Review of Prioritized Projects
Hon’ble CM conducted Review for Prioritized Projects
RECORD OF DISCUSSION
Date Monday, 25th
June 2018
Time 3pm to 5:45pm
Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P
Venue Conference room, AP Secretariat, Velagapudi.
Attendees
Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD
Shri G Sai Prasad. Principle secretary to Hon’ble CM.
Shri. Shashi Bhushan Kumar, Secretary, WRD
Shri M. Venkateswara Rao, EnC, WRD
Forest department
Ground water department & APSRAC
Chief Engineers and officials from AP WRD
M/s Vassar Labs
Consultants to APWRD
Page 2 of 5
# Project / Topic Gist of discussions Action to be
taken by Timeline
1 SKOCH Awards
Hon’ble CM congratulated AP WRD for winning 19 SKOCH awards -
highest for any one department in the country.
AP Water Resource Department achieved 19 awards including 3
Platinum for Pattiseema Lift Irrigation Scheme, NeeruChettu and Real
Time monitoring of groundwater levels, 5 Gold awards for AP Water
Resources Information System, Purushottapatnam Lift Irrigation
Scheme, Gandikota LI Scheme, Muchumurri LI Scheme and Revival of
defunct LI Scheme, 8 Order of Merit Awards and one Bronze Award
apart from Platinum Award of State of the Year in Irrigation under
National Significant Award category and Platinum Award for overall
water resource department.
Hon’ble CM appreciated Minister, Secretary, EnC and officials of AP
WRD for working in unison for seamless execution and implementation
of irrigation projects and initiatives.
It was also mentioned that the entire team of AP WRD worked hard to
reach level of excellence in dry spell mitigation, real-time monitoring &
improving groundwater levels despite rainfall deficits and completing
various crucial projects in record time.
Hon’ble CM advised WRD officials to keep up the spirit and work
towards achieving water security for the state.
For information -
2 Balance tenders for
54 prioritized projects
Hon’ble CM instructed WRD to ensure that all the pending tenders of 54
prioritized projects shall be released by 30th
Aug18 WRD
Ensuring tenders of
all 54 prioritized
projects are
released by 30th
Aug’18
Page 3 of 5
# Project / Topic Gist of discussions Action to be
taken by Timeline
3 Utilization of Rain
guns
Hon’ble CM advised Agriculture and Micro Irrigation department to
evaluate the possibility of transferring the responsibility of deployment
and usage of rain guns to Micro Irrigation department based on the
inputs received by agriculture department. Both the department to
discuss and evaluate various possibilities for optimal utilization of rain
guns and come up with a proposal during review meeting on 2nd
July
2018
Agriculture and
Micro Irrigation
dept.
Present a proposal
for optimal
utilization of rain
guns during review
meeting on 2nd
July
2018
4 Jala-Samrakshana-
Udhyamam
CE, Minor Irrigation briefed Hon’ble CM on status of various activities
under progress as a part of 116 days water conservation drive. Hon’ble
CM reviewed component-wise progress and advised Minor Irrigation
department to take necessary actions for improvement of progress.
For information -
5 Jungle clearance of
tanks
Hon’ble CM instructed Collector, Chittore to take up jungle clearance of
tanks and complete the works at the earliest. For information. -
6
Projects under
purview of CE,
Tirupathi
Hon’ble CM reviewed status of projects under purview of CE, Tirupathi.
Kuppam Branch Canal: Agency to meet Hon’ble CM with explanation
for delay in progress and action plan by 27th
June 2018.
Mulapalli: Hon’ble CM instructed CE, Tirupathi to complete the
project by December 2018.
CE, Tirupathi
Ensuring completion
of ‘Water Supply to
Mulapalli and other
4 tanks’ project by
Dec 2018
7
Projects under
purview of CE,
Ananthapuram
Hon’ble CM reviewed status of projects under purview of CE,
Ananthapuram.
CE,
Ananthapuram
Completion of
tunnel rectification
works for Marala &
Cherlopally by 31st
July 2018.
Page 4 of 5
# Project / Topic Gist of discussions Action to be
taken by Timeline
Marala & Cherlopally: CE, Ananthapuram informed Hon’ble CM that
tunnel rectification works shall be completed by 31st July 2018
(extended from 30th
June to 31st July’18 due soil collapse issue).
Mid Pennar North & South canals: Hon’ble CM instructed CE,
Ananthapuram to complete the projects by 30th
March 2019.
Jeedipalli: Secretary, WRD instructed CE, Ananthapuram to give a
presentation on the scheme during review meeting on 2nd
July’18
8
Projects under purview
of CE, Ongole
Hon’ble CM reviewed status of projects under purview of CE, Ongole.
Yerram Chinnapoli Reddy Korisapadu LIS : Upon discussion with CE,
Ongole and WRD officials, Hon’ble CM instructed that crop
compensation shall be paid to the farmers to clear obstruction to
works villagers.
Veligonda Tunnels: CE, Ongole to submit a revised proposal \ letter
to EnC, WRD regarding evaluation of requisitions made by existing
agencies. Hon’ble CM to visit the project during 2nd
week of July’18.
For information. -
9
Projects under
purview of CE, (North
coast) Visakhapatnam
Hon’ble CM reviewed status of projects under purview of CE, North
coast Visakhapatnam.
Construction of new barrage (10 TMC) across Krishna river near
Vykuntapuram (V) : Hon’ble CM instructed CE, Visakhapatnam to
ensure design clearances are received by 2nd
of July’18 and tenders
are released by 5th
July’18
Interlinking Of Godavari – Penna Rivers Phase-1: Hon’ble CM
instructed CE, Visakhapatnam to release tenders by 10th
July 2018.
Vamsadhara Project Stage II Phase II : CE, Visakhapatnam to ensure
completion of works for storage of 5 TMC of water by 15th
July 2018.
Hon’ble CM instructed WRD to clear pending bills if any and ensure
that project shall be completed by 30th
Nov’18
CE, North Coast
Visakhapatnam
Releasing tenders
for Construction of
new barrage (10
TMC) across Krishna
river near
Vykuntapuram (V) by
5th
July’18
Releasing tenders
for Interlinking of
Godavari – Penna
Rivers Phase-1:
10th July 2018
Page 5 of 5
# Project / Topic Gist of discussions Action to be
taken by Timeline
10
Projects under
purview of CE, KDS,
Vijayawada
Hon’ble CM reviewed status of projects under purview of CE, KDS
Vijayawada.
Taraka Rama Thirtha Sagaram reservoir: Hon’ble CM instructed CE,
KDS to ensure project completion by 31st March 2019.
Offshore reservoir on Mahendratanaya River: Hon’ble CM interacted
with the agency and instructed to complete balance works by 30th
Sept’18.
CE, KDS
Vijayawada
Completion of
offshore reservoir
on Mahendratanaya
River project by 30th
Sept’18
11 Aquaculture and Fish
ponds
Hon’ble CM advised Aquaculture officials to work in unison with Minor
Irrigation department for improvement of Aquaculture and Fish ponds in
the state.
For information -
12
Plantation drive on 4th
Saturday of every
month
Hon’ble CM advised all officials to conduct a plantation drive ‘ Vruksha
Nidhi’ during 4th
Saturday of every month. It was also discussed that
awareness shall be created among public and students shall be involved,
to improve plantation and greenery in the state for better environment.
For information -
Encl.: Annexure 1 (Brief status of 54 prioritized projects as on 25th June’18)
Sl no. Project Major Issue / Current status
Target Date of project
completion
Inaugurated projects
1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 -
2
Construction of Anicut across Sarada
River
Inaugurated on 6th Sept 2017 -
3 Mutchumarri LIS Inaugurated on 8th Sept 2017 -
4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 -
5 Gandikota – CBR Lifts Inaugurated on 3rd Jan 2018 -
6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 -
7 Modernization of Yerracalva Inaugurated on 8th Jan 2018 -
8
Formation of Pogonda Reservoir in
West Godavari
Inaugurated on 19th Feb 2018 -
9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 -
Projects ready for Inauguration
10
Pedapalem LI Scheme on Krishna
River
Ready for inauguration -
11 Chinasana LI Scheme on VLMC Ready for inauguration -
12 Owk Tunnel (GNSS Phase I) Ready for inauguration -
13
Gorakallu Balancing Reservoir (Sri
Narasimharaya Sagar)
Ready for inauguration -
14 Pulikanuma LIS Ready for inauguration -
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
Page 1 of 8
Sl no. Project Major Issue / Current status
Target Date of project
completion
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
Projects in progress under purview of CE, Tirupathi
15
Adavipalli Reservoir (HNSS Phase-II) &
Adavipalli Lift (Peddamandyam lift on
Main canal)
Reservoir : Gates erection in progress.
Lift scheme : LA Payment for 8.63 acres to be done to take up balance length
of 2.499 Km pipeline laying
Reservoir by 30-June-18
Lift scheme by 31-July-
18
16 Kuppam Branch Canal (HNSS Phase II)
Part A :From Km. 0.00 to Km 39.225 (up to II lift) : Pump house erection in
progress
Part B : Work in progress in 3.487 Km. and work to be tackled in 1.850 Km
Canal shall be made
through by 30 June
2018
17 Nellore Barrage
R/s Wing & Divide Walls, Fixing of mechanical elements, Erection of
embedded parts for gates, Pier, Hoist Columns and Slab wearing coat in
progress.
31/Aug/18
18 Sangam Barrage
Rafts, 38 nos. completed out of 42 nos.
Piers, 68 raised to required height and 6 nos above crest level against 86 Nos.
Fabrication of Gates & EM Parts are in Progress
31/Aug/18
19
Water Supply to Mulapalli and other 4
tanks.
Received administrative approval for INR 39.48 Crores on 04 June 2018.
Works shall be grounded by 3 Aug 2018
30/Apr/18
20
Lifting of water from Somasila
Swarnamuki link canal (Merlapaka
Reservoir) to Mallemadugu Reservoir
and Mallemadugu to Balaji Reservoir
Part-A: Lifting of water from Merlapaka to Mallemadugu Reservoir :
Detailed estimate submitted to GoAP for an amount of INR 288.80 Cr, seeking
administrative approval.
Part-B: Lifting of water from Mallemadugu to Balaji Reservoir :
Detailed estimate submitted to GoAP for an amount of INR 198.00 Cr, seeking
administrative approval
-
Page 2 of 8
Sl no. Project Major Issue / Current status
Target Date of project
completion
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
21 Mallimadugu Reservoir
Bund portion at a length of 4.00 Km in progress as against 4.400 Kms (0.40
Kms is pending due to R &R, Forest and HT Lines). Acceptance of CA land
and handing over is pending for uploading stage -1 approval
31/Dec/18
22 Balaji Reservoir
Bund portion at 1.750 Kms in progress as against 3.335 Kms (1.585 Kms is
pending due to Forest Clearance). Forest Clearance proposals uploaded and
accepted by PCCF, Guntur. Acceptance of CA land and handing over is
pending for uploading stage -1 approval. Proposals for additional lead cost to a
tune of Rs.23.81 Crores is submitted for approval
31/Dec/18
23 Venugopala sagar Reservoir
Bund portion at 5.076 Kms in progress as against 6.596 Kms (1.520 Kms is
pending due to Forest and HT Lines). DGPS Survey completed for both
Reservoir and CA Lands. Received suitability certificate for 121.48 Ha. against
375.472 Ha. from DFO, West Divn., Chittoor. The balance CA Lands of
254.064 Ha will be uploaded for Stage-I clearance soon after receiving the
suitability from the DFO, West Divn., Chittoor.
31/Dec/18
24
Somasila Swarnamuki link canal. (from
km 56.000 to 100.425)
Surplus Weir completed. Inlet structures are in progress. Canal length of
5.350 Kms is due. Reserve Forest of 20.83 Ha. - authentication completed in
Divisional Forest Office - Nellore & Chittoor and sent to PCCF, Guntur.CA Land
is to be handed over to Forest department.
31/Dec/18
25
Lifting of water from SSG Canal to
Althurupadu Reservoir (2.356 TMC)
Administrative approval received. Works shall be grounded for reservoir and
lift portion by 30th June 2018.
31/Dec/18
Page 3 of 8
Sl no. Project Major Issue / Current status
Target Date of project
completion
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
Projects in progress under purview of CE, Anantapur
26 Marala Reservoir
Rectification measures for tunnel in progress. Shall be completed by 31-07-
2018.
Since water in Jeedipalli reservoir is not sufficient to supply water to Marala
reservoir, this will be filled in the coming khariff season.
31/Jul/18
27 Cherlopally Reservoir
Rectification measures for tunnel in progress. Shall be completed by 31-07-
2018.
Since water in Jeedipalli reservoir is not sufficient to supply water to Marala
reservoir, this will be filled in the coming khariff season.
31/Jul/18
28
Madakasira Branch Canal beyond
Gollapalli Reservoir
Lepakshi, Peddacheruvu, Korlakunta, Konduru and Chalivendula tanks are filled
in Hindupur Constituency i.e., upto 67 Km and also Penugonda constituency. 31/Jul/18
29
Widening of HNSS Main Canal under
Phase-I
Works resumed on 23rd March 2018. Project shall be completed by 31 July 2018 31/Jul/18
30
Lifting of water from Jeedipalli
Reservoir to Bhairavanithippa Project.
Tenders called for civil works and Electro mechanical works. Project shall be
grounded by 30 June 2018
31/Dec/19
31
Lifting of water from Jeedipalli
Reservoir to Upper Pennar Project
Tenders called for civil works and Electro mechanical works. Project shall be
grounded by 30 June 2018
31/Dec/19
32
Modernization of Mid – Pennar South
Canal from Km 0.000 to Km 40.000 &
from Km 40.000 to Km 84.000
Upto 40th KM : 10,03,500 Cum of Earthwork Excavation is completed out of
30,61,650 Cum. Structures in progress.
40th KM to 84 KM : 5,19,960 Cum of Earthwork Excavation is completed out
of 15,97,480 Cum. Structures in progress
30/Apr/19
Page 4 of 8
Sl no. Project Major Issue / Current status
Target Date of project
completion
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
Projects in progress under purview of CE, Kadapa
33 Gandikota Reservoir (GNSS Phase I)
R&R issues at RS Kondapuram village shall be addressed to store 12 TMC of
water. Funds to the tune of 238 Cr needed for R&R issues resolution.
Proposed for
Inauguration by Hon’ble
CM after Water is
Stored in reservoir up to
12 TMC
34 GNSS Ph-II up to Kodur in Kadapa Dist. LA shall be completed by 30 June 2018. Tenders shall be floated shortly. -
Projects in progress under purview of CE, Kurnool
35
Pulakurthy LIS (Guru Raghavendra
Project)
Project shall be inaugurated after receiving flows into the TungaBhadra River. -
36
Hagari (Vedavathi Project) Lift irrigation
scheme
Hydrological clearances and administrative approval for preparation of DPR in
process by GoAP. Last date for bid submission of SID operations is 25 June
2018
-
37
Water Supply to Western Mandals of
Kurnool District
Tenders are submitted to COT on 15-June-2018 for approval 31/Jan/19
38 Formation of Gundrevula Reservoir
Survey works completed to the tune of 95%. CWC, KRMB and Telangana
Govt. to be addressed for co-operation and concurrence. CE ISWR,
Vijayawada to examine the issue and furnish a detailed report to Govt.
-
39
Rajolibanda Diversion Scheme (RDS)
Right Canal
Clarifications on DPR submitted to GoAP. Project value INR1761.30 Cr -
Page 5 of 8
Sl no. Project Major Issue / Current status
Target Date of project
completion
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
Projects in progress under purview of CE, Ongole
40
Kandula Obul Reddy Gundlakamma
Reservoir Project
Private land owners agreed to give their lands for alternative methods like
laying pipeline. Requested permission from GoAP on 21-June2018, to
executive the balance work based on methodology agreed during meeting
with land owners.
31/Jul/18
41
Yerram Chinnapoli Reddy Korisapadu
LIS
Valuation of structures of Thurpupalem and Pedduru villages by R&B
department is completed. (assessed value INR 14.84 Cr ). Land Acquisition is
under process for R & R Colony and to resettle the PDFs of Thurpupalem and
Pedduru Villages.
Project is proposed to
be inaugurated during
the during next khariff
season after impounding
water in the reservoir.
42
Veligonda Project - Tunnels I & II &
Head Regulator
Tunnel 1 status : Boring completed upto 15.167Km
Tunnel 2 status : Boring completed upto 10.703Km
Tunnel-1 for a length of 3.60 KM and Tunnel-2 for a length of 8.037 Km were
deleted from the existing agencies under clause 60('C). New tenders are
being finalized for balance works. Agencies agreed to give undertaking as per
the Hon’ble High Court judgment and requested for settlement of pending
claims. Report and representations of agencies on pending claims of Tunnel-1
submitted to the GoAP on 19th June'18 for according permission to submit
the proposals before Joint committee.
Head Works : Earth work excavation of Head Regulator portion completed.
Proposal for entrustment for additional 500 m length of Tunnel – 1 at non EPC
rates to the Head regulator agency submitted to the Government.
Tunnel I : 31 Dec 2018
Tunnel II : 31 May 2019
Head Regulator : 31
Aug 2018
Page 6 of 8
Sl no. Project Major Issue / Current status
Target Date of project
completion
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
Projects in progress under purview of CE, North coast Visakhapatnam
43 Vamsadhara Project Stage II Phase II
Package 88 : 45.84 Acres Balance Land to be acquired for Distributary net
work .
Works of all 3 Packages of B.R.R. Vamsadhara Project Phase-II of Stage-II
shall be completed by 15th July-2018, to store 5 TMC of water in
Hiramandalam Reservoir.
Will be ready to store 5
Tmc of water by 15th
July'18
44
Interlinking of Vamsadhara and
Nagavali Rivers
Balance Land to be acquired - 320 acres. LA to be completed by 30th June 2018. 30/Sep/18
45
Offshore reservoir on Mahendratanaya
River
Land Acquisition for R&R Villages is under progress and expected to be
handed over by 30 June 2018.
30/Sep/18
46
High Level Canal from Hiramandalam
Reservoir to Itchapuram
Tender Process for DPR is completed. Survey work shall commenced. Project
shall be grounded by Nov 2018.
30/Jun/20
47
Taraka Rama Thirtha Sagaram
Reservoir Project
Package 21 : Balance Land of 240.31 Ac is to be acquired. 11.00 acres of
reserve forest land clearance is required to execute tunnel work.
Package 21A : R&R Works in progress at Agraharam, Koradapeta and
Padalapeta villages
30/Jun/19
48
Modernization of Thotapalli Old
Regulator System
The Estimate is resubmitted duly attending remarks to the Government for
according Administrative Approval. Tender process shall be initiated post
administrative approval.
-
49 K.L.RAO Pulichinthala Project
Funds to a tune of INR 49 Cr needed towards shifting of L.I Schemes.
Proposed for inauguration after storing 30.00 T.M.C of water during next
season.
-
50 Kondaveeti Vagu Project
Eviction of houses started and Earth work excavation in Fore bay portion is in
progress. Seeking permission for ROW from Railway authorities through AP
Transco for erection of Transmission towers
15/Jul/18
51
Construction of new barrage (10 TMC)
across Krishna river near
Vykuntapuram.
Govt. accorded administrative approval for an amount of INR 2,169 Cr.
Designs under preparation. Tenders shall be called shortly.
1/May/20
Page 7 of 8
Sl no. Project Major Issue / Current status
Target Date of project
completion
ANNEXURE I
Status of 54 prioritized projects as on 25 June 2018
52
Interlinking Of Godavari – Penna Rivers
Phase-1
Total Estimated cost of Project: INR 6,212.08 Cr
(Works : INR 5,535.81 Cr, LA : INR 676.26 Cr)
Utilization (TMC) : 73 TMC
GoAP accorded administrative approval for an amount of Rs. 6020.15 Crs vide
GO Ms. No:- 51, dated 13 June 2018.
DPR preparation in progress. Tenders shall be called by 15th July 2018
-
53
Uttarandhra Sujala Sravanthi Project
Phase-I works
Part I: Agreement concluded with M/s HES Infra on 18 April 2018 and works
commenced.
Part II : Tenders are issued. Last date for tender receipt : 2nd July 2018.
-
54 Chintalapudi Lift Irrigation Scheme
Design approvals awaited from APGENCO & APTRANSCO. Supervision
charges for an amount of INR 10 Cr to be paid to APTRANSCO.
Revised Estimate for INR 6,400 Cr submitted to the Joint Committee of IBM
& SLSC on 04-04-2018 duly incorporating the add-on works of Package-1 & 2
for recommendation to the Government. Remarks are being attended.
Stage-I clearance was accorded by the MOEF to an extent of 347.64Ha of
forest land.
-