RSRDC. UNIT- II, AJMER. ORGANISATION CHART OF RSRDC UNIT-II, AJMER. P.K.Arora. Vacant (Addl. Charge to Sh. Sunil jain. ARE. Sh. Lokesh Gupte Sh. Lalit Sharma. 3. Sh. Ashish Sharma 4. Sh. Harsh Rai. Financial Work Load in Unit. Rs. In Lacs. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/1.jpg)
RSRDC
UNIT- II, AJMER
![Page 2: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/2.jpg)
ORGANISATION CHART OF RSRDC UNIT-II, AJMER
P.K.Arora
ARE1. Sh. Lokesh Gupte
2. Sh. Lalit Sharma
3. Sh. Ashish Sharma
4. Sh. Harsh Rai
Vacant(Addl. Charge to Sh. Sunil jain
![Page 3: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/3.jpg)
Financial Work Load in UnitS.
No. Name of Work Client Deptt. A& F Sanction Expenditure till date
Balance Work
ARE – I Sh. Lokesh Gupta
1 Construction of ROB with approaches (Excluding railway portion) on Dholpur-Rajakhera road Km-3 on SH-2
PWD 1000.00 579.43 420.57
2 Construction of ROB with approaches at LC No. 472 (1305/6-8 Mania-Marena road) Jhansi-Agra Section.
PWD 1000.00 0.03 999.97
ARE – II Sh. Lalit Sharma
1 Construction of 2 lane ROB with approaches (excluding Railway portion) at MDR 37-A on Nagour-Basni Road in lieu of LC No. 63-C (On NH-89)
PWD 1300.00
ARE – II 600.00 191.45 408.55
ARE - IV 700.00 197.41 502.59
Rs. In Lacs
![Page 4: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/4.jpg)
S. No. Name of Work Client
Deptt.A& F
SanctionExpenditure
till dateBalance
Work
ARE – III Sh. Ashish Sharma
1 Construction of ROB & approaches on Bhilwara -Chittorgarh BG Track at Bhilwara. (UIT Work)
UIT Bhilwara
2086.00 1327.31+
385.00(Rly.)
373.69
ARE – IV Sh. Harsh Rai
1 Construction of ROB & approaches on Phalodi-Mandal-Bhilwara road in lieu of LC No. 63-C
PWD 1000.00 870.32 129.68
2 Construction of ROB on Manglana - Makrana road in lieu of LC No. 36 Kuchaman city Makrana section SH-2B
PWD 1000.00 305.16 694.84
ARE – V Sh. Brijesh Mathur of Unit-I,Ajmer
1 Construction of ROB in Km. 70 of Kishangarh -Roopangarh road SH-07 in lieu of LC No. 28 NWR.
PWD 1000.00 843.67 156.33
2 Construction of ROB (excluding Railway portion) and approaches on Ajmer-Beawer road in lieu of LC No. 5A/2E
PWD 1000.00 783.28 216.72
![Page 5: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/5.jpg)
Regional Pollution Control Board office, Bhilwara
Completion Cost – Rs. 23.97 lacs
Important Works Completed during last 5 years
![Page 6: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/6.jpg)
Construction of ROB at Kishangarh, Ajmer
Total Cost : Rs. 10.00 Crores
Location : Kishangarh, Ajmer
Date of Start : 18.03.2007
Stipulated Date of Completion : 17.01.2008
Expenditure till Date : Rs. 843.96 Lacs
Likely Completion date : 30.6.2010 (Depends on Railway work)
Bottlenecks if any : Two nos span and finishing dependant on railway work
Status of railway work : Sub structure work completed. Idle since last six months due to finalisation of drawing & design of super structure.
![Page 7: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/7.jpg)
Construction of ROB at Saradhna, Ajmer
Total Cost : Rs. 10.00 Crores
Location : Beawar road, Ajmer
Date of Start : 17.07.2007
Stipulated Date of Completion : 16.06.2008
Expenditure till Date : Rs. 783.56 Lacs
Likely Completion date : 31.12.2010 (Depends on Railway work)
Bottlenecks if any : Gap slab connecting rly. portion and finishing dependant on railway work
Status of railway work : Lay out & shifting of cable work in progress.
![Page 8: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/8.jpg)
Construction of ROB at Bhilwara(UIT Work)
Total Cost : Rs. 20.86 Crores
Location : Bhilwara
Date of Start : 18.03.2007
Stipulated Date of Completion : 17.11.2007Expenditure till Date : Rs. 1327.31 lacs + Rs385.00 lacs (Rly.)Likely Completion date : 31.05.2010 (Depends on Railway work)
Bottlenecks if any : Two nos span and finishing dependant on railway work
Status of railway work : Sub structure work completed.
Super structure work in progress.
![Page 9: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/9.jpg)
Construction of ROB at Mandal (Bhilwara)
Total Cost : Rs. 10.00 Crores
Location : Mandal, Bhilwara
Date of Start : 19.07.2007
Stipulated Date of Completion : 18.06.2008Expenditure till Date : Rs. 870.46 LacsLikely Completion date : 30.06.2010 (Depends on Railway work)
Bottlenecks if any : Two nos span and finishing dependant on railway work
Status of railway work : Sub structure work in progress.
![Page 10: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/10.jpg)
Construction of ROB at Makrana Distt. - Nagour)
Total Cost : Rs. 10.00 Crores
Location : Makrana, (Distt.-Nagour)
Date of Start : 23.08.2008
Stipulated Date of Completion : 22.07.2009Expenditure till Date : Rs. 390.67 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)
Bottlenecks if any : Shifting of electric lines & encroachments.
Status of railway work : Work order placed. Work yet not started.
![Page 11: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/11.jpg)
Construction of ROB at Nagour
Total Cost : Rs. 13.00 Crores
Location : Nagour
Date of Start : 21.08.2008
Stipulated Date of Completion : 20.07.2009Expenditure till Date : Rs. 405.45 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)
Bottlenecks if any : -
Status of railway work : Work order issued. Work yet not started.
![Page 12: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/12.jpg)
Construction of ROB at Dholpur
Total Cost : Rs. 10.00 Crores
Location : Dholpur
Date of Start : 17.11.2007
Stipulated Date of Completion : 16.10.2008Expenditure till Date : Rs. 609.36 lacs.Likely Completion date : 30.09.2010 (Depends on Railway work)
Bottlenecks if any : -
Status of railway work : Work order issued. Work yet not started.
![Page 13: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/13.jpg)
Construction of ROB at Mania-Marena Road
Total Cost : Rs. 10.00 Crores
Location : Mania, Dholpur
Date of Start : -
Stipulated Date of Completion : -Expenditure till Date : Rs. 0.03 lacs.Likely Completion date :
Bottlenecks if any : The present LC No. 472 is a part of Bye pass for ROB at LC No. 463. Hence traffic is to be bye passed at LC No. 473 which requires interlocking. Railway has agreed for interlocking & up gradation. Which shall be completed by Feb-2010. Revised A&F required amounting to Rs. 16.15 Crore Estimate Submitted to CE PWD through ACE Zone Bharatpur
Status of railway work : Revised GAD pending at Railway part for approval, likely to be received in Dec. 2009’
![Page 14: RSRDC](https://reader034.vdocuments.site/reader034/viewer/2022051821/56815a91550346895dc80512/html5/thumbnails/14.jpg)
Proposed New WorksS. No. Name of Work Client Deptt. Mode Estimated Cost
1 Construction of Academic block at MLV Textile & Engineering College, Bhilwara
MLVT, Bhilwara Actual plus Rs. 350.00 lacs
2 Construction of Urban Co Operative bank at Shastri Nagar Bhilwara
BUCB Bhilwara Actual plus Rs. 50.00 Lacs