risk assessment regarding composite brake blocks during
TRANSCRIPT
REPORT Ref TSJ 2019-5343
September 2020
Risk assessment regarding composite
brake blocks during Swedish winter
conditions
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
2 (91)
© Transportstyrelsen Järnväg
Spårtrafik
This report is available on the Swedish Transport Agency website
www.transportstyrelsen.se
Ref TSJ 2019-5343
ISBN
Author Aho Mikael
Month Year September 2020
May be reproduced with acknowledgement of the source
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
3 (91)
Foreword
Railway noise is a health hazard. The European Commission has acted upon
this and decided to address the issue in their regulation (EU) 1304/2014. In
the near future all freight wagons have to use composite brake blocks or disc
brakes to fulfil the requirements. However, it has been shown that
composite brake blocks do not achieve the expected brake capacity in actual
Nordic winter conditions. The Swedish Transport Agency has initiated tests
in winter conditions, but also this risk analysis. The risk analysis completes
the winter tests, as the analysis is based on the test results, and mitigating
measures are identified for further investigation, aiming to achieve a
tolerable risk level.
Borlänge June 2020
Petra Wermström
Road and Rail Director
The signed and stamped version is available from the Swedish Transport Agency.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
4 (91)
Summary
For several years Swedish railway undertakings have been noticing a
number of incidents during winter conditions where there is a significant
and sudden loss of brake performance on trains with wagons equipped with
composite brake blocks. A significant number of incidents, including a
number of SPAD, have been recorded. There is a danger that the number of
incidents will further increase when more wagons equipped with composite
brake blocks are introduced in Sweden. There would thereby also be an
increase in the probability of accidents.
This report highlights the risks which arise with the use of composite brake
blocks during winter conditions as well as the consequences of these risks
and their severity. The risks are highlighted from both the technical and
operational perspectives. A summary of the results of the tests carried out is
also provided and a range of measures to increase safety is identified for
further investigation.
Risk assessments are based partly on estimated risk and partly on
comparison with reference systems. The relevant reference system consists
of cast-iron brake blocks.
Based on the risk analysis and test results, the following conclusions have
been drawn:
There are composite brake blocks which have demonstrated
substandard properties in winter conditions and the use of these
implies an intolerable level of risk.
Those incidents which form the basis of the risk analysis occurred
despite the implementation of a number of operational measures.
These measures are already producing unacceptable consequences
such as delayed and cancelled trains. Further operational measures
(increased test braking/ exercising of brakes etc.) would have
completely unacceptable consequences and would fail to solve the
problem. Increased numbers of SPAD due to a deliberate choice of
new technical solutions is not acceptable and neither is it acceptable
to transfer responsibility for safety from the technical system to the
driver via further operational instructions.
Currently no incidents or events with trains fitted with only LL-type
composite brake blocks have been reported by Swedish railway
undertakings. It should be noted that there are only very few trains
with solely LL brake blocks in northern Sweden. On the other hand,
tests indicate that these blocks can have significantly lower braking
performance than cast-iron brake blocks.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
5 (91)
Current procedures, according to UIC, for the testing of composite
brake blocks in winter conditions do not correspond to actual Nordic
winter conditions.
Based on these conclusions, incidents which occurred and test results,
possible measures have been identified. These must be investigated
further. The possible measures identified concern freight wagons,
locomotives and operational rules. These measures should not be seen as
in themselves reducing risks to an acceptable level. Rather a
combination of measures will be required, partly over a transition period
and also on a permanent basis. Measures also need to be implemented at
national and international levels. One of these measures, which, during a
transition period, would reduce the risk and enable international
transport to and from Sweden, is an exception from the rules so that a
number of freight wagons with cast-iron brakes are allowed to operate
internationally.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
6 (91)
Terms and abbreviations
Term Explanation
ATC2 Train safety system, ATC version 2 (Automatic Train
Control). The system is used in Sweden and Norway and it
is a class B train safety system.
Bg The type Bg consists of one (1) brake shoe holder and one
(1) brake block. The brake block has the standard
measurement of 320 mm x 80 mm (length x witdh). The
“g” in Bg stands “geteilt” in German, “divided” in English
and it means that brake shoe holder and brake block can be
separated.
Bgu The type Bgu consists of one (1) brake shoe holder and two
(2) brake blocks. The brake blocks have the standard
measurement of 250 mm x 80 mm (length x witdh). The
“gu” in Bgu stands for “geteilt mit unterteilter Sohle” in
German, “divided with subdivided blocks” in English.
1 x Bgu Means that there are only brake blocks on one side of each
wheel (often called push-brakes since it’s just pushing from
one side of the wheel) In this case there are Bgu on one
side of the wheel. Typically used for brake systems based
on K-blocks.
2 x Bgu Means that there are brake blocks on both sides of the
wheel. In this case Bgu. Typically used for brake systems
based on GG- and LL-blocks.
Brake inhibition
valve
Brake inhibition valve is also called secondary brake valve
or brake inhibition function. When the brake inhibition
valve is active, the locomotive only brakes if the pressure
reduction is larger than 1,5 bar in HLL. There are
locomotives that has other HLL pressure limits for the
brake inhibition valve (for example activation at pressure
reduction larger than 1 bar). German term
“Nachbremsventil” or “Nachbremsfunction” is commonly
used also in other languages.
Brake position P
and G
Freight wagons can have their brake system in “P” or “G”
position. In P position is the brake application and release
time faster than in G position. A G-braked train has all
vehicles and the locomotive in brake position G. A P-
braked train has all wagons in P and the locomotive in P or
G. Note that other trains (than normal freight trains) can
have other brake positions for the vehicles.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
7 (91)
Term Explanation
CBB Composite Brake Blocks. A term used for CBB’s with high
friction level (K), medium friction level (L) and with low
friction level (LL). Composite brake blocks can be based
on friction materials that are either organic or sintered.
CSM-RA The common safety method for risk evaluation and
assessment according to COMMISSION
IMPLEMENTING REGULATION (EU) No 402/2013 of
30 April 2013 on the common safety method for risk
evaluation and assessment with amendments from:
COMMISSION IMPLEMENTING REGULATION (EU)
2015/1136 of 13 July 2015 amending Implementing
Regulation (EU) No 402/2013 on the common safety
method for risk evaluation and assessment.
ECM Entity in Charge of Maintenance.
Electro-dynamic
brake
Brake in electric or diesel-electric locomotives (or other
tractive units), in which the traction motors are used for
wear-free braking. Brake power can either be fed back to
the overhead line or just converted into heat in brake
resistors. Often called just “electric brake” or “e-brake”.
Abbreviation is ED. German term for ED is
“Elektrodynamische Bremse”.
ERA European Union Agency for Railways.
Exercising (of
CBB based
brake systems)
A brake application performed at speed with the purpose to
restore and/or check braking performance. General
minimum procedures are described in UIC 541-4, 2.2.1.3.
Fly-off snow Fly-off snow refers to the snow that swirls up from the
wind drag and swirls around the vehicles in the train.
In case of moderate fly-off snow, one can from the
locomotive still see the trailing wagons through the fly-off
snow. At heavy fly-off snow there are no visible wagons
(or only parts of the first wagon are visible).
UIC Leaflet 541-4, appendix G, classifies fly-off snow in
winter classes W1 to W5. Moderate fly-off snow is
classified as W3. Heavy fly-off snow is classified as W5.
GG (brake)
blocks.
Cast iron (brake) blocks. Material class is P10. This is the
type of brake block that has been used for a very long time.
GG= Grau Guss in German.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
8 (91)
Term Explanation
HBL Main air reservoir pipe, popularly called “feeding pipe”.
Locomotives and wagons are marked with HBL (from
German ”Hauptluftbehälterleitung”). HBL has yellow
colour marking. Main air reservoir pipe is present only on
some wagons. The individual wagon with HBL can only
take advantage of the HBL if all wagons before and also
the locomotive have HBL and it is connected.
HLL Brake pipe or popularly called “main brake pipe”
Locomotives and wagons are marked with HLL (from
German “Hauptluftleitung”. HLL has red colour marking.
Brake pipe exists on all freight wagons.
Inflected-curve
valve
Relay valve combination with inflected curve which
reduces brake force at a minor service brake for loaded
wagons. At full service brake there is no reduction. Neither
will there be any reduction in brake force for empty to
medium loaded (≤ 14,5 tons axle load) wagons. German
term is: “Knickventil”.
K (brake) block Composite brake blocks with high friction. The brake
blocks are based on a friction material that is either organic
or sintered.
L (brake) block Composite brake blocks with medium friction. These brake
blocks are unusual in Sweden. From a winter perspective
one can assume that they behave as K and LL block.
LL (brake)
block
Composite brake blocks with low friction. These brake
blocks have a weighted friction that corresponds to GG
brake blocks. The brake blocks are based on a friction
material that is either organic or sintered.
Railway
undertaking
(RU)
Here it refers to a railway operator (that runs trains) and is
accountable for a safety management system to handle
wagons with CBB (during winter conditions).
RAMS Reliability, Availability, Maintainability, Safety
The terms are defined in EN 50126.
s brake or ss
brake
s brake and ss brake corresponds to 14,5 respectively
18 tons brake weight per axle.
SPAD Signal Passed At Danger is an event when a train passes a
red signal (stop signal) or ERTMS-marking board when
not allowed to do so.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
9 (91)
Term Explanation
UIC International union of railways. The acronym comes from
the French name “Union internationale des chemins de
fer”.
VK Vehicle Keeper
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
10 (91)
CONTENTS
FOREWORD ............................................................................................................. 3
SUMMARY ................................................................................................................ 4
TERMS AND ABBREVIATIONS .............................................................................. 6
1 INTRODUCTION .............................................................................................. 13
1.1 Background ............................................................................................ 13
1.2 Purpose and issues studied ................................................................... 13
1.3 Methods and participants ....................................................................... 13
1.4 Scope and boundaries ........................................................................... 14
2 SYSTEM DEFINITION ..................................................................................... 16
2.1 System objective (intended purpose) .................................................... 16
2.2 System functions and elements ............................................................. 16
2.3 System boundary ................................................................................... 17
2.4 Physical and functional interfaces ......................................................... 18
2.4.1 Permitted line speeds ............................................................... 18
2.4.2 Permitted track axle loads ........................................................ 19
2.4.3 Train protection systems .......................................................... 19
2.5 The system environment ....................................................................... 19
2.6 Existing safety measures and safety requirements identified ............... 19
2.6.1 Approved brake configurations ................................................. 20
2.6.2 Bedding in of brake blocks in trains .......................................... 20
2.6.3 Operational rules – definition of winter conditions .................... 21
2.6.4 Operational roles for low speed operation of CBB wagons...... 22
2.6.5 Operational rules for low-speed running of CBB wagons which have winter problems. .................................................... 23
2.6.6 Operational rules for trains with CBB wagons .......................... 24
2.6.7 Operational rules for trains with CBB wagons which have poor winter properties. .............................................................. 26
2.6.8 Non-implemented operational rules for trains with CBB wagons ..................................................................................... 27
2.7 Assumptions which determine the limits for the risk assessment ......... 28
2.7.1 Reference system..................................................................... 28
3 OPERATIONAL EXPERIENCES AND TEST RESULTS ............................... 29
3.1 Summary of incidents ............................................................................ 29
3.2 Summary of test results ......................................................................... 29
3.2.1 Swedish Transport Agency winter tests ................................... 29
3.2.2 Hector Rail winter testing ......................................................... 30
4 RISK ASSESSMENT ....................................................................................... 32
4.1 Method ................................................................................................... 32
4.2 Identification of hazards ......................................................................... 33
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
11 (91)
4.3 Risk assessment .................................................................................... 33
4.3.1 Assessment of severity ............................................................ 33
4.3.2 Estimation of frequency and risk level ...................................... 37
4.4 Comparison with the reference system. ................................................ 46
4.5 Risk assessment – comparison with criteria .......................................... 49
4.5.1 Risk assessment based on explicit risk estimates ................... 49
4.5.2 Risk assessment based on comparison with the reference system ...................................................................................... 50
5 IDENTIFICATION OF POSSIBLE MEASURES ............................................. 51
6 CONCLUSIONS OF THE RISK ANALYSIS ................................................... 60
Appendices
A. Summary of incidents
B. Risk analysis protocol
C. Situations where reduced braking capacity can lead directly to
collision with another train
D. Braking capacity - seen theoretically and practically from the
perspective of the locomotive driver.
E. Comments to ERA’s list of fully approved UIC composite brake
blocks for international transport
F. In-depth account of advantages and disadvantages of certain
proposed measures
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
13 (91)
1 Introduction
1.1 Background
For several years Swedish railway undertakings have been noticing a
number of incidents during winter conditions where there is a significant
and sudden loss of brake performance on trains with wagons equipped with
composite brake blocks. During years 2015 and 2016 a number of incidents
were noted where the speed of the train must be reduced in order to achieve
sufficient braking performance and a couple of Signal Passed at Danger
(SPAD) incidents were recorded. Since this time the problem has continued
and at this point a significant number of events, including a number of
SPAD have been recorded. There is a danger that the number of incidents
will further increase when more wagons equipped with composite brake
blocks are introduced in Sweden. Up until the winter of 2020, wagons with
composite brake blocks have mostly been run in “mixed trains”, i.e. trains
consisting of wagons with both composite brake blocks and cast-iron brake
blocks. The reported incidents mostly occurred on trains with wagons
equipped solely with composite brake blocks1.
It should be noted that up to this point no accidents with serious
consequences in human or property terms have taken place where composite
brake blocks were a contributory factor.
1.2 Purpose and issues studied
This report highlights the risks which arise with the use of composite brake
blocks as well as the consequences of these risks and their severity. In
addition to this, the work should identify possible measures which might
lead to managing these risks.
1.3 Methods and participants
This work is based on principles for risk analysis and risk assessment in
accordance with CSM-RA2.
Identification of hazards and assessment of severity is based on the
experience of the analysis group, see Table 1. Frequency assessments are
1 ERA 2020, Report Task force on the winter performance of composite brake blocks. ERA 1177v0.1 2 CSM RA, COMMISSION IMPLEMENTING REGULATION (EU) No 402/2013 of 30 April 2013 on the
common safety method for risk evaluation and assessment and repealing Regulation (EC) No. 352/2009
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
14 (91)
based on reported incidents from two railway undertakings during the
2017/2018 and 2018/2019 winter periods.
Risk assessments are based partly on estimated risk and partly on
comparison with reference systems. Risk assessment based on estimated
risk is based on the risk assessment matrix in accordance with EN 501263.
The reference system deemed appropriate is freight trains having wagons
braked entirely with cast-iron brake blocks.
The work was carried out by a working group including representatives
from the Swedish Transport Agency and the railway undertakings. The
participants in the team are detailed below.
Participants Organisation Function
Mikael Aho Swedish Transport
Agency
Investigator
Tore Vernersson Chalmers Investigator
Pär-Johan Wedell AFRY Investigator
Petter Hydén Hector Rail Engineering support. Rolling Stock
Lars Fehrlund Green Cargo Brake expert, Green Cargo
Göran Davidsson COWI Risk analysis consultant
Table 1. Participants in the working group
1.4 Scope and boundaries
The analysis covers systems according to the system definition and
boundaries in chapter 2.
The quantitative analysis is based on the current scope and conditions (in
accordance with chapter 2) regarding operation of wagons with composite
brake blocks. The impact of a large-scale introduction of wagons with
composite brake blocks has not been quantitatively analysed.
As far as is known, the introduction of composite blocks has not undergone
any risk analysis. The introduction has been based rather on the fact that
composite blocks were approved in accordance with an accepted testing
procedure.
The braking system is a fundamental system for railway safety, with both
technical and operational safety being completely dependent on it. In this
case it may be retrospectively stated that a risk analysis should have been
3 EN 50126-1 Railway applications - the specification and demonstration of reliability, availability, maintainability
and safety (RAMS)
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
15 (91)
carried out as to whether the current testing methods for brake block
approval successfully reflect actual conditions.
This report is not a risk analysis prior to a proposed change, but rather a risk
analysis of an already existing situation. The Swedish Transport Agency,
who carried out the analysis, is not the proposer and does not itself have
control over the relevant safety measures currently in operation.
It follows, therefore, that this report does not exhaustively include all parts
of the risk management process in accordance with CSM-RA:
The issue of “significant change” is not investigated. It may
retrospectively be stated that the change was significant since it
resulted in a significant number of incidents.
The work does not result in a definitive list of safety measures which
may be implemented, but rather documents possible measures which
need to be investigated further.
Neither does the work show whether safety requirements have been
met following the implementation of the safety measures identified.
The report has not been subject to a formal independent review.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
16 (91)
2 System definition4
2.1 System objective (intended purpose)5
The objective is for the system to be based on K and LL brake blocks
instead of GG brake blocks6. The system must function in trains and at low
speed (shunting with brake active) under normal weather conditions,
including winter conditions.
The system objective is to have the requisite retardation during actual
conditions with the requisite degree of safety.
2.2 System functions and elements7
The system consists of freight wagons with composite brake blocks (CBB)
of types K and LL, which should be used operationally under all Swedish
weather conditions. The brake blocks are either organic or sintered. The
brake blocks are used on wagons whose weight may vary between empty
and fully loaded.
The composite brake blocks which are used in this risk assessment are listed
in8
- ERA Interoperability Unit. List of fully UIC approved composite
brake blocks for international transport. Reference: ERA/TD/2009-
02/INT. Dated 23/07/2015
and/or
- UIC 541-4, Appendix M. Composite brake blocks certified for
international traffic, 5th edition November 2018. Last update
23/04/2020.
The wagons have a brake configuration which is mainly 1 x Bgu for K
brake blocks and 2 x Bgu for LL brake blocks. 2 x Bgu exists for K blocks
but are less common.
4 Translations between different languages must be performed with the same wording as in different language versions of COMMISSION IMPLEMENTING REGULATION (EU) No 402/2013 of 30 April 2013 on the
common safety method for risk evaluation and assessment with amendments from: COMMISSION
IMPLEMENTING REGULATION (EU) 2015/1136 of 13 July 2015 amending Implementing Regulation (EU) No 402/2013 on the common safety method for risk evaluation and assessment 5 CSM-RA, 2.1.2, a. System objective (intended purpose) 6 L brake blocks are not included, but should have the same impact. L brake blocks are currently not in operation in Sweden. 7 CSM-RA, 2.1.2, b. System functions and elements, where relevant (including e.g. human, technical and
operational elements). 8 There are some differences between the ERA list and the UIC list. The ERA list does not list certain brake
blocks, but in those cases the blocks are fitted on TEN (Trans European Network) approved wagons.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
17 (91)
The brake system functions consist of a command given from driver, drivers
safety device or the train safety system regarding braking via the brake pipe
(HLL) that goes through the train. The autonomous (indirect) braking
system, creates a pressure force against the vehicle’s friction elements
which, with the aid of its friction coefficient, generates a braking force when
it is applied to the rotating wheels of the vehicle. In this case there is no
difference between Sweden and the rest of Europe.
The following UIC approved K brake blocks have been assessed based on
observations and incidents9:
CoFren, Cosid 810 (C810), organic
Federal Mogul, Jurid 816 M (J816M), organic
Federal Mogul, Jurid 822 (J822), organic
The following approved brake blocks were assessed based on observation:
Icer Rail / Becorit, IB 116*, organic
CoFren, C952-1, sintered
Wagons with K and LL brake blocks have s or ss brakes.
All trains operate in brake regime P, though it might be the case that the
leading locomotive is in brake regime G.
The wagon axle loads vary between approximately 4.4 and 22.5 tonnes.
Typically, the lowest axle load is approximately 5 tonnes.
Note that the brake blocks are approved by UIC, though it is unclear which
of the testing methods that actually were used10. The temperatures and
exercising used in the UIC bench tests do not, however, correspond to real
winter conditions. For example, the test temperature is either -7 °C or -
10 °C. Additionally, the minimum axle load for UIC testing does not
correspond to the lowest permitted value either.
2.3 System boundary11
In this safety assessment the following are excluded
a) Wagons
o with an axle load of 25 to 35 tonnes operated at the greatest
permitted speed of 50 km/h loaded and 70 km/h empty.
These wagons are operated in a variant of brake position G
on stretches off the normal network.
9 In addition to this there are incidents with nationally approved CBB, but these are far fewer in number. Some
brake blocks previously had UIC approval, for example K brake block, ABEX 229/M128. These were previously approved by UIC based on quality assurance by SNCF. The brake blocks are listed in UIC 541-4, Appendix N.
conformity assessment in accordance with the 2nd edition of UIC 541-4, 1.10.1990 10 The UIC and ERA lists do not specify which testing methods were used, only that the braking blocks are approved. 11 CSM-RA, 2.1.2, c System boundary including other interacting systems.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
18 (91)
o with 25 tonnes axle load at nationally approved and normal
freight train speeds.
The purpose of excluding these is that the wagons cannot be used for
international operation and because these wagons are specially
adapted for national conditions. Also, for the first item braking
performance is adapted for low-speed and 30 tonnes axle load, which
is a special case, not appropriate for the rest of the rail network.
b) Potential environmental impact from alternative brake block types
(compared with GG brake blocks).
c) Effect on braking capacity of the train from potential deficient
braking capacity from the locomotive. We have no deficiencies in
the braking capacity of the locomotive in winter time. This can,
therefore, be completely and entirely excluded.
2.4 Physical and functional interfaces12
2.4.1 Permitted line speeds
Permitted line speeds for freight trains in Sweden depend on available brake
percentage, track design, train length and train protection systems.
Regarding track design, distant signal distance is the crucial parameter, but
gradients also have an impact. A distant signal distance of 1000 m is typical,
but on different tracks this may be greater or less.
Note that the train’s brake percentage must be 61% or higher for it to be
able to be operational as a train in regular traffic. If the brake percentage is
less than 61% the maximum permitted speed is between 20 and 40 km/h
depending on brake percentage and track gradient.
The normal speed for a freight train is 100 km/h, but this may vary. The
whole planning system for the freight train system is based on the standard
train maintaining a line speed of 100 km/h.
The logic regarding the maximum permitted speed is: the longer and heavier
the train, the greater the brake percentage required to maintain a normal
speed (100 km/h).
The objective of the railway companies is to operate trains which are as long
and as heavy as possible, to achieve optimal efficiency. In order to achieve
this, a relatively high brake percentage is required. For example, a brake
12 CSM-RA, 2.1.2, d. Physical (i.e. interacting systems) and functional (i.e. functional data input and output)
interfaces.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
19 (91)
percentage of 80% is required to operate a train with a length of 501 to
600 m with Vmax 100 km/h13.
2.4.2 Permitted track axle loads
In principle an axle load of 22.5 tonnes is permitted, although this may be
higher14 or lower on certain tracks.
2.4.3 Train protection systems
Generally, the national class B System ATC2 is used, but a limited number
of lines have ETCS 2.3.0d with national deviations. In the beginning of
2021, the first lines will be upgraded to ETCS BL 3.6.
There will still be lines with ATC2 at least until 2035.
2.5 The system environment15
The friction element’s capacity to deliver a braking force must be
completely independent of the environment at the time of braking. The
braking system must function both at low speed (shunting) in terminals and
when the train is running.
Low speed operation is carried out at a maximum permitted speed of
30 km/h, but there are sometimes lower maximum permitted speeds.
Normally freight trains operate under all winter conditions, but in the case
of extremely low temperatures (under ca -40° C) and/or extreme snow fall
(where snow clearance has not been carried out) rail traffic is halted by the
infrastructure operators or the rail company. Note that temperatures
below -25° C are uncommon.
2.6 Existing safety measures and safety requirements identified16
Existing safety measures are set out below. These measures are of the kind
that have been applied during previous winters in operation, maintenance
and testing of elements, rolling stock and operations.
The safety requirements which were identified in the iterative risk
assessment process are documented in a later section. The exception is
measures/safety requirements which were identified before this risk
13 This applies to what are known as B lines which are common. 14 The greatest axle load permitted in Sweden is 25 tonnes to the south of Boden. On Malmbanan (the Iron Ore Line) 30 tonnes is permitted. 15 CSM-RA, 2.1.2, e. System environment (e.g. energy and thermal flow, shocks, vibrations, electromagnetic
interference, operational use). 16 CSM-RA, 2.1.2, f. Existing safety measures and, after necessary relevant iterations, definition of the safety
requirements identified by the risk assessment process.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
20 (91)
assessment, but which have still not been tested in operation and
maintenance (which are included below).
2.6.1 Approved brake configurations
All brake systems which are included in this risk assessment are approved
by UIC and ERA. This means that those brake configurations which are
included in this risk assessment are tested for winter conditions. Despite
this, serious shortcomings have been identified.
Note
- that there are three possible testing programmes for winter
conditions17, but it is not stated which programme that was used as a
basis for approval of a certain brake configurations,
- that two of the test programmes are bench tests (which ought to be
the most common). These were carried out at -7 °C and -10 °C
respectively. In these cases artificial snow was used,
- that one of the test programmes is based on field tests18 and here it is
stated that the meteorological conditions must be such that the
temperature is from 0 to -10°C and
- that the test is not carried out at the lowest approved axle loads, i.e.
those axle loads which cause the lowest pressure between brake
block and wheel are not tested.
Based on incidents and observations as well as interviews with experienced
locomotive drivers, it is apparent that the problem of sudden and major
reduction in braking performance is exacerbated by two factors – low-
temperature and fly-off snow. It should also be noted here that the design of
the wagon very likely influences the amount of fly-off snow19. Empty
wagons with high stanchions should produce more fly-off snow. The
maximum negative impact on the function of the brakes is judged to occur
at -15°C or below in combination with maximum fly-off snow20.
This existing safety measure is not sufficient, since the tested brake blocks
have not been verified in winter conditions.
2.6.2 Bedding in of brake blocks in trains
During testing and operationally the blocks must be bedded in21.
17 See UIC 541-4, A.5.1 18 See UIC 541-4, G 19 ”Snow fly-off” (Snörök in Swedish) may be classified according to UIC 541-4, G3.2 20 Hector Rail assessment. 21 With “bedding in” is meant that the geometry of the brake block at the friction surface is the same as the
geometry of the wheel so that maximum contact area is achieved.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
21 (91)
Operationally the rules apply that a maximum of ¼ of the brake blocks may
be changed at the same time22.
Exceptionally, Swedish operators have reduced the speed following a
change on a large number of wagons until the blocks have been bedded in.
This existing safety measure is important in all conditions. However, it is
possible that it might tend more to counteract the sudden and major loss of
braking capacity that may occur in winter conditions. In these cases, the
opposite may apply, since the pressure23 between the brake block and the
wheel increases with low contact area (i.e. blocks not bedded in). Increased
(surface) pressure might increase the capability of wearing off the ice on the
adhesion surfaces of the block.
This existing safety measure is immensely useful during most of the year,
but it is in all likelihood ineffectual in winter conditions.
2.6.3 Operational rules – definition of winter conditions
During winter conditions special rules apply for wagons with CBB. The
definition of winter conditions varies very slightly between different railway
companies but in principle the following definition is applied;
Winter conditions shall be deemed to exist when
- the temperature is below 0°C and
- there is fly-off snow on the tracks and/or
- the tracks are snow or ice-covered and/or
- there is a significant build-up of snow or ice in the underframes of
the wagons.
This definition is in principle identical to the recommendation in UIC 541-4,
section 2.2.1.3:
1. Definition of winter conditions from a braking perspective:
- the temperature is below 0°C and
- there is windblown snow on the tracks and/or
- the tracks are snow or ice-covered and/or
- there is a significant build-up of snow or ice on the wagons in
service
The definition of winter conditions is used to determine the activation of
operational winter measures. It is the individual locomotive driver who is
responsible for applying winter measures in winter conditions.
22 In accordance with recommendations in UIC 541.4, 2.2.2.1. 23 Force per unit of area
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
22 (91)
The definition of winter conditions is particularly conservative. At the same
time, it is extremely important to have safe and simple rules.
This existing safety measure means that the driver implements measures.
However, it is very apparent that the scope of the requisite measures at, for
example,
- temperatures of around 0° C and a snow-covered track (but without
fly-off snow) and
- temperatures of around -15° C and below, accompanied by heavy
fly-off snow
requires completely different operational measures particularly if the
wagons have organic blocks with poor properties. Under the last
aforementioned condition there is a greater likelihood of
- very strong need for exercising and surveillance or
- high risk for incidents or accidents
- the train needing to be stopped.
From the perspective of brake technology this definition is not optimal and
from a driver perspective it is important to have simple rules. However, the
rules must be reliable and here we can identify potential for improvement. It
would appear that this can only be done, if it is possible to exclude the most
unsafe and dangerous braking systems. After such a change, the definition
used to activate winter measures can be applied for the worst winter
conditions.
The rules apply to trains with 50% CBB or more.
2.6.4 Operational roles for low speed operation of CBB wagons
Low-speed operation means shunting with wagon brakes active. The highest
speed permitted is 30 km/h. Under these conditions, the opportunities to
condition the brake system are limited for the simple reason that kinetic
energy and thus braking power is low.
Besides standard brake tests which are carried out all year round, such as
- visual inspection,
- checking that air is connected (HLL and when appropriate HBL) are
checked on the last wagon
- checking that brake applies and release, (on both sides only in
wintertime but for all block types)24,
- leak tightness test,
24 This fulfils the recommendations in UIC 541-4 section 2.2.1.3, point 2, second bullet point: ” During the brake test prior to leaving the departure station, the train should be checked to ensure that the blocks on either side are
released.”
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
23 (91)
- free rolling test25 and
- test braking when rolling has begun.
the measures below during winter conditions for normal CBB wagons also
apply. The rules apply to all types of rolling stock trains with more than
50% CBB wagons26:
a) Brake at standstill with full service brake.
This safety measure complies with UIC recommendations27. It is
adjudged that this measure does not contribute to improving brake
performance. It is not possible to notice visually any impact of an ice
layer on the block compared with testing of brake (with ca 0.6 bars
HLL pressure drop). Even after 10 brake cycles with full service
brake, stationary, the braking capacity is not affected. It is currently
being investigated whether the measure should be discontinued.
b) The locomotive drivers are informed and trained to deal with the fact
that in wintertime braking capacity of wagons with CBB can fall
suddenly and strongly.
2.6.5 Operational rules for low-speed running of CBB wagons which have winter problems.
Certain CBB wagons underperform hugely in winter conditions. For these
wagons additional measures are applied in accordance with the following.
a) Immediately after the vehicles is set in motion there should be a test
braking to standstill.
Normally just one test braking is carried out, not necessarily to
standstill. The aim of this test braking is partly to ensure that the
locomotive driver has a good understanding of the braking capacity
of the wagons and partly, to a certain extent, to carry out exercising
of the brake. Obviously the braking energies are low, but it is
possible that certain improvements will be attained.
b) Repeated test braking shall be carried out at least every 15 minutes.
Test braking at low speed should be carried out with between ⅓ and
full service brake.
The aim of this is the same as for the above measure. Note that to
always require full service brake is simply operationally impossible,
and also the probability of wheel flats would rise greatly following
25 This fulfils the recommendations in UIC 541-4 section 2.2.1.3, point 2, third bullet point: ” During departure it
should be checked that all the wheels on the train are rolling freely.”. Note that this recommendation actually
applies to most operators the year-round. 26 Note that this may be critical since it should not be based on the number of wagons but rather on the proportion
of brake weight which is based on CBB. Nevertheless, in practice it usually complies. Every railway company is
responsible for rules in this area. 27 See UIC 541-4 section 2.2.1.3, point 2, first bullet point: ”Before moving stabled trains or parts of trains, a full
brake application should be carried out (pressure drop in main brake pipe ~ 1.5 bar).”
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
24 (91)
such a requirement. The driver adapts test braking to friction
conditions, gradients and other factors.
c) Every planned braking must be preceded by a test braking. The
brake may not be relied upon and therefore the test braking must be
carried out before a necessary braking.
d) Speed should be adapted according to braking capacity.
It may unfortunately be necessary to limit speed to walking speed.
Following that, extensive test braking (exercising) may be required
before the train can operate on the line.
Generally, locomotive drivers are well trained and aware about the fact that
at low speed in all weather conditions wagons with CBB have lower braking
capacity than those with GG brake blocks. Note that this is well managed.
The above rules were in principle applied during the winters of 2017/2018,
2018/2019 and 2019/2020, though continual improvements have been
implemented and ongoing training has been given. Note that the winter of
2019/2020 was not relevant for the assessment of these rules, since the
winter conditions were very mild.
Overall this is a very troubling situation since large parts of safety have been
moved from the system to the locomotive driver and since there are
uncertainties around whether the requisite safety can be upheld.
2.6.6 Operational rules for trains with CBB wagons
The following rules apply to trains with composite brake blocks in winter
conditions. By CBB trains is meant trains where more than 50% of the
wagons have CBB brake systems.
a) After departure a service braking (without electrodynamic brake)
should be applied before full speed has been reached. This is to
check the braking performance. If the braking is normal, continue in
accordance with normal procedure with the retardation check. If the
braking power is lower than expected this should be repeated until
the braking function is attained and the retardation check can be
carried out. Alternatively, if the braking function is not attained the
train should be stopped28.
This rule is to ensure that the braking function is present before
maximum permitted speed is attained. It is difficult to assess since a
certain speed is required in order to use technical calculations of the
train’s retardation which is carried out in the next step. At this stage
28 This measure corresponds to the recommendation in UIC 541-4, section 2.2.1.3, point 2, fourth bullet point.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
25 (91)
the assessment is completely and entirely in the hands of the
locomotive driver.
b) Retardation check is carried out with technical calculation. For the
retardation check a service brake with 1 bar (without
electrodynamic brake) is performed. If the train’s brake percentage
is not reached, the retardation check must be repeated with full
service brake (1,5 bar). If the brake percentage is not reached, the
brake percentage is reduced to the percentage calculated with the
train's safety system.
This function may be found in ATC2, but not in ETCS29 which is
why this barrier is not always found on ETCS rolling stock.
c) Exercising and test braking must be carried out at least every 15
minutes.
The purpose of this is to condition and check the braking capacity of
the train. With this braking there is no specific requirement for the
reduction of HLL30.
d) All braking, with the exception of a) ovan and parts of b) above,
shall be carried out with full service braking (with a reduction of
HLL by 1.5 bars). When the brakes are applied and a braking
function can be clearly observed, the brakes may be operated in the
normal way31.
The aim with this measure is to maximise exercising in the initial
phase of braking and to obtain margins. Also, the probability of
wheel flats is somewhat lower in the higher speed interval. In the
lowest speed interval, it must be accepted that the braking function is
reduced to avoid wheel flats.
e) After each brake application , i.e. in accordance with c) and d) ovan,
with a pressure drop of more than ~ 1 bar, where possible, the
retardation value should be assessed using the train safety system.
The purpose of this is for the locomotive driver to have support in
the assessment of the train’s current retardation capacity.
One fundamental problem is that there is a long brake application time for
the brake in the wagons further back in a long freight train, therefore those
29 Note that there is an ETCS system with internal STM which has the ability to carry out retardation checks at
ETCS level 2 also. ETCS does not have a requirement for this functionality. When there is no possibility of technical calculation, the driver must carry out a retardation check without technical calculation. 30 This exercising of the brakes corresponds fully and entirely with the recommendations in UIC 541-4, section
2.2.1.3. 31 This measure is not included in UIC and indeed should not appear there. This is something that should be
adapted by each railway company.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
26 (91)
brake blocks do not receive sufficient exercising. This problem is
exacerbated if the exercising cannot be carried out from full line speed.
2.6.7 Operational rules for trains with CBB wagons which have poor winter properties.
Certain CBB wagons underperform hugely in winter conditions. For these
wagons additional measures are applied in accordance with the following.
a) Immediately after setting the train in motion at low speed a test
braking to a standstill with full service brake with brakes on the
locomotive released (using the release button32 or with active brake
inhibition valve33) shall be carried out. In the final phase of the
braking, HLL may be raised to avoid wheel flats.
The aim of this measure is to obtain certain exercising and to ensure
that the locomotive brake do not conceal deficient braking capacity
in the wagons. In addition, the braking energy is maximised for the
wagons since the locomotive is not braking.
b) Electro-dynamic brake shall not be used for normal braking or
exercising of the brake.
c) During exercising the locomotive's brake shall be released (using
the release button or active brake inhibition valve).
d) Exercising must always be carried out with full service brake, at
least every 15 minutes.
The purpose of the measures, set out in a) to d) ovan, is that for each
brake application (which does not take place before a target) the
braking energy to the wagons is maximised. Also, braking
applications on the locomotive, which does not suffer from winter
problems, serve only to create maintenance costs.
We can also see some indications that brake applications with low
drops in HLL may worsen the braking performance of the wagons at
the next brake application. Full service brake produce a significantly
better exercising than lower reductions of HLL34.
e) Service brake shall always be initiated with full service brake and
the majority of the brake phase shall be performed with full service
brake.
This is in principle the same for other CBB, but the difference is that
32Note that not all locomotives on the Swedish market have a function to release the locomotive. 33 Note that only a few locomotives on the Swedish market have brake inhibition valves and some of them have
too high limits (around 4 bar) so they cannot be used. 34 Exception might be if exercising can be performed with traction since it can then be performed at high speed,
i.e. when kinetic energy is high.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
27 (91)
we actually do carry out the majority of the braking with full service
brake.
f) For the retardation check only procedure R235 shall be carried out,
i.e. service brake with a pressure drop of 1.5 bars.
In this case we deviate from customary procedure which is to carry
out the retardation test with 1 bar drop (procedure R1). The purpose
is to maximise brake power. Brake applications with low pressure
reductions are also avoided as they may worsen the braking capacity
of the wagons.
These measures were introduced gradually during the winter of 2017/2018.
During the winter of 2018/2019 all measures were introduced for critical
trains with CBB. Unfortunately, these CBB trains had GG wagons mixed in,
in the hope of attaining a certain level of safety. This safety measure was in
all probability erroneous and inappropriate since
- the quality of exercising of CBB wagons is lowered significantly in
trains with both GG and CBB wagons, since GG wagon braking
initiates directly and absorbs a large amount of the braking energy.
This consequently reduces the exercising of CBB wagons
dramatically,
- the high braking capacity of the GG brakes hides deficiencies of
these CBB wagons and
- damage to the wheels of the GG wagons36 increased sharply as a
result of the increased and unnecessary exercising of the GG
wagons.
2.6.8 Non-implemented operational rules for trains with CBB wagons
During short duration parking of CBB wagons, it is required that they are
braked with at least full service brake. In the winter of 2019/2020 a wagon
set started to roll while it was temporarily parked and braked (in conjunction
with a locomotive turnaround37) and collided with the locomotive thereby
causing a SPAD.
This rule will be introduced by several railway undertakings in Sweden and
is applicable all year round for wagon sets with more than 50% CBB.
35 R1 stipulates a retardation check where, with the aid of technical regulation, the driver can brake with a HLL
drop of 1 bar. R2 stipulates a retardation check with technical calculation where the driver brakes with full service
braking. R2 is normally only carried out were R1 does not produce the required result. 36 Shelling and pitting experienced the greatest increase but the frequency of wheel flats also rose. 37 Moving the locomotive from one end of the wagon set to the other.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
28 (91)
2.7 Assumptions which determine the limits for the risk assessment38
The risk assessment is limited to comparing CBB and GG brake blocks in
Swedish conditions
2.7.1 Reference system
The reference system consists of wagons with cast iron blocks (GG brake
blocks). These have the brake configuration 2 x Bgu and have s or ss brake.
In general, the reference system has the highest permitted axle load of
22.5 tonnes and an 18 tonne brake weight per axle39. Some wagons have a
brake weight of 14,5 ton per axle40. Brake weights lower than 14,5 ton are
not common.
Variant configurations from above are very uncommon and this applies to
wagons with low brake performance. There also exist nationally approved
CBB brake blocks for certain applications. These systems are not used as
reference systems.
38 CSM-RA, 2.1.2, g. Assumptions which determine the limits for the risk assessment. 39 ss brakes 40 s brakes
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
29 (91)
3 Operational experiences and test results
3.1 Summary of incidents
There is a summary of reported incidents in Appendix A. Reported incidents
comes from Green Cargo and Hector Rail.
In the period February 2015 to August 2019, Green Cargo reported 18
events. In most of the cases reduced braking capacity was detected while the
train was running and this was able to be dealt with by reducing speed from
100 to 80 km/h. However, two cases of Signal Passed At Danger (SPAD)
were reported as well as one case where there was very nearly a collision
and one further case where there was a complete loss of braking capacity.
In the period December 2017 to March 2020, Hector Rails reported 21
events. In most of the cases, reduced braking capacity was discovered
during shunting with brake active or in running trains that consequently
were stopped and/or turned back without danger. However, four cases of
SPAD were reported, one case where it was possible to stop merely 1 m
before the signal, one case where during shunting with braked wagons a
level crossing was crossed without permission, and one case where a parked
wagon set began to roll during a locomotive turnaround.
3.2 Summary of test results
3.2.1 Swedish Transport Agency winter tests
The Swedish Transport Agency organised winter testing of LL type
composite brake blocks during the 2016/201741, 2017/201842 and 2019/2020
seasons43.
The results of the brake force comparative test carried out in 2016/2017
showed that the type of wagon can have a major influence on the braking
performance of a composite brake block in winter conditions. During the
tests it was demonstrated that composite blocks lose up to 50% of their
braking capacity compared with cast-iron blocks during heavy fly-off snow
conditions. The amount of fly-off snow appears to vary depending on the
type of wagon; one wagon’s stanchions produced a considerably increased
amount of fly-off snow around the brake apparatus which in turn led to
41 Damill test report “Block Brake Performance in Winter Conditions rev 1.0” 42 ÅF rapport - Report 6179083 and Chalmers evaluation report Swedish tests of block brake performance in
winter conditions Winter 2018-2019 43 Swedish tests of brake block performance in winter conditions 2019-2020: Detailed analyses of experimental
results"
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
30 (91)
greatly reduced braking capacity for composite brake blocks when directly
compared with cast iron brake blocks.
The results of the braking distance tests from the 2019/2020 season showed
that the IB116* organic composite brake block showed a substantial
variation in braking distances (600 m – 1000 m). On average, the braking
distance increases with the low temperature and fly-off snow by around
25%, when a reference test with negligible or no fly-off snow is compared
with winter tests with a large amount of fly-off snow. No such increase was
observed during winter tests for the C952-1 sintered composite brake block.
The results from these tests are built, however, on the fact that
1. the wagons have undergone recent maintenance44 and have a very high
efficiency in the brake rigging,
2. the wagons are de-iced regularly, every second or third week,
3. the braking system is exercised every 15 minutes at 1.5 bars from the
highest speed down to standstill,
4. the wagon is used in mild winter conditions with a lowest temperature of
-10 °C.
3.2.2 Hector Rail winter testing
Hector Rail carried out testing in the winter of 2017/2018. These tests
demonstrated that
- the UIC recommendations for exercising was not sufficient for
critical wagons and
- the actual brake configuration of 1 x Bgu with J822, λempty≈100 %
was deficient during winter conditions for empty wagons.
During the winter of 2019/20 the idea was to test at least two modified
brake configurations:
Case 1: Modification with increased actual brake percentage at empty state.
The increase was from the current λempty≈100 % to λempty≈118 %45.
The aim of this increase is to increase the ability to remove the ice
on the brake blocks during the exercising. This case has been
implemented on a small number of wagons, but the mild conditions
this winter have not been appropriate for measurements and
monitoring can only be done when we can run complete trains (at
least 13 eight-axle wagons). No test results have been obtained.
44 "Recent maintenance" entails lubrication of the braking system so that high performance can be reached. 45 The maximum permitted is 125 % for wagons with automatic load braking. The purpose of only having 118%
braking is partly to avoid actually going over the maximum limit and because the risk of wheel flats increases.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
31 (91)
Case 2: changing blocks from J822 to C810. The purpose was to see
whether this might give improvements. Note that the only reason
for selecting C810 was that the type of wagon (with exactly the
same brake equipment) was already TSI approved. All that was
required was a remarking of the braked weight and type of block. If
this was not simple this alternative would not, of course, be tested
since the probability of achieving improvements with C810 is very
small.
Winter conditions during the winter of 2019/2020 were extremely
mild.
Operational monitoring did, however, show two issues at low speed
(shunting) and for this reason this block will be discontinued on
this type of wagon. However, wear monitoring is ongoing.
Case 3: change of brake block to CoFren C333 (sintered block).
Case 4: change of brake block to Flertex C302 (sintered block). This brake
block does not appear on the UIC or ERA lists of approved brake
blocks. This brake block is, however, the brake block for which no
deficiencies have been identified in Finland hitherto. According to
Hector Rail, this is probably the best alternative, but further testing
will be discussed with the wagon rental company who is also ECM
and VK.
A decision will be made about further tests for the remaining Cases, 1, 3 and
4. It would be reasonable to prioritise Case 4. Cases 1 and 3 would await the
results from this case.
Note that winter conditions in 2019/20 were particularly mild, but sufficient
to reject Case 2 (C810).
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
32 (91)
4 Risk assessment
4.1 Method
The work consists of the following activities:
1. Identification of hazards. This was carried out in the working group
and was based on incidents that took place as well as the experience
of the group, documented in chapter 4.2.
2. Risk estimation including assessment of severity and frequency.
Assessment of severity is based on the experience of the group.
Assessment of frequency is based on reported incidents and is
detailed in chapter 4.3.
3. Comparison with the reference system. The relevant reference
system is cast iron brake blocks. The comparison is documented in
chapter 4.4.
4. Risk evaluation based partly on estimated risk (point 2 above) and
partly on comparisons with the reference system (point 3 above). For
the risk assessment based on estimated risk, the starting point is the
risk matrix in accordance with EN 50126 (Figure 1 below),
documented in chapter 4.5.
Frequency of occurrence of
an accident (caused by a
hazard) Risk Acceptance Categories
Frequent Undesirable Intolerable Intolerable Intolerable
Probable Tolerable Undesirable Intolerable Intolerable
Occasional Negligible Undesirable Undesirable Intolerable
Rare Negligible Tolerable Undesirable Undesirable
Improbable46 Negligible Negligible Tolerable Undesirable
Highly improbable47 Negligible Negligible Negligible Tolerable
Insignificant Marginal Critical Catastrophic
Severity of an accident (caused by a hazard)
Figure 1. Risk matrix in accordance with EN 50126-1
46 Improbable: an occurrence of a malfunction with a frequency below or equal to 10-7 per hour of operation CSM-
RA Article 3, (37) 47 Highly improbable: an occurrence of a malfunction with a frequency below or equal to 10-9 per hour of
operation CSM-RA Article 3, (36)
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
33 (91)
4.2 Identification of hazards
The following hazards and consequences have been identified (see also
analysis protocol Appendix B).
Hazards Possible consequences
1. Reduced braking
capacity leading to
extended braking
distance
1.1 Collision with another train
1.2 Collision at low speed with a stationary vehicle/object
1.3 Derailment due to excess speed through a switch or passing a
track buffer.
1.4 Signal Passed at Danger (SPAD) without collision or
derailment
1.5 Loss of braking capacity without SPAD
2. Driver anxiety due to
variation in the braking
capacity of the train
2.1 Stress
2.2 Repeated testing and exercising of brakes
Table 2. Sources of risk and possible consequences
Consequences 1.1 – 1.5 are explicit (objective) risks from deficient braking
capacity. Events 2.1 – 2.2 are more subjective and will vary between
different drivers in different conditions depending on the composition of the
train, brake configuration, weather and track conditions etc. Appendix D
contains a description of the driver’s working circumstances based on the
properties of the brakes.
4.3 Risk assessment
4.3.1 Assessment of severity
Estimation of severity is based on the examples of severity given in
EN50126 for RAM and RAMS (tables C3 and C4), set out in Table 3
below.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
34 (91)
Estimated severity of respective consequences (1.1-1.5 and 2.1-2.2) is set
out in Table 4 below. In these evaluations both the RAM effect and the S
effect have been considered.
Table 3. Categories of severity EN 50126 for RAM and RAMS
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
35 (91)
Consequences Description Estimated
severity
(EN 50126)
RAM tab. C3
Estimated
severity
(EN 50126)
S tab. C4
1.1 Collision with
another train
Collision between a freight train and another train
may lead to multiple fatalities and/or major
environmental damage.
Not assessed Catastrophic
1.2 Collision at
low speed with a
stationary
vehicle/object
Collision between a freight train and another
stationary vehicle/object may lead to individual
fatalities/serious injury (driver) and/or significant
environmental damage.
Not assessed Critical
1.3 Derailment
due to excess
speed through a
switch or passing
a track buffer.
Derailment of a freight train vehicle/object may lead
to individual fatalities/serious injury (driver) and/or
significant environmental damage.
Not assessed Critical
1.4 Signal passed
at danger (SPAD)
without collision
or derailment
The train must be stopped and the driver taken out of
service. This will lead to major traffic delays. An
enquiry into the incident will be carried out. A
SPAD, even if there are no consequences, comprises
a major infringement of safety barriers. A conscious
increase of this type of event is completely
unacceptable.
Considered comparable to "severe system(s) damage"
Table C4.
Significant
Marginal
1.5 Loss of
braking capacity
without SPAD
The train must be taken out of service or continue
running at greatly reduced speed, which will produce
traffic disruption.
Considered comparable with "minor system(s)
damage" Table C4. This categorisation is on the low
side since many of the events meant that the train had
to return to its departure station.
Significant -
Major
Insignificant
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
36 (91)
Consequences Description Estimated
severity
(EN 50126)
RAM tab. C3
Estimated
severity
(EN 50126)
S tab. C4
2.1 Stress A braking system with variable braking force during
running will in reality lead to a situation where basic
safety can no longer be guaranteed by the technical
system and where responsibility is transferred to the
driver. This situation has resulted in certain drivers
refusing to drive certain trains. Long-term stress and
anxiety can lead to absence from work.
Stress regarding changes to work tasks. The risk of
getting stuck on long uphill inclines, where it is not
possible to condition the brakes, and stress over
falling behind the timetable.
Considered comparable to "severe or minor injuries"
Table C4.
- Marginal
2.2 Repeated
testing and
exercising of
brake
Severely worsened journey times, increased costs.
Considered comparable with "minor system(s)
damage" Table C4.
Major Insignificant
Table 4. Assessment of severity
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
37 (91)
4.3.2 Estimation of frequency and risk level
Frequency of hazard 1. Reduced braking capacity leading to extended
braking distance has been estimated below.
Estimation of frequency Hector Rail Sggrrs wagons
Failure description 1: Lost brake capacity in winter conditions for unloaded trains in high and
low speed operation with J822 in 1xBgu on Sggrrs wagons.
Loss of brake capacity is more than 20% loss (compared to braked weight marking).
Frequency of occurrence during winter 2017/2018 and 2018/2019: 15 events.
Estimation of hazard rate:
Estimation of operating hours:
- 160 wagons
- Average km per year: 80 000 km/wagon and year
- Average speed (incl. large number of shunting operations): 40 km/h
- Average number of wagons in a train or in shunting: 18 wagons
- Total operating hours:2∗160∗80000
40∗18= 35 555 𝑜𝑝. ℎ𝑟𝑠.
Frequency of occurrence: 𝝀𝑭𝒂𝒊𝒍 =𝟏𝟓
𝟑𝟓𝟓𝟓𝟓≈ 𝟒 ∗ 𝟏𝟎−𝟒 Faults per op. hrs
Note that average speed is estimated very low due to the fact that a lot of shunting is included at
terminals. However, if speed is estimated as 70 km/h, then the frequency of occurrence would
increase to 7*10-4.
Estimation of frequency Green Cargo – Jet Fuel Shuttle
Failure description 1: Reduction of brake performance
Frequency of occurrence of Failure description 1: 7 events
Estimation of hazard rate:
Estimation of operating hours:
- Total number of departures (6000 to 8000): 7000 departures
- Average operating hours per trip: 3 hrs
- Total operating hours: 7000*3=21000 op.hrs
Frequency of occurrence 𝝀𝑭𝒂𝒊𝒍 =𝟕
𝟐𝟏𝟎𝟎𝟎≈ 𝟑 ∗ 𝟏𝟎−𝟒 Faults per op. hrs
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
38 (91)
Estimated frequency is thus: 10-4 ≤ λ ≤ 10-3.
Comment regarding reported events:
There are uncertainties in the report basis. On one hand, it is well known
that there is an underreporting because often only events that are judged to
pose a serious danger are reported, the actual number of events is thus
probably significantly higher. On the other hand, the information in the
reported events is not always sufficient to determine the conditions that
prevailed at the time. It may therefore be that some of the events, even if
they occurred during the winter months, are not related to fly-off snow
and/or low temperatures.
Based on the table below this gives a frequency level equivalent to
"Probable". Note that these estimates are based on operating hours for a full
year. Considering winter seasons only would roughly imply a halving of the
operating hours and a doubling of the estimated frequencies. This will
however not change the conclusion of the frequency level.
EN 50126-1
Frequency
level
Description Example of a frequency range
based on a single item
operating 24 h/day.
Expected to happen.
Example of equivalent
occurrence in a 30 year
lifetime of a single item
operating 5000 h/year.
Expected to happen.
Calculated frequency
of occurrence of
hazardous events per
operating hour [h-1]
Frequent Likely to occur
frequently. The event will
be frequently
experienced.
more than once within a period
of approximately 6 weeks
more than about 150 times λ≥10-3
Probable Will occur several times.
The event can be expected
to occur often.
approximately once per 6 weeks
to once per year
about 15 to 150 times 10-4≤λ≤10-3
Occasional Likely to occur several
times. The event can be
expected to occur several
times.
approximately once per 1 year
to once per 10 years
about 2 to 15 times 10-5≤λ≤10-4
Rare Likely to occur sometime
in the system life cycle.
The event can reasonably
be expected to occur.
approximately once per 10
years to once per 1 000 years
perhaps once at most 10-7≤λ≤10-5
Improbable Unlikely to occur but
possible. It can be
assumed that the event
may exceptionally occur.
approximately once per 1 000
years to once per 100 000 years
not expected to happen
within the lifetime
10-9≤λ≤10-7
Highly
improbable
Extremely unlikely to
occur. It can be assumed
that the event will not
occur.
once in a period of
approximately 100 000 years or
more
extremely unlikely to
happen within the lifetime
10-9≤λ
Table 5. Frequency of occurrence of hazardous events (time based) EN50126
Note: The symbol λ in this context signifies frequency of failure and not brake percentage.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
39 (91)
The quantitative estimation is obviously uncertain, since it is based on a
limited number of events. However, this level is considered reasonable,
though possibly on the low side, even with a more qualitative basis. In the
table above the following examples are given for an item in operation 24/h
per day:
Frequent: More than once every six weeks
Probable: Between once every six weeks and once per year.
Occasional: Between once per year and once every 10 years.
A qualitative assessment is that "occasional" is definitely too low to
correspond to experiences during the last two winters. Viewed only as
winter traffic "frequent" is considered a more reasonable estimate. However,
as a basis the class "probable" is allocated.
The frequency of consequences (1.1 – 2.2) is difficult to estimate, since this
depends on a large number of factors such as track geometries, traffic
conditions etc., but risk levels for these events are discussed below; 1.1 –
1.5 and 2.2 based on the risk matrix in accordance with EN 50126.
1.1 Collision with another train
For loss of braking capacity to lead to a collision with another train a
number of conditions must be in place.
There are a number of circumstances and situations where the loss of brake
capacity may lead to collision without other malfunctions occurring. These
are described in Appendix C.
1. Crossover stations48
2. Station with connection to line/track 49
3. Simultaneous entrance to station when trains meet.
4. Conventional station
If any of situations 1 to 4 arises the train brakes to a stop. In addition, it
would require that there is another train which is so close that a collision
cannot be avoided. The circumstances are illustrated in a fault tree below.
48 A crossover station is a station on a double track where there can be four switches which make it possible to change between left and right tracks from both directions. 49 Station where another line is connected
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
40 (91)
Figure 2. Fault tree – collision with moving train
Estimated frequencies and probabilities for these events/circumstances are
documented below.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
41 (91)
Event/
circumstances
"Best estimate"
frequency level/
probability
Sensitivity assessment
Max Min
0. Loss of
braking
capacity
Frequency level:
"Probable" in
accordance with the
above.
For winter traffic
frequency level
"Frequent" is
considered a
reasonable estimate
since a limitation
to winter
conditions implies
that the frequency
increases by just
over a factor of 2.
Not relevant
1. Situation 1
– 4 occurs
For 10% of total running
time the train is in the
situation of braking to a
stop. Example; three
hour journey with four
approaches /exits and
train meetings each of
five minutes gives
20/180 = 0.11
Probability 0.1
Considered to be
small variations –
adjustment not
relevant
Considered to be
small variations –
adjustment not
relevant
2. Another
train is on the
track ahead
An estimate on the low
side is that another train
is present in at least
10% of cases
Probability 0.1
Another train may
be present in up to
every other case
Probability 0.5
10% is considered
to be a low
estimate –
adjustment not
relevant
3. Another
train too close
to avoid
collision
This is difficult to
assess, as it varies
greatly depending on
traffic conditions, best
estimate considered to
be 10% of cases.
Probability 0.1.
In heavy traffic this
figure may be
higher. Probability
0.3
In light traffic this
figure may be
significantly lower.
Probability 0.01
Table 6. Estimate of frequencies/probabilities
This gives the following frequency levels for event 1.1 Collision with
another train:
Best estimate: Probable*0.1*0.1*0.1 → Rare
Max: Frequent*0.1*0.5*0.3 → Occasional
Min: Probable*0.1*0.1*0.01 → Improbable
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
42 (91)
This results in the following risk categories:
Best estimate: Undesirable
Max: Intolerable
Min: Undesirable
This is illustrated in the figure below.
Figure 3. Risk category/categories for event 1.1 Collision with other train.
1.2 and 1.3 Collision at low speed with another stationary vehicle/object
and derailment due to excess speed through a switch or hitting a buffer
stop
Events 1.2 and 1.3 are considered to have the same severity and are together
adjudged to have a frequency which is a factor of 10 higher than event 1.1.
In order for event 1.1 to occur there would have to be another train present
within a "dangerous distance". This requirement is not relevant here. In the
situations in question there is often a track barrier or a safety switch leading
into a buffer stop, so if braking is not possible there would be a derailment
or a collision with a buffer stop. The lowest frequency class from 1.1
(Improbable) stems from the probability of another train being within a
dangerous distance in this case was set at 0.01. This is not relevant.
This produces the following frequency levels for events and 1.2 and 1.3
combined:
Best estimate: Rare
Max: Probable
Min: Rare
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
43 (91)
This results in the following risk categories:
Best estimate: Undesirable
Max: Intolerable
Min: Undesirable
This is illustrated in the figure below.
Figure 4. Risk category/categories for events 1.2 and 1.3 combined. Collision at low speed with another stationary vehicle/object and derailment due to excess speed through a switch or hitting a buffer stop.
1.4 Signal passed at danger (SPAD) without collision or derailment
Of the 15 events with reduced braking capacity, three resulted in SPAD.
Frequency is adjudged, therefore, to be at least 1/10 of the frequency of all
events and thus assessed according to:
Probable*0.1 → Occasional.
If, on the other hand, the initial frequency is set as frequent in accordance
with the above, the assessment would be:
Frequent*0.1 → Probable.
Severity has been assessed as "Marginal", giving the risk category
"Undesirable", illustrated in the figure below.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
44 (91)
Figure 5. Risk category/categories for event 1.4 SPAD without collision or derailment.
1.5 Loss of braking capacity without SPAD
The frequency class for Reduced braking capacity without SPAD is
evaluated above as Probable (best estimate) or Frequent (Max). Together
with severity class Insignificant this produces risk categories Tolerable –
Undesirable.
This is illustrated in the figure below.
Figure 6. Risk category/categories for event 1.5 Reduced braking capacity without SPAD
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
45 (91)
2.2 Repeated testing and exercising of brake
Testing and exercising of brake shall always be carried out when the
weather conditions are such that there is a risk of loss of brake capacity.
Thus the frequency category is "frequent". Negative consequences in the
form of worse journey times and increased costs will always arise too.
This exercising is fundamental to ensuring braking distances for wagons
with composite brake blocks and must be carried out manually by the driver.
Driver action being the first line of safety goes against the desired
development where technical systems should be the first line of action. It
also goes against the safety culture the railway undertakings are trying to
implement; a positive safety culture, including provision of a suitable
working environment, will contribute to safety. Encouragement of positive
safety behaviour.
In an operational railway environment individuals, regardless of their
training, expertise, experience, ability and goodwill, may be confronted with
situations where the limits of human reliability in combination with
undesirable and unpredictable actions by the system may lead to undesirable
results. For this reason, necessary measures should be taken to manage
risks, including those which are related to the limits of human reliability.
Good safety management is proactive and relies on a risk-based strategy.
Transferring more responsibility for safety to the driver works against these
goals.
The severity has been rated "Insignificant", which produces the risk
category "Undesirable", illustrated in the figure below.
Figure 7. Risk category/categories for event 2.2 Repeated testing and exercising of brake.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
46 (91)
Other events
Event 2.1 There is "always" stress during these weather conditions.
However, in this study it has not been viewed as possible to estimate the
probability that this would lead to absence from work or other impact on the
driver. Therefore, this event has not been accorded a risk category. The fact
that certain drivers refused to drive trains with composite brake blocks does,
nevertheless, mean that the problem is real and must be taken into account.
4.4 Comparison with the reference system.
The reference system consists of cast-iron brake blocks in accordance with
chapter 2.7.1
Regarding the events defined as "SPAD" and "train does not have braking
capacity", it can simply be stated that neither Green Cargo nor Hector Rail
have received a report of any such events for trains whose wagons are
equipped solely with cast-iron brake blocks. On the other hand, as reported
in chapter 3.1, six such events have been reported for trains whose wagons
are equipped with composite blocks. In addition, it should be noted that
these events occurred in spite of the operational measures taken in
accordance with chapter 2.6. Wagons with composite brake blocks comprise
a very small part of the total traffic in service. The conclusion from this is
that the introduction of composite brake blocks has increased the risk of
SPAD.
Comparison with the total number of reported SPAD incidents is, on the
other hand, much more difficult. A relatively large number of SPAD
incidents are reported each year, as shown in the figure below
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
47 (91)
Figure 8. The total number of SPAD reported on the Swedish rail network from 2015 to 2018. Source: Nationella OSPA-gruppen (National SPAD group)
Compared with these figures, the number of SPAD incidents due to
deficient brake capacity as a result of composite brake blocks is marginal,
but the following factors must be taken into account when making such a
comparison:
The number of SPAD incidents reported due to composite brake
blocks is probably underestimated since previously there has been no
information regarding the proportion of the total braked weight of
the train coming from composite blocks.
The material as a whole includes both passenger and freight traffic.
Without the operational measures taken in accordance with chapter
2.6, it is reasonable to assume that the number of SPAD incidents
due to composite brake blocks would be considerably higher. Many
of these measures, for example greatly reduced speed and cancelled
trains where test braking showed low brake performance, themselves
produce unacceptable consequences for rail traffic.
The material regarding rail traffic which resulted in the reported
SPAD events with composite brake blocks is very limited compared
with the material on which overall SPAD reporting is based.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
48 (91)
Regarding SPAD which occurred for reasons other than loss of
braking capacity there is often a chance for the driver or the
technical system to avoid an escalation of the event. If there is no
braking capacity, both the driver and the technical system are out of
play.
As the proportion of composite brake blocks increases the probability of
negative traffic impact also increases. Ultimately, the likelihood of more
SPAD incidents increases which in turn leads to increased risk of serious
impact on humans, environment and/or property.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
49 (91)
4.5 Risk assessment – comparison with criteria
4.5.1 Risk assessment based on explicit risk estimates
Estimated risk categories for the following events are shown in the figure
below.
1.1 Collision with another train
1.2 and 1.3 Collision at low speed with another stationary
vehicle/object and Derailment due to excess speed through a switch
or hitting a buffer stop.
1.4 Signal passed at danger (SPAD) without collision or derailment.
1.5 Loss of braking capacity without SPAD
2.2 Repeated testing and exercising of brake
.
Figure 9. Estimated risk categories.
A majority of the events lie in the Undesirable category. The most serious
event "Collision with another train" may, depending above all on which
conditions are in place regarding other traffic, be placed in the categories
from Intolerable to Undesirable. Events 1.2 and 1.3 Collision with stationary
object/derailment may also, depending on circumstances, be placed in a
category from Intolerable to Undesirable.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
50 (91)
4.5.2 Risk assessment based on comparison with the reference system
In the case of risk assessment based on comparison with the reference
system, the judgement is that the introduction of composite brake blocks
instead of cast-iron brake blocks resulted in an increased risk of SPAD, in
spite of the operational measures taken.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
51 (91)
5 Identification of possible measures
These measures should not be seen as in themselves reducing risks to an
acceptable level. Rather a combination of measures will be required, partly
over a transition period and also on a permanent basis. Also, national and
international measures must be taken, for example in the form of changes to
the European Commission's regulations 1304/2014 TSI Rolling stock –
noise and 321/2013 TSI Rolling stock – freight wagons.
These measures are also intended as operational rules for freight wagons
and locomotives. The judgement is that measures are required within all
these areas.
The nature of these measures is partly to increase safety and partly to enable
traffic to move at good speed.
For certain measures detailed there is an in-depth account of the advantages
and disadvantages in Appendix F.
At this time the proposals have not undergone consequence analysis or cost-
benefit analysis. This must be done and also there may be other measures
which need to be taken into account.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
52 (91)
Number Possible measure Impact
G Investigate and test improvements for
freight wagons:
Sub items (G*) provide suggestions for
measures regarding freight wagons.
G1 Develop new testing methods for brake blocks.
Existing tests are carried out within a limited
temperature range which does not correspond
to real conditions. Realistic test conditions
should correspond to temperature, fly-off snow
and realistic conditions regarding exercising
the brake.
Potentially a general requirement for thermal
conductivity may be developed. This could be
tested/calculated relatively easily.
For example, testing could take place under
Module CV in-service running and supervision
of registered organisations. Module CV means
that testing of brake blocks takes place during
in-service running under the auspices of the rail
companies. The registered organisation then
validates the operational experience, together
with other tests which the manufacturer of the
blocks can carry out in bench tests and which
must have passed with approved results before
in-service running takes place.
The registered body issues a certificate
indicating what conditions the blocks may be
used in.
The brake blocks are the interoperability
constituent in TSI freight wagons.
Brake blocks which have
been approved in accordance
with new methods, tests
under real Nordic conditions
provide good braking
performance in wintertime.
Increased transparency where
all test protocols are made
available to whoever wishes
to see them.
The cost of the verification
test will fall, even though
winter tests themselves cost
in the region of SEK 1
million.
G2 Wagons with operational areas consistent with
the Swedish railway system are not permitted
during maintenance to change to, or under
renovation be equipped with, composite brake
block configurations marked with NOT OK or
NOT TESTED in Appendix E.
This means existing wagons
are prevented from being
equipped with brake blocks
with substandard function.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
53 (91)
Number Possible measure Impact
G3 Implement load restrictions and in this way
obtain margins. For wagons with deficient
braking capacity, loads are permitted in relation
to the braked weight of the wagon. Load
restrictions should be established for each
brake configuration.
Allows preservation of line
speed.
Major financial
consequences for transport
purchasers.
G4 Reduce the braked weight which is included in
the braking calculation for the train. Such a rule
would mean that deficient braking capacity for
both empty wagons and wagons loaded up to
the maximum braked weight would be
compensated for. The order of magnitude of
this reduction may be determined based on
tests and in-service running.
Create margins during
braking.
Lower speed
G5 When converting to LL blocks braked weight
shall be maintained or increased.
The empty braked weight shall, if possible, also
be adjusted upwards so that margins are also
maintained for empty wagons and so that the
lowest pressures between wheel and brake
block are avoided.
The impact of increased
margins.
Refitting costs.
G6 Remove the UIC requirement for kink valves50
on wagons with a braked weight of greater than
14.5 tonnes plus 15 % (16.7 tonnes) per axle.
This requirement and its accompanying costs
have meant that rolling stock owners have
reduced or only maintained braked weight of
the wagons when modified to composite brake
blocks.
Significantly reduced
refitting costs for wagons
with s or ss brakes if braked
weights are to be increased
or kept high. This applies to
wagons with RLV (Load
proportional valve) and in
particular to w agons without
such valves.
For rolling stock rakes with
identical wagons a more
proportional braking function
is obtained
50 Requirement in accordance with UIC 541-4, section 2.1.4.1, 3rd indent applying to LL brake blocks and section
2.1.4.2, 4th indent applying to K brake blocks
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
54 (91)
Number Possible measure Impact
G7 Proposal for potential measures for new freight
wagons is to equip the wagons with disc
brakes.
The function of disc brakes is adjudged to be
less sensitive to winter conditions based on
those tests previously carried out by Green
Cargo, the Swedish Transport Agency, and
VTG.
Considered to provide
working braking function in
winter time.
Increased costs of wagons
G8 Proposal for potential measures for new freight
wagons:
- Higher actual brake percentage when
empty (lambda 115–120 % empty)51and 18
tonnes braked weight per axle, and
- if the wagon is equipped with K brake
blocks it should be in the configuration
1xBgu52 and
- use only brake configurations with
acceptable winter properties. Experience
has shown that the current approval system
regarding brake configurations has
shortcomings and thus does not provide
guidance. For this reason it is necessary to
base decisions on experience and tests and
- brake systems must have stable53 (and
high) efficiency levels (e.g. "Compact
Freight Car Brake Unit”)
Proposals for the raising of
brake pressure, brake
configurations and efficiency
levels are intended to ensure
that braking performance is
maintained in the winter
months via an increase of
margins and in such a way as
to mitigate the negative
impacts of the loss of braking
performance with composite
brake blocks.
Increased costs of wagons
51 The purpose here is to avoid the lowest pressure between brake blocks and wheel so that the abrasion is attained
which is very likely to remove ice from the brake blocks and provide a certain margin, since only λ=100 % is
included. 52 K brake blocks in the configuration 1 x Bgu avoid very low pressure between wheel and brake block when
empty in comparison with 2 x Bg and 2 x Bgu, since the total nominal brake block area increases by 28 % for
2 x Bg, and 100 % for 2 x Bgu respectively. K brake blocks in the configuration 1 x Bg mean that the nominal brake block area would be reduced by a further 36 %, but since the braked weight must usually then be reduced
there is normally no alternative. There are clear indications that at low pressure ice is not successfully removed,
especially on high friction blocks where the pressure is already low due to the high friction. 53 A stable level of efficiency compensates for the increased risk of wheel flats if the actual empty braked weight is
raised.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
55 (91)
Number Possible measure Impact
L Investigate and test improvements to
locomotives.
Sub items (L*) provide suggestions for
measures regarding locomotives.
L1 Introduce warm braking function on
locomotives.
This function means that the locomotive can
operate with traction while at the same time
HLL is reduced and thus the wagons are
exercised. In this way it is possible to make
exercising appreciably more efficient, since
average speed would not be lost and since
exercising of freight wagon brakes will take
place at high speed (where brake power is
high). The system requires that the brake of the
locomotive are not active (since there is no
need to condition them as they have an
effective braking system).
May increase the possibility
of operating trains with
composite brake blocks in
winter conditions without
compromising load or speed.
The current assessment is,
nevertheless, that these
measures do not solve the
problem for the blocks with
the worst properties.
Costs for modification of the
locomotive.
L2 Introduce brake inhibition valves on the
locomotives.
Brake inhibition valve (or secondary brake
valve) means that the indirect brake of the
locomotive is inhibited except when full
service brake or emergency/fast/train safety
system brake is demanded. Note that there are
variations of what HLL pressure constitutes the
boundary for when the locomotive brake is
activated. An alternative to having this valve is
that during each exercising of CBB’s the
locomotive brake is released manually.
May increase the possibility
of operating trains with
composite brake blocks in
winter conditions without
compromising load or speed.
The current assessment is,
nevertheless, that these
measures do not solve the
problem for the blocks with
the worst properties.
Costs for modification of the
locomotive.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
56 (91)
Number Possible measure Impact
L3 Electric brake at system emergency braking
In Sweden, when rolling stock is equipped with
electrodynamic brake, these are always
disconnected at emergency, rapid, train safety
system or drivers vigilance device braking. The
reason for this is that it has been difficult to
demonstrate theoretically that the traction block
has the requisite safety levels in these brake
modes when electro-dynamic brake is applied.
Note also that in Sweden braked weight is
never used for R+E or P+E in the calculation of
a train’s braking performance. Thus, in Sweden
we have chosen to protect ourselves against a
possible fault in the traction block (which has
never occurred).
May increase the possibility
of operating trains with
composite brake blocks in
winter conditions without
compromising load or speed.
The current assessment is,
nevertheless, that these
measures do not solve the
problem for the blocks with
the worst properties.
Costs for modification of the
locomotive.
L4 Introduction of automatic exercising
equipment.
Such equipment means that the locomotive will
automatically carry out exercising cycles on the
wagons by automatically reducing HLL. The
exercising cycle can be adapted in terms of size
reduction, duration and interval.
May increase the possibility
of operating trains with
composite brake blocks in
winter conditions without
compromising load or speed.
The current assessment is,
nevertheless, that these
measures do not solve the
problem for the blocks with
the worst properties.
Costs for modification of the
locomotive.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
57 (91)
Number Possible measure Impact
D Investigate and test improved guidelines for
operation.
Sub items (D*) provide suggestions for
operational measures
D1 Exception from TSI Noise to permit cast-iron
blocks until 2028, applies to approximately
17,500 wagons
This would allow traffic to
continue unaffected in
Sweden in the wintertime.
This proposal allows high
noise wagons to operate on
the continent.
D2 Report the total braked weight of the train
provided by composite blocks and cast-iron
blocks respectively. Currently the number of
wagons which have composite blocks and cast-
iron blocks are reported. This gives a
misleading picture since braked weight
depends on actual load, the number of axles,
load capacity and braking capacity for each
individual wagon.
The reporting should be divided up into
composite blocks with and without verified
winter properties.
Information regarding how
large a proportion of the
train's total braked weight is
made up of wagons equipped
with composite brake blocks
gives the driver a clearer
picture of how the braked
weight is arranged and thus
provides the driver with
guidance on how to manage
the brake. The effect of this
would be a more restrictive
way of braking, leading to
larger safety margins.
D3 Reduced speeds for freight trains Improved braking margins.
Major rail traffic and
financial consequences arise
(see Table 8); when too
great speed reductions are
required speed may become
so low that access to the
track is not granted.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
58 (91)
Number Possible measure Impact
D4 Investigate the possibility of applying different
rules for different zones in Sweden during
winter conditions. The intention is to introduce
rules which manage those factors which affect
braking capacity, i.e. combination of low
temperature and fly-off snow.
Limitations are implemented
only when they are useful for
safety considerations. Track
speed or load capacity are
limited only where this
contributes to increased
safety.
D5 Improved exercising technique (operational
rules). Develop the regulatory framework for
drivers. Currently there are a number of driver
measures required which probably have little or
no impact on improving safety. Also introduce
other measures which may have an impact
here.
These measures must be developed to take into
account the functionality of the locomotive.
Regular exercising of the
brake results in reduced
speed.
Drivers might well be able to
carry out the exercising
manually.
Laying responsibility for
safety on the driver rather
than on the automatic system
is a negative factor.
D6 During parking full service brake to prevent
rolling.
This means that the risk of wheel flats due to
freezing will increase as will the risk of delays,
since all frozen blocks must be freed and/or
wagons with wheel flats must be changed out
from the train.
Risk of freezing and wheel
flats.
D7 Extra wagons with cast-iron blocks in parallel
with other wagons. Very large negative effect;
reduced exercising of CBB,
large amounts of shelling on
the wheel, increased
frequency of wheel flats, the
risk of hiding non-tested
CBB wagons
Table 7. Possible safety enhancement measures
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
59 (91)
Negative effects of reduced speed and reduced load respectively. Principal effects of reducing the maximum permitted speed to 80 km/h
(alternatively exercising/testing brake every 15th minute) have been
investigated in a number of reports,54 and are displayed in the table below.
Many of these effects also arise with a reduced load, but this has not been
investigated.
Impact of reduced speed
Reduced freight train capacity
Reduced line capacity which also impacts on passenger trains
Increased transport costs for rail companies (track charges, tickets, etc.)
Increased production cost for railway companies, more wagons, locomotives, drivers
Increased journey times
Shift from railway to road and sea haulage
Increased transport costs for industry (transport purchasers)
Increased environmental impact (CO₂, NOX, Noise, Accidents) when shifting from rail
transport to road and sea haulage
Negative impact on logistics, production planning and warehousing for industry
Collapse of market for single wagon load trains
Insufficient shunting capacity
Worse wagon logistics if extra wagons with cast-iron brake blocks must be used in parallel
with other wagons
Table 8. Impact of reduced speed
54Macroeconomic effects and changed emissions of air pollution and CO2 as a consequence of new regulation of railway noise, Lena Wieweg, Trafikverket, 2018. The national model for freight transportation in Sweden,
REPORT Representation of the Swedish transport and logistics system in Samgods v. 1.1. (Trafikverket, VTI
2016). Konjunkturinstitutet EMEC analysis of proposals for new regulation of noise from railway freight traffic (Ref 2018-209) dated 21 December 2018
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
60 (91)
6 Conclusions of the risk analysis
Based on the risk analysis and test results, the following conclusions have
been drawn:
There are composite brake blocks which have demonstrated
substandard properties in winter conditions and the use of these
implies an intolerable level of risk; a combined report on tested and
non-tested blocks and results of tests and in service running is given
in Appendix E.
Those incidents which form the basis of the risk analysis occurred
despite the implementation of a number of operational measures.
These measures are already producing unacceptable consequences
such as delayed and cancelled trains. Further operational measures
(increased test braking/exercising of brake etc.) would have
completely unacceptable consequences and would fail to solve the
problem. Increased numbers of SPAD incidents due to a deliberate
choice of new technical solutions is not acceptable and neither is it
acceptable to transfer responsibility for safety from the technical
system to the driver via further operational instructions.
Currently no incidents or events with trains fitted with only LL-type
composite brake blocks have been reported by Swedish railway
undertakings. It should be noted that there are only very few trains
with solely LL brake blocks in northern Sweden. On the other hand,
tests have shown that these blocks may have significantly lower
braking performance than cast-iron brake blocks.
The current procedures according to UIC (see section 2.6.1) for the
testing of composite brake blocks in winter conditions do not
correspond to actual Nordic winter conditions.
Based on these conclusions, incidents which occurred and test results,
possible measures have been identified. These must be investigated
further. The possible measures identified concern freight wagons,
locomotives and operational rules. These measures should not be seen as
in themselves reducing risks to an acceptable level. Rather a
combination of measures will be required, partly over a transition period
and also on a permanent basis. Measures also need to be implemented at
national and international levels. One of these measures, which, during a
transition period, would reduce the risk and enable international
transport to and from Sweden, is an exception from the rules so that a
number of freight wagons with cast-iron brakes are allowed to operate
internationally.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
61 (91)
Appendices
A. Summary of incidents
B. Risk analysis protocol
C. Situations where loss of braking capacity can lead directly to
collision with another train
D. Braking capacity - seen theoretically and practically from the
perspective of the locomotive driver
E. Comments to ERA´s list of fully approved UIC composite brake
blocks for international transport
In-depth account of advantages and disadvantages of certain proposed
measures
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
62 (91)
Appendix A. Summary of incidents
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
63 (91)
Green Cargo Incidents
No Date Synergy-
number
Train affected Brake blocks Description Result
1 26-02-
2015
48712 Jet-Fuel Shuttle Cosid 810 100% Braking power very poor on line Had to lower maximum speed from 100 to
80 km/h
2 24-04-
2015
49284 Jet-Fuel Shuttle Cosid 810 100% Braking power very poor on line Had to lower maximum speed from 100 to
80 km/h
3 07-05-
2015
49475 Jet-Fuel Shuttle Cosid 810 100% Braking power very poor on line After a lot of deceleration tests, 100 km/h
was ok
4 03-01-
2016
51713 Jet-Fuel Shuttle Cosid 810 100% Unpermitted passing of STOP-
signal
At low speed in snowy and icy conditions,
the driver could not stop in time. The train
was stopped 20 m after the position of the
signal.
5 13-04-
2016
52538 Jet-Fuel Shuttle Cosid 810 100% Braking power very poor on line Had to lower maximum speed from 100 to
80 km/h
6 14-04-
2016
52545 Steel Shuttle
"Hälleforspendeln“
ABEX 229/M128
Composite brake
blocks (Note 25 tonne
axle load) 100%
Braking power very poor on
line, mixed blocks
After a lot of deceleration tests, 100 km/h
was ok
7 25-11-
2016
54368 Moelven Pellet
Train
Jurid 816M 100% Unpermitted passing of STOP-
signal
Driver was unaware that the train only had
CBB brakes and failed to stop in time. The
train was stopped 20 m after the position of
the signal.
8 10-01-
2017
55732 Ore-shuttle
"Aitikpendeln”
mix of 60 %
S154/C810 Composite
brake blocks and 40%
M134/S153 sintered 9
Braking power very poor on line Often, the maximum speed has to be
lowered from 80 to 70 km/h when about
90% CBB
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
64 (91)
No Date Synergy-
number
Train affected Brake blocks Description Result
brake blocks (Note 25
tonne axle load)
9 25-01-
2017
55855 Jet-Fuel Shuttle Cosid 810 100% Braking power very poor on line Had to lower maximum speed from 100 to
80 km/h
10 01-02-
2017
55906 Jet-Fuel Shuttle Cosid 810 100% Braking power very poor on line 100 km/h was ok despite the lower brake
effect (shorter train)
11 04-02-
2017
55947 Train 6000
between Boden
and Haparanda -
Wagon load train
Mixed brake blocks Complete of loss braking power deteriorating conditions as train came
closer to destination. Almost no braking
power at the end. Minus 3 degrees and
heavy snowdrift.
12 22-02-
2017
56054 Moelven Pellet
Train
Jurid 816M 100% Braking power very poor on line Had to lower maximum speed from 100 to
70 km/h. Light snowfall, -2 degrees
13 29-11-
2017
59383 Train 9662 -
Ställdalen - Wagon
load train
Mixed brake blocks Braking power very poor on line Had to lower maximum speed from 100 to
70 km/h. Heavy snowfall, -2 degrees.
Speed increase from 66 km/h to 70 km/h
going downhill to Ludvika despite 0.7 bar
brake applied.
14 12-01-
2018
59887 Moelven Pellet
Train
Jurid 816M 100% Braking power very poor on line Had to lower maximum speed from 100 to
80 km/h
15 12-01-
2018
59887 Moelven Pellet
Train
Jurid 816M 100% Braking power very poor on line Had to lower maximum speed from 100 to
80 km/h
16 08-04-
2018
63909 Moelven Pellet
Train
Jurid 816M 100% Braking power very low on line Had to lower the speed from 100 to 80
km/h
17 07-02-
2019
75057 Moelven Pellet
Train
Jurid 816M 100% Lost braking force
Possibly SPAD
The train was 70m from colliding with two
parked locos
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
65 (91)
Hector Rail incidents
Number Date Weather
conditions
Incident description Causes Type of wagon Brake block
manufacturer
/ type
1 11-
12-
2017
16:45
Temp: ≈ -10 ° C.
Fly off snow.
Signal passed at Danger
Driver started to brake at 10 km/h. Braking
capacity was extremely low. Passed
approximately 30 meters.
Poor braking capacity Different tank
wagons
High proportion
with CoFren
C810 and
Becorit IB116*
(small amount
of GG)
2 08-
01-
2018
02:00
Temp: ≈ -10 ° C.
Fly off snow.
No incident. Train 41850 from Piteå-
Murjek was stopped in Arnemark 25 km
from Piteå due to poor retardation. Returned
to Piteå with Vmax 30 km/h.
Poor braking performance
from the wagons
13 x Sggrrs Federal Mogul
Jurid 822
3 22-
03-
2018
23:30
Temp: -10 °C ≤ T
≤ -24 °C
Clear weather.
Some minor fly-
off snow.
No incident. Shunting and train operation
was observed. Including shunting in
Svedjan. Train from Piteå-Murjek. Shunting
in Murjek.
Poor braking capacity 12 x Sggrrs Federal Mogul
Jurid 822
4 26-
03-
2018
04:22
Temp - 10 °C
Fly off snow
Report on low braking performance in train
operation. Driver performed several
retardation tests with λ-values around 45 %.
Finally it was very close to passing the
entry signal Nyf 2/6 at danger. Train came
to stop 1 meter in front of signal. λ-value
from emergency brake was 30 %. Nominal
λ-value was 88 %
Poor braking performance
from the CBB wagons
Train consists of:
10 x Sggrrs at tara
weight
2 x Sgnss with a
total weight 27
tonnes incl. loading
equipment
Federal Mogul
UIC GG
Jurid 822
GG
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
66 (91)
Number Date Weather
conditions
Incident description Causes Type of wagon Brake block
manufacturer
/ type
5 23-
12-
2018
20:00
Temp. -21 °C. Fly
off snow.
Passing of level crossing and point in wrong
direction in shunting operation at
approximately 20 km/h. About 200 meters
before level crossing driver brakes with 1
bar, then realising that brake is insufficient
and goes to full service brake and then
emergency brake
Poor braking performance
from the wagons
Train consists of:
13 x Sggrrs at tara
weight
1 x Sgnss with a
total weight 27
tonnes incl. loading
equipment
Federal Mogul
Jurid 822
UIC GG
6 16-
01-
2019
00:00
Temp. -21 °C. A
lot of snow on
track
approximately 10
cm. Fly off snow.
Signal passed at danger. Poor braking performance
from the wagons in
combination with other
disturbances.
Train consists of:
5 x Sggrrs with a
total weight of 145
tonnes
5 x Sggrrs with a
total weight of 134
tonnes
3 x Sgnss with a
total weight of 72
tonnes
Federal Mogul
Jurid 822
UIC GG
7 22-
01-
2019
04:40
Temp. - 25 °C. Fly
off snow.
No incident but cancelled train. Train was
stopped approximately 30 minutes after
departure due to poor retardation. Measured
retardation value was not sufficient for train
operation. Train returned to departure
station with Vmax=30 km/h.
Train was stopped due to
low brake performance
13 x Sggrrs Federal Mogul
Jurid 822
8 23-
01-
2019
20:30
Temp. -7 °C.
Snow on track.
Fly off snow.
Passing of (ETCS) End of Authority (EoA)
at marker board.
Poor braking performance
from the wagons in
combination with other
disturbances.
19 x Sggrrs Federal Mogul
Jurid 822
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
67 (91)
Number Date Weather
conditions
Incident description Causes Type of wagon Brake block
manufacturer
/ type
9 24-
01-
2019
04:40
Temp. - 20 °C. Fly
off snow.
No incident but cancelled train. Train was
stopped approximately 30 minutes after
departure due to poor retardation. Measured
retardation value was not sufficient for train
operation. Train returned to departure
station with Vmax=30 km/h.
Train was stopped due to
low brake performance
13 x Sggrrs Federal Mogul
Jurid 822
10 31-
01-
2019
04:40
Temp. - 27 °C. Fly
off snow.
No incident but cancelled train. Train was
stopped before departure due to poor
braking performance which was identified
at low speed (shunting).
Train did not depart due to
low retardation identified
in shunting operation (low
speed operation with
connected HLL).
13 x Sggrrs Federal Mogul
Jurid 822
11 04-
02-
2019
04:40
Temp. - 14 °C. Fly
off snow.
No incident but cancelled train. Train was
stopped before departure due to poor
braking performance which was identified
at low speed (shunting).
Train did not depart due to
low retardation identified
in shunting operation (low
speed operation with
connected HLL).
13 x Sggrrs Federal Mogul
Jurid 822
12 05-
02-
2019
04:40
Temp. - 21 °C. Fly
off snow.
No incident but cancelled train. Train was
stopped before departure due to poor
braking performance which was identified
at low speed (shunting).
Train did not depart due to
low retardation identified
in shunting operation (low
speed operation with
connected HLL).
13 x Sggrrs Federal Mogul
Jurid 822
13 22-
02-
2019
00:11
Temp. - 12 °C. Fly
off snow.
No incident but cancelled train. Train was
stopped before departure due to poor
braking performance which was identified
at low speed (shunting).
Train did not depart due to
low retardation identified
in shunting operation (low
speed operation with
connected HLL).
13 x Sggrrs Federal Mogul
Jurid 822
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
68 (91)
Number Date Weather
conditions
Incident description Causes Type of wagon Brake block
manufacturer
/ type
14 27-
02-
2019
11:50
Temp. + 4 °C
(uncertainties
regarding actual
temperature). Fly
off snow.
No incident but cancelled train. Train was
stopped before departure due to poor
braking performance which was identified
at low speed (shunting).
Unclear. 13 x Sggrrs Federal Mogul
Jurid 822
15 06-
03-
2019
11:50
Temp. - 9 °C. Fly
off snow.
No incident but cancelled train. Train was
stopped before departure due to poor
braking performance which was identified
at low speed (shunting).
Train did not depart due to
low retardation identified
in shunting operation (low
speed operation with
connected HLL).
13 x Sggrrs Federal Mogul
Jurid 822
16 12-
03-
2019
07:00
Temp. -18 °C. Fly
off snow
Passing of signal at danger Driver started to
brake well ahead and long before
intervention from train safety system.
Poor braking performance
from the wagons.
19 x Sggrrs Federal Mogul
Jurid 822
17 02-
11-
2019
12:30
Temp: -10 °. Clear
weather. Some
minor fly-off
snow.
No incident. Report of low braking
performance at shunting
Poor braking performance
from the wagons
2 x Uacns CoFren
C810
18 03-
11-
2019
10:40
Temp: +0.7 °C.
Light snowfall
Report on low braking performance at
shunting. Not an incident since driver
observed the reduced braking capacity and
adjusted speed.
Poor braking performance
from the wagons.
9 x Sggrrs CoFren
C810
19 30-
11-
2019
00:00
Temp at incident
"a few degrees
minus" but after "a
cold night"
Poor braking performance at shunting in
Lycksele. 19 Sggrrs + TMZ diesel
locomotive
19 x Sggrrs CoFren
C810
20 01-
03-
2020
00:00
Temp -13 °C light
snowfall
Poor braking performance at shunting in
Storuman. 19 Sggrrs + TMZ diesel
locomotive
19 x Sggrrs CoFren
C810
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
69 (91)
Number Date Weather
conditions
Incident description Causes Type of wagon Brake block
manufacturer
/ type
21 29-
03-
2020
01:00
Temp ≈ -5 to -10
°C
AND some fly off
snow.
Shunting incident in Storflon. Train 41721.
Parked train with service brake 3.5 < HLL <
4.4 roll away at standstill when loco was
running round.
Poor braking performance
from the CBB-wagons at
standstill, 1/3 of wagon
brake in 10 ‰ downward
slope.
22 x Sggrrs
Federal Mogul
Jurid 822
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
70 (91)
Appendix B. Risk analysis protocol
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
71 (91)
Haz.
ID
Description of
failure event
Input:
No of
operating
hours
Input:
No of
Occurre
nces
Frequency
of
occurrence
(year
round)
Frequen
cy of
occurre
nce
(year
round)
Consequences Severity Frequency
of
occurrence
(best
estimate)
Risk
level before
additional
safety
measures
1 Reduced brake
performance
when braking
leading to
prolonged brake
distance
Hector Rail:
35555
Green
Cargo:
21000
15
7
4*10-4
3*10-4
Probable
Probable
1.1 Collision with a moving
train
Catastrophic Rare Undesirable
1.2 Collision at low speed
with another object at
standstill
Critical Rare Undesirable
1.3 Derailment due to too
high speed through a switch
or running through buffer
stop
Critical Rare Undesirable
1.4 Signal passed at danger
(SPAD) w/o collision or
derailment
Marginal Occasional Undesirable
1.5 Loss of brake
performance w/o SPAD
Insignificant Probable Tolerable
2 Driver anxiety
due to varying
brake capacity of
the train
2.1 Stress leading to stress
related disease
Marginal Not
assessed
Not
assessed
2.2 Repeated test- and
exercising of the brakes
Insignificant Frequent Undesirable
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
72 (91)
Appendix C. Situations where loss of braking capacity can lead directly
to collision with another train
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
73 (91)
1. “Crossover stations”
A crossover station is a station on a double track where there are
four switches which permit trains from both directions to change between
the left and the right track. These stations also do not have normal safety
switches.
In the example above the route is set for train A, “ TÅG A” in the figure,
driving through signal 52 and on through the station and driving out to
signal U42. The train route is marked in green. The train will switch over to
the other track.
Train B is coming from the other direction on the same track. The train
stops at the approach signal, Signal 21. After train A has passed the station
train B is permitted to drive through.
If train B does not have braking capacity when it arrives at approach signal
21 there will be a SPAD A at approach signal 21 and the train will move
directly into the path of train A. Train A will be travelling at the maximum
permitted speed at certain crossover stations, as much as 130 km/h when
certain switches permit this.
Risk of collision exists.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
74 (91)
2. Connecting track:
Certain stations are branch stations. This means that two (or more) different
lines are joined together at the station.
Laxå is a good example of this, where the Värmland Line connects with the
Western Main Line.
In the above case the route is set for train A through the station passing
through approach signal 22, proceeds to the intermediate signal 24, and the
exit block signal L2. The speed of the train may be up to 200 km/h. The
route set is marked in green.
Train B arrives at the same time or just before from the connecting line and
stops at intermediate signal 2855 before the switch linking the two lines.
If train B has no braking capacity it risks driving directly into the path set
for train A with a SPAD at signal 28, or alternatively derailing close to the
other line, if there is an safety switch.
Risk of collision exists.
55 Signal 28 is partly covered by train B in the picture
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
75 (91)
3. Conventional station
At a conventional station on a single track line where trains meet one train is
admitted into the station at a time. Then the other train passes through the
station while the incoming train remains stationary in the separate main
track.
In the above picture the route is set for train A to proceed through approach
signal 22 on to intermediate signal 34 which is at stop. The train route is
indicated by the green line
From the other direction comes train A which will stop at approach signal
21 which is at stop.
After train A has moved fully in, the route for train B will be set straight
through the station for train B.
If train A does not have braking capacity train A will pass through signal 34
(SPAD-A) and collide with train B at approach signal 21.
If train B does not have braking capacity train B will pass approach signal
21 at stop (SPAD-A) and there is a risk that it will also pass through signal
31 which is indicating stop (SPAD-A), and collide with train A which is on
its way into the separate main track.
Risk of collision exists.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
76 (91)
4. Simultaneous entry into station on a single track.
Simultaneous entry into a station means that two trains are coming from
opposite directions on a single track to the station where they will meet.
In the above case train A has its route set to pass through approach signal
22, and proceed to 84 (stop light) set to stop. For extra safety intermediate
signal 34 is also set at stop.
From the other direction train B has its route to pass through approach
signal 21 proceed to signal 81 (stop light) set to stop. For extra safety
intermediate signal 31 is also set at stop.
The stop lights which are marked are usually located well into the track,
500–600 m into the track in order to take in long trains simultaneously.
When one of the trains has come in to its track in its entirety without
problem the route is set for the oncoming train. The reason for having this
kind of station is to speed up train meets so that neither of the trains need to
stop if the trains arrive simultaneously.
The obstacle to being able to take in two trains at the same time is that these
stop lights are also governed by ATC.
If either of the trains does not have braking capacity that train would carry
out several SPAD A and collide with the oncoming train.
Risk of collision exists.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
77 (91)
Appendix D. Braking capacity - seen theoretically and practically from
the perspective of the locomotive driver.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
78 (91)
Braking capacity - seen theoretically and practically from the
perspective of the locomotive driver.
As a locomotive driver you have a number of tasks to perform during a
shift.
A shift in this context means you will go from one station or marshalling
yard, either on a departing train or as a replacement on an arriving train
which you will take further to another station or marshalling yard following
a timetable, known as the “driving plan”.
One of your most important tasks is to be able to stop your train safely.
Every time.
Fundamental to this is that one knows how the train brakes and “behaves”,
in order to always be able to stop safely before a danger point.
There are many factors that influence and play a part in how the train
behaves during braking. Every wagon is unique, every set of wagons is
unique, every driver has his/her way of driving, etc. It is easy to think that
the same train is the same every day and that it behaves in the same way and
that it can be handled in exactly the same way, but things are not so simple.
It helps to divide freight trains into two different categories: block trains and
single wagon load trains.
Block train means the whole train consist of the same type of wagon in the
same type of load. As a rule, these trains run in a closed circuit with all the
wagons loaded, in one direction, after which the train goes back in the
opposite direction, either loaded or empty depending on the job.
Single wagon load trains consist of different types of wagon, some loaded
and some empty. The wagons are part of a network between different hubs
and transports until they reach their final decision. These trains vary greatly
in length and in weight, from day-to-day, and also by type of wagon.
As a driver, before you depart you will receive a description of your train. A
wagon list which explains how long the train is, how much each wagon
weighs, and how much each wagon brakes expressed in tonnes (braked
weight).
Information about the wagons in the wagon list is supplemented with the
same information regarding the locomotive/locomotives in the train.
All this is in "Information for the driver".
Then the brake percentage is calculated (braked weight in relation to train
weight).
This value is the technical/theoretical calculation of how much the train
brakes. This information is a vital part of the establishment of the maximum
permitted speed of the train.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
79 (91)
Following that, the driver checks in the Trafikverket line manual which
brake percentage table applies to the stretch of line the train will operate on.
The length and brake percentage of the train determine the maximum
permitted speed for that specific train on that specific stretch. The
fundamental principle is that the longer and the heavier the train, the higher
the brake percentage required for higher speeds.
The driver then inputs the following values into the train protection system;
speed ceiling, train length, brake application time, retardation value. (The
retardation value is the brake percentage recalculated as a retardation value
in order to provide the train protection system with information about how
much the train brakes.)
After departure the theoretical calculation is tested in practice via the
execution of retardation checks. There are two different types of check. R1
and R2. What differentiates R1 from R2 is how great the drop in pressure
during the test is. In practice retardation checks are as follows: When the
train has reached its cruising speed braking is initiated with a one bar drop
in pressure in the main pipe. (Retardation check R1).
Braking should develop throughout the whole train before the driver
releases the brakes.
The train speed is reduced significantly since fully applied brake power
must be reached before the brake is released. The same retardation value
that the driver input into the train protection system will now be shown if
the actual braking capacity is the same or better than the theoretical one. A
higher value than the input value cannot be seen in the train protection
system. If the driver does not get the value input he/she repeats the same
procedure, with the difference that the driver now reduces pressure to 1.5
bars. (Retardation check R2). If the driver does not get the value the
procedure is repeated one last time. If the driver does not get the value
which is theoretically calculated, the new retardation value measured with
the last R2 control must be input into the train protection system. Check
must be made with the line manual to be sure of the train’s speed ceiling
with the lower retardation value.
In addition to this check one further dimension is now added, namely how
the train behaves during braking. In certain trains the driver experiences a
rapid and substantial reaction, while on other trains the development of the
braking feels slow at first and then builds up after a while.
This behaviour varies from train to train, from day-to-day. Especially
regarding single wagon load trains which have a different composition
every day, regarding both loaded and empty wagons, their position in the
train, different ratios of composite to cast-iron brake blocks and different
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
80 (91)
train lengths.
Add to this different conditions, different weather with different adhesion.
As a driver, after your first brake applications you will have an idea of how
the train’s brakes are behaving during that particular journey. This means
that you need to and must adapt your actions in line with this.
If you experience the train as having "good brakes" this means that you have
a feeling that the margins are good. You can drive a little more offensively
without feeling there is a risk of being hurried if the situation arises where
you need to brake to a stop. For example a pre-signal that shows that there is
a stop signal 1000 m ahead (normal distant signal distance on most lines).
If you experience the train as having "poor brakes", meaning that it takes
time before full braking capacity is attained then you, as a driver, need to
drive with greater margins in order to feel that you are in full control when
encountering a stop signal.
Cast iron has historically been the predominant material in wagon brake
blocks. The advantage of cast-iron is that the braking capacity is the same
under most conditions.
Currently, circumstances are somewhat different since different composite
materials have begun to replace conventional cast-iron blocks. Brake blocks
made of composite material do not behave in an equivalent manner in all
types of temperature and weather conditions, which has resulted in a
question mark hanging over actual braking capacity.
If the retardation capacity constantly changes, such that the actual braking
capacity is unclear, the risk of SPAD increases, impacting on safety.
Uncertainty around what the retardation capacity is in practice creates a
work environment problem related to driver stress. Having to constantly
check actual braking capacity can only be done in one way, namely
repeatedly carrying out retardation checks. The impact of this becomes very
costly as journey times deteriorate further (freight trains already have
trouble finding their place in the railway network with increased ”dwelling
time” each year: if average speeds fall journey times increase significantly),
energy expenditure increases and rail transport becomes less effective
overall.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
81 (91)
Appendix E
Comments to ERA’s list of fully approved UIC composite brake blocks
for international transport
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
82 (91)
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
83 (91)
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
84 (91)
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
85 (91)
Not tested. In this configuration
Not OK
Proven in use during Nordic winter conditions.OK: Can be usedNot OK: Can not be used.Not tested: UnknownPossibly OK: Needs verification
Not tested. In this configuration
Possibly OK
Not tested. In this configuration
Not OK
Not tested. In this configuration
Not tested. In this configuration
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
86 (91)
L Investigate and test improvements for locomotives:
L1 Introduce warm braking function on locomotives
This function means that the locomotive can operate with traction while at
the same time HLL is reduced and thus the wagons are conditioned. In this
way it is possible to make exercising appreciably more efficient, since
average speed would not be lost and since exercising of freight wagon
brakes will take place at high speed (where brake power is high). The
system requires that the brakes of the locomotive are not active (since there
is no need to condition them as they have an effective braking system).
The advantages are
- that there is less loss of average speed than with exercising without
traction,
- that it is possible to attain maximum traction even at lower speeds,
since it is not necessary to brake to a stop,
- that weak exercising is avoided. There are indications that weak
exercising may even negatively affect braking capacity, which is to
be avoided,
- that exercising is not done, i.e. no wear on the locomotive brakes,
- that exercising also takes place at low speed56 and
- that the driver chooses when to condition, i.e. exercising can be
avoided in those stretches where maximum traction is required.
The disadvantages are
- that safety is transferred from the system to the driver. The driver
must decide him/herself when the exercising should take place. This
is diametrically opposed to the policy adopted,
- that there are safety issues that must be resolved, especially if there
are wagons with apparently underperforming blocks in combination
with wagons with well-functioning blocks. There is then the risk that
the wagons which have well-functioning brake blocks receive too
high braking energies in the wheels,
- that the function must be managed in such a way that running in
HLL is even and stable after each exercising cycle. Problems may
arise with small and frequent drops in HLL. This may increase the
risk of blocked brake57 and uneven braking capacity between the
wagons, with an increased risk of wheel flats.
- that for mixed trains with organic, sintered and GG blocks, the
wagons with GG blocks in particular will experience a higher degree
56 Currently traction is normally blocked if HLL is reduced at speeds over 10 km/h 57 Unintended drag brake
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
87 (91)
of wheel damage in the form of circumferential shelling58 due to the
increased braking energy since they will be braked instantaneously
with a exercising cycle (probably to be followed by damage to the
wheels of wagons with sintered blocks). With trains with only
organic and sintered blocks, circumferential shelling will probably
increase on wagons with sintered blocks compared with those with
organic blocks,
- that wear on wheels and blocks will increase on those wagons which
have well-functioning brake configurations, while wagons with
underperforming brake configurations will have normal wear and
- that it is uneconomical, due to the costs of energy and wear to blocks
and wheels on the wagons.
L2 Introduce brake inhibition valves on the locomotives.
Brake inhibition valve (or secondary brake valve) means that the indirect
brake of the locomotive is inhibited except when full service brake or
emergency/fast/train safety system brake is demanded. Note that there are
variations of what HLL pressure constitutes the boundary for when the
locomotive brakes are activated An alternative to having this valve is that
during each exercising of CBB’s the locomotive brake is released manually.
The advantages are
- that the driver does not need to release the locomotive brake
manually during exercising (if such rules are applied). This makes
things simpler,
- that exercising with the locomotive brake active is avoided if the
driver for some reason does not release the locomotive brake. In
such a case the exercising will be significantly worse, since the
locomotive brake are functioning in wintertime and will brake
immediately and absorb the braking energy that was needed to
condition the wagons, and the risk of deficient exercising is avoided,
and
- that during retardation checks after an exercising cycle (without
warm braking) the retardation value can more clearly identify
current brake performance.
The disadvantages are
- that during retardation checks the locomotive brake is not applied,
- that the indirect brake on the locomotive must be checked and that
the locomotive must be conditioned separately, since in principle the
locomotive brake will never be applied in normal running. Note,
however, that the exercising requirement for the locomotive is
negligible in comparison with the requirement for CBB wagons
58 Circumferential shelling and pitting
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
88 (91)
- that introducing these functions brings costs.
L3 Electric brake at system emergency braking
In Sweden, when rolling stock is equipped with electrodynamic brake, these
are always disconnected at emergency, rapid ,train safety system or drivers
vigilance device braking. The reason for this is that it has been difficult to
demonstrate theoretically that the traction block has the requisite safety
levels in these brake modes when electro-dynamic brake is applied. Note
also that braked weight is never used for R+E or P+E in the calculation of a
train’s braking performance Thus, in Sweden we have chosen to protect
ourselves against a possible fault in the traction block. Note that faults in
traction block are unknown and that faults in CBB function in wintertime
are commonplace.
Advantages are
- that electrodynamic brake provide an extra barrier because in certain
cases the locomotive can compensate for the deficient function of
CBB in wintertime.
The disadvantages are
- that we protect ourselves against traction block malfunctions, but
this can be seen as ”proven in use” for most locomotives, based on
experience from other countries. Also, this fault is unknown in
modern times.
- that it is expensive since new versions of software have to be created
for the locomotive. The safety assessment ought to be simple, since
the solution is "proven in use"59.
L4 Introduction of automatic exercising equipment.
Such equipment means that the locomotive will automatically carry out
exercising cycles on the wagons by automatically reducing HLL. The
exercising cycle can be adapted in terms of size reduction, duration and
interval.
Advantages are
- safety is improved since the execution of exercising is transferred
from the driver to the system. The driver only needs to activate the
system once in winter conditions,
- that there is less loss of average speed than with exercising without
traction,
59 It is possible to use both “Using standard practice” (CSM-RA. Appendix 1, 2.3) and “Comparison with similar
systems” (CSM-RA. Appendix 1, 2.4).
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
89 (91)
- that it is possible to attain maximum traction even at lower speeds,
since it is not necessary to brake to a stop,
- that exercising is not done, i.e. no wear on the locomotive brakes,
- that certain exercising can take place at low speed.
The disadvantages are
- that the system restricts maximum traction when it goes in
automatically. Thus the driver must activate the system in critical
stretches or alternatively reduce the wagon weight for the relevant
braking level during exercising,
- that the level of exercising is always the same. Alternatively the
driver may choose what level of exercising is required for the
current weather conditions,
- that it may be necessary for the driver to carry out additional
exercising,
- that if this is to be successful, major drops in HLL cannot be used.
Tests suggest that low drops in HLL during an exercising cycle can
be counter productive, i.e. braking capacity may be reduced,
- that modern locomotives carry out an automatic equalisation after
each braking cycle, which is not included in the automatic
exercising equipment,
- that this cannot be carried out on all locomotives,
- that there are safety issues that must be resolved, especially if there
are wagons with apparently underperforming blocks in combination
with wagons with well-functioning blocks. There is then the risk
that the wagons which have well-functioning brake blocks receive
too high braking energies in the wheels,
- that the function must be managed in such a way that running in
HLL is even and stable after each exercising cycle. Problems may
arise with small and frequent drops in HLL. This may increase the
risk of blocked brake60 and uneven braking capacity between the
wagons, with an increased risk of wheel flats.
- that for mixed trains with organic, sintered and GG blocks, the
wagons with GG blocks in particular will experience a higher
degree of wheel damage in the form of circumferential shelling61
due to the increased braking energy since they will be braked
instantaneously with a exercising cycle (probably to be followed by
damage to the wheels of wagons with sintered blocks). With trains
with only organic and sintered blocks, circumferential shelling will
probably increase on wagons with sintered blocks compared with
those with organic blocks,
60 Unintended drag brake 61 Circumferential shelling and pitting
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
90 (91)
- that wear on wheels and blocks will increase on those wagons
which have well-functioning brake configurations, while wagons
with underperforming brake configurations will have normal wear
and
- that it is uneconomical, due to the costs of energy and wear to
blocks and wheels on the wagons.
Report Risk assessment regarding composite brake blocks during Swedish winter conditions Ref TSJ 2019-5343
91 (91)
D7 Extra wagons with cast-iron blocks in parallel with other
wagons.
The advantages are
- that a certain braking function from GG wagons is ensured.
The disadvantages are
- that there will be greatly increased wheel damage from
circumferential shelling on GG wagons when they brake
instantaneously,
- that there will be a greater incidence of wheel flats on GG wagons
when they brake instantaneously,
- that exercising of CBB wagons is reduced, since GG wagons brake
instantaneously and absorb exercising energy,
- the a reduced braking function on CBB wagons mixed with GG
wagons is hidden and
- that the proportion of GG wagons must be very high, since mixed
trains enable reduced exercising.
The purpose of the risk analysis is to illustrate the risks in the use of
composite brake blocks on freight trains in Sweden in the wintertime. This
demonstrates that the risk needs to be reduced to an acceptable level. For
this reason, a range of measures has been identified which need to be
investigated further and a programme of decisive measures needs to be
established.