rollovers and contributions implementation update 30... · rollovers and contributions –...

19
Business Engagement Forum Presented by Tracie Crowden Australian Taxation Office | 30 June 2016 Rollovers and Contributions – Implementation Update

Upload: phungcong

Post on 18-Nov-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Business Engagement Forum

Presented by Tracie Crowden

Australian Taxation Office | 30 June 2016

Rollovers and Contributions –

Implementation Update

Page 2: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

B2B G2B B2G

Fund to Fund

Rollovers

2015

2016

2017

2018

2014

Employer to Fund

Contributions

ATO to Fund

Rollovers

ATO to Fund

Contributions Fund to ATO

member attributes

Fund to ATO

Rollovers

Fund to ATO

contribution totals

Business To

Business Government

To Business

Business To

Government

UNCLASSIFIED | SuperStream Business Engagement Forum

Introducing government transactions into SuperStream

• Fund Validation Service (FVS) – list of APRA Fund electronic end service addresses and bank accounts for data

and payments

• SuperTICK – allows funds to correct member TFNs supporting rollovers and contributions

• EmployerTICK – allows employers to correct employees TFNs during on-boarding

• Electronic Portability Form (EPF) – allows a member to request a fund to fund rollover through MyGov

ATO support a number of services

that assist industry make accurate

transactions and correct their

registry data

OCT

2016

MAY

2017

NOV

2017

OCT

2018

JAN

2017

SuperTICK V3

Open and

Closed Accounts

Page 3: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

ROLLOVERS V2 IMPLEMENATION UPDATE

UNCLASSIFIED – SuperStream Business Engagement Forum 3

Page 4: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Rollovers v2.0 – industry readiness

UNCLASSIFIED | SuperStream Business Engagement Forum 4

Key dates:

• B2B – by 11 Nov 2016 - existing industry rollovers upgraded to v2

• G2B – by 16 Dec 2016 - receive/support ATO to fund rollovers of unclaimed super

monies (USM)

• B2G – Nov 2017 - Fund to ATO rollovers of USM and s20c notices for temporary

residents USM

• Complete readiness checklists for production cutover

15 Sept 2016 (B2B) and 15 Oct 2016 (G2B)

Summary of Industry response to APRA/ATO letter April 2016 (published on SIPO)

• Responses received from majority (194 large APRA funds and 100% of small APRA

funds)

• 5 funds have indicated that they will not meet the designated Oct/Nov production

cutover windows;

• ATO will be working with gateway operators and their clients to schedule funds for

production cutover

• Funds have indicated readiness for G2B testing with ATO from August;

Early adopters - after gateways have completed interoperability testing expected to

commence in July.

Page 5: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Rollovers v2.0 – Industry readiness - continued

UNCLASSIFIED | SuperStream Business Engagement Forum 5

ATO is coordinating interoperability testing for Gateway Operators for B2B and G2B

current status of gateway readiness for testing is as follows:

Page 6: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Rollovers v2.0 – testing and transition process

6 UNCLASSIFIED | SuperStream Business Engagement Forum

Timeline – B2B and G2B

Nov 2017 S.20C Notices

Ready to send Business

to Govt Rollovers

Nov 2016 G2B Production

cutover commences

based on USM

aggregation.

(Ready to receive

Govt Rollovers)

Effective dates

B2B Testing

and readiness

Gateway

interoperability and

Peer to Peer

testing

Readiness

notification

15/9 Oct 2016 Production cutover for

B2B commences

coordinated through

Gateway operators

and their clients

(Ready to receive

Industry Rollovers V2)

Integration

testing between

Service Provider

and Funds

• Peer to Peer ( with ATO)

testing in EVTE – conformance

suite

• Coordinated based on the

number of registry solutions

• Gateway

interoperability

testing in EVTE

commences

• Integration testing

between funds

and solution

providers can

occur in parallel

Readiness

notification

15/10

FVS updated

/monitored

G2B Testing

and readiness

April 2016 - Industry provide

readiness dates

- First RIWG

B2B Testing Cycle

G2B Testing Cycle

Sept Jul Jun Aug

Key Milestones

- Jul G2B testing in

EVTE commences

- Production cutover

schedules published

- Sept/Oct – On

completion

of P2P testing

FVS readiness

indicator updated

4 Wk Prod cutover

17/10-11/11

4 Wk Prod cutover

15/11 - 16/12

Page 7: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Rollovers v2.0 – Artefacts to support release

UNCLASSIFIED | SuperStream Business Engagement Forum 7

• Taxonomy updates – published November 2015

• Updated schedules 2, 3 and 6 – published 8 December 2015, updated 30 April 2016

• Change scenarios – published Feb 2016

• Rollover user guide – published March 2016

• Rollover schematron – 31 March, final end of June 2016

• Conformance suite – outline 8 April, draft published 22 April – final end June 2016

• ATO external vendor testing environment (EVTE)

available for gateway interoperability testing – from 21 July 2016

Funds – P2P testing from August 2016 onwards

• Rollover Transition Guide – Draft published May 2016 – finalised July 2016

• Production cutover plan/process – draft Mid July – finalised by end of July 2016

Page 8: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Testing and Production cutover approach

UNCLASSIFIED | SuperStream Business Engagement Forum 8

B2B – V1 to V2

• Funds can use the readiness details published

on SIPO to assist with determining a suitable

test partner for P2P testing*

• ATO to coordinate with Gateway operators to

coordinate production cutover dates for their

clients by end of Jun 2016

• ATO to publish draft production cutover plan

by mid July and final by end of July 2016

• FVS will be updated prior to production.

• Production cutover commences in Oct based

on:

Wk 1: Move some large gateways and

selected funds into production -

confirm integrity of implementation

Wk 2: Next tranche of gateways and

their clients

Wk 3: SAFs tranche

Wk 4: Remainder of trustees

G2B – ATO to fund Rollovers

• Gateway Operators commence interoperability

testing in EVTE from Mid July (opportunities

for earlier connectivity testing to be

undertaken)

• ATO is working with Gateways to coordinate

the schedule for interoperability testing

• Funds have indicated readiness for peer to

peer testing from August onwards will be

coordinated through Gateways*

• ATO to identify and coordinate with the registry

solution providers not necessarily every fund.

• FVS updated prior to production. Cutover in

Nov will be based on:

Wk 1:

Wk 2:

Wk 3:

Wk 4:

* Feedback welcome

Weekly on boarding cycle

to be determined based on

USM aggregation

Page 9: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

G2B testing in EVTE – What is proposed

UNCLASSIFIED – SuperStream Business Engagement Forum 9

DRAFT

Page 10: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Fund Validation Service changes

UNCLASSIFIED | SuperStream Business Engagement Forum 10

The FVS will be updated

B2B - after trustees notify of readiness to receive in v2 of the standard, and

G2B - on completion of testing with ATO for G2B.

Details of who and how FVS will be update will be determined shortly

Trustees will need to be able to send new values (FVS Update) and retrieve new

values (FVS Get and List) to accurately manage the change.

New values will include:

• ROLL2.0-X: able to receive industry rollovers v2

• GROL2.0-X: able to receive Government rollovers v2

• CONT2.0-X: able to receive industry contributions v2

• GCON2.0-X: able to receive Government contributions v2

Page 11: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Current focus of ATO rollovers readiness team

UNCLASSIFIED | SuperStream Business Engagement Forum 11

Finalising design and documentation to support testing in EVTE including scope

resources/responsibilities, points of contact, test data, process etc.

ATO acknowledges feedback about previous experiences with EVTE and are

looking to upgrade performance and provide additional resources to support

rollover testing in EVTE. The data set and business scenarios that will be used in

EVTE are also consistent with standards and patterns industry are using/designing.

Further details of production cutover approach including nerve centre, production

support model and production cutover schedules and certification processes to be

finalised by end of July

Regular updates and feedback provided to/through Rollover Implementation

Working Group – contact Super Stream [email protected]

Page 12: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

CONTRIBUTIONS V2 IMPLEMENATION UPDATE

UNCLASSIFIED – SuperStream Business Engagement Forum 12

Page 13: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Contributions v2

UNCLASSIFIED | SuperStream Business Engagement Forum 13

• Consultation Contributions draft v2 published on 15 March

• Principally adding government contributions, introducing new functionality to

contribution interactions to enable automated processing of amendments (G2B),

and incorporating refund design and relevant guidance notes. Scope of

release includes all trustees and payrolls for B2B and all trustees and

Government for G2B contributions.

• This release was originally targeted at the May 2017 release window to coincide

with an anticipated Single Touch Payroll upgrade - the timing of Single Touch

Payroll rollout has now changed based upon the Government announcement in

December 2015

• The need for further consultation on timing and scope was acknowledged at the

Business Engagement Forum in March and the subsequent ATO/APRA letter

Page 14: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Contributions v2

UNCLASSIFIED | SuperStream Business Engagement Forum 14

The ATO has now revisited the scope of the May 2017 upgrade, noting that

deferring the contributions G2B change is not considered possible without it being

possibly deferred indefinitely and forgoing the benefits involved.

• The ATO is proceeding with a G2B release in May 2017 based upon the

published Contributions V2 MIG, and will allow Trustees to implement over a

three month period.

• The existing contributions (B2B) standard will continue to run in parallel, whilst

the experience of implementing V2 utilising G2B is refined with Trustees.

• Implementation of the contribution V2 B2B changes will be scheduled to align

with a future single touch payroll change.

Page 15: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Contributions v2

UNCLASSIFIED | SuperStream Business Engagement Forum 15

Benefits of revised approach:

• Manage any risk associated with the single touch payroll change, in particular allow for

finalisation of the Superannuation reporting event, and possible changes from the Single

Touch Payroll Pilot

• Created an opportunity for further refinement and return on investment from the

implementation of contributions V1, in particular for trustees to continue to refine internal

changes supporting the implementations.

• Would allow further consideration and consultation on possible improvements for B2B V2

implementation

• Will enable trustees to focus on implementing the G2B contributions design

This position has been tested with a small group of trustees and subsequently the

Superstream Reference Group. Both supported the revised position.

As part of finalising release documentation during July 2016, the ATO will further

investigate and advise on managing any impacts of the change.

Page 16: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Contributions v2.0 - upgrade process

16 UNCLASSIFIED | SuperStream Business Engagement Forum

Timeline of change

S.20C Notices

Ready to send Business

to Govt Rollovers

May 2017

Effective dates

Peer to ATO

testing

G2B

Client

Integration

testing

March 2017

Readiness

notification

G2B Testing and

readiness

July 2016 Final Contribution V2

Published

G2B Testing Cycle Aug 2017

Implement

G2B

Contributions

Nov 2017 July 2018

Possible Realignment

with STP

Proposed/Scheduled

Page 17: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Contributions v2.0 Artefacts to support release

UNCLASSIFIED | SuperStream Business Engagement Forum 17

• Contributions V2.0 MIG – updated Draft 1 July, Final 22 July 2016

• Taxonomy updates – 18 August 2016

• Updated schedules 2, 3, 5 and 6 – Draft 1 July, Final 22 July 2016

• Change scenarios – Draft 1 July, Final 22 July 2016

• Cutover Plan – 22 July 2016

• Conformance suite – 22 July 2016

• Contribution schematron – 29 July 2016

• ATO external vendor testing environment – September 2016

• Contribution user guide – TBC

* All documents released in draft

Page 18: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Contributions v2

UNCLASSIFIED | SuperStream Business Engagement Forum 18

• Next Steps

• Feedback from the Business Engagement Forum

• Updated documents issued for review

• Consultation with industry and SuperStream Technical Committee

• Issue final technical documents 22 July

• Provide change scenarios and cutover plan for G2B implementation

• Outline process for managing alignment to STP design and consideration of

B2B change

Page 19: Rollovers and Contributions Implementation Update 30... · Rollovers and Contributions – Implementation Update . B2B G2B B2G Fund to Fund Rollovers ... EVTE are also consistent

Questions/Feedback Super Stream [email protected]

19 UNCLASSIFIED | SuperStream Business Engagement Forum