rock tunnellingalan pengelly

Upload: mandeepgeology

Post on 14-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Rock tunnellingAlan Pengelly

    1/45

    1

    Cost-effective seepage control

    and ground improvement inrock tunnelling with pre-

    injections.

    Alan Pengelly

    Regional Manager, UGC Asia Pacific

    20th

    September 2008

  • 7/30/2019 Rock tunnellingAlan Pengelly

    2/45

    2

    Contents

    What is pre-injection?

    Why Pre-inject?

    Grout material types

    Penetrability concept

    Practical Aspects

    Maneri Bhali Case Study

    Arrow Head Case Study

  • 7/30/2019 Rock tunnellingAlan Pengelly

    3/45

    3

    What is pre-injection?

  • 7/30/2019 Rock tunnellingAlan Pengelly

    4/45

    4

    Why Pre-injection?

    PrePre--injectioninjectionA proactive mindset!A proactive mindset!

    In front of the tunnel face TunnelTunnel

    1. Safety to reduce risk of tunnel collapse2. Environment drainage and

    contamination of water table

    3. Cost cheaper to deal with aboveproblems with low cost materials cementsthan with expensive chemicals

  • 7/30/2019 Rock tunnellingAlan Pengelly

    5/45

    5

    Safety - Water inrush

    They have serious waterproblems in the TBMtunnel.

    Take a look at the

    pictures, and you willunderstand why

  • 7/30/2019 Rock tunnellingAlan Pengelly

    6/45

    6

    Environmental Impact

  • 7/30/2019 Rock tunnellingAlan Pengelly

    7/45

    7

    Tunnel drainage effect

    Very small water ingress to the tunnel =>

    several meter pressure drop in the sand =>pore pressure loss and settlement in the clay

    Functional requirements for injection

    works

  • 7/30/2019 Rock tunnellingAlan Pengelly

    8/45

    8

    Injection Material Types

    Cement-based grouts Ordinary portland cement (OPC)

    Microcementsystems

    Mineral Grouts and Gels Colloidal silica

    waterglass

    Acrylates

    Sophisticated two-componentsystems

    Low viscosity

    High reactivity

    Taylored properties

    Polyurethanes (PU)

    One-componentsystemsreactingwith water

    Two-component systems withtailored properties

    Pre - injection Materials

    Post - injection Materials

  • 7/30/2019 Rock tunnellingAlan Pengelly

    9/45

    9

    Colloidal Silica Technology

    Colloidal silica gel is a mineral grout, and isnot a chemical grout

    It is a stable liquid containing single, sub-microscopic particles of silica oxide

    To make it gel, a weak solution of salt water ismixed prior to pumping. The more salt wateradded, the faster the gel time

    It is environmentally friendly and durable, as it issimply composed of quartz sand, water andsalt!

    Having the consistency of water, it penetratessands and fine fissures very easily

    It is extremely user-friendly as standard cement

    grout equipment can be used and cleaned withwate

  • 7/30/2019 Rock tunnellingAlan Pengelly

    10/45

    10

    Colloidal Silica Technology

    Silica gel (hard aggregates)

    Precipitated silica (grape clusters)

    Silica fume (chain-like)

    Colloidal silica (primary particles)

    5 to 15 m

    5 m

    0.2m

    0.015m

  • 7/30/2019 Rock tunnellingAlan Pengelly

    11/45

    11

    Penetrability Concept

    not related to w/c ratio !

    < 5% bleedin 2hours

    Marsh conetime < 35 s

    D95

  • 7/30/2019 Rock tunnellingAlan Pengelly

    12/45

    12

    0.0

    2m

    m OPC

    50m

    Rheocem65015m

    Rheocem9009m

    Silica fume 0.2m

    MP3200.015m

    Size matters! Grain size

  • 7/30/2019 Rock tunnellingAlan Pengelly

    13/45

    13

    0.001 0.01 0.1 1 10 100

    Colloidal silica MEYCO MP320

    Urban tunneling require injection down towards 0,02 mm cracks

    Ultrafine - Rheocem 900

    Ultrafine - Rheocem 800

    Microfine - Rheocem 650

    Normal fine cement

    Injection intocracks =3 x cementparticle size

    Rock injection

  • 7/30/2019 Rock tunnellingAlan Pengelly

    14/45

    Grain size - penetration test Rheocem

    Grout pumped from this side

    90cmlongple

    xitube

  • 7/30/2019 Rock tunnellingAlan Pengelly

    15/45

    15

    Penetrability Concept

    not related to w/c ratio !

    < 5% bleedin 2hours

    Marsh conetime < 35 s

    D95

  • 7/30/2019 Rock tunnellingAlan Pengelly

    16/45

    16

    Stability - Bleed

    Fine cementRheocem 650Rheocem650

    Fine cement

    bleed

  • 7/30/2019 Rock tunnellingAlan Pengelly

    17/45

    17

    Penetrability Concept

    not related to w/c ratio !

    Setting time is a very important parameter to minimize the excavation cycle< 2 hours is ideal

    SETTING TIME

    < 5% bleedin 2hours

    Marsh conetime < 35 s

    D95

  • 7/30/2019 Rock tunnellingAlan Pengelly

    18/45

    Water: 30 seconds

    Rheocem 900 w/c = 1.0

    Rheobuild 2000 PF, 2%

    Runs through in 33 sec.

    Viscosity - Marsh cone time

  • 7/30/2019 Rock tunnellingAlan Pengelly

    19/45

    19

    Pro-active mindset:

    pre-injection is an investment to avoid serious difficulties with wateringress and instable ground

    A systematic process thatgives an opportunity to deal with groundinstability before we tunnel into it.

    Drilling of probe holes in front of the tunnel face utlizing normaltunnelling equipment, injection when required ahead of the face

    Utilization of relatively inexpensive injection materials, mainly basedon OPC and microcement

    Injection with high pressure (> 50 bar)

    Practical Aspects

  • 7/30/2019 Rock tunnellingAlan Pengelly

    20/45

    20

    Typical length: 15 to 30 m

    Typical spacing: 1 to 2 m

    PrePre--injection is far more economical than post injection!injection is far more economical than post injection!

    (10 to 50 times less expensive to stop water ingress)(10 to 50 times less expensive to stop water ingress)

    Practical Aspects: low cost, less delays,

    avoid the unexpected

  • 7/30/2019 Rock tunnellingAlan Pengelly

    21/45

    21

    + Water (w/c 1.0) + 1.5% Rheobuild 2000PF

    MIXER PUMP

    AGITATOR TANK

    Packer

    Use mix within 40 minutes!

    Practical Aspects: Simple equipment.

  • 7/30/2019 Rock tunnellingAlan Pengelly

    22/45

    22

    STEP 1:THE PACKER ISATTACHED TO THE INJ ECTION

    LANCE AND PUSHED INTO THEHOLE

    STEP 3:WHEN THE INJ ECTION OFTHE HOLE IS FINISHED, THE

    VALVE CLOSES ITSELF. THEINJ ECTION LANCE ISDISCONNECTED BY SCREWINGBACK THE TIGHTENING LEVER,WHILE THE RUBBER SLEEVE ON

    THE PACKER REMAINSEXPANDED.

    STEP 2:THE PACKER IS

    EXPANDED IN THE DRILLHOLEUSING THE TIGHTENING LEVER.

    THE INJ ECTION CAN START.

    Simple Packer Systems

  • 7/30/2019 Rock tunnellingAlan Pengelly

    23/45

    23

    Hydro Electric Project.

    Power House : 304 MW Project

    HRT : 16 Km x 6 mtr Horse shoe

    Owner : Uttaranchal Jal Vidyut Nigam Limited. (UJVNL)

    Consultant : Irrigation Department, Govt. of Uttaranchal.

    Contractor/s : M/s Hydel Constructions Pvt. Ltd.

    Sub-contractor : M/s Shring Constructions Pvt. Ltd

    Project started init ially in 1978, stopped in 1991 becauseof

    a) collapse in the tunnel

    b) lack of funds.

    Restarted in 2002.

    Indian Pre-Injection Case History

    Maneri Bhali 7m dia head race tunnel

  • 7/30/2019 Rock tunnellingAlan Pengelly

    24/45

    24

    The Clients Problem

  • 7/30/2019 Rock tunnellingAlan Pengelly

    25/45

    25

    Conditions in original 20 year old tunnel

  • 7/30/2019 Rock tunnellingAlan Pengelly

    26/45

    26

    Solution.

    Construct a 150m by-pass tunnel to reconstruct thetunnel to correct profile and allow lining works to be doneto correct profile, whilst main tunnel lining and excavationcontinues

    Use a Systematic Pre-injection technique to excavate

    through the known fault and RBM zone to pass withoutcollapsing the face and minimizing water ingress

    (original tunnel took 2 years to cross this zone)Combined use of Meyco Potenza, ribs and Shotcrete

    to ensure face stability during excavation incombination with pre-injection

  • 7/30/2019 Rock tunnellingAlan Pengelly

    27/45

    27

    Pre-injection Technique used :

    Types of Injection materials used :

    Microfine Cement - Rheocem 650 - 250T

    Colloidal Silica Meyco MP 320 - 80T

    PU Meyco 355 1K for sealing backflows 500kg

    OPC was trialed but no penetration was achieved,despite water inflows continuing

  • 7/30/2019 Rock tunnellingAlan Pengelly

    28/45

    28

    Two-stage pre-injection process chosen

    with rapid hardening microcement andcolloidal silica

    1. Rheocem

    650

    2. MEYCO MP320

    colloidal silica

  • 7/30/2019 Rock tunnellingAlan Pengelly

    29/45

    29

    Drill ing Sequence and pipe installation

  • 7/30/2019 Rock tunnellingAlan Pengelly

    30/45

    30

    Packer Installation

  • 7/30/2019 Rock tunnellingAlan Pengelly

    31/45

    31

    Results stable and substantially dry

  • 7/30/2019 Rock tunnellingAlan Pengelly

    32/45

    32

    Conditions in original 20 year old tunnel

  • 7/30/2019 Rock tunnellingAlan Pengelly

    33/45

    33

    Arrow Head East and West Tunnels

  • 7/30/2019 Rock tunnellingAlan Pengelly

    34/45

    34

    Arrow Head East and West Water Supply

    Tunnels

    5.8m dia. Herrenknecht hydbrid Hard Rock TBM

    Variable and unpredictable Rock Conditions Soft Rock

  • 7/30/2019 Rock tunnellingAlan Pengelly

    35/45

    35

    Cost-effective pre-injections:

    Water ingress reduction and groundimprovement in difficult rock

  • 7/30/2019 Rock tunnellingAlan Pengelly

    36/45

    36

    Arrowhead Tunnels Project San Bernardino, CA

    Pre-injections : drilling patterns

    1,5Face

    4Face

  • 7/30/2019 Rock tunnellingAlan Pengelly

    37/45

    37

    Arrow Head East and West Tunnels

    Main Problems

    Rock mass showed very unpredictable behavior

    Large ultrafine cement takes (several thousands of lb) in one hole andnothing in adjacent regardless of water yield from a few gpmto 200gpm

    Water and silt jets occurred. Several m3 of sand can come in beforepacker can be placed.

    Cement picks up fine silt materials and creates filter cake blockingcracks and fissures.

    Typically no cement intake except when they lost a lot of ground.

    Porous rock mass if insufficiently grouted would lead face and peripherycollapse causing long stoppages for weeks.

    Trials with Cement grouting with varying w/c ratios and stable groutswas proving ineffective in sealing.

  • 7/30/2019 Rock tunnellingAlan Pengelly

    38/45

    38

    Arrow Head East and West Tunnels

    Solutions

    Systematic rock grouting with cement to fill voids to replace washed

    out materials. Extensive use of high penetrating colloidal silica gel with low

    viscosity and particle size to waterproof the rock mass.

    Down stage drilling process using simple bag packers to stabilize

    drill holes for packer placement at correct location ahead of tunnelface.

  • 7/30/2019 Rock tunnellingAlan Pengelly

    39/45

    39

    Plastic Bagpacker and borehole liner for

    down stage drill ing process

  • 7/30/2019 Rock tunnellingAlan Pengelly

    40/45

    40

    Bagpacker ready for grout expansion(Using quick setting mortar)

  • 7/30/2019 Rock tunnellingAlan Pengelly

    41/45

    41

    Drillstring and Bagpacker(Typically down-stage drilling and grouting)

  • 7/30/2019 Rock tunnellingAlan Pengelly

    42/45

    42

    Inflatable packer placed(Typically at 9 m depth)

  • 7/30/2019 Rock tunnellingAlan Pengelly

    43/45

    43

    Typical solution in bad ground.

    Double and triple cover grouting system.

    Ring 3292

    Water hit at 60ft with silt washout, 100 to 220gpm, pressure 250psi.

    Injection 300,000lb cement to replace lost ground

    19,000 gallons of colloidal silica to water proof the rock mass.

    Injection sequence 22 days to complete, advance of 6 rings (30ft)

    Ring 3298

    Drill out to 140 ft, water down to 20gpm with 200psi

    5000lb cement, 25,000 gallons of colloidal silica, complete after 6 days

    Advance 30 ft

    Ring 3304 - at start of original high volume and pressure water. Drill out to 140 ft, water down to 38gpm with 160 psi

    26,000lb cement, 15,000 gallons of colloidal silica, complete after 5 days

    Advance 30 ft and continue cylce until required

  • 7/30/2019 Rock tunnellingAlan Pengelly

    44/45

    44

    Arrow head conclusions

    Systematic use of pre-injection with appropriate materials allowedsuccessful excavation of TBM in poor ground conditions.

    Requires highly competent and dedicated contractor.

    Custom designed TBM required with effective probe drillingequipment designed fit for the purpose, 45 positions available for

    drilling.

    Use of appropriate colloidal silica mineral grout to penetrate finecracks and fissures and flowing ground where ultrafine micro-cement could not penetrate.

    Many thanks forMany thanks for

  • 7/30/2019 Rock tunnellingAlan Pengelly

    45/45

    45

    Many thanks forMany thanks for

    your attentionyour attention