Page 1 of 5 Review of Prioritized Projects Hon’ble CM conducted Review for Prioritized Projects RECORD OF DISCUSSION Date Monday, 25 th June 2018 Time 3pm to 5:45pm Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P Venue Conference room, AP Secretariat, Velagapudi. Attendees Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD Shri G Sai Prasad. Principle secretary to Hon’ble CM. Shri. Shashi Bhushan Kumar, Secretary, WRD Shri M. Venkateswara Rao, EnC, WRD Forest department Ground water department & APSRAC Chief Engineers and officials from AP WRD M/s Vassar Labs Consultants to APWRD

Upload: others

Post on 15-Jan-2020

8 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Page 1 of 5

Review of Prioritized Projects

Hon’ble CM conducted Review for Prioritized Projects

RECORD OF DISCUSSION

Date Monday, 25th

June 2018

Time 3pm to 5:45pm

Agenda Progress review on Prioritized projects by Hon’ble Chief Minister, A.P

Venue Conference room, AP Secretariat, Velagapudi.

Attendees

Shri. D. Uma Maheswara Rao, Hon’ble Minister, WRD

Shri G Sai Prasad. Principle secretary to Hon’ble CM.

Shri. Shashi Bhushan Kumar, Secretary, WRD

Shri M. Venkateswara Rao, EnC, WRD

Forest department

Ground water department & APSRAC

Chief Engineers and officials from AP WRD

M/s Vassar Labs

Consultants to APWRD

Page 2: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Page 2 of 5

# Project / Topic Gist of discussions Action to be

taken by Timeline

1 SKOCH Awards

Hon’ble CM congratulated AP WRD for winning 19 SKOCH awards -

highest for any one department in the country.

AP Water Resource Department achieved 19 awards including 3

Platinum for Pattiseema Lift Irrigation Scheme, NeeruChettu and Real

Time monitoring of groundwater levels, 5 Gold awards for AP Water

Resources Information System, Purushottapatnam Lift Irrigation

Scheme, Gandikota LI Scheme, Muchumurri LI Scheme and Revival of

defunct LI Scheme, 8 Order of Merit Awards and one Bronze Award

apart from Platinum Award of State of the Year in Irrigation under

National Significant Award category and Platinum Award for overall

water resource department.

Hon’ble CM appreciated Minister, Secretary, EnC and officials of AP

WRD for working in unison for seamless execution and implementation

of irrigation projects and initiatives.

It was also mentioned that the entire team of AP WRD worked hard to

reach level of excellence in dry spell mitigation, real-time monitoring &

improving groundwater levels despite rainfall deficits and completing

various crucial projects in record time.

Hon’ble CM advised WRD officials to keep up the spirit and work

towards achieving water security for the state.

For information -

2 Balance tenders for

54 prioritized projects

Hon’ble CM instructed WRD to ensure that all the pending tenders of 54

prioritized projects shall be released by 30th

Aug18 WRD

Ensuring tenders of

all 54 prioritized

projects are

released by 30th

Aug’18

Page 3: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Page 3 of 5

# Project / Topic Gist of discussions Action to be

taken by Timeline

3 Utilization of Rain

guns

Hon’ble CM advised Agriculture and Micro Irrigation department to

evaluate the possibility of transferring the responsibility of deployment

and usage of rain guns to Micro Irrigation department based on the

inputs received by agriculture department. Both the department to

discuss and evaluate various possibilities for optimal utilization of rain

guns and come up with a proposal during review meeting on 2nd

July

2018

Agriculture and

Micro Irrigation

dept.

Present a proposal

for optimal

utilization of rain

guns during review

meeting on 2nd

July

2018

4 Jala-Samrakshana-

Udhyamam

CE, Minor Irrigation briefed Hon’ble CM on status of various activities

under progress as a part of 116 days water conservation drive. Hon’ble

CM reviewed component-wise progress and advised Minor Irrigation

department to take necessary actions for improvement of progress.

For information -

5 Jungle clearance of

tanks

Hon’ble CM instructed Collector, Chittore to take up jungle clearance of

tanks and complete the works at the earliest. For information. -

6

Projects under

purview of CE,

Tirupathi

Hon’ble CM reviewed status of projects under purview of CE, Tirupathi.

Kuppam Branch Canal: Agency to meet Hon’ble CM with explanation

for delay in progress and action plan by 27th

June 2018.

Mulapalli: Hon’ble CM instructed CE, Tirupathi to complete the

project by December 2018.

CE, Tirupathi

Ensuring completion

of ‘Water Supply to

Mulapalli and other

4 tanks’ project by

Dec 2018

7

Projects under

purview of CE,

Ananthapuram

Hon’ble CM reviewed status of projects under purview of CE,

Ananthapuram.

CE,

Ananthapuram

Completion of

tunnel rectification

works for Marala &

Cherlopally by 31st

July 2018.

Page 4: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Page 4 of 5

# Project / Topic Gist of discussions Action to be

taken by Timeline

Marala & Cherlopally: CE, Ananthapuram informed Hon’ble CM that

tunnel rectification works shall be completed by 31st July 2018

(extended from 30th

June to 31st July’18 due soil collapse issue).

Mid Pennar North & South canals: Hon’ble CM instructed CE,

Ananthapuram to complete the projects by 30th

March 2019.

Jeedipalli: Secretary, WRD instructed CE, Ananthapuram to give a

presentation on the scheme during review meeting on 2nd

July’18

8

Projects under purview

of CE, Ongole

Hon’ble CM reviewed status of projects under purview of CE, Ongole.

Yerram Chinnapoli Reddy Korisapadu LIS : Upon discussion with CE,

Ongole and WRD officials, Hon’ble CM instructed that crop

compensation shall be paid to the farmers to clear obstruction to

works villagers.

Veligonda Tunnels: CE, Ongole to submit a revised proposal \ letter

to EnC, WRD regarding evaluation of requisitions made by existing

agencies. Hon’ble CM to visit the project during 2nd

week of July’18.

For information. -

9

Projects under

purview of CE, (North

coast) Visakhapatnam

Hon’ble CM reviewed status of projects under purview of CE, North

coast Visakhapatnam.

Construction of new barrage (10 TMC) across Krishna river near

Vykuntapuram (V) : Hon’ble CM instructed CE, Visakhapatnam to

ensure design clearances are received by 2nd

of July’18 and tenders

are released by 5th

July’18

Interlinking Of Godavari – Penna Rivers Phase-1: Hon’ble CM

instructed CE, Visakhapatnam to release tenders by 10th

July 2018.

Vamsadhara Project Stage II Phase II : CE, Visakhapatnam to ensure

completion of works for storage of 5 TMC of water by 15th

July 2018.

Hon’ble CM instructed WRD to clear pending bills if any and ensure

that project shall be completed by 30th

Nov’18

CE, North Coast

Visakhapatnam

Releasing tenders

for Construction of

new barrage (10

TMC) across Krishna

river near

Vykuntapuram (V) by

5th

July’18

Releasing tenders

for Interlinking of

Godavari – Penna

Rivers Phase-1:

10th July 2018

Page 5: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Page 5 of 5

# Project / Topic Gist of discussions Action to be

taken by Timeline

10

Projects under

purview of CE, KDS,

Vijayawada

Hon’ble CM reviewed status of projects under purview of CE, KDS

Vijayawada.

Taraka Rama Thirtha Sagaram reservoir: Hon’ble CM instructed CE,

KDS to ensure project completion by 31st March 2019.

Offshore reservoir on Mahendratanaya River: Hon’ble CM interacted

with the agency and instructed to complete balance works by 30th

Sept’18.

CE, KDS

Vijayawada

Completion of

offshore reservoir

on Mahendratanaya

River project by 30th

Sept’18

11 Aquaculture and Fish

ponds

Hon’ble CM advised Aquaculture officials to work in unison with Minor

Irrigation department for improvement of Aquaculture and Fish ponds in

the state.

For information -

12

Plantation drive on 4th

Saturday of every

month

Hon’ble CM advised all officials to conduct a plantation drive ‘ Vruksha

Nidhi’ during 4th

Saturday of every month. It was also discussed that

awareness shall be created among public and students shall be involved,

to improve plantation and greenery in the state for better environment.

For information -

Encl.: Annexure 1 (Brief status of 54 prioritized projects as on 25th June’18)

Page 6: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

Inaugurated projects

1 Purushotha Patnam LIS Inaugurated on 15th Aug 2017 -

2

Construction of Anicut across Sarada

River

Inaugurated on 6th Sept 2017 -

3 Mutchumarri LIS Inaugurated on 8th Sept 2017 -

4 Kandaleru Left Canal – Lift Scheme Inaugurated on 12th Nov 2017 -

5 Gandikota – CBR Lifts Inaugurated on 3rd Jan 2018 -

6 Siddapuram Lift Irrigation Scheme Inaugurated on 7th Jan 2018 -

7 Modernization of Yerracalva Inaugurated on 8th Jan 2018 -

8

Formation of Pogonda Reservoir in

West Godavari

Inaugurated on 19th Feb 2018 -

9 SH-31 Road Work (GNSS Phase I) Inaugurated on 6th June 2018 -

Projects ready for Inauguration

10

Pedapalem LI Scheme on Krishna

River

Ready for inauguration -

11 Chinasana LI Scheme on VLMC Ready for inauguration -

12 Owk Tunnel (GNSS Phase I) Ready for inauguration -

13

Gorakallu Balancing Reservoir (Sri

Narasimharaya Sagar)

Ready for inauguration -

14 Pulikanuma LIS Ready for inauguration -

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

Page 1 of 8

Page 7: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

Projects in progress under purview of CE, Tirupathi

15

Adavipalli Reservoir (HNSS Phase-II) &

Adavipalli Lift (Peddamandyam lift on

Main canal)

Reservoir : Gates erection in progress.

Lift scheme : LA Payment for 8.63 acres to be done to take up balance length

of 2.499 Km pipeline laying

Reservoir by 30-June-18

Lift scheme by 31-July-

18

16 Kuppam Branch Canal (HNSS Phase II)

Part A :From Km. 0.00 to Km 39.225 (up to II lift) : Pump house erection in

progress

Part B : Work in progress in 3.487 Km. and work to be tackled in 1.850 Km

Canal shall be made

through by 30 June

2018

17 Nellore Barrage

R/s Wing & Divide Walls, Fixing of mechanical elements, Erection of

embedded parts for gates, Pier, Hoist Columns and Slab wearing coat in

progress.

31/Aug/18

18 Sangam Barrage

Rafts, 38 nos. completed out of 42 nos.

Piers, 68 raised to required height and 6 nos above crest level against 86 Nos.

Fabrication of Gates & EM Parts are in Progress

31/Aug/18

19

Water Supply to Mulapalli and other 4

tanks.

Received administrative approval for INR 39.48 Crores on 04 June 2018.

Works shall be grounded by 3 Aug 2018

30/Apr/18

20

Lifting of water from Somasila

Swarnamuki link canal (Merlapaka

Reservoir) to Mallemadugu Reservoir

and Mallemadugu to Balaji Reservoir

Part-A: Lifting of water from Merlapaka to Mallemadugu Reservoir :

Detailed estimate submitted to GoAP for an amount of INR 288.80 Cr, seeking

administrative approval.

Part-B: Lifting of water from Mallemadugu to Balaji Reservoir :

Detailed estimate submitted to GoAP for an amount of INR 198.00 Cr, seeking

administrative approval

-

Page 2 of 8

Page 8: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

21 Mallimadugu Reservoir

Bund portion at a length of 4.00 Km in progress as against 4.400 Kms (0.40

Kms is pending due to R &R, Forest and HT Lines). Acceptance of CA land

and handing over is pending for uploading stage -1 approval

31/Dec/18

22 Balaji Reservoir

Bund portion at 1.750 Kms in progress as against 3.335 Kms (1.585 Kms is

pending due to Forest Clearance). Forest Clearance proposals uploaded and

accepted by PCCF, Guntur. Acceptance of CA land and handing over is

pending for uploading stage -1 approval. Proposals for additional lead cost to a

tune of Rs.23.81 Crores is submitted for approval

31/Dec/18

23 Venugopala sagar Reservoir

Bund portion at 5.076 Kms in progress as against 6.596 Kms (1.520 Kms is

pending due to Forest and HT Lines). DGPS Survey completed for both

Reservoir and CA Lands. Received suitability certificate for 121.48 Ha. against

375.472 Ha. from DFO, West Divn., Chittoor. The balance CA Lands of

254.064 Ha will be uploaded for Stage-I clearance soon after receiving the

suitability from the DFO, West Divn., Chittoor.

31/Dec/18

24

Somasila Swarnamuki link canal. (from

km 56.000 to 100.425)

Surplus Weir completed. Inlet structures are in progress. Canal length of

5.350 Kms is due. Reserve Forest of 20.83 Ha. - authentication completed in

Divisional Forest Office - Nellore & Chittoor and sent to PCCF, Guntur.CA Land

is to be handed over to Forest department.

31/Dec/18

25

Lifting of water from SSG Canal to

Althurupadu Reservoir (2.356 TMC)

Administrative approval received. Works shall be grounded for reservoir and

lift portion by 30th June 2018.

31/Dec/18

Page 3 of 8

Page 9: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

Projects in progress under purview of CE, Anantapur

26 Marala Reservoir

Rectification measures for tunnel in progress. Shall be completed by 31-07-

2018.

Since water in Jeedipalli reservoir is not sufficient to supply water to Marala

reservoir, this will be filled in the coming khariff season.

31/Jul/18

27 Cherlopally Reservoir

Rectification measures for tunnel in progress. Shall be completed by 31-07-

2018.

Since water in Jeedipalli reservoir is not sufficient to supply water to Marala

reservoir, this will be filled in the coming khariff season.

31/Jul/18

28

Madakasira Branch Canal beyond

Gollapalli Reservoir

Lepakshi, Peddacheruvu, Korlakunta, Konduru and Chalivendula tanks are filled

in Hindupur Constituency i.e., upto 67 Km and also Penugonda constituency. 31/Jul/18

29

Widening of HNSS Main Canal under

Phase-I

Works resumed on 23rd March 2018. Project shall be completed by 31 July 2018 31/Jul/18

30

Lifting of water from Jeedipalli

Reservoir to Bhairavanithippa Project.

Tenders called for civil works and Electro mechanical works. Project shall be

grounded by 30 June 2018

31/Dec/19

31

Lifting of water from Jeedipalli

Reservoir to Upper Pennar Project

Tenders called for civil works and Electro mechanical works. Project shall be

grounded by 30 June 2018

31/Dec/19

32

Modernization of Mid – Pennar South

Canal from Km 0.000 to Km 40.000 &

from Km 40.000 to Km 84.000

Upto 40th KM : 10,03,500 Cum of Earthwork Excavation is completed out of

30,61,650 Cum. Structures in progress.

40th KM to 84 KM : 5,19,960 Cum of Earthwork Excavation is completed out

of 15,97,480 Cum. Structures in progress

30/Apr/19

Page 4 of 8

Page 10: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

Projects in progress under purview of CE, Kadapa

33 Gandikota Reservoir (GNSS Phase I)

R&R issues at RS Kondapuram village shall be addressed to store 12 TMC of

water. Funds to the tune of 238 Cr needed for R&R issues resolution.

Proposed for

Inauguration by Hon’ble

CM after Water is

Stored in reservoir up to

12 TMC

34 GNSS Ph-II up to Kodur in Kadapa Dist. LA shall be completed by 30 June 2018. Tenders shall be floated shortly. -

Projects in progress under purview of CE, Kurnool

35

Pulakurthy LIS (Guru Raghavendra

Project)

Project shall be inaugurated after receiving flows into the TungaBhadra River. -

36

Hagari (Vedavathi Project) Lift irrigation

scheme

Hydrological clearances and administrative approval for preparation of DPR in

process by GoAP. Last date for bid submission of SID operations is 25 June

2018

-

37

Water Supply to Western Mandals of

Kurnool District

Tenders are submitted to COT on 15-June-2018 for approval 31/Jan/19

38 Formation of Gundrevula Reservoir

Survey works completed to the tune of 95%. CWC, KRMB and Telangana

Govt. to be addressed for co-operation and concurrence. CE ISWR,

Vijayawada to examine the issue and furnish a detailed report to Govt.

-

39

Rajolibanda Diversion Scheme (RDS)

Right Canal

Clarifications on DPR submitted to GoAP. Project value INR1761.30 Cr -

Page 5 of 8

Page 11: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

Projects in progress under purview of CE, Ongole

40

Kandula Obul Reddy Gundlakamma

Reservoir Project

Private land owners agreed to give their lands for alternative methods like

laying pipeline. Requested permission from GoAP on 21-June2018, to

executive the balance work based on methodology agreed during meeting

with land owners.

31/Jul/18

41

Yerram Chinnapoli Reddy Korisapadu

LIS

Valuation of structures of Thurpupalem and Pedduru villages by R&B

department is completed. (assessed value INR 14.84 Cr ). Land Acquisition is

under process for R & R Colony and to resettle the PDFs of Thurpupalem and

Pedduru Villages.

Project is proposed to

be inaugurated during

the during next khariff

season after impounding

water in the reservoir.

42

Veligonda Project - Tunnels I & II &

Head Regulator

Tunnel 1 status : Boring completed upto 15.167Km

Tunnel 2 status : Boring completed upto 10.703Km

Tunnel-1 for a length of 3.60 KM and Tunnel-2 for a length of 8.037 Km were

deleted from the existing agencies under clause 60('C). New tenders are

being finalized for balance works. Agencies agreed to give undertaking as per

the Hon’ble High Court judgment and requested for settlement of pending

claims. Report and representations of agencies on pending claims of Tunnel-1

submitted to the GoAP on 19th June'18 for according permission to submit

the proposals before Joint committee.

Head Works : Earth work excavation of Head Regulator portion completed.

Proposal for entrustment for additional 500 m length of Tunnel – 1 at non EPC

rates to the Head regulator agency submitted to the Government.

Tunnel I : 31 Dec 2018

Tunnel II : 31 May 2019

Head Regulator : 31

Aug 2018

Page 6 of 8

Page 12: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

Projects in progress under purview of CE, North coast Visakhapatnam

43 Vamsadhara Project Stage II Phase II

Package 88 : 45.84 Acres Balance Land to be acquired for Distributary net

work .

Works of all 3 Packages of B.R.R. Vamsadhara Project Phase-II of Stage-II

shall be completed by 15th July-2018, to store 5 TMC of water in

Hiramandalam Reservoir.

Will be ready to store 5

Tmc of water by 15th

July'18

44

Interlinking of Vamsadhara and

Nagavali Rivers

Balance Land to be acquired - 320 acres. LA to be completed by 30th June 2018. 30/Sep/18

45

Offshore reservoir on Mahendratanaya

River

Land Acquisition for R&R Villages is under progress and expected to be

handed over by 30 June 2018.

30/Sep/18

46

High Level Canal from Hiramandalam

Reservoir to Itchapuram

Tender Process for DPR is completed. Survey work shall commenced. Project

shall be grounded by Nov 2018.

30/Jun/20

47

Taraka Rama Thirtha Sagaram

Reservoir Project

Package 21 : Balance Land of 240.31 Ac is to be acquired. 11.00 acres of

reserve forest land clearance is required to execute tunnel work.

Package 21A : R&R Works in progress at Agraharam, Koradapeta and

Padalapeta villages

30/Jun/19

48

Modernization of Thotapalli Old

Regulator System

The Estimate is resubmitted duly attending remarks to the Government for

according Administrative Approval. Tender process shall be initiated post

administrative approval.

-

49 K.L.RAO Pulichinthala Project

Funds to a tune of INR 49 Cr needed towards shifting of L.I Schemes.

Proposed for inauguration after storing 30.00 T.M.C of water during next

season.

-

50 Kondaveeti Vagu Project

Eviction of houses started and Earth work excavation in Fore bay portion is in

progress. Seeking permission for ROW from Railway authorities through AP

Transco for erection of Transmission towers

15/Jul/18

51

Construction of new barrage (10 TMC)

across Krishna river near

Vykuntapuram.

Govt. accorded administrative approval for an amount of INR 2,169 Cr.

Designs under preparation. Tenders shall be called shortly.

1/May/20

Page 7 of 8

Page 13: Review of Prioritized Projectsirrigationap.cgg.gov.in/uploadedFiles/Prioritized Projects/201806... · CM reviewed component-wise progress and advised Minor Irrigation department to

Sl no. Project Major Issue / Current status

Target Date of project

completion

ANNEXURE I

Status of 54 prioritized projects as on 25 June 2018

52

Interlinking Of Godavari – Penna Rivers

Phase-1

Total Estimated cost of Project: INR 6,212.08 Cr

(Works : INR 5,535.81 Cr, LA : INR 676.26 Cr)

Utilization (TMC) : 73 TMC

GoAP accorded administrative approval for an amount of Rs. 6020.15 Crs vide

GO Ms. No:- 51, dated 13 June 2018.

DPR preparation in progress. Tenders shall be called by 15th July 2018

-

53

Uttarandhra Sujala Sravanthi Project

Phase-I works

Part I: Agreement concluded with M/s HES Infra on 18 April 2018 and works

commenced.

Part II : Tenders are issued. Last date for tender receipt : 2nd July 2018.

-

54 Chintalapudi Lift Irrigation Scheme

Design approvals awaited from APGENCO & APTRANSCO. Supervision

charges for an amount of INR 10 Cr to be paid to APTRANSCO.

Revised Estimate for INR 6,400 Cr submitted to the Joint Committee of IBM

& SLSC on 04-04-2018 duly incorporating the add-on works of Package-1 & 2

for recommendation to the Government. Remarks are being attended.

Stage-I clearance was accorded by the MOEF to an extent of 347.64Ha of

forest land.

-

Page 8 of 8