24
ADDENDUM NO. 1 ISSUE DATE: 7/8/2019 This Addendum shall become and form a part of the RFQ for: RFQ 484-072319 Bridge Bundle #1 - 2019 Engineering Design Service NOTE: PLEASE REVIEW CAREFULLY! THERE MAYBE CHANGES TO THE INFORMATION TO BE PROVIDED. FAILURE TO ADHERE TO ANY CHANGES ADDRESSED IN THIS ADDENDUM MAY RESULT IN DISQUALIFICATION. In the event of a conflict between previously released information and the information contained herein, the latter shall control. NOTE: A signed acknowledgment of this addendum (this page) MUST be attached to your SUBMITTAL for Phase I. Firm Name Signature Date Typed Name and Title Georgia Department of Transportation (GDOT) Office of Transportation Services Procurement One Georgia Center 600 West Peachtree Street, NW 19 th Floor Atlanta, Georgia 30308 This Addendum, including all questions and answers, shall become and form a part of the original RFQ package and shall be taken into account when preparing your proposal. I. Written Questions and Answers Questions Answers 1. Can the submittal date be extended? See Addendum below. 2. Would the Department consider allowing the 4.01 area classes to be utilized by a subconsultant, rather than a prime requirement? No. The Prime must be prequalified in 3.01 and 4.01a or 4.01b. 3. Where individual projects within the bundle state “In House Road and Bridge”, which services within the scope defined by section 6A through 6J of each contract will the successful consultant be providing? See Addendum below 4. It is our understanding PI 0016532, 0016533 and 0016530 in Contract 2 are part of the SR 17 Grip corridor project. How does the department intend to deliver the projects under this bridge contract? The bridge replacement projects PI 0016532, 0016533 and 0016530, are scoped to replace the existing bridges per those project’s justifications statements. Projects programmed as bridge replacement are used to replace bridges in-kind.

Upload: others

Post on 13-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

ADDENDUM NO. 1

ISSUE DATE: 7/8/2019

This Addendum shall become and form a part of the RFQ for:

RFQ 484-072319 – Bridge Bundle #1 - 2019 Engineering Design Service

NOTE: PLEASE REVIEW CAREFULLY! THERE MAYBE CHANGES TO THE INFORMATION TO BE PROVIDED. FAILURE TO ADHERE TO ANY CHANGES ADDRESSED IN THIS ADDENDUM MAY RESULT IN

DISQUALIFICATION.

In the event of a conflict between previously released information and the information contained herein, the latter shall control. NOTE: A signed acknowledgment of this addendum (this page) MUST be attached to your SUBMITTAL for Phase I. Firm Name Signature Date Typed Name and Title

Georgia Department of Transportation (GDOT) Office of Transportation Services Procurement

One Georgia Center 600 West Peachtree Street, NW

19th Floor Atlanta, Georgia 30308

This Addendum, including all questions and answers, shall become and form a part of the original RFQ package and shall be taken into account when preparing your proposal.

I. Written Questions and Answers

Questions Answers

1.

Can the submittal date be extended?

See Addendum below.

2. Would the Department consider allowing the 4.01 area classes to be utilized by a subconsultant, rather than a prime requirement?

No. The Prime must be prequalified in 3.01 and 4.01a or 4.01b.

3. Where individual projects within the bundle state “In House Road and Bridge”, which services within the scope defined by section 6A through 6J of each contract will the successful consultant be providing?

See Addendum below

4. It is our understanding PI 0016532, 0016533 and 0016530 in Contract 2 are part of the SR 17 Grip corridor project. How does the department intend to deliver the projects under this bridge contract?

The bridge replacement projects PI 0016532, 0016533 and 0016530, are scoped to replace the existing bridges per those project’s justifications statements. Projects programmed as bridge replacement are used to replace bridges in-kind.

Page 2: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 2 of 24

II. RFQ Section III-Schedule of Events will be deleted and replaced by the attached Schedule of Events.

III. RFQ Exhibit I -1; I -2; I -3; I -5 and 1- 8 are DELETED and REPLACED by the attached Exhibit I -1; I -2; I -3; I -5 and 1- 8

EXHIBIT I-1

Project/Contract

1. Project Number(s): N/A

2. PI Number: 3. County: 4. Description:

0016516 Franklin SR 106 @ MIDDLE FORK BROAD RIVER 2.3 MI S OF CARNESVILLE

0016517 Franklin SR 328 @ GUMLOG CREEK 3.8 MI N OF LAVONIA

0016519 Gwinnett SR 8 @ JACKSON CREEK IN LILBURN

0016523 Jackson I-85 @ CR 229/VALENTINE INDUSTRIAL PKWY NW OF JEFFERSON (IN HOUSE ROAD AND BRIDGE)

0016526 Madison SR 106 @ HUDSON RIVER 3.8 MI N OF POCATALICO

5. Required Area Classes:

Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.

A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:

Number Area Class

3.01 Two-Lane or Multi-lane Rural Roadway Design

PHASE I DATE TIME

a. GDOT issues public advertisement of RFQ-484-072319 6/20/2019 ----------

b. Deadline for submission of written questions and requests for clarification 7/8/2019 2:00 PM

c. Deadline for submission of Statements of Qualifications

8/26/2019 2:00 PM

d. GDOT completes evaluation and issues notification and other information to

finalist firms TBD

PHASE II

e. Deadline for submission of written questions from finalists TBD 2:00 PM

f. Phase II Response of Finalist firms due TBD TBA

Page 3: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 3 of 24

4.01(a) Minor Bridge Design

or

4.01(b) Minor Bridge Design - CONDITIONAL

B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be

prequalified by GDOT in the area classes listed below:

Number Area Class

1.06(a) NEPA

1.06(b) History

1.06(c) Air Quality

1.06(d) Noise

1.06(e) Ecology

1.06(f) Archaeology

1.06(g) Freshwater Aquatic Surveys

1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)

1.10 Traffic Analysis

3.12 Hydraulic and Hydrological Studies (Roadway)

4.04 Hydraulic and Hydrological Studies (Bridges)

5.01 Land Surveying

5.02 Engineering Surveying

5.08 Overhead/Subsurface Utility Engineering (SUE)

6.01(a) Soil Survey Studies

6.01(b) Geological and Geophysical Studies

6.02 Bridge Foundation Studies

6.05 Hazardous Waste Site Assessment Studies

9.01 Erosion, Sedimentation, and Pollution Control Plan

6. Scope:

The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.

A. Complete Field Surveys:

1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.

B. Concept Report:

1) Traffic Studies. 2) Cost Estimates. 3) Initial Concept Meeting Preparation and Attendance. 4) PAR Activities. 5) Concept Meeting Preparation and Attendance. 6) Approved Concept Report.

Page 4: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 4 of 24

7) Concept Design Data Book. 8) Public Involvement Plan (for GDOT’s approval).

C. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,

Ecology, and Archaeology). 2) NEPA documents.

a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance. 7) Preparation of a Vegetative Buffer application. 8) Public Involvement (1 possible detour/PIOH). 9) Prepare for and attend the PFPR and FFPR.

D. Preliminary Design:

1) Complete Preliminary Roadway Plans, including but not limited to:

a) Preliminary Bridge Plans. b) Preliminary Signing and Marking Plans. c) Preliminary ESPCP. d) Preliminary Utility Plans. e) Preliminary Staging Plans. f) Drainage Design including MS4, if applicable.

2) Bridge Hydraulic Study. 3) BFI Report. 4) Pavement Evaluation/UST/Soil Survey. 5) Constructability Meeting participation. 6) Cost Estimation with annual updates. 7) Location and Design Report. 8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering

Services).

E. Right-of-Way (ROW) Plans: 1) Prepare ROW plans and coordinate ROW staking. 2) Right of Way revisions during acquisition, as needed.

F. Utilities:

Subsurface Utility Engineering.

G. Final Design:

1) Complete Final Roadway Plans, including but not limited to:

Page 5: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 5 of 24

a) Final Bridge Plans (LRFD). b) Final Signing and Marking Plans. c) Final ESPCP. d) Final Utility Plans. e) Final Staging Plans. f) Final Drainage Design including MS4, if applicable.

2) FFPR participation, report, and responses(all plans sets and other information requested by Engineering

Services). 3) Corrected FFPR Plans. 4) CES Final cost estimate. 5) Final PS&E Package. 6) Amendments & Revisions.

H. Construction:

1) Use on Construction Revisions. 2) Review Shop Drawings.

I. Quality Control/Quality Assurance Reviews for all deliverables.

J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings

may be required to resolve major project issues).

K. For PI 0016523 (Jackson County), I-85 @ CR 229/VALENTINE INDUSTRIAL PKWY, NW OF (IN HOUSE ROAD AND BRIDGE) the Consultant shall provide the following: A. Complete Field Surveys:

1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.

B. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).

2) NEPA documents.

a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.

C. Utilities:

Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional

meetings may be required to resolve major project issues).

Page 6: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 6 of 24

7. Related Key Team Leaders for Exhibit I-1 Contract 1:

A. Roadway Design. B. Bridge Design. C. NEPA Lead.

8. The following milestone dates are proposed: PI-0016516, PI-0016523, & PI-0016526

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration). C. PFPR – Q3 FY 21 D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22. PI-0016517 & PI-0016519

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.

Page 7: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 7 of 24

EXHIBIT I-2

Project/Contract 2

1. Project Number(s): N/A

2. PI Number: 3. County: 4. Description:

0016524 Lincoln SR 43 @ LLOYD CREEK 7 MI SW OF LINCOLNTON

0016525 Lincoln SR 220 @ SOAP CREEK 5 MI E OF LINCOLNTON

0016532 Wilkes SR 17 @ ROCK CREEK 2.3 MI N OF WASHINGTON

0016533 Wilkes SR 17 @ BROAD RIVER OVERFLOW 7.3 MI N OF TIGNALL (IN HOUSE ROAD AND BRIDGE)

0016530 Elbert/Wilkes SR 17 @ BROAD RIVER 7.5 MI N OF TIGNALL (IN HOUSE ROAD AND BRIDGE)

5. Required Area Classes:

Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.

A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:

Number Area Class

3.01 Two-Lane or Multi-lane Rural Roadway Design

4.01(a) Minor Bridge Design

or

4.01(b) Minor Bridge Design - CONDITIONAL

B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be prequalified by GDOT in the area classes listed below:

Number Area Class

1.06(a) NEPA

1.06(b) History

1.06(c) Air Quality

1.06(d) Noise

1.06(e) Ecology

1.06(f) Archaeology

1.06(g) Freshwater Aquatic Surveys

1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)

1.10 Traffic Analysis

3.12 Hydraulic and Hydrological Studies (Roadway)

4.04 Hydraulic and Hydrological Studies (Bridges)

5.01 Land Surveying

5.02 Engineering Surveying

5.08 Overhead/Subsurface Utility Engineering (SUE)

6.01(a) Soil Survey Studies

6.01(b) Geological and Geophysical Studies

6.02 Bridge Foundation Studies

Page 8: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 8 of 24

6.05 Hazardous Waste Site Assessment Studies

9.01 Erosion, Sedimentation, and Pollution Control Plan

6. Scope:

The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual. A. Complete Field Surveys:

1) Provide Survey Control Package.

2) Provide Inroads Survey Database.

3) Staking for Bridge Site Inspection.

4) Staking for ROW acquisition.

B. Concept Report:

1) Traffic Studies.

2) Cost Estimates.

3) Initial Concept Meeting Preparation and Attendance.

4) PAR Activities.

5) Concept Meeting Preparation and Attendance.

6) Approved Concept Report.

7) Concept Design Data Book.

8) Public Involvement Plan (for GDOT’s approval).

C. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,

Ecology, and Archaeology). 2) NEPA documents.

1) Categorical Exclusion.

2) EA/FONSI.

3) Section 4f coordination.

4) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application.

4) Section 408 Coordination.

5) Aquatic Survey.

6) Stream Buffer Variance.

7) Preparation of a Vegetative Buffer application.

8) Public Involvement (1 possible detour/PIOH).

9) Prepare for and attend the PFPR and FFPR.

D. Preliminary Design:

Page 9: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 9 of 24

1) Complete Preliminary Roadway Plans, including but not limited to:

2) Preliminary Bridge Plans.

3) Preliminary Signing and Marking Plans.

4) Preliminary ESPCP.

5) Preliminary Utility Plans.

6) Preliminary Staging Plans.

7) Drainage Design including MS4, if applicable.

8) Bridge Hydraulic Study.

9) BFI Report.

10) Pavement Evaluation/UST/Soil Survey.

11) Constructability Meeting participation.

12) Cost Estimation with annual updates.

13) Location and Design Report.

14) PFPR participation, report, and responses (all plans sets and other information requested by Engineering

Services).

E. Right-of-Way (ROW) Plans:

1) Prepare ROW plans and coordinate ROW staking.

2) Right of Way revisions during acquisition, as needed.

F. Utilities:

Subsurface Utility Engineering.

G. Final Design:

1) Complete Final Roadway Plans, including but not limited to:

1) Final Bridge Plans (LRFD).

2) Final Signing and Marking Plans.

3) Final ESPCP.

4) Final Utility Plans.

5) Final Staging Plans.

6) Final Drainage Design including MS4, if applicable.

2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering

Services).

3) Corrected FFPR Plans.

4) CES Final cost estimate.

5) Final PS&E Package.

6) Amendments & Revisions.

H. Construction:

1) Use on Construction Revisions.

2) Review Shop Drawings.

I. Quality Control/Quality Assurance Reviews for all deliverables.

Page 10: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 10 of 24

J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings

may be required to resolve major project issues).

K. For PI numbers 0016533 and 0016530 (Wilkesand Elbert/Wilkes County), SR 17 @ BROAD RIVER OVERFLOW

7.3 MI N OF TIGNALL (IN HOUSE ROAD AND BRIDGE) and SR 17 @ BROAD RIVER 7.5 MI N OF TIGNALL

(IN HOUSE ROAD AND BRIDGE) the Consultant shall provide the following:

A. Complete Field Surveys:

1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.

B. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).

2) NEPA documents.

a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.

C. Utilities:

Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional

meetings may be required to resolve major project issues).

7. Related Key Team Leaders per Exhibit I-2, Contract 2:

A. Roadway Design. B. Bridge Design. C. NEPA Lead.

8. The following milestone dates are proposed:

PI-0016524

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration). C. PFPR – Q3 FY 21. D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22.

PI-0016530, PI-0016532, & PI-0016533

Page 11: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 11 of 24

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.

PI-0016525

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q1 FY 22. C. PFPR – Q3 FY 22. D. FFPR – Q4 FY 23. E. Let Contract – Q1 FY 24.

Page 12: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 12 of 24

EXHIBIT I-3

Project/Contract

1. Project Number(s): N/A

2. PI Number: 3. County: 4. Description:

0016504 Atkinson SR 31 @ RED BLUFF CREEK TRIB 9 MI S OF PEARSON

0016505 Atkinson SR 31 @ RED BLUFF CREEK 8 MI S OF PEARSON

0016510 Clinch SR 89/US 441 @ CYPRESS CREEK 1.6 MI S OF FARGO

0016514 Echols SR 89/US 441 @ LITTLE SUWANNEE CREEK 8 MIL S OF FARGO

0016531 Turner CR 26/ BETHEL ROAD @ HAT CREEK 6.7 MI SE OF SYCAMORE (IN HOUSE BRIDGE)

5. Required Area Classes:

Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.

A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:

Number Area Class

3.01 Two-Lane or Multi-lane Rural Roadway Design

4.01(a) Minor Bridge Design

or

4.01(b) Minor Bridge Design - CONDITIONAL

B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be

prequalified by GDOT in the area classes listed below:

Number Area Class

1.06(a) NEPA

1.06(b) History

1.06(c) Air Quality

1.06(d) Noise

1.06(e) Ecology

1.06(f) Archaeology

1.06(g) Freshwater Aquatic Surveys

1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)

1.10 Traffic Analysis

3.12 Hydraulic and Hydrological Studies (Roadway)

4.04 Hydraulic and Hydrological Studies (Bridges)

5.01 Land Surveying

5.02 Engineering Surveying

5.08 Overhead/Subsurface Utility Engineering (SUE)

6.01(a) Soil Survey Studies

6.01(b) Geological and Geophysical Studies

6.02 Bridge Foundation Studies

6.05 Hazardous Waste Site Assessment Studies

9.01 Erosion, Sedimentation, and Pollution Control Plan

Page 13: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 13 of 24

6. Scope:

The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.

A. Complete Field Surveys:

1) Provide Survey Control Package.

2) Provide Inroads Survey Database.

3) Staking for Bridge Site Inspection.

4) Staking for ROW acquisition.

B. Concept Report:

1) Traffic Studies.

2) Cost Estimates.

3) Initial Concept Meeting Preparation and Attendance.

4) PAR Activities.

5) Concept Meeting Preparation and Attendance.

6) Approved Concept Report.

7) Concept Design Data Book.

8) Public Involvement Plan (for GDOT’s approval).

C. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).

2) NEPA documents.

a) Categorical Exclusion.

b) EA/FONSI.

c) Section 4f coordination.

d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application.

4) Section 408 Coordination.

5) Aquatic Survey.

6) Stream Buffer Variance.

7) Preparation of a Vegetative Buffer application.

8) Public Involvement (1 possible detour/PIOH).

9) Prepare for and attend the PFPR and FFPR.

D. Preliminary Design:

Page 14: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 14 of 24

1) Complete Preliminary Roadway Plans, including but not limited to:

a) Preliminary Bridge Plans.

b) Preliminary Signing and Marking Plans.

c) Preliminary ESPCP.

d) Preliminary Utility Plans.

e) Preliminary Staging Plans.

f) Drainage Design including MS4, if applicable.

2) Bridge Hydraulic Study.

3) BFI Report.

4) Pavement Evaluation/UST/Soil Survey.

5) Constructability Meeting participation.

6) Cost Estimation with annual updates.

7) Location and Design Report.

8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering

Services).

E. Right-of-Way (ROW) Plans:

1) Prepare ROW plans and coordinate ROW staking.

2) Right of Way revisions during acquisition, as needed.

F. Utilities:

Subsurface Utility Engineering.

G. Final Design:

1) Complete Final Roadway Plans, including but not limited to:

a) Final Bridge Plans (LRFD).

b) Final Signing and Marking Plans.

c) Final ESPCP.

d) Final Utility Plans.

e) Final Staging Plans.

f) Final Drainage Design including MS4, if applicable.

2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering

Services).

3) Corrected FFPR Plans.

4) CES Final cost estimate.

5) Final PS&E Package.

6) Amendments & Revisions.

H. Construction:

1) Use on Construction Revisions.

2) Review Shop Drawings.

I. Quality Control/Quality Assurance Reviews for all deliverables.

Page 15: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 15 of 24

J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings

may be required to resolve major project issues).

K. For PI 0016531 (Turner County), CR 26/ BETHEL ROAD @ HAT CREEK 6.7 MI SE OF SYCAMORE (IN HOUSE

BRIDGE) the Consultant will provide all the scope A – J listed above except for the following:

1) Preliminary Bridge Plans 2) Bridge Hydraulic Study. 3) BFI Report. 4) Final Bridge Plans (LRFD). 5) Review Shop Drawings.

7. Related Key Team Leaders per Exhibit I-3, Contract 3:

A. Roadway Design. B. Bridge Design. C. NEPA Lead.

8. The following milestone dates are proposed:

PI-0016531

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration). C. PFPR – Q3 FY 21. D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22.

PI-0016504, PI-0016505, PI-0016510, & PI-0016514 A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.

Page 16: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 16 of 24

EXHIBIT I-5

Project/Contract

1. Project Number(s): N/A

2. PI Number: 3. County: 4. Description:

0016506 Bartow I-75 @ CR 179/CEDAR CREEK ROAD 5.2 MI NW OF WHITE

0016528 Murray SR 2/SR 61 @ SUMAC CREEK 1.6 MI N OF CRANDALL

0016529 Murray SR 61 @ PERRY CREEK 6.3 MI N OF CRANDALL

0016509 Cherokee SR 108 @ SHOAL CREEK 4.5 MI SW OF WALESKA (IN HOUSE ROAD AND BRIDGE)

5. Required Area Classes:

Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.

A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:

Number Area Class

3.01 Two-Lane or Multi-lane Rural Roadway Design

4.01(a) Minor Bridge Design

or

4.01(b) Minor Bridge Design - CONDITIONAL

B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be

prequalified by GDOT in the area classes listed below:

Number Area Class

1.06(a) NEPA

1.06(b) History

1.06(c) Air Quality

1.06(d) Noise

1.06(e) Ecology

1.06(f) Archaeology

1.06(g) Freshwater Aquatic Surveys

1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)

1.10 Traffic Analysis

3.12 Hydraulic and Hydrological Studies (Roadway)

4.04 Hydraulic and Hydrological Studies (Bridges)

5.01 Land Surveying

5.02 Engineering Surveying

5.08 Overhead/Subsurface Utility Engineering (SUE)

6.01(a) Soil Survey Studies

6.01(b) Geological and Geophysical Studies

6.02 Bridge Foundation Studies

6.05 Hazardous Waste Site Assessment Studies

9.01 Erosion, Sedimentation, and Pollution Control Plan

Page 17: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 17 of 24

6. Scope: The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.

A. Complete Field Surveys:

1) Provide Survey Control Package.

2) Provide Inroads Survey Database.

3) Staking for Bridge Site Inspection.

4) Staking for ROW acquisition.

B. Concept Report:

1) Traffic Studies.

2) Cost Estimates.

3) Initial Concept Meeting Preparation and Attendance.

4) PAR Activities.

5) Concept Meeting Preparation and Attendance.

6) Approved Concept Report.

7) Concept Design Data Book.

8) Public Involvement Plan (for GDOT’s approval).

C. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,

Ecology, and Archaeology). 2) NEPA documents.

a) Categorical Exclusion.

b) EA/FONSI.

c) Section 4f coordination.

d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application.

4) Section 408 Coordination.

5) Aquatic Survey.

6) Stream Buffer Variance.

7) Preparation of a Vegetative Buffer application.

8) Public Involvement (1 possible detour/PIOH).

9) Prepare for and attend the PFPR and FFPR.

D. Preliminary Design:

1) Complete Preliminary Roadway Plans, including but not limited to:

a) Preliminary Bridge Plans.

b) Preliminary Signing and Marking Plans.

Page 18: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 18 of 24

c) Preliminary ESPCP.

d) Preliminary Utility Plans.

e) Preliminary Staging Plans.

f) Drainage Design including MS4, if applicable.

2) Bridge Hydraulic Study.

3) BFI Report.

4) Pavement Evaluation/UST/Soil Survey.

5) Constructability Meeting participation.

6) Cost Estimation with annual updates.

7) Location and Design Report.

8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering

Services).

E. Right-of-Way (ROW) Plans:

1) Prepare ROW plans and coordinate ROW staking.

2) Right of Way revisions during acquisition, as needed.

F. Utilities:

Subsurface Utility Engineering.

G. Final Design:

1) Complete Final Roadway Plans, including but not limited to:

a) Final Bridge Plans (LRFD).

b) Final Signing and Marking Plans.

c) Final ESPCP.

d) Final Utility Plans.

e) Final Staging Plans.

f) Final Drainage Design including MS4, if applicable.

2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering

Services).

3) Corrected FFPR Plans.

4) CES Final cost estimate.

5) Final PS&E Package.

6) Amendments & Revisions.

H. Construction:

1) Use on Construction Revisions.

2) Review Shop Drawings.

I. Quality Control/Quality Assurance Reviews for all deliverables.

J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings

may be required to resolve major project issues).

K. For PI 0016509 (Cherokee County), SR 108 @ SHOAL CREEK 4.5 MI SW OF WALESKA (IN HOUSE ROAD

AND BRIDGE) the Consultant shall provide the following:

A. Complete Field Surveys:

Page 19: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 19 of 24

1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.

B. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).

2) NEPA documents.

a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.

C. Utilities:

Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional

meetings may be required to resolve major project issues).

7. Related Key Team Leaders per Exhibit I-5, Contract 5:

A. Roadway Design. B. Bridge Design. C. NEPA Lead.

8. The following milestone dates are proposed:

PI-0016529

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Limited Concept report submittal – Q1 FY 21 (about 4 months duration) . C. PFPR – Q3 FY 21. D. FFPR – Q1 FY 22. E. Let Contract – Q2 FY 22. PI-0016509 & PI-0016528

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.

PI-0016506

Page 20: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 20 of 24

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q1 FY 22. C. PFPR – Q3 FY 22. D. FFPR – Q4 FY 23. E. Let Contract – Q1 FY 24.

Page 21: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 21 of 24

EXHIBIT I-8

Project/Contract

1. Project Number(s): N/A

2. PI Number: 3. County: 4. Description:

0016508 Chattahoochee SR 520/US 27 @ FIRST DIVISION ROAD 7.5 MI NW OF CUSSETA

0016520 Harris SR 103 @ MOUNTAIN OAK CREEK 5.5 MI SW OF WHITESVILLE (IN HOUSE ROAD AND BRIDGE)

0016521 Harris SR 103 @ HOUSE CREEK 6.5 MI SE OF WEST POINT (IN HOUSE ROAD AND BRIDGE)

0016522 Harris SR 103 @ SAND CREEK 5.5 MI SE OF WEST POINT (IN HOUSE ROAD AND BRIDGE)

0016527 Meriwether SR 362 @ RED OAK CREEK 6 MI NE OF GREENVILLE (IN HOUSE ROAD AND BRIDGE)

5. Required Area Classes:

Prime Consultants are defined as the firm submitting the Statement of Qualifications and the firm with whom GDOT will contract. The Team is defined as the Prime Consultant and their sub-consultants, who are considered team members. The Prime Consultant must be prequalified in the Area Classes identified below in Section 5.A. The Prime Consultant or sub-consultant team members must be prequalified in the Area Classes identified below in Section 5.B. Respondents should submit a summary form (example provided in Exhibit IV) which details the required area classes for the Prime Consultant and all sub-consultants or joint-venture of consultants on the team listed in the Statement of Qualifications. The area classes listed on the summary form must meet all required area classes or the team will be disqualified. The Prequalification Expiration Date must be current by the deadline stated for this RFQ.

A. The Prime Consultant MUST be prequalified by GDOT in the area classes listed below:

Number Area Class

3.01 Two-Lane or Multi-lane Rural Roadway Design

4.01(a) Minor Bridge Design

or

4.01(b) Minor Bridge Design - CONDITIONAL

B. The Team (either the Prime Consultant and/or one or more of their sub-consultant team members) MUST be

prequalified by GDOT in the area classes listed below:

Number Area Class

1.06(a) NEPA

1.06(b) History

1.06(c) Air Quality

1.06(d) Noise

1.06(e) Ecology

1.06(f) Archaeology

1.06(g) Freshwater Aquatic Surveys

1.07 Attitude, Opinion, and Community Value Studies (Public Involvement)

1.10 Traffic Analysis

3.12 Hydraulic and Hydrological Studies (Roadway)

4.04 Hydraulic and Hydrological Studies (Bridges)

5.01 Land Surveying

5.02 Engineering Surveying

5.08 Overhead/Subsurface Utility Engineering (SUE)

6.01(a) Soil Survey Studies

6.01(b) Geological and Geophysical Studies

Page 22: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 22 of 24

6.02 Bridge Foundation Studies

6.05 Hazardous Waste Site Assessment Studies

9.01 Erosion, Sedimentation, and Pollution Control Plan

6. Scope:

The Consultant shall provide concept development, field surveys and database enhancements, development of the environmental document including all required special studies, preliminary construction plans, hydraulic and hydrological studies, preliminary bridge plans, signing and marking plans, final right-of-way plans (including revisions), erosion control plans, staging plans and final construction plans (including revisions through project final acceptance). All required engineering studies are considered part of the scope of services. All deliverables shall be in accordance with the Plan Development Process, Electronic Data Guidelines, Plan Presentation Guide, NEPA and the GDOT Environmental Procedures Manual.

A. Complete Field Surveys:

1) Provide Survey Control Package.

2) Provide Inroads Survey Database.

3) Staking for Bridge Site Inspection.

4) Staking for ROW acquisition.

B. Concept Report:

1) Traffic Studies.

2) Cost Estimates.

3) Initial Concept Meeting Preparation and Attendance.

4) PAR Activities.

5) Concept Meeting Preparation and Attendance.

6) Approved Concept Report.

7) Concept Design Data Book.

8) Public Involvement Plan (for GDOT’s approval).

C. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History,

Ecology, and Archaeology). 2) NEPA documents.

a) Categorical Exclusion.

b) EA/FONSI.

c) Section 4f coordination.

d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application.

4) Section 408 Coordination.

5) Aquatic Survey.

6) Stream Buffer Variance.

7) Preparation of a Vegetative Buffer application.

8) Public Involvement (1 possible detour/PIOH).

9) Prepare for and attend the PFPR and FFPR.

D. Preliminary Design:

Page 23: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 23 of 24

1) Complete Preliminary Roadway Plans, including but not limited to:

a) Preliminary Bridge Plans.

b) Preliminary Signing and Marking Plans.

c) Preliminary ESPCP.

d) Preliminary Utility Plans.

e) Preliminary Staging Plans.

f) Drainage Design including MS4, if applicable.

2) Bridge Hydraulic Study.

3) BFI Report.

4) Pavement Evaluation/UST/Soil Survey.

5) Constructability Meeting participation.

6) Cost Estimation with annual updates.

7) Location and Design Report.

8) PFPR participation, report, and responses (all plans sets and other information requested by Engineering

Services).

E. Right-of-Way (ROW) Plans:

1) Prepare ROW plans and coordinate ROW staking.

2) Right of Way revisions during acquisition, as needed.

F. Utilities:

Subsurface Utility Engineering.

G. Final Design:

1) Complete Final Roadway Plans, including but not limited to:

a) Final Bridge Plans (LRFD).

b) Final Signing and Marking Plans.

c) Final ESPCP.

d) Final Utility Plans.

e) Final Staging Plans.

f) Final Drainage Design including MS4, if applicable.

2) FFPR participation , report, and responses(all plans sets and other information requested by Engineering

Services).

3) Corrected FFPR Plans.

4) CES Final cost estimate.

5) Final PS&E Package.

6) Amendments & Revisions.

H. Construction:

1) Use on Construction Revisions.

2) Review Shop Drawings.

I. Quality Control/Quality Assurance Reviews for all deliverables.

Page 24: RFQ 484-072319 NOTE: PLEASE REVIEW CAREFULLY! THERE …

Addendum No. 1

RFQ 484- 072319

Page 24 of 24

J. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional meetings

may be required to resolve major project issues).

K. For PI numbers 0016521; 0016522, and 0016527 (Harris, and Meriwether County), SR 103 @ HOUSE CREEK

6.5 MI SE OF WEST POINT (IN HOUSE ROAD AND BRIDGE); SR 103 @ SAND CREEK 5.5 MI SE OF WEST

POINT (IN HOUSE ROAD AND BRIDGE) and SR 362 @ RED OAK CREEK 6 MI NE OF GREENVILLE (IN

HOUSE ROAD AND BRIDGE) the Consultant shall provide the following:

A. Complete Field Surveys:

1) Provide Survey Control Package. 2) Provide Inroads Survey Database. 3) Staking for Bridge Site Inspection. 4) Staking for ROW acquisition.

B. Environmental Document:

1) Necessary Environmental Special Studies surveys reports and assessment of effects (i.e., Air, Noise, History, Ecology, and Archaeology).

2) NEPA documents.

a) Categorical Exclusion. b) EA/FONSI. c) Section 4f coordination. d) One NEPA document reevaluation for Construction.

3) Preparation of a Section 404 Permit application. 4) Section 408 Coordination. 5) Aquatic Survey. 6) Stream Buffer Variance.

C. Utilities:

Subsurface Utility Engineering. D. Quality Control/Quality Assurance Reviews for all deliverables. E. Attendance in and meeting minutes of monthly meetings to discuss progress and/or issues (additional

meetings may be required to resolve major project issues).

7. Related Key Team Leaders per Exhibit I-8, Contract 8:

A. Roadway Design. B. Bridge Design. C. NEPA Lead.

8. The following milestone dates are proposed PI #’s 0016508, 0016520, 0016521, 0016522 & 0016527:

A. Preliminary Engineering (PE) Notice to Proceed – Q4 FY 20. B. Concept report submittal – Q3 FY 21. C. PFPR – Q1 FY 22. D. FFPR – Q4 FY 22. E. Let Contract – Q4 FY 23.