sample ngc3 [1]
DESCRIPTION
NEBOSHTRANSCRIPT
-
Repair to roof
1) Individuals working on roof in close
proximity to unprotected fragile
clear roof panel light, potential for
individuals to fall through clear
panel resulting in a serious or
major injury.
Stopped work activity until appropriate
controls have been put in place following
a suitable and sufficient risk assessment.
Carry out suitable and sufficient risk
assessment by competent individuals
and implement appropriate control
actions to minimise the risk to as low as
reasonably practicable.
Carry out training on awareness on
working at height to all employees who
are expected to work at heights.
Immediately
10 days
2 months
2) Area below overhead work activity
not cordoned off, potential for
objects to fall from height resulting
in serious injury.
Stop roof repair activity.
Cordon off area below.
Immediately
1 day
3) Although barriers have been
installed around roof edge to
prevent falls no edge protection
installed to prevent object falling
from height.
Stop roof repair activity.
Install edge protection/toe boards to
prevent objects falling from height.
Immediately
1 week
4) No signage to identify PPE
requirements while working in
area, this could result in individuals
entering the area without required
PPE.
Install appropriate PPE signage in entry
to work area.
1 week
5) Good access to roof by scaffolding,
access ladder secured.
-
Office block
6) Area in front of fire escape blocked
by waste skip placed there by
roofing contractor preventing
escape in an emergency. In an
emergency situation this could lead
to multiple injuries or fatalities.
Remove obstruction.
Carry out investigation to determine why
the contractor placed skip in front of
emergency escape.
Introduce weekly inspections on all
escape routes to ensure they are clear
and free from obstructions.
Implement finding of investigations.
Immediately
1 week
4 weeks
8 weeks
7) Fire assembly point located across
a busy road, potential for
individuals to be struck by a
moving vehicle leading to a serious
or major injury.
Carry out risk assessment on assembly
point location, is there a more suitable
location that does not require
pedestrians to cross road. If not can
other traffic control measures be put in
place such as reduced speed limits in
this area.
Install up to date pictorial signage.
2 weeks
2 weeks
8) Fire escape route not clearly
marked could cause
confusion/disorientation during an
emergency.
Introduce periodic emergency
evacuation drills so employees become
familiar with the access routes and what
to do in an emergency.
4 weeks
9) Fire extinguisher not mounted on
wall, this could result in unit falling
over and being accidentally
activated.
Purchase correct fixing brackets and fix
to wall.
4 weeks
10) Emergency break glass units and
emergency lighting in place by the
emergency exit. - GOOD PRACTICE
-
Workshop
11) Machine being operated with a
damaged guard that could lead to
objects being ejected from the
machine resulting in a serious or
major injury.
Stop work activity and isolate machine
until guarding is repaired or replaced.
Implement a scheduled safety tour
focusing on machine guarding.
Implement a pre-start check programme
on all machines.
Immediately
2 weeks
6 weeks
12) Coolant on workshop floor could
lead to a potential slip resulting in
a serious injury.
Clear up spill.
Carry out a risk assessment of machine
and suitability of floor covering to ensure
the risk of slips is reduced as far as
reasonably practicable.
Implement controls identified in the risk
assessment such as installation of splash
guards to prevent spill occurring or
installation of anti-slip mats around the
machine.
Immediately
2 weeks
6 weeks
13) Signage on machine not clearly
visible due to wear and tear as well
as smeared with oil and grease.
This could lead to incorrect
operation of the machine which
could result in an injury.
Stop use and clean machine.
Review machine maintenance
programme to see if it is still suitable
and sufficient considering the frequency
of use and age of the machine.
Implement a pre use check for the
machines. Obtain replacement signage.
Immediately
4 weeks
14) Operator was trained in the use of
machine. - GOOD PRACTICE
-
Workshop
15) Vehicles driving down centre of
workshop with no
vehicle/pedestrian segregation.
Potential for pedestrian to be
struck by a vehicle resulting in a
serious or major injury.
Restrict vehicle movements within the
workshop during normal working hours,
by scheduling vehicle operation during
lunch breaks or out of hours.
Carry out a vehicle/pedestrian risk
assessment and put in adequate control
to minimise the risk of
vehicle/pedestrian collisions to as low as
reasonably practicable.
Provide information, training and
instruction of new traffic management
system.
A control to consider is to purchase and
install barriers and have specific signed
and marked up crossing points.
Immediate
1 week
4 weeks
12 weeks
16) Although vehicles were travelling
at slow speed there was no visible
signage of maximum speed at the
entrance to the workshop.
Purchase and install speed limit signage
at entrances to workshop. Typical
speeds should be restricted to 5 mph,
should also consider the installation of
speed restriction devices to vehicles in
use in the workshop.
4 weeks
17) Vehicle parked next to machine
generating a blind spot.
Review parking requirements within the
workshop, if it is required mark out a
specific parking area for the vehicles.
4 weeks
18) Good use of safety/lap belts. -
GOOD PRACTICE
-
Workshop
19) High noise levels generated when
press in operation. Operator was
wearing ear defenders, however
other individuals in close proximity
did not have hearing protection,
which could result in noise induced
hearing loss.
Put in place temporary controls, for
example making the wearing of hearing
protection mandatory until a noise
survey determines otherwise.
Carry out noise survey to determine
individual daily exposure levels.
Carry out noise survey to determine
sources and levels of noise within the
workshop and develop an action plan to
reduce individual exposure levels.
Implement noise reduction plan.
1 day
4 weeks
6 weeks
12 months
20) A number of radios were in use
throughout the workshop
contributing to the overall noise
levels. This could cause
communication issues and prevent
individuals hearing approaching
vehicles.
Review and risk assess the use of the
radios within the workshop.
1 week
21) Space heater fan generating
excess noise.
Shut down space heater at earliest
opportunity and replace faulty
components.
1 week
22) Overall the workshop
housekeeping was in reasonable
condition. - GOOD PRACTICE
-
Introduction
This report covers the workplace inspection that took place on the 15th November 2012 at the premises of
Sample Engineering. Sample Engineering have 45 employees and manufacture electrical control panels
ranging from panel mounted units to walk in panels. The areas covered by the inspection were the roof
repairs, workshops, and office areas. The activities taking place during the inspection were roofing repairs,
general machine operation and vehicle movements within the workshop.
Executive Summary
During the inspection good health and safety practices were observed, such as the wearing of safety boots
and glasses. Individuals who were approached during the inspection were open and helpful, with regards to
health and safety matters.
The inspection has raised a number of concerns with respect to Working at Height, Contractor Management,
Emergency Preparations, Machinery guarding, Vehicle and Pedestrian interaction and Noise. These concerns
could lead to potential breaches in legislation resulting in possible prosecutions to both employees and the
company.
The concerns raised are:
Two contractors were observed working on a roof near clear fragile roof panels, there was no protection
to prevent these individuals falling through the panels to ground, potentially resulting in a major or fatal
injury. There was no evidence of a suitable or sufficient risk assessment.
The office fire escape was blocked by a waste skip placed there by the roofing repair contractor. The
blocked escape would have prevented the evacuation of fifteen individuals who were working in the office
building at the time.
A machine operator was operating a machine with a damaged guard that could have resulted in objects
being ejected from the machine, potentially resulting in a serious or major injury.
There appears to be little control over vehicle/pedestrian interaction in the main workshop. On a number
of occasions pedestrians crossed the path of a fork lift truck in the main workshop.
A machine in the workshop was found to be generating high level of noise when operated. Although the
machinist was wearing ear protection, other individuals working in close proximity were not wearing
hearing protection.
-
Main findings of the inspection
Observation No 1 - Refer to observation sheet
Two contractors were observed working on a roof near clear fragile roof panels, access to the roof via
scaffolding was good and there was adequate edge protection.
However there was no protection to prevent these individuals falling through these panels and no safety
netting to prevent the individuals falling to the ground. Also the area below the roof activity had not been
cordoned off. Due to the distance of the potential fall, the fall would likely to have resulted in a major or
even fatal injury not only to the person that could fall through the clear panel, but also anyone who might be
directly below at the time. There was no evidence of a suitable and sufficient risk assessment. The work
activity was immediately stopped due to the serious and imminent danger to the individuals involved.
The implication to the company and the contractor could be significant as both have obligations under the
Health and Safety at Work Act 1974 section 2 and 3. If a fall had occurred or an enforcement officer came
to inspect the activity, potential breaches of the Health and Safety at Work Act 1974, Management of Health
and Safety at Work Regulations 1999 and Work at Height Regulations 2005 would be found. The
Management Regulations require clients and contractor to coordinate work, and the Work at Height
regulations require work at height to be planned and managed safely.
It is recommended that a suitable and sufficient risk assessment is carried out by competent individuals to
see if working at height could be avoided. If not, put in place suitable controls to first prevent a fall and f
this is not possible then reduce the distance and consequence of the fall by installing safety netting or
equivalent type safety devices or fall arrest equipment together with the appropriate rescue plan for the type
of fall protection selected.
Observation No 6 - Refer to observation sheet
The office fire escape was blocked by a waste skip placed there by the roofing repair contractor. The blocked
escape would have prevented the evacuation of fifteen individuals who were working in the office building at
the time, and could have resulted in multiple injuries of a serious or fatal nature. The skip blocking the
emergency exit breaches the requirements of the Regulation 8 of the Management of Health and Safety at
Work regulations which require employers to have emergency procedures in place for individuals to follow in
the event of an emergency.
Immediate corrective action was taken by removing the obstruction. A formal investigation should now be
conducted to determine the failure mechanisms in the contractor management system that resulted in the
contractor placing the skip in front of the fire escape.
It is recommended that a routine inspection should now be scheduled to ensure emergency evacuation
routes are not obstructed and set up routine fire evacuation drills so employees are well informed and
trained in what to do in the event of an emergency.
Observation No 11 - Refer to observation sheet
While inspecting the workshop area one machine being operated was found to have a damaged guard that
reduced the protection against objects being ejected from the machine potentially resulting in a serious or
major injury. There are potential multiple breaches of legislation and prosecutions when using machinery
-
with faulty guards, the Health and Safety at Work Act section 2(2)(a) - Employers must provide safe plant,
section 2(2)c - Employers must provide information, instruction, training and supervision, Section 7 -
Employees must take reasonable care of themselves or others who may be affected by their acts or
omissions, Section 8 - No person may misuse or interfere with anything provided in the interest of Health,
Safety or Welfare. The provision and use of Work Related Equipment Regulations also require machinery to
be adequately guarded.
As this observation identified a situation that could lead to serious and imminent danger the machine was
immediately stopped and isolated. It is recommended that this machine must not be bought back into
operation until the defective guarding has been repaired or replaced. It is recommended that a pre start
inspection programme on all machines is implemented together with a scheduled safety tour focusing on
machinery to ensure they are in good condition..
A further recommendation would be to review the maintenance program of the machines in the workshop to
ensure they are fit for purpose based on machine usage, age and recommendation from manufacturer
instructions.
Observation 15 - Refer to observation sheet
There appears to be little control over vehicle/pedestrian interaction in the main workshop. On a number of
occasions pedestrians crossed the path of a fork truck in the main workshop. There was no vehicle
pedestrian segregation, or other traffic control measures in place. There was no evidence of a risk
assessment to identify the hazards, who might be harmed or suitable controls that need to be in place.
It is recommended that immediate controls are put in place to reduce the risk as far as reasonably
practicable, such as using the fork truck or other vehicles in the main workshop during out of hours activities
or during lunch breaks so removing pedestrians from the building while vehicles are in use and setting
appropriate maximum speed limits inside the workshop building i.e. 5 MPH.
It is recommended that a full vehicle pedestrian interaction risk assessment be conducted identifying the
hazard, who might be harmed, and identifying suitable and sufficient control measures to reduce the risk of
collision to as low as reasonably practicable, such as segregation procedures, speed restrictions on vehicles
information and training.
Failure to have a suitable and sufficient risk assessment is in breach of the Management of Health and Safety
Regulations and could potentially lead to enforcement notices being issued impacting on the business output,
reputation and employee morale. If enforcement notices are upheld the company could potentially receive
fines or individuals being imprisoned.
The Workplace (Health, Safety and Welfare) Regulations also require safe interaction between vehicles and
pedestrians.
Observation 19 - Refer to observation sheet
One of the machines in the workshop was generating a high level of noise when being operated. Although
the machinist was wearing ear protection other individuals working in close proximity were not wearing
hearing protection. Following discussions with the supervisor no noise surveys had been carried out to
determine individuals daily exposure levels and if they were exceeding the lower exposure action value of
80db(A)Lep.d.
-
It is recommended as an immediate control measure to restrict the machines operation to when the majority
of the individuals are not present for example out of hours or during breaks.
If this is not possible ensure all employees in the workshop wear hearing protection when the machine is
operating.
It is recommended the company carry out an adequate noise survey to determine the exposure levels of its
employees, should the survey show the exposure level breaches the upper exposure limit of 85db(A)Lep.d
implement plans to reduce the noise exposure by relocating the machine. If the machine cannot be
relocated then consider installing an acoustic booth around the machine or screening the machine from other
individuals working in the workshop. Installing noise dampening materials on the walls and ceilings can also
reduce the noise impact.
The company is at risk of being in breach of the Control of Noise at Work Regulations 2005 as it cannot
demonstrate they have carried out adequate assessment of noise within the workshop so they do not know
the noise levels they are exposing their employees to.
Conclusions
This report has identified several failings in the health and safety management system, and breaches of
legislation. Each of the breaches of legislation could lead to a fine of up to 20,000 or imprisonment of up to
12 months. More serious breaches that result in a major or fatal injury could lead to unlimited fines and up
to two year imprisonment.
In addition to these legal issues, the cost of accidents in these areas could have a serious financial impact on
the company. Lost production time, training costs, increased insurance premiums, management time and
many other costs could result. Spending the money required now will have much greater savings in the long
term.
Additionally, the company has a moral duty of care to look after employees. It is not acceptable to have
employees at work who are at risk of being injured, or even worse, not going home at all.
For these reasons, it is important that the deficiencies identified are addressed within the timescales given.
Recommendations
Recommendation Likely resource implications Priority Target date
Competent individuals to conduct a
suitable and sufficient Working at
Height Risk Assessment and
implement appropriate controls to
minimise the risk to as low as
reasonably practicable
Resources required will be Contractor
personnel and Company Contracts
Manager. Depending on the roof
repair specification and terms and
conditions of the contract the cost of
the assessment and the
implementation of control actions sit
with the contractor. Estimated costs
3000
High 22nd November
-
Recommendation Likely resource implications Priority Target date
Carry out a formal investigation into
the failure of the contractor
management system. Set up
routine inspection of the emergency
escape routes.
Set up an investigation team,
consisting of a competent investigator
and company contract manager.
Further internal resources will be
required to modify the contractor
management system based on the
finding of the investigation. Although
not a direct cost, these individuals will
not be able to carry out their normal
working duties during the
investigation and implementation of
corrective actions. Estimated costs
1500
Medium End December
2012
Carry out repair to machine guard.
Review maintenance requirements
and schedule.
An external cost will be incurred to
bring in a machine specialist to
repair/replace the guard. An internal
cost will be incurred carrying out a
review of the maintenance
requirements and scheduled and there
will be a cost associated with
production losses as the machine will
be out of use until the guard is fixed.
Estimated cost 4000 for the repair
High 22nd November
Carry out a suitable and sufficient
vehicle and pedestrian interaction
risk assessment and implement
appropriate controls.
A team of employees from across the
company assisted by an external
vehicle/pedestrian consultant. The
large cost will be the design and
installation of any segregation controls
such as barriers and markings.
Estimated costs 20000
High February 2013
Carry out Noise Survey to determine
individual exposure rates and
sources of noise.
A competent external specialist would
need to be employed. 1 to 2 hour
awareness training session need to be
set up for all employees. Further
engineering requirements to reduce
noise exposure levels over the coming
12 months.
High December
2012