results of several years operation of a funnel and … · lamella separator bioreactor 1 bioreactor...
TRANSCRIPT
RESULTS OF SEVERAL YEARS OPERATION OF A FUNNEL AND GATE SYSTEM WITH BIO REACTOR
AT A FORMER TAR FACTORY SITE
Christian Weingran (HIM GmbH, Biebesheim, Germany) Jörn Müller and Tobias Bartelsen (CDM Smith Consult GmbH, Alsbach, Germany)Andreas Tiehm and Axel Müller (Water Technology Center, Karlsruhe, Germany)
Hermann Schad (I.M.E.S. GmbH, Amtzell, Germany)
I.M.E.S.
Table of Contents
• Description of the Site
• Preliminary Tests, Design and Construction of the Pilot Gate
• Results of the Operation of the Bioreactor
• Next Steps
• Since 1989 HIM GmbH is responsible on behalf of the land Hesse for the remediation of contaminated sites in those cases, where responsible parties can not at all or not in time be charged with the cost for remediation.
• HIM-ASG in Hesse manages about 40 projects with a financial volume of approx. 15 - 17 m. €per year.
HIM GmbHDepartment Remediation of Contaminated Sites - HIM-ASG
Site Description
Area:25.000 m²
Contamination:Tar oil (partly in phase)
Aquifer:quaternary sand and gravel
Base of aquifer:6-8 m bgl
Depth to water level:2-3 mgroundwater flow
Barrage
Groundwater Flow
Former Tar Factory
Tar oil
Contamination in Groundwater
BTEX 8.000 µg/l
Benzene 3.000 µg/l
PAH2-16 400 µg/l
Naphthalene 5.600 µg/l
NSO-HET 1.500 µg/l
Benzofuran 700 µg/l
Benzothiophen 300 µg/l
Phenole 1.900 µg/l
Plume
Contamination
Contaminant Concentration Aerobic Degradation
Sorption on Activated Carbon
BTEX 8.000 µg/l ++ +
Other Aromatic Hydrocarbons
4.500 µg/l ++ ++
Naphthalene 5.600 µg/l ++ ++
3 ring PAH 400 µg/l ++ ++
4-6 ring PAH 5 µg/l +/- +++
Heterocyclic Compounds (HCY)
1.500 µg/l ++ +
Potential for Elimination of Contaminants
• Description of the Site
• Preliminary Tests, Design and Construction of the Pilot Gate
• Results of the Operation of the Bioreactor
• Next Steps
Preliminary Tests
Batch tests in the lab Column tests in the lab On-site column test
The system gets more complex and approaches on-site conditions.
• Which contaminants are degraded by the autochthonous micro-organisms?
• How long is the duration of the degradation?
• Which amounts of oxygen (delivered as H2O2) and nitrate are necessary?
• How do micro-organisms and toxicity develop during the degradation?
Benchmark Data for the Operation of the Pilot Gate
• Approx. 180 mg H2O2 / L of contaminated groundwater
• Stepwise and moderate increase of dose rate in the start phase
• Total residence time in the bioreactors: > 72 h
• Iron removal in front of the bioreactors
• As many dosing ports as possible for H2O2 injection
• Accessible dosing ports (development of free water zones)
• Avoiding gas clogging by O2 and other gases in the bioreactors
Technical Design of the Gate (Top View)
Technical Design of the Gate (Sectional View)
Construction Pit for the Gate
Inflow Area of the Gate
Construction of the Free Water Zones
1
2
3
Sampling Well
Dosing Station Free Water Zone
Bioreactors 1 to 3 (filled with fine gravel)
Top of the Gate and Surroundings
• Description of the Site
• Preliminary Tests, Design and Construction of the Pilot Gate
• Results of the Operation of the Bioreactor
• Next Steps
Flow Rate and Water Level
0
100
200
300
400
500
600
700
800
900
1000
94,40
94,60
94,80
95,00
95,20
95,40
95,60
2009-05 2009-09 2010-01 2010-05 2010-09 2011-01 2011-05 2011-09 2012-01 2012-05 2012-09
Flo
w R
ate
[l/h]W
ate
rlevel
[m N
N]
Waterlevel FWZ1 Waterlevel FWZ4
Waterlevel lamella separator Waterlevel GWM21
Flowrate
Degradation along the Reactor (January 2012)
0,01
0,10
1,00
10,00
100,00
1.000,00
10.000,00
Untreated Water Lamella Separator Bioreactor 1 Bioreaktor 2 Bioreactor 3
Co
ncen
trati
on
of
Co
nta
min
an
ts [
µg
/l] Benzene
BTEX
Naphthalene
PAH (2-16)
HCY
Alkyl-Phenole
Phenol-Index
< L
OD
< L
OD
< L
OD
< L
OD
< L
OD
< L
OD
< L
OD
< L
OD
< L
OD
< L
OD
< LOD
0,01
0,10
1,00
10,00
100,00
1.000,00
10.000,00
Mar 2007 Aug 2008 Dec 2009 May 2011 Sep 2012
Co
ncen
trati
on
of
PA
H (
1-1
6)
[µg
/l]
Input
Lamella Separator
Bioreactor 1
Bioreactor 2
Bioreactor 3
Degradation of PAH
0
10
20
30
40
50
60
70
80
90
100
Co
nta
min
an
t -
Eli
min
ati
on
[%
]
Lamella separator
Bioreactor 3Bioreactor 1
Bioreactor 2
Elimination of Contaminants (Average)
2009 2012
0
10
20
30
40
50
60
70
80
90
100
Co
nta
min
an
t -
Eli
min
ati
on
[%
]
Lamella Separator
Bioreactor 3
Bioreactor 1
Bioreactor 2
Elimination Rates
Parameter Average 2011
January 2012
July 2012
Average 2012
Benzene 97,7 100,0 100,0 100,0
BTEX 97,9 100,0 100,0 100,0
Naphthalene 99,8 100,0 100,0 100,0
PAH w/o Naph. 97,3 100,0 100,0 100,0
HCY 96,3 99,9 100,0 100,0
Phenol-Index 87,6 100,0 100,0 100,0
Reduction of Toxicity (Average 2011)
*
Untreated Water
Lamella Separator
Bioreactor 1 Bioreactor 2 Bioreactor 3
Low
est
Ineffective D
ilution (
LID
)* [
-]
Mass Flow 2007 to 2012
0
5
10
15
20
25
30
35
40
45
50
55
March 2007 July 2008 December 2009 April 2011 September 2012
Mass F
low
[kg
]
BTEX Benzene
PAH (2-16) Naphthalene
HCY Phenol-Index
Development of Contaminants (Source)
0
1000
2000
3000
4000
5000
6000
7000
Benzene BTEX Naphthalene PAH (2-16) HCY
Co
ncen
trait
on
of
Co
nta
min
an
ts [
µg
/l]
2010 2011 2012
Development of Contaminants (Downstream)
0,01
0,10
1,00
10,00
100,00
Benzene BTEX Naphthalene PAH (2-16) HCY
Co
ncen
trati
on
of
Co
nta
min
an
ts [
µg
/l]
Sep 2010 Apr 2011 Sep 2011 Feb 2012 Apr 2012 Jul 2012 Oct 2012
Contamination Downstream
Monitoring and Operating
Monitoring Parameter Control Points Time Intervall
SAK254nm, Oxygen Input & Output Gate Monthly
Contaminants (PAH, HCY, BTEX, Phenol)
Input gate, Output BR1, Output Gate, Control Points Downstream
Quarterly
Inorganic Parameters (Fe, Nitrate, Nitrite, Ammonium, Phosphate)
Input Gate, Output BR1-BR3, Output Gate, Control Points Downstream
Semiannually
Operating Activities Responsibility Time Intervall
Maintenance (Pumps for Dosing 300 mg/l H2O2, Electrics, etc.)
Operator of the Facility Monthly
Groundwater Monitoring, Field Survey, Supervision of the Site
Engineering Consultant Monthly / Quarterly
• Construction 770,000 €
• Monitoring 50,000 €/a
• Operating 40,000 €/a
• Monitoring and operating cost will be reduced after the extension of the system and the demonstration of a permanent effective clean up.
Cost
• Description of the Site
• Preliminary Tests, Design and Construction of the Pilot Gate
• Results of the Operation of the Bioreactor
• Next Steps
∑ 650 l/h
Funnel Extension East
Groundwater Extraction
Groundwater Extraction
Tar Oil
Funnel Extension West
Extension of the Funnel and Gate System
• Full hydraulic containment of the site by extension of the funnels
• No need for a second gate
• Active groundwater-extraction
• Controll of groundwater-flow
• Stabilization of degradation processes
• No need for an activated carbon zone
• Establishing ENA processes downstream
Important Features
Thank you for your attention !
It was sponsored by the German Federal Government and the state of Hesse.
This projekt was part of RUBIN research network.