rsrdc unit- iii jaipur. organisation chart re sh. a.m. khan are sh. rajesh gupta are sh. s.k....

13
RSRDC UNIT- III JAIPUR

Upload: holly-morton

Post on 05-Jan-2016

234 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

RSRDC

UNIT- III JAIPUR

Page 2: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

ORGANISATION CHART

RESh. A.M. Khan

ARESh. Rajesh Gupta

ARESh. S.K. Chejara

ARESh. V.B.Mathur

ACCOUNTANTSh. B.C. Jain

ARESh. Rakeev

Gupta

JENSmt. Alka

Mathur

Page 3: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

Financial Work Load in Unit

S. No.

Name of Work Client Deptt.

A& F Sanction

Expenditure till date

Balance Work

ARE – I Sh Rajesh Gupta

1 USQ & LSQ at Chainpura

Home 1244.19 816.31 427.88

ARE – II Sh.S.K. Chejara

1 Satsang Bhawan at Shri Radha Govind Deoji temple, Jaipur

Trust 400.00 325.77 74.23

ARE – III Sh.V.B. Mathur

1 Research Hospital at RHSU, Pratap Nagar

Medical 1000.00 677.76 322.24

Total 824.35

Rs. In Lacs

Page 4: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

Important Works Completed during last 5 years

Page 5: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

AMBEDKAR BHAWAN, JAIPUR

Completion Cost – Rs. 3.83 Crs.

Foundation Stone laid by Hon’ble Chief Minister on 14.04.2005

Inaugurated by Hon’ble Chief Minister on 14.04.2006

Page 6: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

RAJASTHAN HEALTH SCIENCE UNIVERSITY, JAIPUR

Completion Cost – Rs. 4.60 Crs.

Foundation Stone laid by Hon’ble Chief Minister on 08.12.2005

Inaugurated by Hon’ble Chief Minister on 10.12.2007

Page 7: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

Important Works in Progress

Page 8: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

POLICE HOUSING SCHEME

No. of Quarters : 200 Nos. LSQ and 8 Nos. USQ

Total Cost : Rs. 12.44 Crores

Location : Chainpura, Jaipur

Date of Start : 28-02-2008

Stipulated Date of Completion : 30-06-2009

Expenditure till Date : Rs. 8.16 Crores

Likely Completion date : 31-01-2010

Bottlenecks if any : slow progress by contractor

Page 9: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

Satsang Bhawan at Shri Radha Govind Deoji temple, Jaipur

Total Cost : Rs. 4.0 CroresLocation : Shri Radha Govind

Deoji temple, JaipurDate of Start : July, 07Date of Completion : September, 09Expenditure till Date : Rs. 3.26 CroresLikely Completion date : 31-12-2009Present Status : Structure work

completed, Finishing work in progress

Page 10: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

Research Hospital at RHSU, Pratap Nagar, Jaipur

Total Cost : Rs. 10.00 CroresLocation : Pratap Nagar, JaipurDate of Start : Jan, 08Date of Completion : March, 09Expenditure till Date : Rs. 6.77 CroresLikely Completion date : 30-06-2010Bottlenecks if any : Work stopped as client has not deposited money

Page 11: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

Monitoring of Toll ProjectsS. No.

Name of Work Mode Construction Cost

Concession Period

Toll Collection Agency

1 Masi Bridge on Sanganer-Malpura Road (SH-12)

Actual Plus

Rs. 161.59 lacs

13 Years 05 Months & 01 Days(upto 22-12-2020)

Departmental (Tender for toll contract under process)

2 Chomu-Ajitgarh-Shahpura Road

Actual Plus

Rs. 2223.15 lacs

14 Years 11 Months & 22 Days(upto 01-09-2014)

Departmental (Tender for toll contract under process)

3 Chala- Neem ka Thana –Kotputli Road

Tender Rs. 1809.00 lacs

6 Years 02 Months & 27 Days(upto 06-10-2010)

M/s Ramfool Gurjar, Bhiwadi

Page 12: RSRDC UNIT- III JAIPUR. ORGANISATION CHART RE Sh. A.M. Khan ARE Sh. Rajesh Gupta ARE Sh. S.K. Chejara ARE Sh. V.B. Mathur ARE Sh. Rakeev Gupta JEN Smt

Proposed New Works

S. No.

Name of Work Client Deptt. Mode Estimated Cost

1. Buildings for different Bards near Ambedkar Bhawan

Social Justice and Empowerment Deptt.

Actual plus

Rs. 3.40 Crores