scott corey cpas project crashing homework solution mgmt e-5050

49
Scott Corey CPAs Scott Corey CPAs Project Crashing Project Crashing Homework Solution MGMT E-5050

Upload: carol-young

Post on 16-Dec-2015

247 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAsProject CrashingProject Crashing

Homework Solution

MGMT E-5050

Page 2: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAs

The Scott Corey accounting firm is installing a newcomputer system. Several things must be done tomake sure the system works properly before all theaccounts are put into the new system.

The following table provides information about thisproject:

Page 3: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAs

Activity Immediate Predecessor Time ( Weeks )

A - 3

B - 4

C A 6

D B 2

E A 5

F C 2

G D,E 4

H F,G 5

Page 4: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAs

REQUIREMENT:

1. How long will it take to install the system?

2. What is the critical path?

Page 5: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAs

The managing partner of the firm has decided that thesystem must be up and running in 16 weeks.

Consequently, information about crashing the projectwas put together and is shown in the following table:

Page 6: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAs

Activity

Immediate

Predecessor

Normal

Time

( weeks )

Crash

Time

( weeks )

Normal

Cost

( $ )

Crash

Cost

( $ )

A - 3 2 8,000 9,800

B - 4 3 9,000 10,000

C A 6 4 12,000 15,000

D B 2 1 15,000 15,500

E A 5 3 5,000 8,700

F C 2 1 7,500 9,000

G D,E 4 2 8,000 9,400

H F,G 5 3 5,000 6,600

Page 7: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAs

REQUIREMENT:

1. If the project is to be finished in 16 weeks, which activity or activities should be crashed to do this at the least additional cost? 2. What is the total cost of this?

3. List all the paths in this network. After the crash- ing has been done, what is the time required for each path?

Page 8: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Scott Corey CPAsScott Corey CPAs

REQUIREMENTS:

4. If the project completion time must be reduced another week so that the total time is 15 weeks, which activity or activities should be crashed? Solve this by inspection.

NOTE: It is sometimes better to crash an activity that is not the least cost for crashing if it is on several paths rather than to crash several activities on separate paths when there is more than one critical path.

Page 9: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050

Homework SolutionHomework Solution

The total time to complete the project is 17 weeks.

The critical path is A-E-G-H

Crash activity “G” one week at an additional cost of $700.00

The paths are A-E-G-H, A-C-F-H, and B-D-G-H.

When “G” is crashed by 1 week, the project completion time is reduced to 16 weeks.

Page 10: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 11: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 12: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 13: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 14: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 15: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 16: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 17: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 18: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 19: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 20: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 21: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 22: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 23: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 24: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 25: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 26: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 27: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 28: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 29: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 30: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 31: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 32: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 33: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 34: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 35: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 36: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 37: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 38: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 39: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 40: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 41: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 42: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 43: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 44: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 45: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 46: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 47: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 48: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050
Page 49: Scott Corey CPAs Project Crashing Homework Solution MGMT E-5050