section 38 referral supporting document · 2020. 6. 2. · section 38 referral supporting document...
TRANSCRIPT
100-TE-DC-0003_5
Report
Section 38 Referral Supporting Document
Pilbara Energy Generation Power Station
May 2020
45-10015-RP-EN-0001 Rev 145-10015-RP-EN-0001Rev 1
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 2 of 49
This document is protected by copyright, no part of this document may be reproduced or adapted without the consent of the originator/company owner, all rights are reserved. This document is “uncontrolled when printed”.
Section 38 Referral Supporting Document
Document &
Revision Number 45-10015-RP-EN-0001 Rev 1
21/05/2020
Status IFU Issued for Use
Summary of
Changes
Author Katherine Fox / David Thompson
Checked or Squad
Review#
(if applicable)
FMG Squad Review
Approved Brett McGuire
Access to this
document:
Public Use (Access to
all)Public Use (Access to
all)Public Use (Access to
all)
Next Review Date
(if applicable)
Click here to enter a
date.
Revision History (to be completed for each version retained by Document Control)
Author Checker Approver Rev
No. Status Issued Date
Initial/Surname Initial/Surname Initial/Surname Choose
an item.
Click here to
enter a date.
Initial/Surname Initial/Surname Initial/Surname Choose
an item.
Click here to
enter a date.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 3 of 49
TABLE OF CONTENTS
1. INTRODUCTION .......................................................................................................... 7
1.1 Purpose and Scope ....................................................................................... 7
1.2 Proponent ...................................................................................................... 8
1.2.1 Company details ............................................................................................. 8
1.2.2 Proponent representative ................................................................................ 8
1.2.3 Referral contact ............................................................................................... 8
1.3 Environmental Impact Assessment Process .............................................. 9
1.4 Other Approvals and Regulation ................................................................. 9
1.4.1 Land Tenure.................................................................................................... 9
1.4.2 Decision-making authorities .......................................................................... 10
1.4.3 Other approvals required............................................................................... 10
2. THE PROPOSAL ....................................................................................................... 11
2.1 Background ................................................................................................. 11
2.2 Justification ................................................................................................. 11
2.2.1 Benefits of the Proposal ................................................................................ 11
2.2.2 Optimisation of the proposal .......................................................................... 13
2.2.3 Options and alternatives considered ............................................................. 13
2.2.3.1 Proposed scenario ........................................................................................ 13
2.2.3.2 Alternative power station option .................................................................... 14
2.2.3.3 Alternative locations and technologies .......................................................... 14
2.2.3.4 No development option ................................................................................. 14
2.3 Proposal description .................................................................................. 15
2.4 Local and Regional context ........................................................................ 16
2.4.1 Climate .......................................................................................................... 16
2.4.2 Physical environment .................................................................................... 17
2.4.3 Bioregions ..................................................................................................... 18
2.4.4 Land system.................................................................................................. 18
2.4.5 Hydrology ...................................................................................................... 19
2.4.6 Hydrogeology ................................................................................................ 19
2.4.7 Flora and vegetation ..................................................................................... 19
2.4.8 Conservation reserves .................................................................................. 20
2.4.9 RAMSAR wetlands ........................................................................................ 20
2.4.10 Other developments ...................................................................................... 20
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 4 of 49
3. STAKEHOLDER ENGAGEMENT .............................................................................. 20
3.1 Key stakeholders ........................................................................................ 21
3.2 Stakeholder engagement process ............................................................. 21
3.3 Stakeholder consultation ........................................................................... 21
4. ENVIRONMENTAL PRINCIPLES AND FACTORS .................................................... 23
4.1 Principles ..................................................................................................... 23
4.2 Greenhouse gas .......................................................................................... 25
4.2.1 EPA objective ................................................................................................ 25
4.2.2 Policy and Guidance ..................................................................................... 25
4.2.3 Receiving environment .................................................................................. 26
4.2.3.1 Surveys and studies ...................................................................................... 26
4.2.4 Assessment of impacts ................................................................................. 27
4.2.4.1 Gaseous emissions to air .............................................................................. 27
4.2.4.2 Greenhouse gas emissions in a broader context ........................................... 28
4.2.4.3 Cumulative impacts ....................................................................................... 29
4.2.5 Mitigation ...................................................................................................... 29
4.2.6 Predicted outcome ........................................................................................ 30
5. OTHER ENVIRONMENTAL FACTORS OR MATTERS ............................................. 30
5.1 Air quality .................................................................................................... 31
5.1.1 EPA objective ................................................................................................ 31
5.1.2 Policy and guidance ...................................................................................... 31
5.1.3 Receiving environment .................................................................................. 31
5.1.4 Assessment of impacts ................................................................................. 32
5.1.5 Mitigation ...................................................................................................... 33
5.1.6 Predicted outcome ........................................................................................ 33
6. OFFSETS ................................................................................................................... 33
6.1 Biodiversity offsets ..................................................................................... 33
6.2 Carbon offsets ............................................................................................. 34
7. MATTERS OF NATIONAL ENVIRONMENTAL SIGNIFICANCE ............................... 34
8. HOLISTIC IMPACT ASSESSMENT ........................................................................... 35
8.1 EPA Objectives ........................................................................................... 39
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 5 of 49
List of Tables
Table 1: Decision making authorities .......................................................................... 10
Table 2: State and local government approvals required for the Proposal................... 10
Table 3: Summary of the Proposal .............................................................................. 15
Table 4: Summary of the Proposal .............................................................................. 15
Table 5: Stakeholder consultation ............................................................................... 22
Table 6: EP Act Principles .......................................................................................... 23
Table 7: Modelled emissions and emission reductions from the Proposal and associated infrastructure ............................................................................... 27
Table 8: Calculated emissions from the PEG power station ........................................ 28
Table 9: Calculated emissions from the power station approved under MS993 .......... 29
Table 10: Reduction in generation and emissions through construction and operation of the PEG1 ....................................................................................................... 29
Table 11: Application of the mitigation hierarchy through the Proposal ......................... 30
Table 12. Maximum emission mass flow rates (per engine stack) ................................. 32
Table 13: Holistic Impact Assessment .......................................................................... 36
List of Figures
Figure 1: Pilbara Energy Connect Program .................................................................... 8
Figure 2: Likely generation scenario, when combined with solar generation and a battery system ............................................................................................... 13
Figure 3: Monthly averages for rainfall, evaporation and temperature, Wittenoom 1949-2019 .............................................................................................................. 17
Figure 4: 9am and 3pm average wind roses ................................................................ 17
Figure 5: Regional and local context ............................................................................ 43
Figure 6: Location ........................................................................................................ 44
Figure 7: Proposed site layout ...................................................................................... 45
Figure 8: Vegetation and flora receiving environment................................................... 46
Figure 9: Air quality receiving environment ................................................................... 47
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 6 of 49
LIST OF APPENDICES
Appendix 1: Greenhouse Gas Management Plan
Appendix 2: Air Emissions Impact Assessment
GLOSSARY
Abbreviation Definition CO Carbon Monoxide
CO2, CO2-e Carbon dioxide and carbon dioxide equivalent (emissions of other greenhouse gases are multiplied by their GWP so that their effects can be compared to equivalent emissions of carbon dioxide)
t Tonnes
GHG Greenhouse Gas
GJ Gigajoules
IPCC Intergovernmental Panel on Climate Change
kilotonne One Thousand Tonnes
m3 Cubic Metre
mbgl Metres Below Ground Level
MW, MWh Megawatt and Megawatt Hour
NGER, NGERS National Greenhouse and Energy Reporting System
PM Particulate Matter
PM10 and PM2.5 PM10 is particulate matter 10 micrometers or less in diameter, PM2.5 is particulate matter 2.5 micrometers or less in diameter.
NOx, NO2 Oxides of Nitrogen, Nitrogen Dioxide
PV Photovoltaic
SOx, SO2 Oxides of Sulphur, Sulphur Dioxide
SF6 Sulphur Hexafluoride
tCO2-e Tonnes of Carbon Dioxide equivalent
μg Microgram
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 7 of 49
1. INTRODUCTION
Pilbara Energy Generation Pty Ltd (PEG), a wholly-owned subsidiary company of Fortescue
Metals Group Ltd (Fortescue), proposes to develop a strategic Pilbara Energy Connect Program
which consists of a number of discrete projects including transmission infrastructure, gas fired
power generation and renewable energy generation such has solar and aeolian components
across several locations in the Pilbara Region of Western Australia (Figure 1). All of which can
exist independently of one another. This Project involves the development of the PEG power
station which is the subject of this referral (the Proposal). The energy generated by the power
station will be used to provide power to a range of Fortescue and Fortescue Joint Venture
Projects.
The new power generation facility (PEG power station), will be located on miscellaneous licence
L47/901, adjacent to the existing, Fortescue owned and operated, Solomon power station at the
Solomon Iron Ore Mine. The Proposal will involve the construction of 14 gas-fired reciprocating
engines with a combined maximum installed capacity of 165 MW (megawatt). It is expected that
the annual average throughput of the facility will be approximately 150 MW.
This supplementary report has been prepared in accordance with the Environmental Review
Document template.
1.1 Purpose and Scope
This document provides the supporting information for formal referral of the Proposal to the
Environmental Protection Authority (EPA) under Section 38 of the Environmental Protection Act
1986 (the EP Act). It has been prepared in accordance with Part IV Division 1 of the EP Act and
the Environmental Impact Assessment (Part IV Divisions 1 and 2) Administrative Procedures
2016.
This document presents the environmental factors relevant to the Proposal, details of completed
and ongoing investigations to assess potential environmental impacts and the management
proposed to achieve acceptable environmental outcomes.
The scope of this referral is limited to the development and operation of the PEG power station
that will be located adjacent the existing Solomon power station. The PEG power station will be
constructed with an installed capacity of 165MW, to produce on average 150 MW of power.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 8 of 49
Figure 1: Pilbara Energy Connect Program
1.2 Proponent
Pilbara Energy (Generation), PEG, is a wholly-owned subsidiary of Fortescue.
1.2.1 Company details
Pilbara Energy (Generation) Pty Ltd (PEG)
ACN: 630 303 305
1.2.2 Proponent representative
Brett McGuire
Group Manager Environment
Level 2, 87 Adelaide Terrace
East Perth WA 6004
08 6218 8671
1.2.3 Referral contact
Sean McGunnigle
Manager Environmental Approvals
Level 2, 87 Adelaide Terrace
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 9 of 49
East Perth WA 6004
+61 438 958 771
1.3 Environmental Impact Assessment Process
There are no existing environmental approvals in place for the Proposal, however there are
several existing Fortescue environmental approvals that interact with this proposal. The
proposed power station is within the Solomon Iron Ore Mine footprint (MS1062).
The Proposal includes the development and operation of a new power station that is expected
to result in maximum annual greenhouse gas emissions of 609,696 tCO2-e and therefore will be
referred under Part IV of the EP Act to allow the EPA to determine whether the Proposal
requires formal assessment.
Although this Proposal will generate annual greenhouse gas emissions in excess of 100,000
tCO2-e, it does negate the need to construct a 221MW power station at North Star (approved
under MS993) and therefore results in a net reduction of greenhouse gas emissions of
approximately 568,727 tCO2-e/annum.
PEG consider that the likely environmental effects of this Proposal are not so significant to
warrant a formal assessment under Part IV. The predicted outcome of the impacts on
greenhouse gas results in a net environmental benefit (and less emissions) compared to the
construction and operation of a power station approved under MS 993. PEG is of the view that
the proposal can be assessed and regulated under Part V of the EP Act. Greenhouse Gas
emissions will be managed with the implementation of a site-specific Greenhouse Gas
management plan.
A self-assessment was undertaken by PEG of the significance of the impacts of the proposal in
reference to the DoEE Matters of Environmental Significance: Significant Impact Guidelines
(2013) and determined that the proposal will not have a significant impact on any matter of
National Environmental Significance (NES). Further detail is provided in Section 7.
The Proposal is not being referred under the Environment Protection and Biodiversity
Conservation Act 1999 (Commonwealth) (EPBC Act) or be subject to a State Agreement Act.
1.4 Other Approvals and Regulation
1.4.1 Land Tenure
The power station development envelope is located on L47/901 (live) for the purpose of a
‘power generation and transmission facility’.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 10 of 49
Pastoral land affected by the Proposal includes Mt Florance Pastoral Station.
No File Notation Areas occur within the proposed PEG power station Development Envelope.
The nearest conservation reserve is Karijini National Park, located approximately 8 km south of
the proposed power station. There is relatively complex topography, including higher elevations
between the PEG power station and Karijini (Kendrick, 2002, cited in Appendix 2, page 38).
1.4.2 Decision-making authorities
The authorities listed in Table 1 have been identified as decision-making authorities (DMAs) for
the Proposal.
Table 1: Decision making authorities
Decision making authority Relevant legislation
Minister for Environment Biodiversity Conservation Act 2016 – Taking of flora and fauna
Environmental Protection Act 1986 – Section 38
Minister for Mines and Petroleum Mining Act 1978
• Programmes of Work
• Mining Proposals
Director General, Department of Water and Environmental Regulation
Environmental Protection Act 1986
• Part V Works Approval Licence
Environmental Protection (Clearing of Native Vegetation Regulations 2004)
• Clearing Permit
1.4.3 Other approvals required
The Proposal will require other state and local Government approvals (Table 2).
Table 2: State and local government approvals required for the Proposal
Proposal Activities Land Tenure/Access Type of Approval Legislation Regulating Activity
Construction and operation of infrastructure
Miscellaneous Licence Works Approval/Licence Environmental Protection Act 1986
Part V
Mining Proposal Mining Act 1978
The Proposal will require approval under the provisions of the Mining Act 1978 (Mining Act), as
the Proposal will be developed within Mining Act tenure. PEG will prepare and submit a Mining
Proposal in accordance with the Statutory Guideline for Mining Proposals in Western Australia,
March 2020 (Government of Western Australia 2020).
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 11 of 49
Licensing of the construction and operation of the PEG power station is required under Part V of
the EP Act, in the form of a works approval. Air emissions modelling has been completed given
the proposed size of the power station.
2. THE PROPOSAL
2.1 Background
The Solomon Iron Ore Project was assessed at the level of Public Environmental Review. The
Environmental Protection Authority (EPA) reported in November 2016 and Solomon was
approved on 3 October 2017 under Ministerial Statement 1062 (MS 1062). The PEG power
station will be constructed within an area previously cleared as part of the Solomon mining
operation activities.
The existing North Star Magnetite development was assessed at the level of Public
Environmental Review (PER). The Environmental Protection Authority (EPA) reported in June
2014 and North Star was approved on 5 January 2015 under Ministerial Statement 993 (MS
993). North Star (as amended) includes power being supplied to the mine area via an onsite
221 MW gas fired power station. To supply gas to the power station, the PER included the
construction of gas lateral from the existing Epic pipeline.
2.2 Justification
In January 2020, Fortescue announced the US$450 million Pilbara Generation Project, the next
stage of the Pilbara Energy Connect program. The Pilbara Generation Project complements the
US$250 million Pilbara Transmission Project announced in October 2019 and referred to the
EPA in November 2018. The project will provide low cost power to the energy efficient Iron
Bridge Magnetite Project. The Pilbara Generation Project includes 165MW of gas fired
generation, together with 150MW of solar photovoltaic (PV) generation (Lambda Junction solar
farm and North Star Junction solar farm) which will be supplemented by large scale battery
storage. All elements of the project; power station, PV generation and battery system can exist
independently of one another. This referral relates to the construction and operation of the
165MW gas fired power station (PEG power station - the Proposal) component of the Pilbara
Generation Project.
2.2.1 Benefits of the Proposal
The key benefit of this Proposal is a net reduction in greenhouse gas emissions when
compared to the previously approved 221 MW North Star power station, and negating the
requirement to build the North Star facility.
The net reduction in greenhouse gas emissions, when compared to the power station at North
Star approved under MS 993 (North Star power station) is achieved by:
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 12 of 49
• The procurement of extremely efficient engines (with a conservatively calculated
heat rate of ~9 GJ/MWh) to minimise greenhouse gas emissions and greenhouse
gas emission intensity. The 14 x 12MW Gas Reciprocating Engines proposed for
the PEG power station have been chosen for their advanced technology, are
highly efficient with very low emissions and heat rates. To compare the ~9
GJ/MWh efficiency from units to be procured for the PEG power station, the
Solomon power station as a whole achieves a heat rate of ~12 GJ/MWh A lower
heat rate results in an improved emission intensity, and in this case, results in a
25% reduction in greenhouse gas emissions per MWh.
• Reduction in the capacity of the power station due, in part to, future
supplementation with renewable energy from two proposed tracking photovoltaic
(PV) solar farms (outside of the scope of this Proposal but with an additional
combined capacity of 150 MW).
• An optimised dispatch strategy which involves units running at high loads (close to
optimal efficiency), units are added or subtracted from dispatch as power
requirements change (rather that running units at lower less efficient loads).
• A contemporary Power Management System (PMS), which uses complex
algorithms and seamlessly monitors, interacts, controls and provides for the most
efficient use of the entire generation network, meaning minimised fuel combustion.
While these engines have efficiency comparable to modern combined cycle power stations,
they use a fraction of the water that a gas turbine fitted with a heat recovery steam generator
would consume, these 14 engines combined are expected to use 7 kilolitres of water a week
under a worst-case scenario. For comparison water demand at the 122MW Solomon power
station is around 1300 to 1800 kilolitres per week (units fitted with heat recovery steam
generators would use even more). Circuit breakers, which are essential infrastructure for
electricity network, have been selected specially to avoid models filled with Sulphur
Hexafluoride (SF6), which is an extremely potent greenhouse gas. The 20, 100 and 500 year
global warming potentials for SF6 are considered to be 18,000, 23,800 and 31,300 times that of
CO2 respectively (Kovács et al. 2016).
In addition to the reduction and minimisation of greenhouse gases, the construction of the PEG
power station will also see a reduction in the gross emission and emission intensity of key
pollutants such as oxides of nitrogen (NOx), oxides of sulphur (SOx), carbon monoxide (CO) and
particulate matter (PM).
Another key benefit of this proposed location, when compared to the construction of a power
station at North Star, is that much of the infrastructure from the existing Solomon operations can
be utilised for the PEG power station. The proposed siting of the PEG power station has been
disturbed by previous activities, so further disturbance is not required. The construction of a gas
pipeline to the North Star site is also avoided by this Proposal, as there is no gas pipeline
currently existing to service this site.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 13 of 49
2.2.2 Optimisation of the proposal
Further emission reduction, of both greenhouse gas, and key pollutants (oxides of nitrogen,
oxides of sulphur, carbon monoxide and particulate matter) will be realised with the integration
of proposed additions such as:
• The construction of a 60MW battery system to provide spinning reserve services.
The battery system will remove the need to dispatch fossil fuel generation to
provide these services. Which in the case of this network would mean the dispatch
of one of the Solomon power station 40MW gas turbines.
• The future construction of a transmission line linking Eliwana mine to the PEG
power station allowing the displacement of approved 20MW of diesel fired
generation at the Eliwana mine approved under MS1109 (Fortescue, 2018).
• The proposed construction of the two tracking PV solar farms, North Star Junction
and Lambda Junction, are expected to achieve high levels of penetration in
daylight hours (see Figure 2), and at peak solar generation (150MW) displace all
but 80MW of the PEG generation (compared to the 150MW of generation
expected overnight), and all generation from the Solomon power station.
Figure 2: Likely generation scenario, when combined with solar generation and a battery system
2.2.3 Options and alternatives considered
2.2.3.1 Proposed scenario
The location of this option is preferred as there is gas supply, previously cleared land and much
of the infrastructure required to support power generation and transmission are already in place.
PEG hold the view that due to the lack of disturbance, lower emissions (609,696 tCO2-e per
annum) and reduced emission intensity (0.464 tCO2-e/MWh) of the PEG power station (even
before solar and battery integration) that the PEG power station compares very favourably with
the alternative development option (construction of the North Star power station). This option
would ensure that development and operation of North Star approved under MS 993 (without
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 14 of 49
the development of the 221 MW power station) is able to proceed, with reliable and secure
energy supply, while also minimising environmental impact as far as practicable.
2.2.3.2 Alternative power station option
In the most likely alternative power supply scenario, the construction of the power station at
North Star approved under MS 993 would take place.
This power station would be larger in capacity and would have higher overall emissions
(1,196,423 tCO2-e per annum) and emission intensity (0.618 tCO2-e/MWh) of Greenhouse
Gases). Total emissions and emission intensity of pollutants such as NOx SOx, CO and PM
would also be proportionally higher due to the combustion of additional fuel.
The calculations for this scenario were based on the procurement of GE LM6000 gas turbines in
combination with Solar Titan Turbines, similar to that at Solomon power station. LM6000 gas
turbines offer high reliability, fast dispatch, dry low emission technology and best cost per
megawatt in their power class while occupying a small footprint (Baker Hughes, 2020) and fit
the specifications that were outlined (~40MW gas turbines) in the original North Star PER
(Fortescue, 2013), with auxiliary support from Solar Titans when increased from 120MW to
221MW. Two LM6000s and four Solar Titans are installed at Solomon power station, and data
from these units including heat rates was used in the calculation of emissions
This option would also necessitate the construction of an additional gas pipeline to the North
Star mine, which would involve fugitive emissions during normal operations as well as additional
clearing for both the power station and pipeline.
2.2.3.3 Alternative locations and technologies
Alternative locations were considered for siting the PEG power station, including within the area
approved for North Star under MS 993, however this would have required clearing, and the
construction of a new gas pipeline. The proposed location adjacent to the Solomon power
station makes use of previously cleared land and existing infrastructure (including the existing
Fortescue River gas pipeline).
Alternative technologies such as gas turbines were considered for the Proposal. These were
less efficient, and more greenhouse gas intensive. Integration of additional technologies,
including energy storage and renewable energy have been considered and will be investigated
throughout the life of the Proposal.
2.2.3.4 No development option
In a no-development scenario, there would be no potential environmental impacts. The no
development scenario would mean a halt to the further development of North Star approved
under MS 993, as it would be unable to proceed without an electrical power supply, this would
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 15 of 49
also mean that the Eliwana Project would be powered by an on-site power station, and would
be fired on diesel for the life of mine.
However, there would also be a loss of social and economic benefit at a local, regional and
state level, such as:
• New infrastructure for the Pilbara, including power transmission.
• A lack of employment and training opportunities for remote and isolated communities.
• The halt of development of the expansion to the existing North Star Project, which will
prevent the opportunity for the further optimisation and improved return on investment.
2.3 Proposal description
The Proposal consists of the construction and operation of the PEG power station that will be
located adjacent to the existing Solomon power station. The PEG power station will be
constructed with an installed capacity of 165MW, to produce on average 150 MW of power. The
Key Proposal Characteristics are presented in Tables 3 and 4.
Table 3: Summary of the Proposal
Proposal Title Pilbara Energy Generation Power Station
Proponent Name Pilbara Energy (Generation) Pty Ltd
Short Description The Proposal is for the construction and operation of a gas-fired power station, in the Pilbara bioregion of Western Australia. The Proposal will supply up to 150MW of power to the North Star mining operations and the Pilbara Transmission Project.
Table 4: Summary of the Proposal
Element Location Proposed Extent
Physical Elements
Clearing of native vegetation
N/A No additional clearing is required for the development of the PEG power station.
Operational Elements
Power generation Figure 5 & 6 Gas-fired reciprocating engines with an installed capacity of 165MW
Key infrastructure Figure 7 • 14 x gas reciprocating engines with installed
capacity of 165 MW
• 14 x exhaust stacks, approximately 18 m in height.
Supporting infrastructure Figure 7 • 50 KL self-bunded Oil Storage Tank
• 10 KL self-bunded Service Oil Tank
• 40 KL self-bunded Waste Oil Tank
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 16 of 49
Element Location Proposed Extent
• transformers (including approximately 1.5 KL of
insulating oil, self-bunded)
• black start diesel generator (1 KL diesel, self-
bunded)
• closed circuit external engine radiator cooling
systems
• oily water collection sumps and treatment plant
with holding tanks
• site storm water drainage
• site access roads.
2.4 Local and Regional context
The Solomon Iron Ore Project – Sustaining Production Public Environmental Review (PER)
(Fortescue, 2015) provided an extensive overview of the physical, biological and social
environment associated with the Solomon Project area, including the proposed location of the
PEG power station.
The Proposal is located within the Pilbara region of Western Australia, within the Shire of
Ashburton local Government areas.
2.4.1 Climate
Climatic conditions in the Pilbara region are arid to tropical, characterised by hot, wet summers
(October to April) and mild winters (May to September). Rainfall is generally low throughout the
year and is at its greatest in summer and autumn when storms and off-shore cyclonic activity
generate rainfall events (BoM, 2020, Van Vreeswyk et. al., 2004).
The closest operational Bureau of Meteorology weather station was established in 1949 in
Wittenoom, approximately 50 km to the east of the Proposal area. The mean annual rainfall at
Wittenoom is 461.8 mm with the majority of rainfall occurring between December and March
(BoM, 2020). Average minimum temperatures range from 11.6°C in July to 26.0°C in January.
Average maximum temperature varies between 24.3°C in July to 39.8°C in December (BoM,
2020). Between mid-December and April, the Pilbara region is susceptible to tropical cyclones,
which are capable of producing damaging winds, heavy rainfall, and flooding in inland areas.
Figure 3 shows the monthly averages for rainfall, evaporation and temperature, and Figure 4
shows the annual average wind roses for 9am and 3pm at Wittenoom.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 17 of 49
Figure 3: Monthly averages for rainfall, evaporation and temperature, Wittenoom 1949-2019
Figure 4: 9am and 3pm average wind roses
2.4.2 Physical environment
The geological stratigraphy in the Pilbara region is relatively continuous. Similar geological
processes have occurred throughout the region resulting in the enrichment of iron deposits.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 18 of 49
The Fortescue province lies over the Pilbara craton. The Hamersley Range was formed on the
late Archaean-Palaeoproterozoic metamorphosed banded iron formation, shales, dolerite,
carbonate, chert and rhyolite of the south Pilbara sub-basin. These rocks belong to the
Hamersley group and make-up part of the Ophthalmia fold belt. Tille (2006) described the
Hamersley plateau as hills and dissected plateau (with some stony plains and hardpan wash
plains) on sedimentary and volcanic rocks of the Hamersley basin. Much of the area is covered
with stony soils with shallow red loams and some red-brown non-cracking clays and red loamy
earths.
Acid drainage risk for soils within the Solomon Mine area is very low. As a result, investigations
have been focused on determining the risk of neutral metal drainage with extensive short- and
long-term leach testing of subsurface material. There has been no indication that any
metalliferous drainage has or is likely to occur from material in this area. Kinetic leach testing
also indicates that metalliferous drainage is unlikely to evolve over time.
2.4.3 Bioregions
The Proposal area is located in the Pilbara biogeographic region of the Interim Biogeographic
Regionalisation for Australia (IBRA) (Thackway & Cresswell, 1995) and within the Fortescue
Plains subregion near the boundary of the Hamersley subregion.
Kendrick (2002) described the Fortescue Plains subregion as “Alluvial plains and river frontage.
Extensive salt marsh, mulga-bunch grass, and short grass communities on alluvial plains in the
east. Deeply incised gorge systems in the western (lower) part of the drainage. River gum
woodlands fringe the drainage lines. Northern limit of Mulga (Acacia aneura). An extensive
calcrete aquifer (originating within a palaeo-drainage valley) feeds numerous permanent springs
in the central Fortescue, supporting large permanent wetlands with extensive stands of river
gum and cadjeput Melaleuca woodlands. Climatic conditions are semi desert tropical, with
average rainfall of 300 mm, falling mainly in summer cyclonic events. Drainage occurs to the
north-west.”
2.4.4 Land system
The Commonwealth Department of Agriculture and Water Resources, as part of the rangeland
resource surveys, has comprehensively described and mapped the biophysical resources of the
Pilbara region (Van Vreeswyk et al., 2004). As part of this process an inventory of land system
units, the Pilbara Regional Inventory (PRI) was established based on landform, soil, vegetation,
drainage characteristics and condition.
The PEG power station is situated within Boolgeeda land system, which is described as “stony
lower slopes and plains below hill systems supporting hard and soft spinifex grasslands and
mulga shrublands”.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 19 of 49
2.4.5 Hydrology
The Proposal area lies in the Lower Fortescue River Watershed. The system has an intermittent
flow pattern resulting in rivers and creeks being dry for most of the year. Following significant
rainfall, channels in the region carry large volumes of water with peak flows usually occurring
within 24 hours of the rainfall event (MWH, 2010).
Three streams traverse operational areas of the Solomon Mine: Zalamea (South East Flow),
Kangeenarina (Central Flow) and Queens (West Flow). The eastern boundary of the Solomon
operation is formed by Weelumurra Creek (MWH, 2010). The PEG power station lies within the
subcatchment of an unnamed tributary to the Lower Fortescue River, to the north of the
Zalamea Creek Subcatchment.
2.4.6 Hydrogeology
The primary aquifer within the Solomon mine area is associated with secondary permeability
within the ochreous goethite lower Channel Iron Deposit (CID) unit. The enhanced permeability
is thought to be derived from interconnected vugs and cavities within the highly
altered/weathered lower CID.
Water quality is classified as fresh to marginal, with Total Dissolved Solids (TDS) ranging from
200 mg/L to 1,000 mg/L. Individual bore yields are variable, ranging from 50 L/s to 2,500 L/s
reflecting the interfingering relationship between the alluvium and colluvium. Groundwater flow
is a subdued reflection of topography, flowing from areas of high elevation to low elevation. The
water table is generally between 10 and 30 mbgl.
2.4.7 Flora and vegetation
Broad scale vegetation mapping of the Pilbara region has been completed by Beard (1975).
The Solomon Project is located within the Fortescue Botanical District of the Eremaean
Botanical Province (Beard, 1975). The vegetation of this province is typically open, and
frequently dominated by spinifex, acacias and occasional Eucalypts. The Solomon mine lies
predominantly within the Hamersley subregion, which is described as Mulga low woodland over
bunch grasses in valley floors and Eucalyptus leucophloia over Triodia on the ranges (Ecologia
Environment, 2014). The Solomon mine has been the subject of extensive biological survey
work, including flora and vegetation assessments covering the Proposed PEG power station
area in 2008, 2010, 2011 and most recently in 2014. Vegetation communities surrounding the
PEG power station are shown in Figure 8 and include:
• EllHcTw4: Eucalyptus leucophloia subsp. leucophloia low sparse woodland over
Hakea chordophylla tall sparse shrubland over Senna glutinosa subsp. glutinosa
mid sparse shrubland over Triodia wiseana closed hummock grassland.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 20 of 49
• EllAiTw: Eucalyptus leucophloia subsp. leucophloia and Corymbia hamersleyana
low sparse woodland over Acacia inaequilatera tall sparse shrubland over Acacia
bivenosa and Senna glutinosa subsp. glutinosa mid sparse shrubland over Ptilotus
calostachyus low sparse shrubland.
2.4.8 Conservation reserves
Karijini National Park is located 8.3 km south of the Proposal. Karijini covers an area of 627,422
ha just north of the Tropic of Capricorn in the Hamersley Ranges. Karijini remains in relatively
undisturbed condition and has only been lightly grazed, although there is evidence of
exploration and mining activity at a number of locations.
The primary feature of the National Park is the deep, steep-sided gorges that are the focus of
the tourist activity during the cooler months of the year. Karijini is managed by the Department
of Biodiversity, Conservation and Attractions (DBCA) and is vested in the Conservation
Commission.
2.4.9 RAMSAR wetlands
The nearest Ramsar wetland is the Eighty Mile Beach Ramsar site consisting of Eighty Mile
Beach from Cape Keraudren to Cape Missiessy and Mandora Salt Marsh located 40 km to the
east (Commonwealth of Australia, 2014).
The PEG power station is located approximately 310 km south west of the Eighty Mile Beach
Ramsar site at the closest point.
2.4.10 Other developments
A number of existing iron ore mining operations are located in close proximity to the Proposal.
These include the following mines, located within ~ 50 km of the Proposal.
• Solomon Hub (Fortescue)
• Brockman 2 Nammuldi (Rio Tinto)
• Silvergrass (Rio Tinto)
• Western Turner Syncline (Rio Tinto)
3. STAKEHOLDER ENGAGEMENT
Extensive stakeholder consultation has been undertaken for the Solomon Iron Ore Project –
Sustaining Production proposal approved under Part IV of the EP Act pursuant to MS 1062.
While the proposed PEG power station does not fall within the scope of the Solomon Iron Ore
Mine, the stakeholder relationships are well established.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 21 of 49
3.1 Key stakeholders
Key stakeholders relevant to the PEG power station include the following:
• Environmental Protection Authority (EPA)
• Department of Water and Environmental Regulation (DWER); including EPA
Services, Water and Regulation branches
• Department of Mines, Industry Regulation and Safety (DMIRS)
• Department of Jobs, Tourism, Science and Innovation (DJTSI)
• Department of Planning, Lands and Heritage (DPLH)
• Shire of Ashburton
• Mt Florance Pastoral Station
• Yindjibarndi People
3.2 Stakeholder engagement process
Stakeholder consultation for the Proposal has formed part of the broader stakeholder
engagement strategy for Fortescue projects undergoing environmental approvals. The
overarching objectives of the strategy are:
• To inform stakeholders about the Proposal and its impacts to the environment and
to describe the outcomes of consultation on Proposal design
• To establish relationships with key stakeholders that enable ongoing dialogue
through implementation and regulation of the Proposal.
A summary of the stakeholder engagement and consultation undertaken to date with specific
relevance to the PEG power station is provided in Section 3.3. In accordance with Fortescue’s
Stakeholder Engagement Strategy, consultation with the key stakeholders listed above is
ongoing and will be undertaken on either a regular or ad-hoc basis, depending on the nature of
the relationship and the progression of the PEG power station Proposal.
3.3 Stakeholder consultation
Specific regulator consultation for the PEG power station has been undertaken with DWER
(regarding both Part IV and Part V regulation) and the Department of Mines, Industry Regulation
and Safety (DMIRS). The following stakeholders have also been consulted regarding the PEG
power station:
• Shire of Ashburton
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 22 of 49
• Mt Florance Pastoral Station
• Yindjibarndi People
Consultation undertaken is presented in Table 5.
Table 5: Stakeholder consultation
Stakeholder Date Issues/Topic Raised Proponent Response/Outcome
Yindjibarndi People + Brad Goode Associates
July 2011 Ethnographic Heritage Survey
No Heritage Sites recorded within L47/901
Yindjibarndi People + Alpha Archaeology
August 2011 and July 2012
Archaeological Heritage Survey
No Heritage Sites recorded within L47/901
Yindjibarndi People 13/11/2017 Native Title Determination N/A
Mt Florance Station 29/01/2019 PEC construction and operation of a power generation and transmission facility.
Access agreement signed for construction and operation of a power generation and transmission facility.
DMIRS 13/03/2019 Tenement application L47/901
Consultation process for tenement completed, granted 26/06/19
Shire of Ashburton 18/03/2019 Tenement application L47/901
Consultation process for tenement completed, granted 26/06/19
Mt Florance Station 18/03/2019 Tenement application L47/901
Consultation process for tenement completed, granted 26/06/19
Yindjibarndi People 05/04/2019 Notification of tenement application for L47/901
N/A
Yindjibarndi People 05/06/2019 No objections were received from the Yindjibarndi People for L47/901
Consultation process for tenement completed, granted 26/06/19
DMIRS 26/06/2019 Tenement approval (no objections received)
Consultation process for tenement completed, granted 26/06/19
DWER (EPA Services) 16/10/2019 Introduction to PEG Project – focus on PEG Solar Farms
PEG Solar Farms do not require Part IV referral
Mt Florance Station October 2019 Mt. Florance agreed to not lodge any objections to FMG / TPI tenure applications or mining related works within Mt. Florance to the South of the Solomon Railway.
General agreement that Fortescue can use areas south of the Solomon Railway Line for Mining purposes.
Mt Florance Station 19/10/2019 PEC tenures Deed of amendment agreed between PEC and Mt Florance.
DWER (EPA Services) 04/02/2020 Introduction to PEG Project – focus on PEG power station. Discussion
PEG to provide further information in letter
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 23 of 49
Stakeholder Date Issues/Topic Raised Proponent Response/Outcome
regarding approvals strategy and need for referral under Part IV
DWER (EPA Services) 13/02/2020 Correspondence to DWER following meeting on 04/02/2020, outlining case for non-referral
PEG to prepare s38 referral
Yindjibarndi People 12/03/2020 Discussion around impacts to cultural significance and emission numbers requested.
Fortescue confirmed no impact to cultural significance in the area, from construction or operation of Facility.
Fortescue supplied requested emission numbers.
DMIRS 19/03/2020 Pre-submission consultation
PEG to submit Mining Proposal application as discussed.
DWER (Part V) 19/03/2020 Pre-submission consultation
PEG to submit Works Approval application as discussed.
4. ENVIRONMENTAL PRINCIPLES AND FACTORS
This section identifies the environmental factors relevant to the Proposal and outlines the overall
assessment methodology presented in this document.
The environmental factors and objectives adopted by the EPA are listed in the Statement of
Environmental Principles, Factors and Objectives (SEP) (EPA, 2020a). The Proponent has
identified the following preliminary key environmental factors relevant to the Proposal:
• Greenhouse Gas
The Proponent considers the other environmental factors identified in the SEP are either not
relevant to the Proposal or are unlikely to result in a significant impact (refer section 5).
4.1 Principles
The Proponent’s consideration of the EP Act principles of environmental protection in relation to
the Proposal is detailed in Table 6.
Table 6: EP Act Principles
Principle Consideration
1. The precautionary principle
Where there are threats of serious or irreversible damage, lack of full scientific certainty should not be
The proponent will maintain an environmental management system (EMS) that addresses activities with a potential to affect the environment. A key element of the EMS includes assessing risk to identify
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 24 of 49
Principle Consideration
used as a reason for postponing measures to prevent environmental degradation.
In application of this precautionary principle, decisions should be guided by:
a) careful evaluation to avoid, where practicable, serious or irreversible damage to the environment; and
b) an assessment of the risk-weighted consequences of various options.
potential impacts early in the process to enable planning for avoidance and/or mitigation. PEG has conducted scientific studies to understand the Proposal area and the potential risks to the environment. The proposal has sought to avoid, minimise and mitigate environmental impacts. The environmental risks associated with the Proposal have been assessed.
2. The principle of intergenerational equity
The present generation should ensure that the health, diversity and productivity of the environment is maintained and enhanced for the benefit of future generations.
The Proposal meets the principle of intergenerational equity by ensuring the health of the environmental values, maintaining ecological functions for future generations, whilst minimising any impacts on the environment.
PEG has identified measures to avoid and minimise impacts to these factors, such as siting the Proposal on already cleared land, and minimising emissions and emission intensity as far as practicable.
3. Principles relating to improved valuation, pricing and incentive mechanisms
(1) Environmental factors should be included in the valuation of assets and services.
(2) The polluter pays principles – those who generate pollution and waste should bear the cost of containment, avoidance and abatement.
(3) The users of goods and services should pay prices based on the full life-cycle costs of providing goods and services, including the use of natural resources and assets and the ultimate disposal of any waste.
Environmental goals, having been established, should be pursued in the most cost-effective way, by establishing incentive structure, including market mechanisms, which enable those best placed to maximise benefits and/or minimise costs to develop their own solution and responses to environmental problems.
PEG acknowledges the need for improved valuation, pricing and incentive mechanisms and endeavours to pursue these principles when practicable. For example:
• environmental factors have played a role in determining infrastructure types, specifications and locations.
• the cost of rehabilitation and closure has been incorporated into the costs of the product from the commencement of operation.
• There is currently no CO2-e pricing mechanism in place in Australia, but other key fees will be calculated for other key pollution generated under the EP Act.
• Given the intensity of the new power station is estimated at 0.464 tCO2-e/MWh, the proponent will not be required to offset any emissions in excess of the Benchmark-Emissions Baseline of .583 tCO2-e/MWh.
• PEG proposes to implement a Greenhouse
Gas Management Plan during development of
the Proposal, this plan can be found in
Appendix 2.
• PEG will adhere to the requirements outlined
in the National Greenhouse and Energy
Reporting Act, 2007 (NGER Act).
4. The principle of the conservation of biological diversity and ecological integrity
Conservation of biological diversity and ecological integrity should be a fundamental consideration.
The conservation of biological diversity and ecological integrity was a fundamental consideration in the assessment of this proposal. Clearing has been avoided and infrastructure sited away from ecologically significant areas.
5. The principle of waste minimisation
All reasonable and practicable measures should be taken to minimise the generation of waste and its discharge into the environment.
The efficiency of the proposed engines and integration of a battery for spinning reserve purposes, avoids significant quantities of air emissions.
Closed cooling systems minimise the production of waste water and design of the system ensures minimal production generation of waste hydrocarbon.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 25 of 49
Principle Consideration
PEG’s approach to waste management, in order of priority is:
• avoid and reduce at source
• reuse and recycle
• treat and/or dispose.
4.2 Greenhouse gas
4.2.1 EPA objective
The environmental objective of the EPA’s Greenhouse Gas Emissions factor is: To reduce net
greenhouse gas emissions in order to minimise the risk of environmental harm associated with
climate change (EPA, 2020a).
4.2.2 Policy and Guidance
Instructions on how to prepare an Environmental Review Document (EPA, 2020c)
This guideline is relevant to all Environmental Factors and will only be discussed once in this
document. This EPA guideline provides a template for the structure of the Environmental
Review Document (ERD) and the minimum requirements for an ERD (including tables and
figures). It also provides guidance for preparing each section of the ERD and details the spatial
data requirements.
Statement of Environmental Principals, Factors and Objectives (EPA, 2020a)
This guideline is relevant to all Environmental Factors and will only be discussed once in this
document. This guideline communicates how the EPA undertake the following, during their
assessment process:
• considers the object and principles of the Environmental Protection Act, 1986
• uses environmental factors and objectives to organise and systemise
environmental impact assessment and reporting
• takes a holistic view of the environment and a proposal or scheme’s potential
impact on the environment
• considers significance when determining whether or not to assess a proposal or
scheme and recommend whether or not an assessed proposal or scheme may be
implemented
Environmental Factor Guideline - Greenhouse Gas Emissions (EPA 2020b)
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 26 of 49
This factor guideline communicates the environmental objective of the Greenhouse Gas
Emissions “to reduce net greenhouse gas emissions in order to minimise the risk of
environmental harm associated with climate change.” As well as communicating considerations
for EIA for Greenhouse Gas Emissions factor include, but are not necessarily limited to:
• application of the mitigation hierarchy to avoid, reduce and offset emissions
• the interim and long-term emissions reduction targets the proponent proposes to
achieve
• the adoption of best practice design, technology and management appropriate to
mitigate GHG emissions
• whether proposed mitigation is plausible, timely, achievable and is all that is
reasonable and practicable.
Technical Guidance - Mitigating Greenhouse Gas Emissions (EPA, 2019)
This document covers:
• Avoiding emissions through best practice design, benchmarking
• Continuous improvement to reduce emissions over the project life
• Offsets
• Reporting
National Greenhouse and Energy Reporting Act, 2007 (Commonwealth)
National framework for reporting and disseminating company information about greenhouse gas
emissions, energy production and energy consumption.
4.2.3 Receiving environment
The new power generation facility (PEG power station), will be located on L47/901, adjacent to
the existing, Fortescue owned and operated, Solomon power station at the Solomon Iron Ore
Mine. The location of the Proposal, in a local and regional context for greenhouse gas is shown
in Figures 4 and 5.
4.2.3.1 Surveys and studies
Greenhouse gas emissions contribute to a changing climate on a global scale. The effects of
the changing climate are predicted to be significant for Western Australia (EPA, 2020d).
Fortescue currently reports emissions in accordance with the requirements of NGER and NPI
for its operating sites. The reports are prepared internally, audited by an external party and
submitted to the relevant regulators. PEG will undertake the same reporting (NGER and NPI)
meeting the same high standards. Fortescue’s NGER reports can be found at the following
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 27 of 49
website http://www.cleanenergyregulator.gov.au/NGER/, PEG’s reports will be made available
on the same website when completed.
The maximum likely impact of this proposal in terms of greenhouse gas emissions will be
609,696 tCO2-e per annum. However, the net impact of this proposal will be that a greenhouse
gas reduction of 586,727 tCO2-e per annum is achieved, through a smaller and more efficient
power station (see Table 7 for details). additional emission intensity benefits are expected with
the integration of renewable generation and energy storage.
4.2.4 Assessment of impacts
4.2.4.1 Gaseous emissions to air
Annual greenhouse gas emissions from the PEG power station are estimated at 609,696 tCO2-
e. PEG hold the view that the Proposal will provide a net reduction in greenhouse gas
emissions to atmosphere compared to the construction and operation of the North Star power
station. Table 7 demonstrates how PEG replacing the North Star power station would reduce
total annual greenhouse gas emissions, and how future additions are calculated to provide
further reductions through displacement of fossil fuel combustion.
Table 7: Modelled emissions and emission reductions from the Proposal and associated infrastructure
Emission
Intensity
tCO2-e/MWh
Annual
Emissions
tCO2-e
Annual Reduction Compared to Approved scenario
tCO2-e
Modelled Annual benefits from PEG1
tCO2-e
Annual Net
benefit2
tCO2-e
North Star power station approved under MS 993
0.618 1,196,423 NA NA NA
Proposed PEG power station (gas only)
0.464 609,696 586,727 - -
Integration of Lambda and North Star Junction Solar Farms
- - - 64,627 185,075
Integration of 60MW Battery system for Spinning Reserve Services
- - - - 162,410
1This column illustrates modelled benefit to the PEG Gas fired emissions when PEG Gas fired generation is augmented by Solar
generation in a future scenario.
2Including other entities such as Solomon power station, but excluding reductions already counted in Annual Modelled reductions
from PEG
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 28 of 49
The calculations undertaken for Table 8 are based on likely scenarios, but are calculated in a
conservative way. Estimation techniques developed for NGER reporting were utilised where
applicable. Data collected at existing Fortescue operations was used to estimate the
greenhouse gas emissions where appropriate.
The already approved scenario was based on the procurement of GE LM6000 gas turbines in
combination with Solar Titan Turbines to construct a power station at North Star approved under
MS 993. Two LM6000s and four Solar Titan turbines are installed at Solomon power station,
and the specifications fit what was outlined, ~40MW gas turbines, in the original North Star PER
(Fortescue, 2013) with some of the difference between the original 120MW and the revised
221MW to be made up with Solar Titan units.
PEG has utilised data from the likely engine supplier. The PEG power station emissions were
calculated based on the highest likely dispatch of the power station, 150MW.
The net CO2-e benefit that the integration of a 60MW Battery system to provide Spinning
Reserve Services, is calculated on the assumption that one Solomon power station LM6000
would need to be continuously dispatched to provide this service. The minimum speed a
LM6000 unit could run at to provide this service would be 75%, so this figure (75%) was used in
the calculation.
4.2.4.2 Greenhouse gas emissions in a broader context
The Australian government publishes the National Greenhouse Gas Inventory as part of the
commitments made under the Kyoto Protocol. For the 2017 inventory year the Australian
greenhouse gas emissions were 530,840.90 kilotonnes (1,000 tonnes) of CO2-e within which
Western Australia’s contribution was 86,420.56 kilotonnes of CO2-e (Department of Industry,
Science, Energy and Resources, 2020). The annual maximum emission of greenhouse gases
estimated for the Proposal is 609.696 kilotonnes of CO2-e.
The estimated annual emissions are equivalent to 0.11% of the nation’s emissions and 0.7% of
Western Australia’s emissions. The GHG emission estimate results in an estimated emission
intensity of 0.464 tCO2-e per MWh (without integration of Solar generation or Energy Storage).
A summary of the estimated greenhouse gas emissions is provided in Table 8.
Table 8: Calculated emissions from the PEG power station
Source Quantity
Annual Power Generation (MWh) 1,314,000
Total Annual Greenhouse Gas Emission (tonnes of CO2-e) 609,696
Total Annual Greenhouse Gas Emission (kilotonnes of CO2-e) 609.696
Australia’s 2017 Greenhouse Gas inventory (kilotonnes) 530,840.90
% of Australia’s 2017 Greenhouse Gas inventory 0.115
Western Australia’s 2017 Greenhouse Gas inventory (kilotonnes of CO2-e) 86,420.56
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 29 of 49
% of Western Australia’s 2017 Greenhouse Gas inventory 0.705
Note: These calculations are before integration of a Battery System or Solar Generation.
However, the North Star power station would have had annual emissions estimated to be
equivalent to 0.225% of the nation’s emissions and 1.38% of Western Australia’s emissions.
The estimated GHG emission in the alternative scenario results in an estimate emission
intensity of 0.618 tCO2-e per MWh (without integration of Solar generation or Energy Storage),
these figures are detailed below in Table 9.
Table 9: Calculated emissions from the power station approved under MS993
Source Quantity
Annual Power Generation (MWh) 1,314,000
Total Annual Greenhouse Gas Emission (tonnes of CO2-e) 1,196,423
Total Annual Greenhouse Gas Emission (kilotonnes of CO2-e) 1196.423
Australia’s 2017 Greenhouse Gas inventory (kilotonnes) 530,840.90
% of Australia’s 2017 Greenhouse Gas inventory 0.225
Western Australia’s 2017 Greenhouse Gas inventory (kilotonnes of CO2-e) 86,420.56
% of Western Australia’s 2017 Greenhouse Gas inventory 1.384
4.2.4.3 Cumulative impacts
PEG does not consider the Proposal’s estimated greenhouse gas emissions to significantly
increase the contribution of Western Australia’s emissions to the national greenhouse gas
inventory. In fact, when compared to the North Star power station, would provide a reduction
equivalent to around 0.679% of Western Australia’s total emissions (without including Solar or
Battery integration reductions). This is displayed in Table 10.
Table 10: Reduction in generation and emissions through construction and operation of the PEG1
Source Quantity
Reduction in Annual Fossil Fuel Power Generation (MWh) 621,960
Reduction Total Annual Greenhouse Gas Emission (tonnes of CO2-e) 586,727
Total Annual Greenhouse Gas Emission (kilotonnes of CO2-e) 586.727
Australia’s 2017 Greenhouse Gas inventory (kilotonnes) 530,840.90
% of Australia’s 2017 Greenhouse Gas inventory 0.111
Western Australia’s 2017 Greenhouse Gas inventor (kilotonnes of CO2-e) 86,420.56
% of Western Australia’s 2017 Greenhouse Gas inventory 0.679
1Compared to the calculated emissions from the North Star power station, and without integration of Solar or Battery at PEG.
4.2.5 Mitigation
PEG has applied the mitigation hierarchy to the Proposal in relation to greenhouse gas
emissions. Mitigation measures are summarised in Table 11.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 30 of 49
Table 11: Application of the mitigation hierarchy through the Proposal
Category Mitigation
Avoidance The commencement of the Proposal avoids a calculated 586,727 tonnes of CO2-e emissions per annum compared to the operation of the power station approved under MS 993.
The Proposal avoids reliance on diesel fuel or the construction of an additional gas pipeline by siting at a location with an existing natural gas supply.
PEG has also avoided the procurement of Sulphur Hexafluoride (SF6) filled circuit breakers, because of the high warming potential that this gas has.
Future activities including the construction of Solar PV Generation and the integration of a battery system will each avoid significant quantities of greenhouse gas emissions.
Minimisation The proposal minimises the consumption of natural gas through the procurement of modern engines, innovative control system and through regular maintenance the engines and other infrastructure.
Management A greenhouse gas management plan will be adhered to by the proponent.
• PEG proposes to implement a Greenhouse Gas Management
Plan during development and implementation of the Proposal,
this plan can be found in Appendix 1.
• PEG will adhere to the requirements outlined in the National
Greenhouse and Energy Reporting Act, 2007 (NGER Act).
Research and modelling Modelling of emission reduction under different scenarios has been carried out for the operation of the PEG power station including with and without combinations of Solar Generation and a Battery System. All scenarios show significantly lower annual greenhouse gas emissions when compared to the operation of the North Star power station.
Offsets The Benchmark-Emissions Baseline will be supported by a Default Emissions Intensity for electricity generation (currently set at 0.583 tCO2-e/MWh, benchmarked by Australian Government to industry best-practice). GHG emissions from the PEG power station will be benchmarked against the Default Emissions Intensity. Given the intensity of the new power station is estimated at 0.464 tCO2-e/MWh, the proponent will not be required to offset any emissions in excess of the Benchmark-Emissions Baseline.
4.2.6 Predicted outcome
Under section 15 of the Environmental Protection Act 1986, the EPA has the objective to use its
best endeavours to protect the environment and to prevent, control and abate pollution and
environmental harm. PEG considers the Proposal is consistent with the EPA’s objective for the
Greenhouse Gas Emissions factor “to reduce net greenhouse gas emissions in order to
minimise the risk of environmental harm associated with climate change” (EPA, 2020) and that
the factor can be managed with the implementation of a site-specific Greenhouse Gas
management plan (Appendix 1), as the Proposal is considered to provide a net reduction in
greenhouse gas emissions compared to other development options (including those that are
already approved), and that modern technology and efficient engines are to be procured for the
Proposal. The estimated annual emissions are equivalent to 0.11% of the nation’s emissions
and 0.7% of Western Australia’s emissions.
5. OTHER ENVIRONMENTAL FACTORS OR MATTERS
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 31 of 49
5.1 Air quality
5.1.1 EPA objective
The environmental objective of the EPA’s Air Quality factor is: to maintain air quality and
minimise emissions so that environmental values are protected (EPA, 2020a).
5.1.2 Policy and guidance
The following policy and guidance is relevant to this factor:
• Statement of Environmental Principles, Factors and Objectives (EPA, 2020a)
• Environmental Factor Guideline: Air Quality (EPA, 2020d)
This guideline outlines how the EPA considers air quality in the environmental impact
assessment (EIA) process including:
• application of the mitigation hierarchy to avoid and minimise emissions, where
possible
• characterisation of potentially harmful emissions and the pathways by which they
may be released to air
• the application of technology appropriate to the potential environmental impacts
and risks
• the significance of the likely change to air quality as well as the environmental
values affected by those changes, in the context of existing and predicted
cumulative impacts
• whether proposed mitigation is technically and practically feasible
• whether siting of the proposal’s main emission sources takes into consideration
current and future sensitive land uses.
5.1.3 Receiving environment
An air quality assessment has been undertaken by SLR Consulting (2020; Appendix 2). This
assessment considered the air emissions resulting from the proposed 165 MW gas-fired PEG
power station in isolation, and cumulatively with the existing Solomon power station. Stack and
emission data for the proposed PEG power station engines were compiled based on the
supplier’s engine specifications data.
Ambient dust levels in the Pilbara region, are known to be elevated due to the semi-arid
landscape. Fugitive dust emissions from the Solomon Mine operations (and other mines in the
region) contributes to regional background particulate levels. The Fortescue ambient air quality
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 32 of 49
monitoring network was used to characterise the background particulate levels for PM10
between 2015 and 2019. The 2018 calendar year was used to derive a representative
background dataset. This annual average PM10 concentration during 2018 was above the
annual average ambient guideline value of 25 μg/m3 and included 30 days above the 24hr
average ambient guideline value of 50 μg/m3.
Dispersion modelling of NO2, SO2, PM10, PM2.5, CO and VOC (as formaldehyde, benzene,
toluene, ethylbenzene and xylene) emissions was performed using the CALPUFF dispersion
model. A 3-dimensional, 1-year meteorological data file was compiled using the WRF and
CALMET models for input in CALPUFF, incorporating observational data from the Fortescue
weather station located at Castle Camp. The modelling results showed that the maximum
ground level concentrations of NO2, SO2, CO and VOCs are all well below the relevant
assessment guideline values.
The nearest sensitive receptor to the PEG power station is Karijini National Park which is
located 8.3 km south of the proposal. There is relatively complex topography, including higher
elevations between the PEG power station and this receptor (Kendrick, 2002, cited in Appendix
2 page 38).
5.1.4 Assessment of impacts
Air emissions can affect both environmental receptors and human health if not managed
correctly. The main emissions from the PEG power station are emissions to air of nitrogen
oxide, carbon dioxide, sulphur dioxide and particulates (Table 12). These emissions have been
determined by the manufacturer and will be confirmed during commissioning.
Table 12. Maximum emission mass flow rates (per engine stack)
Emission Emission Rate (g/s)
75% Load 100% Load Start-up
NOx, Nitrogen oxides (Calculated as NO2) 1.5 2.0 4.0
CO, Carbon monoxide 4.4 5.8 11.6
SO2, Sulphur dioxide 0.17 0.22 0.44
PM, Particulate matter (as dry dust) 0.17 0.22 0.44
The emissions assessment indicates that emissions to air during commissioning and operations
will not exceed any applicable guideline values at receptor locations. Modelling indicates
pollutant concentrations will not exceed 25% of any relevant guidelines at receptors even under
worst case scenarios.
Construction activities associated with proposal that may cause dust emissions include:
• ground disturbance
• vehicle movement
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 33 of 49
The air emissions assessment indicates that particulate emissions from the proposed power
station will have a negligible impact on the annual average PM10 and PM2.5 in the region. The
assessment focussed on the potential incremental impacts of PM10 and PM2.5 emissions from
the PEG power station in the context of the existing background level due to the elevated
background concentrations in the region. This assessment found that the incremental annual
average particulate concentration predicted at the closest sensitive receptor to be less than
0.1µg/m3 in each of the modelled scenarios.
5.1.5 Mitigation
Fortescue has applied the mitigation hierarchy to the proposal in relation to air quality. Site
specific management measures include:
• Engineering design and procurements have considered energy efficiency,
greenhouse and other emissions in the selection of the reciprocating gas engine
technology to be used for the PEG power station
• The engines will be operated in line with manufacturer specifications to minimise
emissions.
• Restrict vehicle movements and speeds;
• Use water trucks for dust suppression on access tracks and high traffic areas.
5.1.6 Predicted outcome
PEG considers the Proposal is consistent with the EPA’s objective for the Air Quality factor to
maintain air quality and minimise emissions so that environmental values are protected (EPA,
2020a) and that the factor can be managed within the requirements of the EP Act and
regulations.
The results of the modelling found emissions to air during commissioning and operation of the
PEG power station “do not have potential for significant air quality impacts at the nearest
sensitive receptors and do not represent a constraint to the Project” from Particulate Matter,
Carbon Monoxide, Sulphur Dioxide or Oxides of Nitrogen. Modelling indicates pollutant
concentrations will not exceed 25% of any relevant guidelines at the closest sensitive receptor.
6. OFFSETS
Biodiversity and carbon offsets related to the Proposal are outlined below.
6.1 Biodiversity offsets
Environmental offsets are required in order to protect and conserve environmental and
biodiversity values for present and future generations. The WA Environmental Offsets Policy
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 34 of 49
(Government of Western Australia, 2011) and WA Environmental Offsets Guidelines
(Government of Western Australia, 2014) provide guidance on the approach needed to
determine biodiversity offset requirements for proposals. Application of these guidelines ensure
that consistent and accountable decisions are made under the Environmental Protection Act
1986.
The EPBC Act Environmental Offsets Policy (Department of Sustainability, Environment, Water,
Population and Communities, 2012) outlines the Commonwealth government’s approach to the
use of offsets under the EPBC Act. The Policy defines offsets as ‘measures that compensate
the residual adverse impacts of an action on the environment’.
The PEG power station will be constructed within in area that has been assessed and cleared
as part of the Solomon mining operation activities (MS 1062). No additional clearing of native
vegetation is required as part of this referral, as such no residual adverse impacts on the
environment from clearing and no further consideration has been given to biodiversity offsets.
6.2 Carbon offsets
The PEG power station will trigger the requirements of the National Greenhouse and Energy
Reporting (Safeguard Mechanism) Rule 2015 (Safeguard Mechanism) during the first year of
operation. The Safeguard Mechanism is triggered when a responsible emitter produces greater
than 100,000 tCO2-e during a financial year.
With forecast GHG emissions greater than 100,000 tCO2-e during a financial year, Fortescue
will apply for a Benchmark-Emissions Baseline under the Safeguard Mechanism based on the
following production variable, defined in Schedule 2 of the Safeguard Mechanism: Electricity
generation
The Benchmark-Emissions Baseline will be supported by a Default Emissions Intensity for
electricity generation (currently set at 0.583 tCO2-e/MWh, benchmarked by Australian
Government to industry best-practice). GHG emissions from the PEG power station will be
benchmarked against the Default Emissions Intensity. Given the intensity of the new power
station is estimated at 0.464 tCO2-e/MWh, the proponent will not be required to offset any
emissions in excess of the Benchmark-Emissions Baseline.
7. MATTERS OF NATIONAL ENVIRONMENTAL SIGNIFICANCE
The EPBC Act is administered by the DAWE and provides a legal framework for the protection
and management of nationally and internationally important flora, fauna, ecological communities
and heritage places, which are referred to as MNES. Specifically, the EPBC Act protects the
following MNES:
• World heritage places
• National heritage places
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 35 of 49
• Wetlands of international importance
• Listed threatened species and ecological communities
• Migratory species
• Commonwealth marine areas
• The Great Barrier Reef Marine Park
• Nuclear actions
• A water resource, in relation to coal seam gas development and large coal mining
development.
Pursuant to the EPBC Act, any proposed action that has or is likely to have a significant impact
on a MNES requires approval from the Commonwealth Minister for the Environment.
A self-assessment undertaken by Fortescue of the significance of the impacts of the PEG power
station in reference to the DoEE Matters of Environmental Significance: Significant Impact
Guidelines (2013) and determined that the PEG power station will not have a significant impact
on any matter of National Environmental Significance (NES).
8. HOLISTIC IMPACT ASSESSMENT
This referral provides an assessment of the potential environmental impacts associated with the
Proposal and the management strategies independently. In this section, Table 13 provides an
assessment that has been made regarding the themes of Land, Air, People, Water and Sea and
the interaction between the environmental factors.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 36 of 49
Table 13: Holistic Impact Assessment
Theme Environmental Factor
Impact Predicted outcomes Management and Mitigation EP Act Principles
Se
a
Benthic communities and habitat
Impacts not considered as the Proposal is not coastal.
N/A N/A N/A
Coastal processes Impacts not considered as the Proposal is not coastal.
N/A N/A N/A
Marine Environmental Quality
Impacts not considered as the Proposal is not coastal.
N/A N/A N/A
Marine Fauna Impacts not considered as the Proposal is not coastal.
N/A N/A N/A
La
nd
Flora and Vegetation No clearing of vegetation is required for this Proposal.
N/A N/A N/A
Landforms Physical landforms will not be altered as a result of this Proposal.
N/A N/A N/A
Subterranean Fauna The Proposal is not considered to have an impact on subterranean fauna because there will be no significant ground excavations associated with the development.
N/A N/A N/A
Terrestrial Environmental Quality
Localised disturbance within an already disturbed development envelope. No significant excavations associated with the Proposal.
Proposal designed to minimise risk of land and soil contamination with minor quantities of hydrocarbons stored on site and oily water collection, storage and treatment infrastructure installed and maintained.
N/A N/A N/A
Terrestrial Fauna No clearing of terrestrial fauna habitat is associated with this Proposal.
N/A N/A N/A
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 37 of 49
Theme Environmental Factor
Impact Predicted outcomes Management and Mitigation EP Act Principles
Wa
ter
Inland waters Surface and groundwater hydrological
processes will not be altered by this
Proposal. Operational water use will be
7,000L/week under maximum
scenarios which will be supplied from
the existing Solomon mine process
water allocation.
N/A N/A N/A
Air
Air Quality Emissions of oxides of nitrogen, oxides of sulphur, carbon monoxide and particulates. Maximum concentration emission rates during normal operation, per engine stack are estimated at:
• NOx: 2.0 g/s
• CO: 5.8 g/s
• SO2: 0.22 g/s
• PM: 0.22 g/s
PEG considers the Proposal is consistent with the EPA’s objective for the Air Quality factor and that the factor can be managed within the requirements of the EP Act and regulations.
The results of the modelling found emissions to air during commissioning and operation of the PEG power station “do not have potential for significant air quality impacts at the nearest sensitive receptors and do not represent a constraint to the Project” from Particulate Matter (PM) Carbon Monoxide (CO), Sulphur Dioxide (SO2) or Oxides of Nitrogen (NOx).
Incremental annual average particulate concentration predicted at the closest sensitive receptor to be less than 0.1µg/m3 in each of the modelled scenarios.
Concentrations of Particulate Matter (PM) Carbon Monoxide (CO), Sulphur Dioxide (SO2) or Oxides of Nitrogen (NOx) will not exceed 25% of the relevant guideline at the closest sensitive receptor.
Non- greenhouse gas emissions to air will be managed under part V of the EP act, as well as being reported through NPI.
1. The precautionary principle
Air emission impact assessment modelling has assumed worst case scenarios, and has considered worst case scenarios from Solomon power station in cumulative modelling.
2. The principle of intergenerational equity
Emissions to air are reduced due to lower emission intensity, higher efficiency, and smaller capacity of power station compared to the operation of the North Star power station.
3. Principles relating to improved valuation, pricing and incentive mechanisms
Emissions to air will be managed under part V of the EP act, annual fees will be calculated and paid where applicable.
4. The principle of the conservation of biological diversity and ecological integrity
Modelling has indicated no breach of guideline levels as sensitive receptors resulting from air emissions.
5. The principle of waste minimisation
Emissions to air are reduced due to lower emission intensity, higher efficiency, and smaller capacity of power station compared to the operation of the North Star power station.
Greenhouse Gas Emissions
The Proposal will result in 609,696 tCO2-e per annum and emission intensity of 0.464 tCO2-e/MWh.
Under section 15 of the Environmental Protection Act 1986 (EP Act), the EPA has the objective to use its best endeavours to protect the environment and to prevent, control and abate pollution and environmental harm. PEG considers the Proposal is consistent with the EPA’s objective for the Greenhouse Gas Emissions factor “to reduce net greenhouse gas emissions in order to minimise the risk of environmental harm associated with climate change” (EPA, 2020) and that the factor can be managed by a greenhouse gas management plan, as the Proposal is considered to provide a net reduction in greenhouse gas emissions compared to other development options (including those that are already approved), and that modern technology and efficient engines are to be procured for the Proposal. The estimated annual emissions are equivalent to 0.11% of the nation’s emissions and 0.7% of Western Australia’s emissions.
The commencement of the Proposal avoids a modelled 586,727 tonnes of CO2-e emissions per annum compared to the operation of the North Star power station.
The Proposal avoids reliance on diesel fuel or the construction of an additional gas pipeline by siting at a location with an existing natural gas supply.
PEG will avoid the procurement of Sulphur Hexafluoride (SF6) filled circuit breakers, because of the high warming potential that this gas has.
The proposal minimises the consumption of natural gas through the procurement of modern engines, innovative control system and through regular maintenance the engines and other infrastructure.
A greenhouse gas management plan will be adhered to by the proponent.
• PEG proposes to implement a Greenhouse Gas Management Plan during development of the Proposal, this plan can be found in Appendix 1.
• PEG will adhere to the requirements outlined in the National Greenhouse and Energy Reporting Act, 2007 (NGER Act).
1. The precautionary principle
Greenhouse gas modelling has assumed worst case scenarios.
2. The principle of intergenerational equity
Emissions to air are reduced due to lower emission intensity, higher efficiency, and smaller capacity of power station compared to the operation of the North Star power station.
3. Principles relating to improved valuation, pricing and incentive mechanisms
Given the intensity of the new power station is estimated at 0.464 tCO2-e/MWh, the proponent will not be required to offset any emissions in excess of the Benchmark-Emissions Baseline.
4. The principle of the conservation of biological diversity and ecological integrity
PEG will minimise emissions as far as practicable to support this principle.
5. The principle of waste minimisation
Emissions to air are reduced due to lower emission intensity, higher efficiency, and smaller capacity of power station compared to the operation of the North Star power station.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 38 of 49
Theme Environmental Factor
Impact Predicted outcomes Management and Mitigation EP Act Principles
Pe
op
le
Social Surroundings The remote location of the Proposal and 14km separation distance between the Dally camp and the Proposal ensures that there will be no adverse impacts on social surrounds due to air, noise or amenity.
The nearest heritage place is ~1.4km from the proposed power station and will not be impacted by the Proposal.
The closest conservation reserve is Karijini National Park, located 8.3 km south of the Proposal. Modelling in the air quality impact assessment (Appendix 2) indicated pollutant concentrations will not exceed 25% of any relevant guidelines at receptors even under worst case scenarios.
Mt Florance pastoral lease is an operating cattle station which includes a homestead located ~40km from the proposed power station and is not expected to experience any adverse impacts on social surrounds due to air, noise or amenity.
N/A N/A N/A
Human Health There are no communities near the Proposal and no sources of radiation for emissions to adversely impact human health.
Asbestos monitoring undertaken for the Solomon Iron Ore Project – Sustaining Production identified the decommissioned asbestos mine at Wittenoom Gorge was identified as potential source of contamination where water and wind erosion has potentially transported fibres to the Solomon Mine Site. Asbestos fibres were below the detection limit (0.01 fibres/mL) within the Solomon Mine Development Envelope in both the soil and air pump samples (Heggies, 2010 cited in Fortescue, 2015).
Human health is not expected to be significantly impacted as result of the proposed activities.
N/A N/A N/A
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 39 of 49
8.1 EPA Objectives
Terrestrial Environmental Quality
To maintain the quality of land and soils so that environmental values are protected
The holistic assessment has demonstrated that impacts to terrestrial environmental quality are
localised with no significant excavations associated with the development of the Proposal. The
Proposal will be designed to minimise the risk of land and soil contamination with minor
quantities of hydrocarbons stored on site and oily water collection, storage and treatment
infrastructure installed and maintained. The quality of land and soils can be maintained so that
the environmental values are protected.
The Proposal can be implemented to meet the EPA’s objective for this factor.
Greenhouse Gas
To reduce net greenhouse gas emissions in order to minimise the risk of environmental harm
associated with climate change.”
The Proposal is considered to provide a net reduction in greenhouse gas emissions when
compared to the North Star power station. The proponent will ensure the procurement of
extremely efficient engines to minimise greenhouse gas emissions and greenhouse gas
emission intensity. The 14 x 12MW Gas Reciprocating Engines proposed for the PEG Station
have been chosen for their advanced technology, are highly efficient with very low emissions
and heat rates. Greenhouse gas emissions will be reduced to as low as practicable, reporting of
greenhouse gas emissions is regulated under Federal legislation.
The Proposal can be implemented to meet the EPA’s objectives for this factor.
Air Quality
To maintain air quality and minimise emissions so that environmental values are protected.
The air emission impact assessment carried out (Appendix 2), which included worst case
scenarios has demonstrated that no guidelines levels will be exceeded due to emissions from
the PEG power station, even in combination with the existing Solomon power station. Fortescue
considers that air quality can be managed under Part V of the EP Act. The Proposal can be
implemented to meet the EPA’s objectives for this factor
Social Surroundings
To protect social surroundings from significant harm.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 40 of 49
The proposal will not impact to population centres, recreation or tourism values, or non-
Aboriginal heritage. PEG is committed to minimising impacts on Aboriginal heritage places in all
of its Proposal areas which includes wherever possible, avoidance of impacts on Aboriginal
heritage places. PEG will continue to work with the traditional owners, heritage professionals
and the regulatory body to mitigate and minimise the impact by undertaking additional research,
investigate recording and analysis and salvage and repatriation of cultural material.
The Proposal can be implemented to meet the EPA’s objectives for this factor.
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 41 of 49
REFERENCES
Baker Hughes (2020) LM6000, <https://www.bhge.com/lm6000> retrieved May 2020
Beard (1975) Vegetation Survey of Western Australia: Sheet 5 Pilbara. Perth: University of
Western Australia Press.
Bureau of Meteorology (BoM) (2020) Climate Data Online. Retrieved from Bureau of
Meteorology: http://www.bom.gov.au/climate/data/. Accessed 20 February 2020.
Commonwealth of Australia (2014) Celebrating Australia’s wetlands – A showcase of Australian
Ramsar sites (Department of the Environment)
Department of Industry, Science, Energy and Resources (2020) National Greenhouse Gas
Inventory, retrieved from < https://ageis.climatechange.gov.au/> May 2020
Department of Sustainability, Environment, Water, Population and Communities, (2012)
Environment Protection and Biodiversity Conservation Act 1999 Environmental Offsets Policy
Ecologia Environment (2014) Solomon Hub - Flora and Vegetation Assessment. Perth:
Unpublished Report for Fortescue Metals Group Ltd
EPA (2020a) Statement of Environmental Principles, Factors and Objectives. Western Australia:
Environmental Protection Authority (EPA)
EPA (2020b) Environmental Factor Guideline – Greenhouse Gas Emissions Western Australia:
Environmental Protection Authority (EPA).
EPA (2020c) Instructions on how to prepare an Environmental Review Document. Perth:
Environmental Protection Authority.
EPA (2020d) Environmental Factor Guideline: Air Quality. Environmental Protection Authority.
EPA (2019) Technical Guidance Mitigating Greenhouse Gas Emissions Western Australia:
Environmental Protection Authority (EPA).
Fortescue Metals Group (Fortescue) (2013) North Star Magnetite Project, Public Environmental
Review <
https://epa.wa.gov.au/sites/default/files/PER_documentation/NorthStarPER_20130816b.pdf>
Fortescue Metals Group (Fortescue) (2018) Eliwana Iron Ore Mine Project Public Environmental
Review
<http://www.epa.wa.gov.au/sites/default/files/PER_documentation2/Eliwana%20Iron%20Ore%2
0Mine%20FINAL%20Environmental%20Review%20Document.pdf>
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 42 of 49
Fortescue Metals Group (Fortescue) (2015) Solomon Iron Ore Project – Sustaining Production
Public Environmental Review. Fortescue Metals Group Ltd.
Government of Western Australia (2014) WA Environmental Offsets Guidelines
Government of Western Australia (2011) WA ENVIRONMENTAL OFFSETS POLICY
Kendrick, P. (2002) Fortescue Plains Subregion in CALM 2002. Bioregional Summary of the
2002 Biodiversity Audit for Western Australia. Department of Conservation and Land
Management.
Kovács, Tamás & Wuhu, Feng & Totterdill, Anna & Plane, John & Dhomse, Sandip & Gómez-
Martín, Juan & Stiller, Gabriele & Haenel, Florian & Smith, Chris & Forster, Piers & García,
Rolando & Marsh, Daniel & Chipperfield, Martyn (2016) Determination of the atmospheric
lifetime and global warming potential of sulphur hexafluoride using a three-dimensional model.
Atmospheric Chemistry and Physics Discussions. 17. 1-32. 10.5194/acp-2016-671.
MWH (2010) Hydrogeological Assessment of the Solomon Project. Prepared for Fortescue
Metals Group Pty Ltd.
Tille, P J. (2006) Soil-landscapes of Western Australia's rangelands and arid interior.
Department of Agriculture and Food, Western Australia.
Van Vreeswyk, A. M., Payne, A. L., Leighton, K. A., & Hennig, P. (2004) An Inventory and
Condition Survey of the Pilbara Region, Western Australia. Department of Agriculture,
Government of Western Australia.
Figure 5: Regional and local context
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 44 of 49
Figure 6: Location
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 45 of 49
Figure 7: Proposed site layout
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 46 of 49
Figure 8: Vegetation and flora receiving environment
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 47 of 49
Figure 9: Air quality receiving environment
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 48 of 49
Appendix 1: Greenhouse Gas Management Plan
Section 38 Referral Supporting Document 45-10015-RP-EN-0001 Rev 1
This document is uncontrolled when printed Page 49 of 49
Appendix 2: Air Emissions Impact Assessment