Rubblization and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling

Upload: hoangkhuong

Post on 25-Mar-2018

219 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Rubblization and Perpetual Pavement Save Money and

ResourcesNational Symposium

onHMA Energy & Recycling

Page 2: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

HMA Overlay of PCC Pavement

• Surface Preparation– Cut & Patch with Saw & Seal– Crack & Seat– Break & Seat– Rubblization

• HMA Overlay– Thickness– Mix Type

Page 3: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Purposes for OverlayingPCC Pavements

• Improve ride quality• Correct surface defects

– improve surface drainage– increase surface friction

• Delay/prevent structural deterioration• Strengthen pavement structure

(rehabilitation)

Page 4: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

HMA

PCC

Larger Pieces = Larger Movement = Cracking

Page 5: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

HMA

PCC

Smaller Pieces = Smaller Movement = No Cracking

Page 6: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Rubblization•Fracturing:

•Eliminates slab action•Destroys bond between concrete and steel

•Rubblized base responds as a tightly keyed, interlocked high-density, unbound layer

•Layer cannot crack; already fractured

Page 7: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Why Rubblize?• Fracturing PCC to segments less than

9” precludes reflection of:– Joints– Cracks– Faults

• Production Rates up to 1 lane-mile/day

Page 8: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Benefits• Time savings

– Choose work hours– High production rates

• Economic Savings– Reduce user delay costs– Reduce construction costs

Page 9: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

• Environmentally friendly– Reduce landfill– Reduce fuel consumption/air pollution

• Smoothness– Eliminate reflection cracking/faulting

Benefits (continued)

Page 10: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Resonant Pavement Breaker

Page 11: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Multi-Head Breaker (MHB)

Page 12: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Rolling

Page 13: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Particle Size• PCC fractured into 9

in.-minus pieces• Most pieces are 1- 4

in. diameter• Aggregate interlock

maintained beneath surface

• Rolling knits together surface particles

Page 14: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

When to RubblizePatching > 10%.Severe D-cracking.Severe ASR or ACR cracking.Dowel bar lockingSevere joint deteriorationPersistent faulting.

Page 15: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

How Effective is Rubblization?

• Witczak and Rada, 1992– "Rubblization . . . is the preferred

rehabilitation method for all types of PCC pavements."

• Thompson, 1999– Rubblization is a "viable and cost-effective

rehabilitation option."

Page 16: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

How Effective is Rubblization?

• 39 States have had Rubblization projects

• Arkansas– 383 miles of rubblized and overlayed

primary routes• Performance Projections: Over 20 years

before PCR = 70

Page 17: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

An Example of Economics

• Interstate Highway– 40,000 ADT– 4 Lanes– Existing Concrete Pavement– Condition Suitable for Rubblization or Replace

• 3 Alternatives– Rubblization and Overlay– Unbonded Concrete Overlay– Remove and Replace

Page 18: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Oklahoma Bid Prices

• HMA in place $60/ton @ 145 lb/ft3

• PCC in place $34.44/SY @11" thick and $27.78/SY @ 8” thick

• PCC removal $40/CY• PCC Patch $100/SY• HMA milling $2/SY-INCH• Rubblization: ~ $1.50/SY

Page 19: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

First Cost Comparisons

• One Lane-Mile (7040 SY)• Case 1: Rubblization with Perpetual

Pavement• Case 2: Unbonded PCC Overlay• Case 3: Remove PCC and Replace with

PCC

Page 20: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

20

Page 21: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Case 1

• Perpetual Pavement with Rubblization– Rubblize 11” PCC– Overlay with 8” HMA

• Initial Cost:

$10,5601.50/SYRubblize

$215,424TOTAL

$183,74460.00/tonHMA Overlay

$21,1204.00/lfEdge Drains

TotalUnit Cost

Item

Page 22: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Case 2

• Unbonded PCC Overlay– 10% Patching– Bond Breaker – 2”

HMA– Overlay with 8” PCC

• Initial Cost:

$70,400100.00/SYConcrete Patching

$195,57127.78/SYPCC

$311,907TOTAL

$45,93660.00/tonBond Breaker

TotalUnit Cost

Item

Page 23: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Case 3

• Remove/Replace PCC – Remove PCC– Replace with 11” PCC

• Initial Cost:

$242,45834.44/SYPCC Placement

$328,502TOTAL

$86,04440.00/CYRemove PCC

TotalUnit Cost

Item

Page 24: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Initial Cost Comparison

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

$ pe

r Lan

e-M

ile

Rubblize &Overlay

PCC Overlay Remove/ReplacePCC

+45% +52%

Page 25: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

General Experience

• First Cost: Rubblization ~ 1/3 the cost of remove/replace

• Speed of Construction: days vs. weeks• Impact of User Costs?

Page 26: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

User Costs• Use FHWA Guidelines for Life Cycle Cost

Analysis• Work Zone:

– Speed Change – VOC– Speed Change – Delay– Speed Change – Reduced Speed

• Queuing– Stopping – VOC– Stopping – Delay– Idle Time– Added Travel Time

Page 27: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Work Zone User Cost Rates

0

5

10

15

20

25

30

35

Passenger Car Single Unit Truck Combination Unit Truck

$/v

eh/h

r

July 2006 Dollars

Page 28: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Work Zone Assumptions

• 1 mile long• 4 lanes • One lane open each direction during work• 40,000 ADT

Page 29: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Case 1• Rubblization: One lane-mile/day production

– Paving: 2 lane-miles/day– Sequence

• 3” bottom lift• 3” 2nd lift• 2.5” 3rd lift• 2.5” 4th lift

– 24 hour closure until 2nd asphalt lift– 12 hour closure each for 3rd and 4th

• User Cost = $138,714

Page 30: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Case 2

• Unbonded PCC Overlay– Patching: 350 SY/day ~ 2 days – 24 hr/day– Curing: 3 days – 24 hr/day– Bond Breaker: 2 lane-miles/day – 4 hr– Set Dowel Baskets: 1 mile/day – 8 hr– Paving: 0.75 mile/day – 11 hr– Curing: 14 days – 24 hr/day

• User Cost = $2,601,161

Page 31: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Case 3

• Remove/Replace PCC– Removal: 200 SY/day ~ 3.5 days – 24 hr/day– Trim Base: 1 mile/day – 8 hr– Set Dowel Baskets: 1 mile/day – 8 hr– Paving: 0.75 mile/day – 11 hr– Curing: 14 days – 24 hr/day

• User Cost = $2,471,103

Page 32: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

User Costs

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

$ pe

r Lan

e-M

ile

Rubblize &Overlay

PCC Overlay Remove/ReplacePCC

Page 33: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

References

Page 34: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Perpetual Pavements

• Save asphalt and aggregate over the long term. It’s sustainable.

• Lower Life Cycle Cost• Lower User Cost

Page 35: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Concept

Max Tensile Strain

Pavement Foundation

High ModulusRut Resistant Material(Varies As Needed)

Flexible Fatigue ResistantMaterial 75 - 100 mm

40-75 mm SMA, OGFC or Superpave

}100 mmto150 mm

ZoneOf High

Compression

Page 36: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Perpetual Pavementversus

Conventional Design

0

5

10

15

20

25

0.1 1 10 100 1000

Traffic, ESAL

HM

A T

hick

ness

, in.

AASHTO HighPerRoad

Page 37: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Comparison of Structures

Mill 2”/Overlay 3”50

Reconstruct with 8” HMA35

10% Patching + Mill 2”/Overlay 3”

25

Mill 2”/Overlay 3”15

6” HMA/10” Base0

ActivityYear

------50

Mill 2”/Overlay 2”48

Mill 2”/Overlay 2”33

Mill 2”/Overlay 2”18

11” HMA/6” Base0

ActivityYear

Conventional Perpetual

Page 38: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

252350Asphalt Binder**

1,9014,7973,1686,659Aggregate1,6832,337RAP

1,9016,7323,1689,346Total1,18850

792483,16835

792331,42625

792181,18815

1,9014,3563,1682,3760Gravel Base*HMA*Gravel Base*HMA*Year

Perpetual Pavement (tons/lane-mile)

Conventional (tons/lane-mile)

Page 39: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Material Usage

0

5000

10000

HM

A, t

ons

Conv. Perp. Pvmt.0

1000

2000

3000

RA

P, to

ns

Conv. Perp. Pvmt.

0

5000

10000

Agg

rega

te,

tons

Conv. Perp. Pvmt. 0100200300400

Bin

der,

tons

Conv. Perp. Pvmt.

Save 32% Save 28%

Save 31% Save 28%

Page 40: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Costs

0

50000

100000

150000

200000

250000

300000

350000

400000

Tot

al L

ife C

osts

, $

Conv. Perp. Pvmt.

Save 44%

Page 41: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Summary

• Rubblization saves:– Time – especially for users– Money – about 50% for agencies, 17X less user costs– Materials

• Perpetual Pavements saves:– Asphalt– Aggregate– RAP– Money

• Need to apply proper solutions.• Need to apply engineering principles.• DON’T SACRIFICE QUALITY!

Page 42: Rubblization and Perpetual Pavement Save Money … and Perpetual Pavement Save Money and Resources National Symposium on HMA Energy & Recycling HMA Overlay of PCC Pavement • Surface

Other Ideas

• Get Pavement considered as part of solution to road noise – Lower Noise Barriers by 3 ft by resurfacing with a low noise asphalt!