sample ngc3 [1]

10
5/21/2018 SampleNGC3[1]-slidepdf.com http://slidepdf.com/reader/full/sample-ngc3-1 1/10 Repair to roof 1)  Individuals working on roof in close  proximity to unprotected fragile clear roof panel light, potential for individuals to fall through clear  panel resulting in a serious or major injury. Stopped work activity until appropriate controls have been put in place following a suitable and sufficient risk assessment. Carry out suitable and sufficient risk assessment by competent individuals and implement appropriate control actions to minimise the risk to as low as reasonably practicable. Carry out training on awareness on working at height to all employees who are expected to work at heights.  Immediately 10 days  2 months  2)  Area below overhead work activity not cordoned off, potential for objects to fall from height resulting in serious injury. Stop roof repair activity. Cordon off area below.  Immediately 1 day 3)  Although barriers have been installed around roof edge to  prevent falls no edge protection installed to prevent object falling from height. Stop roof repair activity.  Install edge protection/toe boards to  prevent objects falling from height.  Immediately 1 week 4) No signage to identify PPE requirements while working in area, this could result in individuals entering the area without required PPE.  Install appropriate PPE signage in entry to work area. 1 week 5)  Good access to roof by scaffolding, access ladder secured.

Upload: joel-cummings

Post on 11-Oct-2015

923 views

Category:

Documents


0 download

DESCRIPTION

NEBOSH

TRANSCRIPT

  • Repair to roof

    1) Individuals working on roof in close

    proximity to unprotected fragile

    clear roof panel light, potential for

    individuals to fall through clear

    panel resulting in a serious or

    major injury.

    Stopped work activity until appropriate

    controls have been put in place following

    a suitable and sufficient risk assessment.

    Carry out suitable and sufficient risk

    assessment by competent individuals

    and implement appropriate control

    actions to minimise the risk to as low as

    reasonably practicable.

    Carry out training on awareness on

    working at height to all employees who

    are expected to work at heights.

    Immediately

    10 days

    2 months

    2) Area below overhead work activity

    not cordoned off, potential for

    objects to fall from height resulting

    in serious injury.

    Stop roof repair activity.

    Cordon off area below.

    Immediately

    1 day

    3) Although barriers have been

    installed around roof edge to

    prevent falls no edge protection

    installed to prevent object falling

    from height.

    Stop roof repair activity.

    Install edge protection/toe boards to

    prevent objects falling from height.

    Immediately

    1 week

    4) No signage to identify PPE

    requirements while working in

    area, this could result in individuals

    entering the area without required

    PPE.

    Install appropriate PPE signage in entry

    to work area.

    1 week

    5) Good access to roof by scaffolding,

    access ladder secured.

  • Office block

    6) Area in front of fire escape blocked

    by waste skip placed there by

    roofing contractor preventing

    escape in an emergency. In an

    emergency situation this could lead

    to multiple injuries or fatalities.

    Remove obstruction.

    Carry out investigation to determine why

    the contractor placed skip in front of

    emergency escape.

    Introduce weekly inspections on all

    escape routes to ensure they are clear

    and free from obstructions.

    Implement finding of investigations.

    Immediately

    1 week

    4 weeks

    8 weeks

    7) Fire assembly point located across

    a busy road, potential for

    individuals to be struck by a

    moving vehicle leading to a serious

    or major injury.

    Carry out risk assessment on assembly

    point location, is there a more suitable

    location that does not require

    pedestrians to cross road. If not can

    other traffic control measures be put in

    place such as reduced speed limits in

    this area.

    Install up to date pictorial signage.

    2 weeks

    2 weeks

    8) Fire escape route not clearly

    marked could cause

    confusion/disorientation during an

    emergency.

    Introduce periodic emergency

    evacuation drills so employees become

    familiar with the access routes and what

    to do in an emergency.

    4 weeks

    9) Fire extinguisher not mounted on

    wall, this could result in unit falling

    over and being accidentally

    activated.

    Purchase correct fixing brackets and fix

    to wall.

    4 weeks

    10) Emergency break glass units and

    emergency lighting in place by the

    emergency exit. - GOOD PRACTICE

  • Workshop

    11) Machine being operated with a

    damaged guard that could lead to

    objects being ejected from the

    machine resulting in a serious or

    major injury.

    Stop work activity and isolate machine

    until guarding is repaired or replaced.

    Implement a scheduled safety tour

    focusing on machine guarding.

    Implement a pre-start check programme

    on all machines.

    Immediately

    2 weeks

    6 weeks

    12) Coolant on workshop floor could

    lead to a potential slip resulting in

    a serious injury.

    Clear up spill.

    Carry out a risk assessment of machine

    and suitability of floor covering to ensure

    the risk of slips is reduced as far as

    reasonably practicable.

    Implement controls identified in the risk

    assessment such as installation of splash

    guards to prevent spill occurring or

    installation of anti-slip mats around the

    machine.

    Immediately

    2 weeks

    6 weeks

    13) Signage on machine not clearly

    visible due to wear and tear as well

    as smeared with oil and grease.

    This could lead to incorrect

    operation of the machine which

    could result in an injury.

    Stop use and clean machine.

    Review machine maintenance

    programme to see if it is still suitable

    and sufficient considering the frequency

    of use and age of the machine.

    Implement a pre use check for the

    machines. Obtain replacement signage.

    Immediately

    4 weeks

    14) Operator was trained in the use of

    machine. - GOOD PRACTICE

  • Workshop

    15) Vehicles driving down centre of

    workshop with no

    vehicle/pedestrian segregation.

    Potential for pedestrian to be

    struck by a vehicle resulting in a

    serious or major injury.

    Restrict vehicle movements within the

    workshop during normal working hours,

    by scheduling vehicle operation during

    lunch breaks or out of hours.

    Carry out a vehicle/pedestrian risk

    assessment and put in adequate control

    to minimise the risk of

    vehicle/pedestrian collisions to as low as

    reasonably practicable.

    Provide information, training and

    instruction of new traffic management

    system.

    A control to consider is to purchase and

    install barriers and have specific signed

    and marked up crossing points.

    Immediate

    1 week

    4 weeks

    12 weeks

    16) Although vehicles were travelling

    at slow speed there was no visible

    signage of maximum speed at the

    entrance to the workshop.

    Purchase and install speed limit signage

    at entrances to workshop. Typical

    speeds should be restricted to 5 mph,

    should also consider the installation of

    speed restriction devices to vehicles in

    use in the workshop.

    4 weeks

    17) Vehicle parked next to machine

    generating a blind spot.

    Review parking requirements within the

    workshop, if it is required mark out a

    specific parking area for the vehicles.

    4 weeks

    18) Good use of safety/lap belts. -

    GOOD PRACTICE

  • Workshop

    19) High noise levels generated when

    press in operation. Operator was

    wearing ear defenders, however

    other individuals in close proximity

    did not have hearing protection,

    which could result in noise induced

    hearing loss.

    Put in place temporary controls, for

    example making the wearing of hearing

    protection mandatory until a noise

    survey determines otherwise.

    Carry out noise survey to determine

    individual daily exposure levels.

    Carry out noise survey to determine

    sources and levels of noise within the

    workshop and develop an action plan to

    reduce individual exposure levels.

    Implement noise reduction plan.

    1 day

    4 weeks

    6 weeks

    12 months

    20) A number of radios were in use

    throughout the workshop

    contributing to the overall noise

    levels. This could cause

    communication issues and prevent

    individuals hearing approaching

    vehicles.

    Review and risk assess the use of the

    radios within the workshop.

    1 week

    21) Space heater fan generating

    excess noise.

    Shut down space heater at earliest

    opportunity and replace faulty

    components.

    1 week

    22) Overall the workshop

    housekeeping was in reasonable

    condition. - GOOD PRACTICE

  • Introduction

    This report covers the workplace inspection that took place on the 15th November 2012 at the premises of

    Sample Engineering. Sample Engineering have 45 employees and manufacture electrical control panels

    ranging from panel mounted units to walk in panels. The areas covered by the inspection were the roof

    repairs, workshops, and office areas. The activities taking place during the inspection were roofing repairs,

    general machine operation and vehicle movements within the workshop.

    Executive Summary

    During the inspection good health and safety practices were observed, such as the wearing of safety boots

    and glasses. Individuals who were approached during the inspection were open and helpful, with regards to

    health and safety matters.

    The inspection has raised a number of concerns with respect to Working at Height, Contractor Management,

    Emergency Preparations, Machinery guarding, Vehicle and Pedestrian interaction and Noise. These concerns

    could lead to potential breaches in legislation resulting in possible prosecutions to both employees and the

    company.

    The concerns raised are:

    Two contractors were observed working on a roof near clear fragile roof panels, there was no protection

    to prevent these individuals falling through the panels to ground, potentially resulting in a major or fatal

    injury. There was no evidence of a suitable or sufficient risk assessment.

    The office fire escape was blocked by a waste skip placed there by the roofing repair contractor. The

    blocked escape would have prevented the evacuation of fifteen individuals who were working in the office

    building at the time.

    A machine operator was operating a machine with a damaged guard that could have resulted in objects

    being ejected from the machine, potentially resulting in a serious or major injury.

    There appears to be little control over vehicle/pedestrian interaction in the main workshop. On a number

    of occasions pedestrians crossed the path of a fork lift truck in the main workshop.

    A machine in the workshop was found to be generating high level of noise when operated. Although the

    machinist was wearing ear protection, other individuals working in close proximity were not wearing

    hearing protection.

  • Main findings of the inspection

    Observation No 1 - Refer to observation sheet

    Two contractors were observed working on a roof near clear fragile roof panels, access to the roof via

    scaffolding was good and there was adequate edge protection.

    However there was no protection to prevent these individuals falling through these panels and no safety

    netting to prevent the individuals falling to the ground. Also the area below the roof activity had not been

    cordoned off. Due to the distance of the potential fall, the fall would likely to have resulted in a major or

    even fatal injury not only to the person that could fall through the clear panel, but also anyone who might be

    directly below at the time. There was no evidence of a suitable and sufficient risk assessment. The work

    activity was immediately stopped due to the serious and imminent danger to the individuals involved.

    The implication to the company and the contractor could be significant as both have obligations under the

    Health and Safety at Work Act 1974 section 2 and 3. If a fall had occurred or an enforcement officer came

    to inspect the activity, potential breaches of the Health and Safety at Work Act 1974, Management of Health

    and Safety at Work Regulations 1999 and Work at Height Regulations 2005 would be found. The

    Management Regulations require clients and contractor to coordinate work, and the Work at Height

    regulations require work at height to be planned and managed safely.

    It is recommended that a suitable and sufficient risk assessment is carried out by competent individuals to

    see if working at height could be avoided. If not, put in place suitable controls to first prevent a fall and f

    this is not possible then reduce the distance and consequence of the fall by installing safety netting or

    equivalent type safety devices or fall arrest equipment together with the appropriate rescue plan for the type

    of fall protection selected.

    Observation No 6 - Refer to observation sheet

    The office fire escape was blocked by a waste skip placed there by the roofing repair contractor. The blocked

    escape would have prevented the evacuation of fifteen individuals who were working in the office building at

    the time, and could have resulted in multiple injuries of a serious or fatal nature. The skip blocking the

    emergency exit breaches the requirements of the Regulation 8 of the Management of Health and Safety at

    Work regulations which require employers to have emergency procedures in place for individuals to follow in

    the event of an emergency.

    Immediate corrective action was taken by removing the obstruction. A formal investigation should now be

    conducted to determine the failure mechanisms in the contractor management system that resulted in the

    contractor placing the skip in front of the fire escape.

    It is recommended that a routine inspection should now be scheduled to ensure emergency evacuation

    routes are not obstructed and set up routine fire evacuation drills so employees are well informed and

    trained in what to do in the event of an emergency.

    Observation No 11 - Refer to observation sheet

    While inspecting the workshop area one machine being operated was found to have a damaged guard that

    reduced the protection against objects being ejected from the machine potentially resulting in a serious or

    major injury. There are potential multiple breaches of legislation and prosecutions when using machinery

  • with faulty guards, the Health and Safety at Work Act section 2(2)(a) - Employers must provide safe plant,

    section 2(2)c - Employers must provide information, instruction, training and supervision, Section 7 -

    Employees must take reasonable care of themselves or others who may be affected by their acts or

    omissions, Section 8 - No person may misuse or interfere with anything provided in the interest of Health,

    Safety or Welfare. The provision and use of Work Related Equipment Regulations also require machinery to

    be adequately guarded.

    As this observation identified a situation that could lead to serious and imminent danger the machine was

    immediately stopped and isolated. It is recommended that this machine must not be bought back into

    operation until the defective guarding has been repaired or replaced. It is recommended that a pre start

    inspection programme on all machines is implemented together with a scheduled safety tour focusing on

    machinery to ensure they are in good condition..

    A further recommendation would be to review the maintenance program of the machines in the workshop to

    ensure they are fit for purpose based on machine usage, age and recommendation from manufacturer

    instructions.

    Observation 15 - Refer to observation sheet

    There appears to be little control over vehicle/pedestrian interaction in the main workshop. On a number of

    occasions pedestrians crossed the path of a fork truck in the main workshop. There was no vehicle

    pedestrian segregation, or other traffic control measures in place. There was no evidence of a risk

    assessment to identify the hazards, who might be harmed or suitable controls that need to be in place.

    It is recommended that immediate controls are put in place to reduce the risk as far as reasonably

    practicable, such as using the fork truck or other vehicles in the main workshop during out of hours activities

    or during lunch breaks so removing pedestrians from the building while vehicles are in use and setting

    appropriate maximum speed limits inside the workshop building i.e. 5 MPH.

    It is recommended that a full vehicle pedestrian interaction risk assessment be conducted identifying the

    hazard, who might be harmed, and identifying suitable and sufficient control measures to reduce the risk of

    collision to as low as reasonably practicable, such as segregation procedures, speed restrictions on vehicles

    information and training.

    Failure to have a suitable and sufficient risk assessment is in breach of the Management of Health and Safety

    Regulations and could potentially lead to enforcement notices being issued impacting on the business output,

    reputation and employee morale. If enforcement notices are upheld the company could potentially receive

    fines or individuals being imprisoned.

    The Workplace (Health, Safety and Welfare) Regulations also require safe interaction between vehicles and

    pedestrians.

    Observation 19 - Refer to observation sheet

    One of the machines in the workshop was generating a high level of noise when being operated. Although

    the machinist was wearing ear protection other individuals working in close proximity were not wearing

    hearing protection. Following discussions with the supervisor no noise surveys had been carried out to

    determine individuals daily exposure levels and if they were exceeding the lower exposure action value of

    80db(A)Lep.d.

  • It is recommended as an immediate control measure to restrict the machines operation to when the majority

    of the individuals are not present for example out of hours or during breaks.

    If this is not possible ensure all employees in the workshop wear hearing protection when the machine is

    operating.

    It is recommended the company carry out an adequate noise survey to determine the exposure levels of its

    employees, should the survey show the exposure level breaches the upper exposure limit of 85db(A)Lep.d

    implement plans to reduce the noise exposure by relocating the machine. If the machine cannot be

    relocated then consider installing an acoustic booth around the machine or screening the machine from other

    individuals working in the workshop. Installing noise dampening materials on the walls and ceilings can also

    reduce the noise impact.

    The company is at risk of being in breach of the Control of Noise at Work Regulations 2005 as it cannot

    demonstrate they have carried out adequate assessment of noise within the workshop so they do not know

    the noise levels they are exposing their employees to.

    Conclusions

    This report has identified several failings in the health and safety management system, and breaches of

    legislation. Each of the breaches of legislation could lead to a fine of up to 20,000 or imprisonment of up to

    12 months. More serious breaches that result in a major or fatal injury could lead to unlimited fines and up

    to two year imprisonment.

    In addition to these legal issues, the cost of accidents in these areas could have a serious financial impact on

    the company. Lost production time, training costs, increased insurance premiums, management time and

    many other costs could result. Spending the money required now will have much greater savings in the long

    term.

    Additionally, the company has a moral duty of care to look after employees. It is not acceptable to have

    employees at work who are at risk of being injured, or even worse, not going home at all.

    For these reasons, it is important that the deficiencies identified are addressed within the timescales given.

    Recommendations

    Recommendation Likely resource implications Priority Target date

    Competent individuals to conduct a

    suitable and sufficient Working at

    Height Risk Assessment and

    implement appropriate controls to

    minimise the risk to as low as

    reasonably practicable

    Resources required will be Contractor

    personnel and Company Contracts

    Manager. Depending on the roof

    repair specification and terms and

    conditions of the contract the cost of

    the assessment and the

    implementation of control actions sit

    with the contractor. Estimated costs

    3000

    High 22nd November

  • Recommendation Likely resource implications Priority Target date

    Carry out a formal investigation into

    the failure of the contractor

    management system. Set up

    routine inspection of the emergency

    escape routes.

    Set up an investigation team,

    consisting of a competent investigator

    and company contract manager.

    Further internal resources will be

    required to modify the contractor

    management system based on the

    finding of the investigation. Although

    not a direct cost, these individuals will

    not be able to carry out their normal

    working duties during the

    investigation and implementation of

    corrective actions. Estimated costs

    1500

    Medium End December

    2012

    Carry out repair to machine guard.

    Review maintenance requirements

    and schedule.

    An external cost will be incurred to

    bring in a machine specialist to

    repair/replace the guard. An internal

    cost will be incurred carrying out a

    review of the maintenance

    requirements and scheduled and there

    will be a cost associated with

    production losses as the machine will

    be out of use until the guard is fixed.

    Estimated cost 4000 for the repair

    High 22nd November

    Carry out a suitable and sufficient

    vehicle and pedestrian interaction

    risk assessment and implement

    appropriate controls.

    A team of employees from across the

    company assisted by an external

    vehicle/pedestrian consultant. The

    large cost will be the design and

    installation of any segregation controls

    such as barriers and markings.

    Estimated costs 20000

    High February 2013

    Carry out Noise Survey to determine

    individual exposure rates and

    sources of noise.

    A competent external specialist would

    need to be employed. 1 to 2 hour

    awareness training session need to be

    set up for all employees. Further

    engineering requirements to reduce

    noise exposure levels over the coming

    12 months.

    High December

    2012