SAXE MIDDLE SCHOOL

Upload: dinhkiet

Post on 12-Mar-2018

217 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: SAXE MIDDLE SCHOOL - New Canaan Public Schools ... Confidence Phasing Plan Saxe Middle Schoo l Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase

SAXE MIDDLE SCHOOL

Page 2: SAXE MIDDLE SCHOOL - New Canaan Public Schools ... Confidence Phasing Plan Saxe Middle Schoo l Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase

YOUR PROJECT TEAM

EXPERIENCE COLLABORATION EXPERTISE

Project Executive

MARK JEFFKO, LEED AP

Superintendent

ROGER JOHNSON

Project Manager

GEORGE GRAIKOSKI

Pre-Construction Manager

LOREL PURCELL, PE, LEED AP

Page 3: SAXE MIDDLE SCHOOL - New Canaan Public Schools ... Confidence Phasing Plan Saxe Middle Schoo l Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase

PHASE 1A New Addition Jun 2016* – Fall 2017

PHASE 1B Auditorium Renovation Jun 2016* – June 2017

PHASE 1C Partial Renovation Summer 2016 of Existing Classrooms

PHASE 2A Convert Existing Choral Room Jun 2017* – Fall 2017 into Expanded Band Room

Convert Existing Art Rooms into Choral and Storage Rooms

PHASE 2B Minor Renovations to General Summer 2017 Music, Orchestra & Small Band

Complete New Wing Connection * After End of School

Building Confidence Construction Phases Saxe Middle School

Page 4: SAXE MIDDLE SCHOOL - New Canaan Public Schools ... Confidence Phasing Plan Saxe Middle Schoo l Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase

Building Confidence Phasing Plan Saxe Middle School

Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase 2A Jun 2017 – Fall 2017 Phase 2B Summer 2017

CMU infills & HVAC ventilation work only during Phase 1C.

Remainder of work Phase 2B.

Abate Boiler Room

Overall  Construc/on:    June  2016  –  Fall  2017  

WORK  HOURS:  DURING  SCHOOL  YEAR    12:00  PM  –  8:30  PM  DURING  SUMMER    6:00  AM  –  3:30  PM  

Page 5: SAXE MIDDLE SCHOOL - New Canaan Public Schools ... Confidence Phasing Plan Saxe Middle Schoo l Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase

Second Floor Area B

Temporary enclosed Stair Tower from roof to grade

4’ wide aluminum planking with ballasted weighted bases and OSHA approved guardrails on both sides

Temporary handrail

UP

Rated Temporary Partition

Fire Exit Plan Saxe Middle School

Building Confidence

-­‐              -­‐  

Page 6: SAXE MIDDLE SCHOOL - New Canaan Public Schools ... Confidence Phasing Plan Saxe Middle Schoo l Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase

Designated Contractor Parking

Dumpsters

20’ Double Drive

Gate

20’ Double Drive

Gate Moveable Fencing

Moveable Fencing

20’ Double Drive

Gate

20’ Double Drive

Gate

Construction Entrance

Construction Entrance

Site Logistics Plan Saxe Middle School

Building Confidence

Page 7: SAXE MIDDLE SCHOOL - New Canaan Public Schools ... Confidence Phasing Plan Saxe Middle Schoo l Phase 1A Jun 2016 – Fall2017 Phase 1B Jun 2016 – Jun 2017 Phase 1C Summer 2016 Phase

SAFETY IS MORE THAN A SLOGAN

Work Zone Separation

Safety Coordination with Pre-construction

Background Checks

Job Safety Task Analysis

Weekly Safety Meetings

Constant Monitoring

24-HOUR SAFETY HOTLINE

SAFETY MONITORING & INCIDENT TRACKING

EXPERT SAFETY TEAM