Page 1: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

A Fairfax County, VA, publication

Department of Public Works and Environmental Services

Working for You!

Scotts Run Tributary at Windy Hill Road

Stream Stabilization Project

May 2016

Page 2: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

2Stormwater Planning Division

Agenda

Project ScopeBackgroundGoals and ObjectivesExisting ConditionsProject ConceptNext StepsContact Information

Page 3: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

3Stormwater Planning Division

Stormwater Program Regulatory Drivers

• National Pollutant Discharge Elimination System (NPDES)

• Virginia Stormwater Management Program (VSMP)– Municipal Separate Storm Sewer Permit (MS4)– Discharge from approximately 7,000 storm drain outfalls– Includes watershed planning and project implementation

• Total Maximum Daily Loads (TMDLs)– Chesapeake Bay– Local Streams– Establishes pollutant loading budget for a given impaired water

body to meet water quality standards

Page 4: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

4

Scotts Run Watershed• 3,860 acres in Fairfax County• 30% impervious of mostly low

density residential land use• Drains significant commercial

and medium-density resident areas located near Tysons Corner

• Scotts Run discharges into the Potomac River

• Watershed Management Plan identifies frequent flooding at Scotts Run Road

http://www.fairfaxcounty.gov/dpwes/watersheds/middlepotomac.htm

Stormwater Planning Division

Page 5: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

5Stormwater Planning Division

Project Objectives

Restore up to 650 linear feet of stream from Windy Hill Road to Box Elder Court:

Stabilize streambed and banks Reduce sediment and nutrient inputs into stream system

Improve habitat Maintain close coordination with stakeholders

Page 6: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

6Stormwater Planning Division

Social Goals1. Maintain open dialog and share information.2. Coordinate with all the stakeholders and the community.3. Design Team:

o Rinker Design Associates, P.C.o Utilities Design and Construction Divisiono Stormwater Management

o Stormwater Planning Divisiono Maintenance and Stormwater Management Division

o Urban Forestry

Page 7: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

7Stormwater Planning Division

Environmental Benefits

Improve watershed conditions and reduce downstream impacts through….

Controlling quantityMitigate flooding where possible

Controlling velocityReduce erosionProtect infrastructure

Page 8: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

8Stormwater Planning Division

Project Location

Windy Hill Road

Box Elder Court

Scotts Run RoadProject Limits

Lewinsville Road

495

Page 9: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

9Stormwater Planning Division

Drainage Area

Page 10: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

10Stormwater Planning Division

Existing Conditions

Page 11: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

11Stormwater Planning Division

Existing Conditions

Page 12: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

12Stormwater Planning Division

Existing Conditions

Page 13: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

13Stormwater Planning Division

Existing Conditions

Page 14: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

14Stormwater Planning Division

Existing Conditions

Page 15: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

15Stormwater Planning Division

Existing Conditions

Page 16: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

16Stormwater Planning Division

Existing Conditions

Page 17: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

17Stormwater Planning Division

Existing Conditions

Page 18: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

18Stormwater Planning Division

Existing Conditions

Page 19: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

19Stormwater Planning Division

Typical Structures Used – Plunge Pool

Page 20: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

20Stormwater Planning Division

Typical Structures Used – Cross Vanes

Page 21: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

21Stormwater Planning Division

Typical Structures Used – Rock Weirs

Page 22: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

22Stormwater Planning Division

Typical Structures Used – Boulder Toe

Page 23: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

23

Vegetation

• Coordinate tree preservation and removal with Urban Forestry

• Native trees, shrubs, and plugs will be planted

• Native seed mix

Stormwater Planning Division

Page 24: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

24Stormwater Planning Division

Tentative Construction Access

Windy Hill RoadScotts Run Road

Page 25: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

25Stormwater Planning Division

Before and After Stream Restoration

Page 26: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

26Stormwater Planning Division

Construction Access

• Timber matting along the length of the access route

• Safety fencing around the site

Page 27: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

27Stormwater Planning Division

Construction Example

Page 28: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

28Stormwater Planning Division

Construction Example

Page 29: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

29Stormwater Planning Division

Construction Example

Page 30: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

30Stormwater Planning Division

Growing Season Following Construction Completion

Page 31: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

31Stormwater Planning Division

One Year After Construction Completion

Page 32: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

32Stormwater Planning Division

Three Years After Construction Completion

Page 33: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

33Stormwater Planning Division

Before and After Examples

Flatlick Confluence

January 2011 September 2015

Page 34: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

34Stormwater Planning Division

Before and After Examples

Big Rocky Run II

April 2011 September 2015

Page 35: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

35Stormwater Planning Division

2011

2013 2015

Before

Before and After Examples

Bridle Path

Page 36: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

36Stormwater Planning Division

Next Steps – Schedule

• Complete Preliminary Design- July 2016

• Complete 95% Design- September 2016

• Community Meeting- September 2016

• Complete Final Design- Late Fall 2016

• Construction:

• Start- Spring 2017

• Length- 3 to 4 months (constructed in phases)

• Planting may take place in the fall

Page 37: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

37Stormwater Planning Division

Online ResourcesStormwater Planning Division Websitehttp://www.fairfaxcounty.gov/dpwes/stormwater/

Fairfax County Watershed Planninghttp://www.fairfaxcounty.gov/nvswcd/newsletter/planning.htm

Scotts Run Watershed Planhttp://www.fairfaxcounty.gov/dpwes/watersheds/middlepotomac.htm

EPA Water Quality Laws & Regulationshttp://www.epa.gov/water/laws.html

Please sign in and provide your contact information to be included in project progress updates

Page 38: Scotts Run Tributary at Windy Hill Road: Stream Stabilization Project

38Stormwater Planning Division

Contact InformationContact Information

DesignCatie Torgersen– Project Manager

[email protected]

Fairfax County Stormwater Planning Division703-324-5500 TTY 711

12000 Government Center ParkwaySuite 449

Fairfax, Virginia 22035www.fairfaxcounty.gov/dpwes/stormwater