scheduling in repetitive manufacturing

8
Scheduling Page 1 Scheduling in Repetitive Manufacturing Prepared by: Dr. Don Maes Mascidon LLC November 2012

Upload: others

Post on 12-Sep-2021

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Scheduling in Repetitive Manufacturing

Scheduling Page 1

Scheduling in

Repetitive

Manufacturing

Prepared by: Dr. Don Maes

Mascidon LLC

November 2012

Page 2: Scheduling in Repetitive Manufacturing

Scheduling Page 2

Contents Scheduling ..................................................................................................................................................... 3

Figure 1.1 Production Scheduling Screen ................................................................................................. 4

Figure 1.2 Selective Production Scheduling Screen .................................................................................. 6

Figure 1.3 Item Detail Demand Screen ..................................................................................................... 6

Figure 1.5 Add an Item to the Schedule ................................................................................................... 7

Page 3: Scheduling in Repetitive Manufacturing

Scheduling Page 3

Scheduling

Scheduling from within SAP flows from the MRP calculations. The ‘Order Recommendations’ file /

report provides the means for reviewing the requirements. In an environment where recommendations

are turned into production orders (PDOs) and these PDO’s are distributed to the floor, this works well.

Let’s assume that individual production orders for the floor are not required. A supervisor manages the

schedule by telling the personnel in his or her department how many to make and what operations to

work on. After creating the schedule, the supervisor can print a copy of the schedule and post it in their

department. The operators would then begin their assignments. This eliminates the need to produce a

piece of paper (PDO) for each production requirement. This schedule is in turn linked to the production

entry from the shop floor. Conceptually, the MRP recommendations have not been eliminated. The

means of presentation and usage of the information has changed.

Mascidon has altered this process by adding the flexibility to create the schedule from open sales, the

MRP recommendations, or Both of these. From an operations view, you must make certain you are not

double dipping – getting the same requirements from MRP and Sales Orders.

The scheduling is based on the requirements for fulfilling sales orders for specific due dates. Each

evening the schedules for open sales orders are recalculated based on the current date and all sales

orders due within the next x days (x is set once and used each evening. The default is 10 days.). This

information is stored in a temporary file that is then used to do the actual scheduling of production. The

production supervisor utilizes the screen shown in Figure 1.1 to begin the daily scheduling process. As

the scheduling screen is accessed, the grid of items is displayed.

The operators cannot access the ‘Scheduling’ screens. This is a supervisor process that must be done on

a daily basis. It can be modified during the day to account for schedule changes. Essentially, the

supervisor looks over the schedule generated by the system and creates a daily manufacturing schedule.

In some instances this may be a weekly schedule. For instance, in shops where coil stamping is used the

machine setups may take several hours to a day. Machine runs typically would be for several days.

Let’s review the scheduling function in depth. When the screen is initially displayed it shows all items

that have requirements but are not currently scheduled. On the screen, the ‘All Items’ would be

checked, the ‘Scheduled Items’ unchecked, and the number of days defaulted to 10.

Page 4: Scheduling in Repetitive Manufacturing

Scheduling Page 4

Figure 1.1 Production Scheduling Screen

The screen has 3 check boxes and 3 radial buttons that selectively show scheduling data. The usage of

the check boxes and radial buttons are as follows:

1. Scheduled items check box is checked – when this is checked, only items already scheduled by

the production supervisor are displayed. The schedule for all departments is shown unless the

specific department is entered. This is the same information as would be displayed if the

‘Schedule’ report button were clicked and the schedule report is run. Depending on the radial

button settings, portions of the schedule will be presented:

a. All – if this radial button is activated then all items flagged by the production supervisor

as scheduled would be shown.

b. Not Reported – some items within the schedule may be ‘phantom’ parts. Yes, they need

to be produced and the production supervisor needs to inform the floor of the need to

produce these items, but the reported completion of these items will not be entered

into SAP B1 because they are phantom parts. In this instance, only items in the schedule

with the Phantom Flag in the item master set to Yes will be displayed in the schedule.

From a manufacturing reporting view, these could be reported, but would not update

inventory.

c. Reported – items within the schedule that are not ‘phantom’ parts need to be produced

and the production supervisor needs to inform the floor of the need to produce these

items. In this instance, only items in the schedule with the Phantom Flag not set will be

displayed in the schedule.

2. Scheduled items check box is NOT checked – when this is not checked, only items not scheduled

by the production supervisor are displayed. Depending on the radial button settings, portions of

the items not scheduled will be presented:

a. All – if this radial button is activated then all items not scheduled by the production

supervisor would be shown.

Page 5: Scheduling in Repetitive Manufacturing

Scheduling Page 5

b. Not Reported – some items may be ‘phantom’ parts. Yes, they need to be produced and

the production supervisor needs to inform the floor of the need to produce these items,

but the reported completion of these items will not be entered into SAP B1 because

they are phantom parts. In this instance, only items not in the schedule and phantom

flag set to yes will be displayed.

c. Reported – items not scheduled that are not ‘phantom’ parts need to be produced and

the production supervisor needs to inform the floor of the need to produce these items.

In this instance, only items not scheduled and with phantom flag not set will be

displayed.

3. Select all check box is checked – this flags all the items currently on the screen with the check

box.

Referring back to Figure 1.1, assuming the production supervisor is creating a schedule, then the check

box for the ‘Scheduled Items’ would not be checked. Items would be displayed on the screen. The

supervisor would schedule a part by:

• Entering the quantity to make

• Selecting the operator to assign to making the parts

• Clicking the ‘Select’ check box in the grid portion of the screen (not the ‘Select All’ button).

After performing this operation on as many items as required, clicking the ‘Process’ button moves the

checked items to the ‘Schedule’. This process can be repeated as many times as necessary to create a

full production schedule. At any time, the user can click on the ‘Scheduled Items’ check box and refresh

the screen to see the current schedule. Alternatively, the ‘Schedule’ button can be clicked to print a

report of the scheduled items.

The ‘# of days’ field defaults to 10 days. If the user wants to see the requirements for a shorter period

of time so that immediate demand can be scheduled first, then this number can be changed. The items

on display may change (some items may not be required for the first 5 days for example), and the

quantity required will change. The Details behind the schedule will still show total demand so the

scheduling person can make a determination of how many to run if they are setting up the tooling /

machine to run anyway.

With a large data file it is difficult to manage entries to the schedule. The ‘Item’ field entry under the ‘#

of days’ label provides for a shortening of the list of items to manage at any time.

The user can change the sort sequence of the information by clicking on the column header to sort.

Clicking on the same column header a second time reverses the sort sequence for that column.

Page 6: Scheduling in Repetitive Manufacturing

Scheduling Page 6

Figure 1.2 Selective Production Scheduling Screen

During the creation of the schedule, the user may look at a requirement for an item and want to know

what created demand for a specific item. To obtain this information the user would double click on a

field within the schedule. The item details screen as shown in Figure 1.3 is displayed. The example

shows the source of the demand – in this instance Sales Orders. The MRP Forecast could be a second

source. If any items are currently produced, then the total quantity already produced will be displayed.

Figure 1.3 Item Detail Demand Screen

With the ‘Scheduled Items’ check box checked, the screen shows the schedule. The scheduling person

enters the quantity to make for any item and assigns the work to an operator. As they select a

particular item to produce, that line is highlighted so that scheduled items are easy to identify. To print

a report of the schedule, click on the ‘Schedule’ button. The report is shown in Figure1.4.

Page 7: Scheduling in Repetitive Manufacturing

Scheduling Page 7

Figure 1.4 Scheduled Items Shown On Screen

This report has a page break based on the date and the operator. This is done for convenience so the

production scheduling person can hand out the assignments. The blue, italicized item is an indication

that the production for this item needs to be entered into SAP.

If a row that is scheduled (see settings for check boxes and radial buttons) is highlighted and then the

‘Remove Row’ button is clicked, then the item in that row is removed from the schedule.

The ‘Add Item’ button on the screen provides a means to add an item to the schedule that may not be in

current demand. This provides the ability to schedule a production run to use a coil of steel (for

instance) in its entirety to produce some items that will have demand in the near future or can be used

as components for multiple popular parts. Clicking on the ‘Add Item’ button presents the screen shown

in Figure 1.5. The scheduling person enters the item, quantity and operator to assign and clicks the ‘Add

Item’ button. This item is then added to the schedule.

Figure 1.5 Add an Item to the Schedule

The schedule produced by entering quantity – operator information remains in the schedule file across

multiple days. This is intentional. It is done so that items that are scheduled once per week can be

intermingled with the schedule for items scheduled every day. It is likely, but not mandatory, that a

Page 8: Scheduling in Repetitive Manufacturing

Scheduling Page 8

single operator will have a schedule for a single date. Remember, the overall demand is recalculated

each evening and stored in a file. As the scheduling is revisited each day, the user can review previously

scheduled production or clear out the prior information. To clear out prior date information, enter the

From and To Dates on the bottom corner of the screen and click the Clear Schedule button. To clear the

entire schedule use a from – to date range that would cover any information in the schedule file.