rock tunnellingalan pengelly
TRANSCRIPT
-
7/30/2019 Rock tunnellingAlan Pengelly
1/45
1
Cost-effective seepage control
and ground improvement inrock tunnelling with pre-
injections.
Alan Pengelly
Regional Manager, UGC Asia Pacific
20th
September 2008
-
7/30/2019 Rock tunnellingAlan Pengelly
2/45
2
Contents
What is pre-injection?
Why Pre-inject?
Grout material types
Penetrability concept
Practical Aspects
Maneri Bhali Case Study
Arrow Head Case Study
-
7/30/2019 Rock tunnellingAlan Pengelly
3/45
3
What is pre-injection?
-
7/30/2019 Rock tunnellingAlan Pengelly
4/45
4
Why Pre-injection?
PrePre--injectioninjectionA proactive mindset!A proactive mindset!
In front of the tunnel face TunnelTunnel
1. Safety to reduce risk of tunnel collapse2. Environment drainage and
contamination of water table
3. Cost cheaper to deal with aboveproblems with low cost materials cementsthan with expensive chemicals
-
7/30/2019 Rock tunnellingAlan Pengelly
5/45
5
Safety - Water inrush
They have serious waterproblems in the TBMtunnel.
Take a look at the
pictures, and you willunderstand why
-
7/30/2019 Rock tunnellingAlan Pengelly
6/45
6
Environmental Impact
-
7/30/2019 Rock tunnellingAlan Pengelly
7/45
7
Tunnel drainage effect
Very small water ingress to the tunnel =>
several meter pressure drop in the sand =>pore pressure loss and settlement in the clay
Functional requirements for injection
works
-
7/30/2019 Rock tunnellingAlan Pengelly
8/45
8
Injection Material Types
Cement-based grouts Ordinary portland cement (OPC)
Microcementsystems
Mineral Grouts and Gels Colloidal silica
waterglass
Acrylates
Sophisticated two-componentsystems
Low viscosity
High reactivity
Taylored properties
Polyurethanes (PU)
One-componentsystemsreactingwith water
Two-component systems withtailored properties
Pre - injection Materials
Post - injection Materials
-
7/30/2019 Rock tunnellingAlan Pengelly
9/45
9
Colloidal Silica Technology
Colloidal silica gel is a mineral grout, and isnot a chemical grout
It is a stable liquid containing single, sub-microscopic particles of silica oxide
To make it gel, a weak solution of salt water ismixed prior to pumping. The more salt wateradded, the faster the gel time
It is environmentally friendly and durable, as it issimply composed of quartz sand, water andsalt!
Having the consistency of water, it penetratessands and fine fissures very easily
It is extremely user-friendly as standard cement
grout equipment can be used and cleaned withwate
-
7/30/2019 Rock tunnellingAlan Pengelly
10/45
10
Colloidal Silica Technology
Silica gel (hard aggregates)
Precipitated silica (grape clusters)
Silica fume (chain-like)
Colloidal silica (primary particles)
5 to 15 m
5 m
0.2m
0.015m
-
7/30/2019 Rock tunnellingAlan Pengelly
11/45
11
Penetrability Concept
not related to w/c ratio !
< 5% bleedin 2hours
Marsh conetime < 35 s
D95
-
7/30/2019 Rock tunnellingAlan Pengelly
12/45
12
0.0
2m
m OPC
50m
Rheocem65015m
Rheocem9009m
Silica fume 0.2m
MP3200.015m
Size matters! Grain size
-
7/30/2019 Rock tunnellingAlan Pengelly
13/45
13
0.001 0.01 0.1 1 10 100
Colloidal silica MEYCO MP320
Urban tunneling require injection down towards 0,02 mm cracks
Ultrafine - Rheocem 900
Ultrafine - Rheocem 800
Microfine - Rheocem 650
Normal fine cement
Injection intocracks =3 x cementparticle size
Rock injection
-
7/30/2019 Rock tunnellingAlan Pengelly
14/45
Grain size - penetration test Rheocem
Grout pumped from this side
90cmlongple
xitube
-
7/30/2019 Rock tunnellingAlan Pengelly
15/45
15
Penetrability Concept
not related to w/c ratio !
< 5% bleedin 2hours
Marsh conetime < 35 s
D95
-
7/30/2019 Rock tunnellingAlan Pengelly
16/45
16
Stability - Bleed
Fine cementRheocem 650Rheocem650
Fine cement
bleed
-
7/30/2019 Rock tunnellingAlan Pengelly
17/45
17
Penetrability Concept
not related to w/c ratio !
Setting time is a very important parameter to minimize the excavation cycle< 2 hours is ideal
SETTING TIME
< 5% bleedin 2hours
Marsh conetime < 35 s
D95
-
7/30/2019 Rock tunnellingAlan Pengelly
18/45
Water: 30 seconds
Rheocem 900 w/c = 1.0
Rheobuild 2000 PF, 2%
Runs through in 33 sec.
Viscosity - Marsh cone time
-
7/30/2019 Rock tunnellingAlan Pengelly
19/45
19
Pro-active mindset:
pre-injection is an investment to avoid serious difficulties with wateringress and instable ground
A systematic process thatgives an opportunity to deal with groundinstability before we tunnel into it.
Drilling of probe holes in front of the tunnel face utlizing normaltunnelling equipment, injection when required ahead of the face
Utilization of relatively inexpensive injection materials, mainly basedon OPC and microcement
Injection with high pressure (> 50 bar)
Practical Aspects
-
7/30/2019 Rock tunnellingAlan Pengelly
20/45
20
Typical length: 15 to 30 m
Typical spacing: 1 to 2 m
PrePre--injection is far more economical than post injection!injection is far more economical than post injection!
(10 to 50 times less expensive to stop water ingress)(10 to 50 times less expensive to stop water ingress)
Practical Aspects: low cost, less delays,
avoid the unexpected
-
7/30/2019 Rock tunnellingAlan Pengelly
21/45
21
+ Water (w/c 1.0) + 1.5% Rheobuild 2000PF
MIXER PUMP
AGITATOR TANK
Packer
Use mix within 40 minutes!
Practical Aspects: Simple equipment.
-
7/30/2019 Rock tunnellingAlan Pengelly
22/45
22
STEP 1:THE PACKER ISATTACHED TO THE INJ ECTION
LANCE AND PUSHED INTO THEHOLE
STEP 3:WHEN THE INJ ECTION OFTHE HOLE IS FINISHED, THE
VALVE CLOSES ITSELF. THEINJ ECTION LANCE ISDISCONNECTED BY SCREWINGBACK THE TIGHTENING LEVER,WHILE THE RUBBER SLEEVE ON
THE PACKER REMAINSEXPANDED.
STEP 2:THE PACKER IS
EXPANDED IN THE DRILLHOLEUSING THE TIGHTENING LEVER.
THE INJ ECTION CAN START.
Simple Packer Systems
-
7/30/2019 Rock tunnellingAlan Pengelly
23/45
23
Hydro Electric Project.
Power House : 304 MW Project
HRT : 16 Km x 6 mtr Horse shoe
Owner : Uttaranchal Jal Vidyut Nigam Limited. (UJVNL)
Consultant : Irrigation Department, Govt. of Uttaranchal.
Contractor/s : M/s Hydel Constructions Pvt. Ltd.
Sub-contractor : M/s Shring Constructions Pvt. Ltd
Project started init ially in 1978, stopped in 1991 becauseof
a) collapse in the tunnel
b) lack of funds.
Restarted in 2002.
Indian Pre-Injection Case History
Maneri Bhali 7m dia head race tunnel
-
7/30/2019 Rock tunnellingAlan Pengelly
24/45
24
The Clients Problem
-
7/30/2019 Rock tunnellingAlan Pengelly
25/45
25
Conditions in original 20 year old tunnel
-
7/30/2019 Rock tunnellingAlan Pengelly
26/45
26
Solution.
Construct a 150m by-pass tunnel to reconstruct thetunnel to correct profile and allow lining works to be doneto correct profile, whilst main tunnel lining and excavationcontinues
Use a Systematic Pre-injection technique to excavate
through the known fault and RBM zone to pass withoutcollapsing the face and minimizing water ingress
(original tunnel took 2 years to cross this zone)Combined use of Meyco Potenza, ribs and Shotcrete
to ensure face stability during excavation incombination with pre-injection
-
7/30/2019 Rock tunnellingAlan Pengelly
27/45
27
Pre-injection Technique used :
Types of Injection materials used :
Microfine Cement - Rheocem 650 - 250T
Colloidal Silica Meyco MP 320 - 80T
PU Meyco 355 1K for sealing backflows 500kg
OPC was trialed but no penetration was achieved,despite water inflows continuing
-
7/30/2019 Rock tunnellingAlan Pengelly
28/45
28
Two-stage pre-injection process chosen
with rapid hardening microcement andcolloidal silica
1. Rheocem
650
2. MEYCO MP320
colloidal silica
-
7/30/2019 Rock tunnellingAlan Pengelly
29/45
29
Drill ing Sequence and pipe installation
-
7/30/2019 Rock tunnellingAlan Pengelly
30/45
30
Packer Installation
-
7/30/2019 Rock tunnellingAlan Pengelly
31/45
31
Results stable and substantially dry
-
7/30/2019 Rock tunnellingAlan Pengelly
32/45
32
Conditions in original 20 year old tunnel
-
7/30/2019 Rock tunnellingAlan Pengelly
33/45
33
Arrow Head East and West Tunnels
-
7/30/2019 Rock tunnellingAlan Pengelly
34/45
34
Arrow Head East and West Water Supply
Tunnels
5.8m dia. Herrenknecht hydbrid Hard Rock TBM
Variable and unpredictable Rock Conditions Soft Rock
-
7/30/2019 Rock tunnellingAlan Pengelly
35/45
35
Cost-effective pre-injections:
Water ingress reduction and groundimprovement in difficult rock
-
7/30/2019 Rock tunnellingAlan Pengelly
36/45
36
Arrowhead Tunnels Project San Bernardino, CA
Pre-injections : drilling patterns
1,5Face
4Face
-
7/30/2019 Rock tunnellingAlan Pengelly
37/45
37
Arrow Head East and West Tunnels
Main Problems
Rock mass showed very unpredictable behavior
Large ultrafine cement takes (several thousands of lb) in one hole andnothing in adjacent regardless of water yield from a few gpmto 200gpm
Water and silt jets occurred. Several m3 of sand can come in beforepacker can be placed.
Cement picks up fine silt materials and creates filter cake blockingcracks and fissures.
Typically no cement intake except when they lost a lot of ground.
Porous rock mass if insufficiently grouted would lead face and peripherycollapse causing long stoppages for weeks.
Trials with Cement grouting with varying w/c ratios and stable groutswas proving ineffective in sealing.
-
7/30/2019 Rock tunnellingAlan Pengelly
38/45
38
Arrow Head East and West Tunnels
Solutions
Systematic rock grouting with cement to fill voids to replace washed
out materials. Extensive use of high penetrating colloidal silica gel with low
viscosity and particle size to waterproof the rock mass.
Down stage drilling process using simple bag packers to stabilize
drill holes for packer placement at correct location ahead of tunnelface.
-
7/30/2019 Rock tunnellingAlan Pengelly
39/45
39
Plastic Bagpacker and borehole liner for
down stage drill ing process
-
7/30/2019 Rock tunnellingAlan Pengelly
40/45
40
Bagpacker ready for grout expansion(Using quick setting mortar)
-
7/30/2019 Rock tunnellingAlan Pengelly
41/45
41
Drillstring and Bagpacker(Typically down-stage drilling and grouting)
-
7/30/2019 Rock tunnellingAlan Pengelly
42/45
42
Inflatable packer placed(Typically at 9 m depth)
-
7/30/2019 Rock tunnellingAlan Pengelly
43/45
43
Typical solution in bad ground.
Double and triple cover grouting system.
Ring 3292
Water hit at 60ft with silt washout, 100 to 220gpm, pressure 250psi.
Injection 300,000lb cement to replace lost ground
19,000 gallons of colloidal silica to water proof the rock mass.
Injection sequence 22 days to complete, advance of 6 rings (30ft)
Ring 3298
Drill out to 140 ft, water down to 20gpm with 200psi
5000lb cement, 25,000 gallons of colloidal silica, complete after 6 days
Advance 30 ft
Ring 3304 - at start of original high volume and pressure water. Drill out to 140 ft, water down to 38gpm with 160 psi
26,000lb cement, 15,000 gallons of colloidal silica, complete after 5 days
Advance 30 ft and continue cylce until required
-
7/30/2019 Rock tunnellingAlan Pengelly
44/45
44
Arrow head conclusions
Systematic use of pre-injection with appropriate materials allowedsuccessful excavation of TBM in poor ground conditions.
Requires highly competent and dedicated contractor.
Custom designed TBM required with effective probe drillingequipment designed fit for the purpose, 45 positions available for
drilling.
Use of appropriate colloidal silica mineral grout to penetrate finecracks and fissures and flowing ground where ultrafine micro-cement could not penetrate.
Many thanks forMany thanks for
-
7/30/2019 Rock tunnellingAlan Pengelly
45/45
45
Many thanks forMany thanks for
your attentionyour attention