rhic status haixin huang time meeting 01/18/2011
TRANSCRIPT
![Page 1: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/1.jpg)
RHIC Status
Haixin Huang
Time Meeting01/18/2011
![Page 2: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/2.jpg)
Haixin Huang2
Jan. 12: Snow Storm, but RHIC held on well and commissioning continued.
Jan. 13: It took us three shifts of hunting to find out a wrong cable was put in for the yellow injection kicker timing.
Jan. 14: Circulated beam in Yellow with snake on. Some polarimeter setup was done in blue.
Jan. 15: Beam captured in Yellow with 28MHz cavity and snake on. Jan. 16: P/S work done. Started ramp development and beam reached store
in 4th try. The work was slowed due to various problems: LINAC mod8, RF station trips in the AGS.
Jan. 17: Done ring-to-ring synchro. Continue ramp setup, seen collisions at IP8. 111 bunch injection tested. Highest readings are at CNI polarimeters.
Jan. 18: Start 9MHz cavity capture at injection.
Progress in Last One Week
![Page 3: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/3.jpg)
Haixin Huang3
Straight Tunes on Ramp with Tune/Coupling Feedback
![Page 4: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/4.jpg)
Haixin Huang4
Orbit on Ramp Still Need Work
![Page 5: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/5.jpg)
Haixin Huang5
Collisions at IP8 Responsive to IR Steering
![Page 6: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/6.jpg)
Haixin Huang6
Yellow IPM Gives ~15pi Emittance
![Page 7: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/7.jpg)
Haixin Huang7
Near Term Plan
Setup ramp with 9MHz cavity during day and evening shifts.
Continue ramp development overnight with 28MHz cavity if 9MHz cavity is not ready yet.
Yellow polarimeter setup. Store setup (collimation, collision). Increase bunch number
gradually.
![Page 8: RHIC Status Haixin Huang Time Meeting 01/18/2011](https://reader036.vdocuments.site/reader036/viewer/2022082711/56649f065503460f94c1c21d/html5/thumbnails/8.jpg)
Haixin Huang8
Original Schedule
Cool-Down Mode : one week (01/03-01/09) Injection setup (6 days: first 4 days are blue only) (01/10-
01/15). Ramp development (6 days) (01/16-01/21) Commissioning 9MHz at injection and on the ramp (5
days) (01/19-01/23) Store development (6 days) (01/22-01/27) Ramp development with intense beam (7 days) (01/28-
02/03). What left on the job list of first two periods: yellow
polarimeter setup and capture beam with 9MHz cavity.