TRANSCRIPT
![Page 1: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/1.jpg)
Rockford PowertrainTraining Workshop
Process Capability
and Cpk
![Page 2: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/2.jpg)
Training materials, reference documents, and functional SPC templates are available free on the Rockford Powertrain web
site. Go to:
www.rockfordpowertrain.com/supplier
![Page 3: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/3.jpg)
Process Capability
• Enables successful manufacturing and sales
• Prevents scrap, sorting, rework
• Allows jobs to run well
• Has major impact on cost and schedule
![Page 4: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/4.jpg)
“Process Capability”
is the ability of a process to make a feature
within its tolerance.
![Page 5: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/5.jpg)
Everything Varies (and the variation can be seen if we measure precisely enough)
• Heights• Weights• Lengths• Widths• Diameters• Wattage• Horsepower• Miles per Gallon
• Pressure• Roughness• Strength• Conductivity• Loudness• Speed• Torque• Etc. etc. etc.
![Page 6: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/6.jpg)
Eli Whitney in 1798• Won a U.S. Military contract to supply 10,000 guns• Reduced variation and created interchangeable parts for
assembly and service by:– Installing powered factory machinery– Using specialized fixtures, tools, jigs, templates, and end-stops– Creating drawings, routings, operations & training
![Page 7: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/7.jpg)
Manufacturing in the 21st Century• International competition to provide defect-free products
at competitive cost• Reducing variation and providing interchangeable parts
for assembly and service by:– Using machine tools– Using specialized fixtures, tools, jigs, templates, and end-stops– Using drawings, routings, operations & training
![Page 8: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/8.jpg)
Graphing the tolerance and a measurement
It’s useful to see the tolerance and the part measurement on a graph.Suppose that:
.512 .513 .514 .515 . 516 .517 .518 .519 .520 .521 .522 .523 .524 .525 .526 .527 .528
![Page 9: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/9.jpg)
Graphing the tolerance and a measurement
It’s useful to see the tolerance and the part measurement on a graph.Suppose that:
--the tolerance is .515”
SpecificationLimit MIN
.512 .513 .514 .515 . 516 .517 .518 .519 .520 .521 .522 .523 .524 .525 .526 .527 .528
![Page 10: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/10.jpg)
Graphing the tolerance and a measurement
It’s useful to see the tolerance and the part measurement on a graph.Suppose that:
--the tolerance is .515” to .525”
SpecificationLimit MAX
SpecificationLimit MIN
.512 .513 .514 .515 . 516 .517 .518 .519 .520 .521 .522 .523 .524 .525 .526 .527 .528
![Page 11: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/11.jpg)
Graphing the tolerance and a measurement
It’s useful to see the tolerance and the part measurement on a graph.Suppose that:
--the tolerance is .515” to .525”--and an individual part is measured at .520”.
SpecificationLimit MAX
SpecificationLimit MIN
.512 .513 .514 .515 . 516 .517 .518 .519 .520 .521 .522 .523 .524 .525 .526 .527 .528
X
![Page 12: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/12.jpg)
Graphing the tolerance and measurements
Suppose we made and measured several more units, and they were all EXACTLY the same!
We wouldn’t have very many part problems!
SpecificationLimit MAX
SpecificationLimit MIN
.512 .513 .514 .515 . 516 .517 .518 .519 .520 .521 .522 .523 .524 .525 .526 .527 .528
XXXX
![Page 13: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/13.jpg)
Graphing the tolerance and measurements
In the real world, units are NOT EXACTLY the same. Everything VARIES.
The question isn’t IF units vary.It’s how much, when, and why.
SpecificationLimit MAX
SpecificationLimit MIN
.512 .513 .514 .515 . 516 .517 .518 .519 .520 .521 .522 .523 .524 .525 .526 .527 .528
XX XXX XXXXXXXXXXXX
![Page 14: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/14.jpg)
The “normal bell curve”
Widths, heights, depths, thicknesses, weights, speeds, strengths, and many other types of measurements, when charted as a histogram, often form the shape of a bell.*
A “perfect bell,” like a “perfect circle,” doesn’t occur in nature, but many processes are close enough to make the bell curve useful.
(*A number of common industrial measurements, such as flatness and straightness, do NOT tend to distribute in a bell shape; their proper statistical analysis is performed using models other than the bell curve.)
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XX XXX XXXX XXXX XXXXX XXXXX XXXXXX XXXXXX XXXXXXX XXXXXXXX XXXXXXXXX XXXXXXXXXXX
![Page 15: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/15.jpg)
What is a “standard deviation”?
If we measure the DISTANCE from the CENTER of the bellto each individual measurement that makes up the bell curve,we can find a TYPICAL DISTANCE.
The most commonly used statistic to estimate this distance is theStandard Deviation (also called “Sigma”).
Because of the natural shape of the bell curve, the area of +1 to –1 standard deviations includes about 68% of the curve.
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XX XXX XXXX XXXX XXXXX XXXXX XXXXXX XXXXXX XXXXXXX XXXXXXXX XXXXXXXXX XXXXXXXXXXX
Typical distance from the center: +1 standard deviation
Typical distance from the center: -1 standard deviation
![Page 16: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/16.jpg)
How much of the curve is included in how many standard deviations?
From –1 to +1 is about 68% of the bell curve.From –2 to +2 is about 95%From –3 to +3 is about 99.73%From –4 to +4 is about 99.99%
(NOTE: We usually show the bell from –3 to +3 to make it easier to draw, but in concept, the “tails” of the bell get very thin and go on forever.)
-6 -5 -4 -3 -2 -1 +1 +2 +3 +4 +5 +6 0
![Page 17: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/17.jpg)
A
B
What is Cpk? It is a measure of how wella process is within a specification.
Cpk = A divided by BA = Distance from process mean to closest spec limitB = 3 Standard Deviations (also called “3 Sigma”)
A bigger Cpk is better because fewer units will be beyond spec.(A bigger “A” and a smaller “B” are better.)
SpecificationLimit
SpecificationLimit
Cpk = A divided by B
![Page 18: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/18.jpg)
A
B
“Process Capability” is the ability of a process to fit its output within the tolerances.
…a LARGER “A”…and a SMALLER “B”…means BETTER “Process Capability”
SpecificationLimit
SpecificationLimit
Cpk = A divided by B
![Page 19: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/19.jpg)
A
B
An Analogy
Analogy:The bell curve is your automobile.The spec limits are the edges of your garage door.If A = B, you are hitting the frame of your garage door with your car.
SpecificationLimit
SpecificationLimit
Cpk = A divided by B
![Page 20: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/20.jpg)
A
B
How can we make Cpk (A divided by B) better?
1. Design the product so a wider tolerance is functional (“robust design”)2. Choose equipment and methods for a good safety margin (“process capability”)3. Correctly adjust, but only when needed (“control”)4. Discover ways to narrow the natural variation (“improvement”)
SpecificationLimit
SpecificationLimit
Cpk = A divided by B
![Page 21: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/21.jpg)
A
B
What does a very good Cpk do for us?
This process is producing good units with a good safety margin.
Note that when Cpk = 2, our process mean is 6 standard deviations from the nearest spec, so we say it has “6 Sigma Capability.”
SpecificationLimit
SpecificationLimit
This Cpk is about 2. Very good!
Mean
![Page 22: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/22.jpg)
A
B
What does a problem Cpk look like?
This process is in danger of producing some defects.It is too close to the specification limits.
(Remember: the bell curve tail goes further than B……we only show the bell to 3-sigma to make it easier to draw.)
SpecificationLimit
SpecificationLimit
This Cpk is just slightly greater than 1. Not good!
![Page 23: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/23.jpg)
A
B
What does a very bad Cpk look like?
A significant part of the “tail” is hanging out beyond the spec limits.This process is producing scrap, rework, and customer rejects.
Notice that if distance “A” approaches zero… …the Cpk would approach zero, and……the process would become 50% defective!
SpecificationLimit
SpecificationLimit
This Cpk is less than 1. We desire a minimum of 1.33 and ultimately we want 2 or more.
![Page 24: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/24.jpg)
Free software is available to draw a histogramand calculate average, standard deviation, and Cpk.
Located at: www.rockfordpowertrain.com/supplier
![Page 25: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/25.jpg)
What “Six Sigma Philosophy” did Motorolateach its suppliers in the 1980’s?
In the 1980’s, Motorola achieved dramatic quality improvements and won the USA’s Malcolm Baldrige National Quality Award.
Motorola began seminars teaching its “Six Sigma Philosophy” to its suppliers, and to other companies.
The following few slides depict some original messages from that time.
SpecificationLimit
SpecificationLimit
![Page 26: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/26.jpg)
Robust Design – part of the original Six Sigma
The new design above has tolerances set “tight” to a known existing process, while the one below has tolerances that allow “six sigma capability”.
Products have thousands of tolerances. They result from choices about shapes, thicknesses, grades of materials, and grades of components. “Robust design” is NOT about permitting “sloppiness.” It requires very smart engineering to allow ample tolerances AND achieve satisfactory function.
New ProductSpecificationLimit
New ProductSpecificationLimit
KnownExistingProcess
New ProductSpecificationLimit
New ProductSpecificationLimit
KnownExistingProcess
![Page 27: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/27.jpg)
Robust Design – part of the original Six Sigma
CAUTION:
Suppliers must negotiate the widening of tolerances BEFORE competitive bids, quotations, and acceptance of orders. Competitive bids are commitments to meet all existing tolerances. Failure to meet customer tolerances means failure to meet contract requirements. Prevent breaches of contract.
New ProductSpecificationLimit
New ProductSpecificationLimit
KnownExistingProcess
New ProductSpecificationLimit
New ProductSpecificationLimit
KnownExistingProcess
![Page 28: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/28.jpg)
Robust Processes – part of the original Six Sigma
The process above varies so much that it “fills” the design tolerance. The different process below has good repeatability for “six sigma capability”.
It’s a false-economy to choose an allegedly lower-cost process that “uses up” all tolerance. The resulting scrap, rework, rejections, recalls, damage to reputation, crisis communications, and fire-fighting cancel out the alleged economy. “Robust Process” requires skillful insight to choose ways to make defect-free product at the lowest real cost.
New ProductSpecificationLimit
New ProductSpecificationLimit
New Process choice “Y”
New ProductSpecificationLimit
New ProductSpecificationLimit
New Process choice “X”
![Page 29: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/29.jpg)
6 Sigma Philosophy – Not Just The Shop FloorGetting every person “capable” and in “self control”
Achieving delivery and project deadlinesMeeting budgets & financial goalsAdministrative tasksDesign workPurchasing/sourcingSpecial projectsSecurity and SafetyHealth and EnvironmentalLegal complianceAnything that can be defined and measured
![Page 30: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/30.jpg)
Getting every person “capable” and in “self control”
Defined & Understood Requirements
Ability toMeasure Results
Process Capability and
Ability to Control
The 3Requisites
Of Self-Control
![Page 31: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/31.jpg)
Summary:• To call a process “capable” typically requires at
least a Cpk of 1.33 (+ and - 4 standard deviations within tolerance)
• Many customers desire a Cpk of 2.0 (+ and - 6 standard deviations within tolerance)
• Organizations need:
1. Feasible designs
2. Capable processes
3. Process self-control
![Page 32: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/32.jpg)
Conclusion:Process Capability:
Yes: No:
No:
No:
Yes:
Yes:
potentially capableif re-centered
potentially capableif re-centered
too wide
![Page 33: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/33.jpg)
Review Question 1
What is “Process Capability?”
![Page 34: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/34.jpg)
Review Question 2
How is the “process average” calculated or estimated?
![Page 35: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/35.jpg)
Review Question 3
What is a “Standard Deviation”?
(also known as a “sigma”)
![Page 36: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/36.jpg)
Review Question 4
What is Cpk used for?
![Page 37: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/37.jpg)
Review Question 5
Suppose that a feature tolerance is .750”/.760”,
and the process average is .759”,
and the process standard deviation is .002”
…is the process satisfactory and capable?
![Page 38: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/38.jpg)
Review Question 6
Suppose that a torque tolerance is 25 foot pounds minimum,
and the process average is 26 foot pounds,and the process standard deviation is 3 foot
pounds……is the process capable?
![Page 39: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/39.jpg)
Review Question 7
Suppose that a diameter tolerance is 8.010” to 8.060”,
and the process average is 8.041”,
and the process standard deviation is .002”…
…is the process capable?
![Page 40: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/40.jpg)
Review Question 8Fred is cutting an outside diameter on a lathe
and the diameter is easily adjustable.
The diameter tolerance is 5.050” to 5.090”,
the process average is 5.090”,
and the process standard deviation is .001”…• What is the Cpk?• What should Fred do with the process?
![Page 41: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/41.jpg)
Review Question 9Joe is boring an inside diameter on a lathe.
The diameter tolerance is 1.980” to 2.020”.
Joe has measured three random samples at
2.005”, 2.004”, and 2.006”.• Estimate the process average.• Estimate the standard deviation (best guess).• Estimate whether the process can be
capable.
![Page 42: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/42.jpg)
Review Question 10TechCorp is demonstrating a new “high-precision”
grease dispenser machine.
TechCorp claims that they can “dispense grease all day with an accuracy of plus or minus half an ounce.”
During the demo, ten samples of grease in a row were dispensed (in ounces) as follows:
2.3, 2.0, 2.6, 3.0, 2.1, 2.7, 2.9, 2.5, 2.0, 2.4• Based on the sample data, evaluate TechCorp’s
claim that they can “dispense grease all day with an accuracy of plus or minus half an ounce.”
![Page 43: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/43.jpg)
Quiz Question 1
True or False?
“Process Capability” can be defined as
the ability of a process to make a feature
within its tolerance.
![Page 44: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/44.jpg)
Quiz Question 2
True of False?
We can estimate the process average
by taking a set of sample measurements,
adding them up, and dividing by the number of measurements.
![Page 45: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/45.jpg)
Quiz Question 3
True or False?
A “Standard Deviation” can be thought of as the “typical” distance of the
measurements from the average;
about 68% of the individuals will fall within
+ or – 1 standard deviation of a bell curve.
![Page 46: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/46.jpg)
Quiz Question 4
True or False?
When using Cpk, the goal is to keep the Cpk value as low as possible.
![Page 47: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/47.jpg)
Quiz Question 5True or False?
If the feature tolerance is .350”/.360”,
and the process average is .351”,
and the process standard deviation is .004”
…then the process should be called “capable.”
![Page 48: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/48.jpg)
Quiz Question 6True or False?
If a pressure tolerance is 250 PSI minimum,
and the process average is 260 PSI,
and the process standard deviation is 4 PSI,
…then the process is “capable.”
![Page 49: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/49.jpg)
Quiz Question 7
True or False?
If a height tolerance is 7.010” to 7.060”,
and the process average is 7.042”,
and the process standard deviation is .002”…
…then the process is “capable.”
![Page 50: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/50.jpg)
Quiz Question 8True or False?
If Larry is cutting an O.D. and the diameter is easily adjustable, the tolerance is 4.055” to 4.095”, the process average is 4.095”, and the standard deviation is .001”…
…then Larry should be able to make the process fully “capable” by adjusting the process.
![Page 51: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/51.jpg)
Quiz Question 9True or False?
If Jill is boring an I.D. with a tolerance of 1.475” to 1.525”, and has measured three samples at 1.501”, 1.500”, and 1.499”…
…then the average of the samples is 1.501”, the standard deviation is probably larger than .010”, and the Cpk is probably zero.
![Page 52: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/52.jpg)
Quiz Question 10True or False?
If HiTechCo is demonstrating a new “high-precision” surface coating machine, and claims that their machine “can coat all day with an accuracy of plus or minus .010 inches,” and during the demo the coating thickness readings (in inches) were as follows:
.027, .028, .027, .029, .028, .029, .028, .029, .028, .027
…then the sample readings suggest that HiTechCo might be telling the truth about being able to hold plus or minus .010 inches.
![Page 53: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/53.jpg)
Appendix
Cpk and PPM
(Parts Per Million Defective)
![Page 54: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/54.jpg)
Cpk: Avoid confusion and pitfalls
• DOES IT VARY? Cpk varies when sampled, because it’s calculated from the average and the standard deviation, both of which are estimated from samples.
• CARROTS AND STICKS? Giving rewards or reprimands based on minor, short-term fluctuations of Cpk amounts to a lottery. Watch real trends.
• MAKE A “PLANT AVERAGE” CPK? It’s unhelpful to report a plant average Cpk of multiple characteristics and products, because:
1. Cpk values depend on each chosen tolerance
2. An “okay average Cpk” could come from 50% “good” and 50% “bad” numbers -- highly misleading!
![Page 55: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/55.jpg)
A
B
What is PPM (defect Parts Per Million)?
“PPM” is an estimate of the portion that is beyond the spec limit.If we know the Cpk…--we can look up the PPM “out of spec” in a statistics book table, or--we can use software, such as Microsoft Excel, to calculate the PPM.(REMEMBER that the “tail” of the bell goes out further than it is drawn.)
SpecificationLimit
SpecificationLimit
The defect PPM is the area outsidespec limits
![Page 56: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/56.jpg)
What is the “6-Sigma Philosophy”“1.5-Sigma Shift”?
The “6 Sigma Philosophy” includes the premise that real-world processes move around to some extent, and produce more defects than a static process. As an arbitrary convention, this is represented as an “unfavorable shift” of 1.5 sigma in Parts Per Million tables for Six Sigma programs. The intention is to plan conservatively.
(This means that the “PPM vs. Sigma” charts published for “6-Sigma Programs” show
higher defect rates than the similar but traditional “Z-tables” in statistical textbooks.)
SpecificationLimit
SpecificationLimit
Unfavorableprocess shift of 1.5 standard deviations
![Page 57: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/57.jpg)
The following page is a table showing the relationships among the following:
• Cpk,
• “How Many Sigma Capability,”
• Parts Per Million according to traditional statistical tables
• Parts Per Million taking into account the “6-Sigma Philosophy” of an unfavorable shift in the mean of 1.5 Sigma
![Page 58: Rockford Powertrain Training Workshop Process Capability and Cpk](https://reader035.vdocuments.site/reader035/viewer/2022081418/551c0a8b550346ad4f8b50a9/html5/thumbnails/58.jpg)
Cpk (Defined as
distance from process mean to the nearest spec,
divided by 3 Standard
Deviations)
"How Many Sigma
Capability?" Distance of
Process Mean to Spec Limit in
Standard Deviations
Within Spec (Process Perfectly
Centered, Both Tails
Considered)Good Units Per
Million
PPM of the Bell Curve
Out of Spec (Process Perfectly
Centered, Both Tails
Considered)
PPM of the Bell Curve
Out of Spec (Process Not
Centered, Only One Tail Considered)
The column AT LEFT equates to 1 defective out of how
many total?
PPM of the Bell Curve
Out of Spec with Six-Sigma
Philosophy of 1.5 Standard
Deviation Penalty for Anticipated Unfavorable
Process Mean Drift
0 0 0 1,000,000 500,000 2
0.17 0.5 382,925 617,075 308,538 3
0.33 1 682,689 317,311 158,655 6
0.5 1.5 866,386 133,614 66,807 15 500,000
0.67 2 954,500 45,500 22,750 44 308,538
0.83 2.5 987,581 12,419 6,210 161 158,655
1 3 997,300 2,700 1,350 741 66,807
1.17 3.5 999,535 465 233 4,298 22,750
1.33 4 999,937 63 32 31,560 6,210
1.5 4.5 999,993.2 6.8 3.4 294,048 1,350
1.67 5 999,999.4 0.6 0.3 3,483,046 233
1.83 5.5 999,999.96 0.04 0.02 52,530,944 32
2 6 999,999.998 0.002 0.001 1,009,976,693 3.4
2.17 6.5 999,999.99992 0.00008 0.00004 24,778,276,273 0.3
Cpk, PPM, and "Six Sigma"