Talleyrand Marine Terminal – Berth 3 Project
-
Overview
Sinkhole and asphalt patches along
Berth 3 at JAXPORT’s 173-acre
Talleyrand Terminal
-
Existing Berth 3
-
Project Challenges
Avoid complete demolition of the berth
Allow Southeast Toyota to continue to import cars across the dock
-
Design of new Berth 3
-
TIME: 0START Phase 1RELOCATE SHIP NORTHWARD
BERTH 3: 700’ +/-
END OF MONTH 3FINISH PHASE 1 & START PHASE 2RELOCATE SHIP TO NORMAL POSITION
EXISTING DOCKSHIP AT NORMAL POSITION
BERTH 4BERTH 3 (TOYOTA)START
PHASE 1PHASE 1
COMPLETESTART
PHASE 2PHASE 2
COMPLETESTART
PHASE 3PHASE 3
COMPLETESTART
PHASE 4PHASE 4
COMPLETE
END OF MONTH 6FINISH PHASE 2 & START PHASE 3RELOCATE SHIP NORTHWARD
END OF MONTH 9FINISH PHASE 3 & START PHASE 4RELOCATE SHIP TO NORMAL POSITION
END OF MONTH 12FINISH PHASE 4 (PROJECT COMPLETE)SHIP STAYS AT NORMAL POSITION
-
Halcrow
Southeast Toyota
Talleyrand Operations
JAXPORT Engineering