE densely populated with available
social infrastructure viz: Primary, secondary schools, dispensary, hospitals, Mandir, Masjid, Church
etc.
Medical Facilities:
Max Super Specialty Hospital : 2.95 km towards NNW
Bharat Hospital : 3.30 km towards North
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IV/ Site Analysis
43
Raman Hospital : 3.74 km towards North
Post & Telegraph Offices: Available in Bathinda
Schools:
G.N.D.P Secondary School : 3.37 km towards North
Worship /Temple:
Gurudwara : 1.53 km towards NNE
Shri Panchmukhi Balaji Dham: 4.28 km towards west
On the basis of the preliminary site visit, the infrastructure available was identified. Further after the grant of TOR,
available infrastructure (baseline data) will be encompassed, along with socio economic observations and submitted at the
time of final presentation regarding EIA/EMP.
**************
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section V/ Planning Brief
44
SECTION – V
PLANNING BRIEF
INDEX
5.1 PLANNING CONCEPT (type of Industries, facilities transportation etc.) TOWN AND
COUNTRY PLANNING/ DEVELOPMENT AUTHORITY CLASSIFICATION ............................. 45
5.2 POPULATION PROJECTION................................................................................................. 45
5.3 LAND USE PLANNING (Break up along with green Belt, etc.) ............................................ 45
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (Physical & Social) ............................ 45
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section V/ Planning Brief
45
SECTION V
PLANNING BRIEF
5.1 PLANNING CONCEPT (type of Industries, facilities transportation etc.) TOWN AND
COUNTRY PLANNING/ DEVELOPMENT AUTHORITY CLASSIFICATION
The project is for LPG storage and bottling unit. The unit has 3 nos. of existing A/G bullets storage
vessels of 150 MT each. The unit operates in two shifts. Now, the plant is planning for increasing the
storage capacity by installing 300 MT x 3 mounded storage vessels. The capital investment required
for the proposed augmentation is 2600 lacs.
5.2 POPULATION PROJECTION
The proposed capacity augmentation in the LPG bottling plant shall not require additional permanent
manpower. Hence, there will be no change in the population projection of the nearest and farther most
villages due to the proposed expansion unit. A temporary influx of 50 local workers for erection and
fabrication will be there in the plant premises.
5.3 LAND USE PLANNING (Break up along with green Belt, etc.)
Land Use: The land use after the proposed expansion of the project is as under:
Particulars Existing
(Acres)
Proposed
(Acres)
After
Expansion
(Acres)
Percentage
(%)
Plant Area, Office Area, and
housing (all covered area) 17.10 - 17.10 45
Paved Area ( Road, Corridor,
Parking and drainage) 3.04 - 3.04 8
Green Belt Area 12.54 - 12.54 33
Open Area 5.32 - 5.32 14
Total Plot Area 38.00 38.00 100
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND (Physical & Social)
Social Demand
There is an infrastructure demand of new storage vessel. The storage capacity augmentation aims to
moderately reduce the waiting time of its distribution, thereby fulfilling social demand of LPG. The
manpower requirements will remain the same hence there is no additional social Infrastructure
demanded inside the project periphery.
Physical Demand
Water: The plant has daily fresh water requirement to the tune of 10 KLD. Out of which the 7 KLD is
required for washing and mock drills (once in a month) and 3 KLD for domestic purposes.
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section V/ Planning Brief
46
Electricity:
The existing power demand of the unit is 225 kVA (180 KW) and is obtained from grid power supply.
The existing plant has D.G. of 125 kVA, and 250 kVA at the site. The existing power supply and
backup is sufficient for the proposed augmentation. No additional D.G. set is required for the
proposed augmentation.
******************
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section VI/ Proposed Infrastructure
47
SECTION – VI
PROPOSED INFRASTRUCTURE
INDEX
6.1 INDUSTRIAL AREA (processing area) ........................................................................................ 48
6.2 RESIDENTIAL AREA (non processing area) ............................................................................... 48
6.3 GREEN BELT ................................................................................................................................ 48
6.4 SOCIAL INFRASTRUCTURE ...................................................................................................... 48
6.5 CONNECTIVITY ........................................................................................................................... 48
6.6 WATER MANAGEMENT (source & supply of water) ................................................................. 49
6.7 SEWERAGE SYSTEM .................................................................................................................. 49
6.8 INDUSTRIAL WASTE MANAGEMENT .................................................................................... 49
6.9 SOLID WASTE MANAGEMENT ................................................................................................. 49
6.10 POWER REQUIREMENT & SUPPLY/ SOURCE ........................................................................ 49
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section VI/ Proposed Infrastructure
48
SECTION VI
PROPOSED INFRASTRUCTURE
6.1 INDUSTRIAL AREA (processing area)
The existing LPG storage and bottling plant is established in an area of 38.0 acres. The proposed
augmentation will be installed in the existing land area. No additional land is required for the
proposed expansion of the storage capacity.
6.2 RESIDENTIAL AREA (non processing area)
The plant does not have any residential facility for the workers and employee.
6.3 GREEN BELT
The existing unit has approximately 33% total land area in green belt and plantation.
6.4 SOCIAL INFRASTRUCTURE
Establishment of a self help group of area women (minimum 7 local women) for income generating
activity viz: community kitchen. Proposed social infrastructure shall involve construction and
facilities installation for the Community Kitchen. Training to invest and manage funds for self
sustainable employment will be imparted.
6.5 CONNECTIVITY
BPCL, Bathinda an LPG storage and bottling plant is situated at located at plot nos.- A1 and A2,
PSIEC Growth Centre, Mansa Road, Distt.- Bathinda, Punjab which has all possible amenities that are
feasible for industrial projects viability.
Particular Details
Airport Bathinda Airport -21.24km towards NW
IGI Airport-274 km towards SE
Nearest National Highway,
State Highway, Major
District road
SH-17: 1.20 km towards NNE
NH-15: 7.47 km towards NNW
NH-64: 5.72 km towards N
SH-41: 10.20 km towards NW
SH-16A: 14.30 km towards ENE
Railway Station Bathinda R.S.- 4.70 km towards NNW
Water Bodies Bid Talab P.F : 7.15km towards WNW
Lower Lisada Nala : 10.47 km towards SSW
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section VI/ Proposed Infrastructure
49
Pond : 2.93 km towards NW
Nahar Bathinda Shakha : 6.45 km towards NW
6.6 WATER MANAGEMENT (source & supply of water)
Existing average water consumption of LPG storage and bottling plant is 10 m3 /day. The water is
utilized for cleaning and washing of cylinders to the tune of 7 KLD, while 3 KLD water is required
for domestic purposes. The project proposal is only for installation of 3 nos. of additional mounded
storage vessels to augment the storage capacity. The water consumption due to the proposed augment
will not increase because the total bottling capacity will remain intact after augmentation.
The unit has one 5400 KL (Above ground M.S. fire water Tank) in compliance of OISD guidelines
for emergency purpose. The water of the tanks is replaced on half yearly basis.
6.7 SEWERAGE SYSTEM
The domestic waste water is being routed to septic tank followed by soak pit. The same will be
followed after expansion.
6.8 INDUSTRIAL WASTE MANAGEMENT
Effluent Treatment Plant (ETP) of 25KLD is already in operation at the existing plant to treat the
effluent generated through washing of cylinders. Sludge generated from ETP is stored in pit &
disposed as per MOEF&CC/PSPCB guidelines.
6.9 SOLID WASTE MANAGEMENT
Hazardous Waste:
Used oil generated occasionally from maintenance of DG sets and engines is hazardous waste, which
is handed over to authorized used oil recyclers as per MOEF&CC/PSPCB guidelines.
Municipal Solid Wastes:
Approx 5 kg municipal waste is generated at existing LPG plant, which is disposed as per Solid
Wastes Management Rule, 2016.
6.10 POWER REQUIREMENT & SUPPLY/ SOURCE
The existing power demand of the unit is 180 KW and is obtained from grid power supply. The
existing plant has D.G. of 125 kVA and 250 kVA at the site. The existing power supply and backup is
sufficient for the proposed augmentation. No additional D.G. set is required for the proposed
augmentation.
**************
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section VII/ Rehabilitation &
Resettlement Plan
50
SECTION – VII
REHABILITATION & RESETTLEMENT (R&R) PLAN
7.1. REHABILITATION & RESETTLEMENT (R&R) PLAN ...................................................... 51
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section VII/ Rehabilitation &
Resettlement Plan
51
SECTION VII
REHABILITATION & RESETTLEMENT (R&R) PLAN
7.1. REHABILITATION & RESETTLEMENT (R&R) PLAN
Not Applicable
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section VIII/ Project Schedule & Cost
Estimates
52
SECTION – VIII
PROJECT SCHEDULE & COST ESTIMATES
INDEX
8.1. PROJECT SCHEDULE & COST ESTIMATES ...................................................................... 53
PROJECT: BPCL, LPG BOTTLING PLANT, BATHINDA Section VIII/ Project Schedule & Cost
Estimates
53
SECTION – VIII
PROJECT SCHEDULE & COST ESTIMATES
8.1. PROJECT SCHEDULE & COST ESTIMATES
Likely date of start of construction and likely date of completion (time schedule for the project to be
given) Estimated project cost along with analysis in terms of economic viability of the project.
The likely date of the start of erection or fabrication will be after the grant of all required
clearances.
The likely date of completion / time required for the fabrication and erection of the one
storage vessel would take one year, from the grant of clearances. The proposed vessel will be
operationalised after successful erection.
The project cost is Rs. 2600 for the entire fabrication and erection of one new storage vessel.
As per the prevailing market conditions, there is high rising demand for LPG.
*************
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IX/ Analysis of Proposal
54
SECTION – IX
ANALYSIS OF PROPOSAL
INDEX
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IX/ Analysis of Proposal
55
SECTION – IX
ANALYSIS OF PROPOSAL
Financial and social benefits with special emphasis on the benefit to the local people
including tribal population, if any, in the area.
BPCL has been engaged with various CSR programmes for more than two decades.
CSR Initiatives at Sultanpur , Gonda and nearby region in the study area by Bharatgas (Brand name of BPCL
LPG products) :
Free community Kitchen: Campaigns were organized
to provide cooking gas, stove, and utensils to flood
victims to establish community kitchens.
Rural safety for sure: A rally organized in areas of
district Gonda, in Dec. 2011 where safety concepts in
general & “Safety for Sure” concepts were given on
awareness in Jansabhas.
Safety Clinics: In 2011, 38 Safety Clinics were
organized resulting in 2000 beneficiaries around the
study area of the proposed project (regional area of
Sultanpur). The study area residents were educated
(along with demonstrations) of safe use of LPG,
features of Suraksha rubber tube, flame lighter, &
flame retardant aprons etc.
Recognition and awards of BPCL
BPCL bagged the „CIDC Vishwakarma Awards‟ for
the second time in a row for CSR on March „12. The
proposed project was awarded for CSR for women
empowerment and livelihood generation initiative in
Lucknow with the NGO partner SEWA. Through this
CSR project we have been able to generate livelihood
option for more than 500 underprivileged rural women.
Project: BPCL, LPG BOTTLING PLANT, BATHINDA Section IX/ Analysis of Proposal
56
A humble contribution made of Rs. 11.35 lacs to the
Chief ministers relief fund, by North Region – LPG
territories including Amethi to assist 500 affected
families in the worst effected District of Rudraprayag
covering Kedar Valley & other blocks by distributing
“Single Burner Hotplate & Pressure cooker”, a joint
effort undertaken for rehabilitation of families affected
during floods. Chief Minister applaudes Bharatgas
Parivar for noble steps for social causes in the hour of
crisis.
BPCL bags the „Aaj Tak Care Awards‟ for CSR under
the livelihood category for the project “Economic
empowerment and income generation” , which has
touched and impacted 600 rural women in Lucknow ,
near the (bottling plant) proposed expansion project.
During the award ceremony, video clips of the
beneficiaries were also shown, which spoke volumes
on the contribution BPCL and our NGO partner SEWA
has made in the lives of these women and their
families.
There will be social benefits from the proposed storage capacity augmentation; the underlying benefit
through the proposed project aims to:
The appropriate amount for the CSR is proposed to be Rs. 4,00,000 /- as capital cost year and Rs
50,000/- as recurring cost.
Establishment of a self help group of area women (minimum 7 in number) for income generating
activity viz. community kitchen. Proposed social infrastructure shall involve construction and
facilities installation for the Community Kitchen in involvement of local authorities. Training to
invest and manage funds for self sustainable employment will be imparted.
The above Women empowerment activity was identified on the basis of the preliminary site visit.
However after the analysis of the baseline data generation, socio – economic observation, and the
public hearing, the appropriate sustainable development will be contributed and projected by the