resource pack ian harries cmiosh nebosh national construction certificate © 2013 ian harries. all...

74
Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted or reproduced or utilised in any form or by any electronic, mechanical or other means, now known or hereafter invented, including photocopying and recording, or in any storage retrieval system without permission in writing from the publishers.

Upload: robert-lockhart

Post on 26-Mar-2015

228 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Resource Pack

Ian Harries CMIOSH

NEBOSH National Construction Certificate

© 2013 Ian Harries. All rights reserved. No part of this material may be reprinted or reproduced or utilised in any form or by any electronic, mechanical or other means, now known or hereafter invented, including photocopying and recording, or in any storage retrieval system without permission in writing from the publishers.

Page 2: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

NEBOSH National Certificatein Construction Health and Safety

NCC1.1

Construction Law and Management

Chapter 6

Page 3: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Contents

Introduction to the UK construction industry Scope, definition and nature of construction

activities Why manage health and safety within the

construction industry? Construction (Design and Management)

Regulations Sources of external construction health and

safety information

Page 4: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Learning outcomes

Identify the scope, definition and particular issues relating to construction activities.

Outline the legal, moral and financial consequences of failing to manage health and safety within the construction industry.

Outline the scope and application of the Construction (Design and Management) Regulations.

Identify the nature and main sources of external construction health and safety information.

Page 5: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Scope and nature of Scope and nature of the UK construction the UK construction industryindustry

Page 6: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Represents 8% of the UK’s Gross Domestic Product; roughly worth £17bn.

 

Consists of more than 200,000 companies (19,000 employing less than 7 employees) employing 1.75 million labourers and tradesmen, plus 450,000 professionals & consultants.

 

In 2009/2010 made up 4% of the UK workforce, though 27% of workplace fatalities, 10% of major accidents and 6% of over 3 day injuries are construction related.

Page 7: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

In 2009/2010 the construction industry accounted for the largest number of fatalities in any work sector (46) compared to an average of 66 over the preceding 5 years. 

In 2009/2010 there were 46 construction fatalities, 3,120 major injuries, 6,173 Lost Time Accidents, 3,700 cases of self-reported cases of workplace ill health costing the UK economy 3.3M working days.

Page 8: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Building works, both for domestic industrial and commercial clients

Renovation of existing or derelict premises Alteration to existing structures, premises,

etc. Maintenance of existing premises which

are either occupied or unoccupied Civil engineering projects Engineering construction projects Demolition of all or part of a structure or

premises

Page 9: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Site clearance Demolition of all or part of a structure

or premises within the construction site

Dismantling of all or part of a structure Excavation to identify underground

services or structures for clearance, maintenance or connection into

Loading, unloading and storage of debris, building materials, plant and equipment

Page 10: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Site movements of plant, equipment, materials and persons

Fabrication of building components, structures, etc. for movement/lifting into place

Decorating of external and internal surfaces, structures, etc.

Cleaning of part or all of a premises, structure, grounds etc.

Installation, removal and maintenance of services such as water, gas, electricity, etc.

Landscaping of the site following construction completion and before handover to the client.

Page 11: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

By their very nature construction sites are temporary in nature, and throughout the project constantly changing in their appearance, layout and traffic/pedestrian routes.

Other issues will be weather related; heavy rain, snow or high winds may cause the following issues:

delays due to unsafe conditions, or repairs required to scaffolding, excavations, tower cranes, etc. which can lead to financial penalty clauses being activated by the client.

Page 12: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Time pressure and financial constraints set by the client can cause issues and problems, with the temptation being to compromise on the arrangements for safeguarding the health safety and welfare of those working on the construction site, visitors and members of the public.

What aspects of construction site safety could be affected if compromises are made?

Page 13: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Compromises can include:

Lack or poor provision of welfare facilities Non-segregation of tasks taking place at below ground

level, ground level and those taking place at height Lifting of materials, fabricated sections, etc. over areas

where employees are working Non-segregation of pedestrian and vehicle routes,

protection against accidental contact between vehicles and scaffolding.

Page 14: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

The level of competency and skills within the workforce may also be an issue:

employees new to the construction industry, or migrant employees from outside the UK will require additional training and supervision than more experienced employees used to working in the construction industry.

Page 15: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Other management issues facing the construction industry is the increasing employment of migrant labourers from outside of the UK.

In 2007: Migrant labour accounted for 6% of the UK’s

construction workforce – in Greater London this accounted for 26% of those employed in the construction industry

5 migrant workers died following an accident at one construction site alone.

Page 16: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Over the past 3 years migrant worker deaths accounted for 8% of all construction related deaths.

So who has responsibility for migrant workers; the gang-master or the construction employer?

Page 17: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

The answer is both the gangmaster and construction employer both have a

duty of care and should liaise to ensure appropriate risk assessments, personal protective equipment, training and appropriate supervision are in place.

Before any migrant worker starts on a construction site what should be determined by the employer?

Page 18: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Does the work the migrant worker(s) will be employed for require any special vocational skills, if so can the migrant worker supply copies of qualifications or demonstrate the required skill level?

Do the migrant workers have a reasonable command of written and spoken English?

What information, instruction, training and supervision will the migrant workers require?

Page 19: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

To identify the above, employers should conduct a specific risk assessment on the hazards posed to migrant workers when working on their site.

What should such an assessment cover?

Page 20: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

Their command of written and spoken English so that basic communication is possible with them on site

Their level of literacy and numeracy and previous skills, past work experience

The compatibility of non-UK vocational qualifications with those available in the UK

Any physical and health attributes required for the work(s) they will undertake

The provision and level of training instruction information and supervision – are supervisors able to effectively communicate with the migrant worker?

Any special welfare or emergency arrangements required.

Page 21: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

An effective induction will need to cover: Consideration to the needs of migrant workers with a poor

command of English – using accredited translators, use of non-verbal visual training aids

Translation of any critical safety information, such as fire and emergency procedures, risk assessments, method statements, etc.

How migrant workers can identify their supervisor, first aiders, etc.

An evaluation on the understanding on the information and instruction given out during the induction to ensure an adequate level of understanding.

Page 22: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Types of construction work

Construction industry issues

Construction

activities Introduction

Group discussion

Scope & nature of UK construction

1 What are some of the pressures on managers of construction projects that could lead to accidents on construction sites?

2 A principal contractor needs to employ sub-contractors, some of whom may not have English as their first language.

How can the principal contractor ensure that all site operatives fully understand site rules with regards to health and safety?

Page 23: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Why manage Why manage health & safety health & safety in construction?in construction?

Page 24: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

In 2002 the Construction Industry Advisory Committee set the following revitalising targets for the UK construction industry:

Reducing the incidence rate for fatalities and major injuries by 40% in 2004/2005 and 60% by 2009/2010

Reducing the incidence rate of cases of work-related ill health by 20% by 2004/2005 and by 50% by 2009/2010 

Reducing the number of working days lost per 100,000 employees from work-related injury and ill health by 20%.

Page 25: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

In reality these figures represented a commitment to a reduction of 3,000 major injuries by 2009/2010 than there were in 1999/2000.

So how did the UK construction industry fare in meeting these targets?

Page 26: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

Since 2000/2001 all the accident incidence rates have fallen by between 34% and 63%, with an overall reduction of 72% in the fatality rate.

However, this still means that 700 construction workers have been killed in the last 10 years, and 2,765 since 1981.

Page 27: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

2009/2010 Construction Industry Accident Statistics

FatalitiesMajor

injuriesOver 3 days

Total 46 3,120 6,173

Employees 30 (65%) 2,585 5,651

Self-employed 12 (26%) 535 522

Members of the public

4 (9%) N/A N/A

Page 28: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

Percentage of fatalities by construction activities from 1999 to 2010

Activity1999 – 2007

(687)

2008 – 2009

(52)

2009 – 20010

(42)Domestic – repair, refurbishment, etc.

27 26 34

Non-domestic – repair, refurbishment, etc.

22 26 34

New build – housing 11 10 12New build – commercial 13 10 5New build – industrial 4 2 2.5Roadworks 9 6 9Civil engineering 7 14 0Demolition 7 6 3

Page 29: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

2009/2010 Construction Industry Accident Statistics

The fatalities were caused by:

Falling through roof lights and fragile roofs, from ladders, scaffolds and other workplaces

Being struck by excavators, lift trucks or dumpers Being struck by falling loads and equipment Being crushed by collapsing structures.

Page 30: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

2009/2010 Construction Industry Accident Statistics

Analysis of major injuries reveals that 35% of all construction industry accidents were the result of falls from heights:

62% were painters or decorators 38% were bricklayers and masons 36% were scaffolders, stagers and steeplejacks 36% were electrical fitters.

Page 31: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

2009/2010 Construction Industry Ill-health Statistics 3.3 million days were lost in the construction industry

due to work-related ill health and workplace injuries.

In the construction industry this equates to 1.5 days per worker as opposed to 1.3 days per worker in all other industries.

Page 32: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

In 2009 the HSE undertook an inspection programme covering 1,759 construction sites, and encompassing 2,145 contractors operating on these sites.

Of these sites 348 were identified as having serious health and safety risks, resulting in over 500 enforcement notices being issued.

Page 33: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

A comparison of the number of enforcement notices issued between 2007 and 2010 to the construction industry and all other industries shows:

Page 34: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

A comparison of prosecutions, convictions and average level of fines for 2007 to 2010 shows:

Page 35: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

In 1999 the HSE undertook a cost comparison between ill-health, injury and damage accidents:

Damage accident (involving plant and equipment) costs were 80% of the total costs and between 3 to 11 times the cost of injury accidents.

Ill health(£million)

Injury(£million)

Damage(£million)

Total(£million)

Min Max Min Max Min Max Min Max100 180 140 140 420 1,570 660 1,890

Page 36: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

Sharing best practice Ensuring that all construction workers receive induction

training before starting on any project Raise competence levels of all construction workers in

the house building sector Encourage worker participation and involvement through

trade union or employee safety representatives Tackling the informal economy within the construction

industry, together with the use of casual labour.

Page 37: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

The HSE has also published its inspection criteria for construction sites, which covers the following:

Competence and control of contractors and employees Risk assessments Communication of risk controls to the workforce Selection, use, inspection and maintenance of

equipment Welfare facilities and site cleanliness/tidiness.

Page 38: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Key improvement targetsFinancialLegalMoralGroup discussion

Why manage H&S in construction?

1 What is the HSE’s role in improving the health and safety performance of the construction industry?

2 How can construction industry employers prevent workplace fatalities and major injuries from occurring?

Page 39: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Construction Construction (Design & Management) (Design & Management) RegulationsRegulations

Page 40: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

The CDM Regulations cover all construction activities in the UK, and apply to the whole of a construction project from the initial design, the construction phase and finally the hand-over of the completed structure to the client.

The CDM Regulations came into effect on 6 April 2007, replacing the original CDM Regulations from 1994 and the Construction (Welfare, Health & Safety) Regulations 1996.

Page 41: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

The CDM Regulations are split into several main parts:

Part 1 Definitions

Part 2 Covers construction projects & management duties

Part 3 Sets out additional duties for notifiable projects

Part 4 Sets out the duties relating to health, safety and welfare on construction sites.

Page 42: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Main requirements & changes from CDM 1994

The Construction (Health Safety & Welfare) Regulations 1996 have been repealed and included within Part 4 and Schedule 2

Work for domestic clients is no longer notifiable A group of clients involved in a project can elect one or

more of its members to act as the client The role of the CDM co-ordinator is to support the

client and co-ordinate design and planning – the planning supervisor role does not exist

Page 43: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Main requirements & changes from CDM 1994

The CDM co-ordinator, principle contractor and written health & safety plan are only required for notificable projects

Duty holders must be competent to carry out their roles, likewise anyone instructed to carry out or manage the design or construction work must be competent too

The ACOP L144 Managing Health & Safety in Consultation sets out the requirements for individual and corporate competence

Page 44: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Main requirements & changes from CDM 1994 All parties involved in the project have a duty for

effective co-operation and co-ordination Clients are required to take reasonable steps to

ensure management arrangements will allow the construction work to be undertaken without risk to health safety and welfare, and that such arrangements are reviewed throughout the project

Clients must inform designers and contractors of the time they have before work commences on site for planning and preparing construction work.

Page 45: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Client

Anyone involved in a trade, business or other undertaking (for profit or not) and who commissions the construction work to be carried out.

Can be an individual client or a consortium.

Domestic clients do not have duties under the CDM Regulations.

Page 46: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Designer

Organizations or individuals who carry out the design stage of the project, and can include: 

Architects Structural engineers Quantity surveyors Building service engineers Interior designers, shop fitters, etc.

Page 47: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

CDM co-ordinator

Appointed under for notifiable projects only, and provides clients with a key project advisor in respect of construction health and safety management risks, in particular:

Giving advice and assistance to the client in order for them to appoint competent designers and principal contractor

Giving advice and guidance to the client to allow them to meet their duty to ensure adequate management and welfare arrangements are in place

Page 48: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

CDM co-ordinator Develop the pre-construction phase information for

issuing to prospective designers and contractors

Notify the HSE of the construction project

Advise the client on the suitability of the construction phase health and safety plan developed with the principal contractor

Ensure designers comply with their duties

Prepare, update and issue the health and safety file to the client on completion of the project.

Page 49: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Principal contractor

Appointed by the client for notifiable projects, and can be an individual, an organization or management contractor.

The principal contractor’s main duties are to co-ordinate and manage the construction phase, including the health, safety and welfare arrangements and practices for the site, and anyone who could be affected by the work.

Page 50: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Pre-construction health and safety information

The client must provide designers and contractors, and for notifiable projects the CDM co-ordinator, with specific health and safety information to allow the identification of hazards and risks associated with the design and construction work.

What information should be included?

Page 51: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Pre-construction health and safety information

What information should be included?

Project description Client’s considerations and management requirements Environmental considerations Significant design and construction hazards.

Page 52: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Construction phase health and safety plan

Sets out the principal contractor’s organization and arrangements to manage construction risks, site welfare and co-ordinate the construction activities.

Only contains information relevant to the project, and reflects how the project was organized and managed to provide a safe working environment.

Page 53: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

There is no requirement to appoint a CDM co-ordinator, principal contractor or prepare a construction phase health and safety plan for non-notifiable projects.

The architect or lead designer will normally lead the co-ordination of the design work, while the main contractor or builder will co-ordinate the construction work in line with Part 4 and Schedule 2.

Page 54: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Clients are expected to manage or plan projects themselves.

The client is responsible for ensuring designers, contractors and others are competent, or work under the supervision of competent persons, who are adequately resourced and appointed early enough to fulfil their responsibilities.

Page 55: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

HSE notifiable construction projects

Commercial or industrial client

Will the construction phase last more than 30 days?

NO Notify the HSE on form F10

Domestic clientDomestic client

Will the construction phase involve more than 500 person days of construction activity?

YES

YES

NO

HSE notification not applicable

Page 56: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Clients – responsible for

The impact they have on health and safety Making sure things are done, not do them themselves Appointing a CDM co-ordinator to advise and co-ordinate

activities on notifiable projects Ensuring enough time and resources are provided to

allow the project to be delivered safely Focusing on establishing a competent project team early

on which fosters a culture of co-operation and integration Not allow work to commence until the principal contractor

has prepared the construction phase plan

Page 57: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Designers – responsible for

Ensure clients are aware of their duties Make sure they (the designer) are competent for the

work they do Co-ordinate & co-operate their work with the CDM co-

ordinator and others as necessary to manage risk Provide information to the CDM co-ordinator for the

health and safety file.

Page 58: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Designers – in relation to their design

Eliminate hazards from the construction, cleaning, maintenance and proposed use & demolition of a structure

Reduce risks from any remaining hazards Give collective risk reduction measures priority over

individual measures.

Page 59: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

CDM co-ordinator – responsibilities

Be appointed before the designer and principle contractor and have the relevant competence for the construction project

Give suitable and sufficient advice to clients co-ordinate the arrangements for health and safety for planning and design work

Prepare a health and safety file.

Page 60: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Principal contractor – responsibilities

Be appointed for notifiable projects and as soon as is practicable

Ensure the client is aware of duties, a CDM co-ordinator has been appointed and HSE notified

Appoint competent contractors Properly plan, manage, monitor and resource the

construction phase Inform contractors of the minimum time allowed for

planning and preparation

Page 61: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Principal contractor – responsibilities

Ensure safe working, co-ordination and co-operation between contractors

Arrange for suitable welfare arrangement and facilities from the start, together with arrangements for securing the site outside of working hours

Promptly provide the CDM co-ordinator with information for the file

Liaise with CDM co-ordinator in relation to design and design changes.

Page 62: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Principal contractor – responsibilities

Ensure the construction phase health and safety plan is prepared and implemented prior to work commencing covering:

The organization and arrangements for managing risk and co-ordinating work

Plan should be tailored to the particular project and risks involved

Prepare and enforce site rules as required Give reasonable direction to contractors including client

appointed contractors

Page 63: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Principal contractor – responsibilities

Provide the plan to those who need it Ensure all workers have been provided with suitable

health and safety induction, information and training Ensure the workforce is consulted about health and

safety matters Display key project information to workers.

Page 64: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Principal contractor

The principal contractor does not have to:

Provide training to workers they do not employ Undertake detailed supervision of contractors’ work Fill the construction phase plan with irrelevant

information or endless generic paperwork.

Page 65: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Contractors and the self-employed

Contractor should:

Check that a CDM Co-ordinator has been appointed and the HSE notified before they start work

Co-operate with the principal contractor, CDM Co-ordinator and others working on the project or at adjacent sites

Inform the principal contractor about risks arising from their work

Provide the principal contractor of any contractor who they are using as a sub-contractor

Page 66: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Contractors and the self-employed

Contractor should:

Comply with reasonable directions from the principal contractor, and with any relevant rules as set out in the Construction Phase Health and Safety Plan

Inform the principal contractor of any problems with the plan or risks identified during their work which have significant implications for the management of the project

Inform the principal contractor about accidents and dangerous occurrences

Provide information for the Health and Safety File.

Page 67: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Pre-construction information

Description of the project Client’s considerations and management requirements Environmental restrictions and existing on-site risks,

including safety and health hazards Significant design and construction hazards.

Page 68: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Construction phase plan

Description of the project Management of risk Arrangements for controlling significant site risks –

safety and health hazards.

Page 69: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM Scope

Group discussion

CDM

Health and safety file

Description of the work carried out Residual hazards and how they are being controlled Key structural principles Hazardous materials used Information regarding the removal or dismantling of installed

plant and equipment Health and safety information relevant to the cleaning and

maintenance of the building/structure Types and marking of services supplying the building or

structure Information and ‘as-built’ drawings of the structure, plant and

equipment.

Page 70: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Notifiable projects

Definitions Non-notifiable projects

CDM 2007 Scope

Group discussion

CDM

1 What are the main duties of designers under the CDM Regulations 2007?

2 What are the main duties of clients under the CDM Regulations 2007?

3 What role does the CDM co-ordinator play in relation to notifiable construction activities?

4 What are the main duties of the principal contractor under the CDM Regulations 2007?

5 When is a construction project notifiable to the HSE under the CDM Regulations 2007?

6 What information should be included within the construction phase plan under the CDM Regulations 2007?

Page 71: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

Sources of external Sources of external construction health and construction health and safety informationsafety information

Page 72: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

External construction H&S information sources

Group discussion

External information sources

General sources of informationUK Construction legislation – CDM Regulations, Construction (Head Protection) RegulationsHSE construction publicationsReports published by organization such as Construction Skills, Construction Industry Researching Board, Civil Engineering Contractors Association, Major Contractors GroupChartered Institute of BuildingConstruction Skills Certification SchemeEuropean Committee for StandardisationBritish Standards InstituteInternet.

Page 73: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

External construction H&S information sources

Group discussion

External information sources

Construction health and safety forumsConstruction Industry Research and Information Association

Civil Engineering Contractors Association

Major Contractors Group.

Page 74: Resource Pack Ian Harries CMIOSH NEBOSH National Construction Certificate © 2013 Ian Harries. All rights reserved. No part of this material may be reprinted

External construction H&S information sources

Group discussion

External information sources

1. What are the main sources of published information that may be consulted when dealing with a health and safety issue on a construction site.