residences at forsyth parkside 2016 state of the...
TRANSCRIPT
Page 1 of 16
Residences at Forsyth Parkside
2016 State of the Building
1. Introduction
1.1. General: I am writing this letter to better share information about the state of our
building. I ask you to please take a few minutes to read through this letter and I invite
anyone interested in learning more about the building to call any one of your Board
members…we would love to talk with you. I encourage everyone to get involved by
considering volunteering on the Board or for one of the new committees. Please
contact Laura Dixon if you are interested in joining the Board or a committee.
1.2. Deferred Maintenance: The foundation for the building was laid in circa 1917, which
makes it almost a century old building. The building appears to have been under
maintained for a majority of that time, but within the last decade there has been some
much needed maintenance done to the building due to the hard work of previous
Board members and the commitment of the owners. I will write in more detail about
what some of those maintenance tasks were, but they include; replacing the roof;
replacing the shaft on the elevator; modernizing the controls in the passenger elevator
and starting repairs on the outside brickwork. We should be grateful to those Board
members and owners that constructed the forward momentum to bring our building
into a state of repair. However, we have a long way to go, as I will write in more detail
following, but the major projects include; finishing the outside brickwork; repairing or
replacing windows; upgrading the building plumbing; parking lot work; and lobby work.
1.3. Shoddy Construction Practices: There has been an abundance of shoddy construction
practices in the past. I have seen many electrical and plumbing code violations
throughout the building that not only put owners at risk of property damage, but
introduced safety concerns. As an example, I was shown by one contractor where a
previous owner or contractor had tied a unit's bathroom ventilation systems into a
plumbing stack, which could have introduced sewer gases into a unit. We are lucky in
that several units have been recently renovated by, not just by qualified contractors,
but by conscientious contractors that have corrected code violations. Kudos to those
unit owners that have had quality work done in their units…it is appreciated by all.
1.4. Priorities
1.4.1. General: Having limited budget and time, as we move forward in bringing the
building into a state of repair, we need to manage our priorities. Not to say we will
strictly follow these priorities, but for the most part, it is a guide we use. We should
Page 2 of 16
also note that some projects fall into more than one category. The order of
priorities are:
1.4.1.1. Safety Issues: Anything that mitigates risk of injury. An example would
be; the recent repairs to our fire alarm system; or properly tying the outside
corner brickwork into the main structure of the building so that it would not
fall on a passerby.
1.4.1.2. Structural Issues: Anything that supports the integrity of the building. An
example would be; the recent roof replacement; or the repairs being made to
the outside brickwork.
1.4.1.3. Nuisance Issues: Anything that is outside the scope of the first two
priorities but pose a significant nuisance to the owners. An example of this
would be to stop unauthorized access to our parking lot by installing a gate
access system.
1.4.1.4. Aesthetics: Lastly, but not to be under emphasized, is anything that is
purely aesthetic in nature. I do not want to imply that no work will be done
sprucing up the place until the other priorities are complete. Quite the
contrary, we have a Lobby Committee that has been doing wonderful work.
2. Brickwork
2.1. General Repointing: Repointing consists of grinding out cracked and damaged mortar
and replacing with new. That sounds easy, but it is not. The old mortar needs to be
ground to a minimum depth for the new mortar to do its job. The new mortar must be
allowed to set properly in order to establish a good bond to the brick and have the
required compression strength when it sets. It was also discovered that we had many
missing or rotted brick ties (metal strips that hold the brick to the building). Most of the
repointing work has been completed; with the North, East and West sides complete.
The North side was in the worst condition because it is constructed of a much softer
brick than the other three sides. We still have the South side to do, but the good news
is that it is constructed of a very strong brick and appears to be in much better
condition compared to the North side of the building. Window lintels, the steel angle
iron that supports the brick above each window, which were found to be in poor
condition have been replaced along the way. Figure no.1 shows the condition of one of
the lintels that was replaced.
Page 3 of 16
figure no.1
2.2. Air conditioner Openings: Several air conditioner opening on the East side of the
building, which were abandoned in place, were closed in under the general repointing
project. We have decided to back assess each unit owner the cost associated with that
work. Ben Coli has kept records of his work that can be viewed in the HOA office. Please
contact Tom Paxton if you wish to review those records. Before we move to the South
side of the building to continue general repointing work, we will be taking a break to
work on closing up the abandoned-in-place air conditioner openings and doing repairs
to other openings that are still in use. Unit owners will be assessed the associated costs
of repairs appurtenant to their units. An assessment schedule was sent out in an email
to all members in 2015.
2.3. Dryer and Bathroom Ventilation Openings: Several dryer ventilation and bathroom
ventilation openings have been installed under the general repointing project. As these
ventilation openings are appurtenant to the units we will also be back assessing each
unit owner the cost associated with that work. Again, you are free to view Ben Coli's
records of work located in the HOA office. If anyone is interested in having a ventilation
opening added for either a bathroom or dryer, please send the HOA an email at
2.4. Painting of Yellow Brick: Some research has been done in the past to test various
paints. At some point in the future we will be sending out Requests for Proposals
Page 4 of 16
soliciting bids to repaint the yellow brick. This is not an immediate need, so I am not
sure when we will be doing this work.
3. Windows
3.1. General: Maintenance of the windows is a responsibility of the HOA. The general plan
for moving forward in replacing or repairing the windows is to remove a window from a
unit for exploratory investigation to help us determine what our options might be. We
will be working with the Metropolitan Planning Commission (MPC) through this
process. From our initial discussion with the MPC…we have two possibilities to rework
our windows; one is to repair or rebuild the existing windows in place; the other is to
replace the windows with custom replica window that has been approved by the MPC.
Replacement windows will give us better performance and functionality and, from
preliminary discussions, will generally be less expensive then repairing the existing
windows. Whatever we will be doing…we will be doing the same to all the windows.
We will be assessing each unit the costs associated with working on the windows
appurtenant to each unit. We are working hard to start this work as soon as possible
and this is our next highest priority after completing the repairs to the brickwork and
upgrading the building plumbing.
3.2. Replacement Windows
3.2.1. Custom Replica Windows: One-over-one (one pane of glass in each sash), double
hung (upper sash and lower sash opens) glazed, or simulated glazed, window.
3.2.2. Sound Proof Glass: After a discussion with the MPC, we will not be allowed to
use double pane windows, but we will be allowed to use sound mitigating
laminated glass. Laminated glass is very strong, sound absorbent and more energy
efficient than single pane glass.
3.2.3. Ultraviolet Protection: We will be allowed to use ultraviolet (UV) blocking glass.
UV blocking glass reduces energy use and helps to protect interior finishes.
3.2.4. Tilt-in for Easy Cleaning: I dream of a day we can have clean windows…enough
said.
3.3. Rebuild Existing Windows
3.3.1. Repair in Place: From preliminary proposals, the labor required to repair
windows in place is significant. The advantage of this option is we would keep any
hand drawn glass panes; the disadvantage is we would not be able to clean
windows from inside our units and no option for UV protection or sound
mitigation.
Page 5 of 16
3.4. Storm Windows: As we work on replacing or repairing windows we will be removing
the storm windows. A storm window would only be removed from a given window as
we start work on replacing or repairing that window.
4. Elevators
4.1. Passenger Elevator
4.1.1. General: At the start of 2015 we changed the elevator service company we were
using because of lack of service issues and escalating costs. The old company we
were using was purchased by a national chain and was failing to provide the
contracted services and it was becoming increasingly difficult to get them to
respond to a call for service. We decided to change to a smaller local company in
hopes that we could build a new relationship with local folks. Our old elevator
service contract pricing included insurance for the elevator hydraulic pump, which
was about two-thirds the cost of replacing the pump all together.
4.1.2. Elevator Shaft and Hydraulic Pump: The elevator shaft was replaced a few years
back and has a life expectancy of 25 years, depending on use.
4.1.3. Elevator Car: The car itself is in good shape but we might have to upgrade some
components of the car as we move forward. We will continue looking into this.
4.1.4. Controls: The controls used to run the elevator were original to the elevator and
outlived their life expectancy. In 2015 we did ae elevator modernization project
which included replacing all the controls in the mechanical room, replacing the
hydraulic power plant, and replacing the controls in the hoist-way and car.
4.2. Freight Elevator
4.2.1. General: The freight elevator has simple controls, which is a significant factor in
its longevity. You can find the rules on using the freight elevator on the HOAs
website at https://forsythparkside.managebuilding.com.
4.2.2. Elevator Car: We replaced the emergency light fixture in the car. We also did a
little work to tidy up the safety circuit.
4.2.3. Controls: The logic to run the elevator is accomplished via electromechanical
relays. The control logic circuitry to run the freight elevator is simple because there
is no call system circuitry, automatic car leveling circuitry and very little in the way
of safety circuitry. Even though we will have to upgrade the controls at some
point…it is not an issue that we need to deal with immediately because of the
simplicity and duty cycle. Figure no.4 is a picture of the inside of the control panel
for the freight elevator.
Page 6 of 16
figure no.4
5. Roof
5.1. New Roof: The roof was replaced with a commercial grade roof in the last decade. It is
a very nice roof and, if cared for properly, is expected to last 50 years plus.
5.2. Regular Roof Maintenance: We have a large investment in the roof and it needs to be
cared for like any other system. I can see from doing a cursory inspection that it is time
to have some routine maintenance done. We will be looking into this later this summer.
Page 7 of 16
6. Lobby
6.1. General Lobby: The lobby was repainted in the not too distant past, but is already
showing signs of wear. There are some things that we could do to make the lobby look
better.
6.2. Front Door: The 1970s style front door is not only out of place in our turn of the century
building it is also in a state of disrepair. It is working for now, but we do have plans of
replacing the door with one that is more in keeping with the architectural style of the
building.
6.3. Mailboxes: The mailboxes are in a bad place and also in a state of disrepair. We have
talked about finding a better solution for the mailboxes when we get to remodeling the
lobby.
6.4. Lighting: The lighting is in poor condition and the incandescent bulbs need frequent
changing. Without considering the cost of the bulbs, we spend about $400.00 (5,250
KW-Hours) per year burning the incandescent bulbs in the lobby alone. Someone
(usually Tom Paxton) is on a ladder changing bulbs every month…if not more
frequently. In my opinion, having someone climb a ladder that often to change bulb is
not only unfair to that person, but it is also a safety concern. We are investigating using
LED lighting that will last much longer and cost less to operate.
7. Limited common hallways
7.1. General: The hallways are considered limited common space, meaning that the
common space is shared by a limited number of owners…the owners that live on that
floor. As such, any costs associated with improvements to the hallways is carried by the
owners on that floor. The hallways are in need of some attention. For now we are going
to hold off from doing any remodels to the hallways until after the building plumbing
has been upgraded.
7.2. Flooring: Some flooring suggestions that I have heard are tile, hardwood, and polished
concrete. I think most everyone would like to see the filthy worn carpeting go. We
could always put runners down the halls if we end up with some type of hard
flooring…at least with runners we can pick them up and have them cleaned.
7.3. Drop Ceilings: Just like the carpet, the drop ceilings are in poor condition and need to
be replaced.
7.4. Lighting: In 2015 we replaced the lighting on the 2nd, 4th and 5th floors with LED lighting
on motion sensors. The redesign of the lighting on those floors have reduced the
electricity cost on each floor from $380.00/year to $7.50/year.
8. Plumbing
Page 8 of 16
8.1. General: The common plumbing systems are original to the building. It is made of
galvanized pipe, which has a life expectancy of 50 years in open air and 20 years in
concrete (and we have some of both). The plumbing systems are in very poor condition
and should have been replaced when the building was converted to condominiums in
the 1970s. The plumbing systems are so bad that it has come to a head…and we need
to deal with it before it is a real emergency. The domestic water supply plumbing and
waste plumping is first distributed under the building in common headers and then
tapped off from that into smaller multiple vertical headers that travel up through many
walls. Replacing the plumbing systems will take lots of investigation and planning. It is
going to take a while to do the due diligence. We have started doing discovery of the
plumbing systems and are working on a plan for upgrade to minimize impact to unit
owners during the upgrade.
8.2. Recent Repairs: We did do some modifications to piping in the boiler room in 2014 in
an attempt to alleviate some of the pain people were going through with not having
hot water. We removed eleven 90 degree turns that were not necessary and only
existed because of poor plumbing practices. Removing the 90 degree turns helped to
reduce head loss. We also replaced a failed check valve that helped with circulation. It
appears the hot water situation is as good as it is going to get with our existing
plumbing system. For now we only plan to make emergency repairs to get us by until
the plumbing upgrade.
9. Electrical
9.1. General: Electrical systems are one of the easier systems to deal with because it can be
worked on in phases. As part of the plumbing upgrades, each unit will need to provide
their own hot water, thus we may have to look at doing some electrical service
upgrades to support point-of-use water heaters or conventional electric water heaters
for each unit.
10. Parking lot
10.1. Joint Ownership: The far North-West corner of the parking lot is owned by our
neighbor, which will make it a little more difficult when we are ready to make
improvements to the lot. Easements would have to be granted if we were to consider
closing in the parking lot.
10.2. Parking Lot Surface: There are various depressions in the parking lot most likely
caused by poor preparation; poor base; lack of proper compaction; or not being graded
properly to begin with. Some of the deeper depressions were repaired in 2015. Before
the entire parking lot can be resurfaced we would need to deal with the root cause of
the depressions first. Resurfacing the lot would be a project further down the road.
Page 9 of 16
10.3. Fence: The East side of the lot has the split rail fence that is in disrepair. There
are a couple of Palm trees in the fence line that would have to be removed for us to
replace this fence with a masonry wall or rod iron fence. Some investigation would
have to be done and we would have to work with the MPC to get this done.
10.4. Controlled Access: If we can enter into an easement with our neighbor that owns
the far North-West corner of the parking lot we could install a security gate to control
access.
11. Boiler Room
11.1. Domestic Hot Water Boiler: The domestic hot water boiler is in relatively good
repair. We did some maintenance in 2015 that should keep in good running condition
for the near future. It appears that it will last until we do the whole building plumbing
upgrade.
11.2. Domestic Hot Water Storage Tank: This is a 200 gallon storage tank used to
support the domestic building hot water. The recommended size for a hot water
storage tank to service a family of four is 50 gallons…thus any layperson can
understand how undersized this storage tank is for a building with 35 units. I do not
recommend we upgrade the storage tank until we know what our plans are for the
plumbing system.
11.3. Building Steam Heat Exchanger: In 2015 we removed the abandoned in place
steam heat exchanger that was used to supply steam heating to the building in the
distant past. It was made of cast iron and weighed several thousand pounds and was
size of a minivan. The steam heat exchanger was removed using volunteer work and
was a herculean effort with many hours of cutting and hauling.
11.4. Building Heat Hot Water Storage Tank: This is an abandoned in place hot water
storage tank that was used to support the old building heat exchanger. It is very large
and takes up a lot of space in the boiler room. It is asbestos wrapped and having it
removed by an asbestos abatement company is cost prohibitive. Ben Colli will be
getting his asbestos abatement license this spring and we will be removing the tank
ourselves.
12. Laundry room
12.1. Remodel: There has been a significant interest to remodel the laundry room. We
are looking into what this is going to take.
12.2. Machine Replacements: The machines that we have are commercial grade
machines. We have had a few repairs made in 2015. We continue to evaluate repairs
vs. replacement costs.
Page 10 of 16
13. Miscellaneous
13.1. Fire Alarm System: We recently discovered that the fire alarm system on the fifth
and sixth floors did not work and appears to have never worked. Our old security
company provided us a proposal to replace our entire fire alarm system. We decided to
get a competitive quote from a local service company that provided us a quote to
upgrade what we had at a much lower cost. So…at the start of this year we changed the
security company we were using to maintain and monitor the system. The new
company came in and brought wiring up to the fifth and six floors and tied in the
existing fire alarm pull boxes and installed new smoke detectors. They also upgraded
the controls and converted us over to a wireless connection back to the service center,
saving us $840.00 each year.
13.2. Front Door Callbox System: The front door call box system was recently
upgraded to allow us to program in phone numbers that are outside of the local 912
area code. The only plan I have on this system is to install an LED light inside the call
box itself and to upgrade the wiring between the phone demarcation and the call
box…and neither one of those tasks are pressing.
13.3. Security: We rarely get keys back when someone moves out of the building. This
essentially makes the building unsecured. There has been some interest in installing a
card access system, which we have included on our task list so that we can come back
at some point to discuss further.
13.4. Camera System: The camera system is capable of up to eight cameras. We
currently have seven cameras connected. We intend to add one more that will be
installed in the lobby. There are instructions on the HOA website on how to access the
camera system from the internet (Note: you have to have Microsoft Internet Explorer
to access the camera system).
13.5. Wooden Ventilation Slats: The wooden ventilation slats on the West side of the
building are falling apart. They serve no purpose so we have decided to close them up
with yellow brick to match the existing yellow brick.
13.6. Freight Entrance Door (West Door): The freight entrance door is rotting (rusting
away) at the bottom and has been sprung from people blocking it open by placing a
brick or stone between the door and jamb. This item is not pressing but is on our task
list.
13.7. Parking Lot Entrance Door (North Door): The door and frame appears to be in
fair condition, but the door could use some paint and the lock could use replacement.
This item is not pressing but is on our task list.
Page 11 of 16
13.8. Bicycle Room Doors: Both of the bicycle room doors need replacement. Maybe
this time we can get it done right. This item is not pressing but is on our task list.
13.9. Roof Deck: There has been a significant interest to build a roof deck. This item is
on our task list for discussion.
14. Building Management
14.1. General: In 2014 our building manager, Stay Savannah, resigned from managing
the building. We have deciding to self-manage while the brickwork repair continues.
While self-performing the building maintenance has saved us a considerable amount of
money, it is our intent to find a replacement building manager once the brickwork
repair is complete.
15. By-Laws
15.1. General: We have rewritten our by-laws in 2015. They can be found on the
Forsyth Parkside Buildium website.
16. Debt
16.1. None…zippo…nada….ziltch. Unlike many other condominiums…we are
completely debt free. We have been paying for maintenance and improvements out of
pocket as we go along. It is my understanding that, at one point in the past, the
condominium was almost insolvent. Thanks to the hard work by past board members,
and a common commitment by all owners, we have climbed out of that situation.
17. Task List
17.1. General: We maintain a general task list, in the form of a spreadsheet, to help us
manage our priorities and to keep us moving forward in maintaining the building. The
overwhelming majority of the tasks on the list are done through owners volunteering
their time. I have attached our task list for your review.
18. Summary
18.1. I hope this letter better informed us all on the many different aspects of
managing this condominium and the many different task list items in the works by the
board members and committee members. Surprises are unavoidable in a building of
this age, but by sharing what we know we can minimize those surprises. Even though
the lion's share of this letter dealt with problem issues, we should also remember the
major tasks that have been already accomplished; a $250K roof replacement; a $40K
passenger elevator shaft replacement; a $50K passenger elevator modernization
project and completing 80% of the brickwork repairs at a cost of $180K…all done while
Page 12 of 16
staying out of debt! Those are huge tasks and you should all be proud of your
stewardship rolls in taking care of this century old building.
19. Attachments
19.1. Forsyth Parkside HOA Task List (pdf document): This is a spreadsheet that we
maintain to help keep us moving forward with building repairs and improvements. We
started this task list in 2014 to provide a central document to jot tasks down as we
become aware of them. The task list is not in any specific order and just because it is on
the list does not necessarily mean we are going to do the task. The task list is just a
place for us to record our thoughts so we don't lose sight of them. Depending on
urgency, funds and available time, we do a task and strike it out as it is accomplished.
You can see that we have accomplished many tasks…all performed with volunteered
time. I would like to thank everyone that has volunteered their time and talents to
work on the many tasks.
Forsyth Parkside HOA Task List Item Task Description
129 send out State of the Building letter
130 send out letter for A/C opening repairs
131 program realtor agencies into the front door call box
132 replace the failed protection timer in the passenger elevator control panel
133 made copies of building drawings (digital copies) and added to Buildium
134 installed telephone line booster on the VoIP line (loop current and battery voltage)
135 installed new passage set in the 6th floor stairway door
136 made nine updates to the front door call box system
137 relamped to 3rd floor hallway
138 installed fire rated ventilation louver in elevator mechanical room
139 got ducting parts at home depot
140 installed new 4-lamp fluorescent light fixture in elevator mechanical room
141 installed new GFCI receptacle in elevator mechanical room
142 installed dedicated exhaust fan receptacle in elevator mechanical room
143 installed dedicated light fixture receptacle in elevator mechanical room
144 repaired and reinstalled lock on the downstairs bathroom door
145 replaced garden hose (50ft) at front of building
146 replaced broken garden hose nozzle at rear of building
147 replaced flood lamp at west end of 6th floor hallway
148 replaced multiple CHL bulbs in 6th floor hallway
149 cleaned the inside of the 5th and 6th floor freight elevator doors
150 installed flower bed around the Magnolia tree at rear of building
151 replace passenger elevator controls
Page 13 of 16
152 follow up with Wright Security on new smoke detectors
153 get fan t-stat from Grainger Industrial Supply
154 strap down conduit better in the elevator mechanical room
155 install exhaust fan and ductwork for the elevator mechanical room
156 rewire exterior light fixture at the rear door
157 coordinate inspection of boiler for insurance
158 hang new paintings in the lobby
159 replace HVAC filter in lobby
160 get roof drainage issue fixed
161 replace cat5 cable for hall call stations in elevator hoistway damaged during on-going work
162 get pass code from Wright Security in case of false alarm (forsyth)
163 troubleshoot and repair Howard street camera
164 troubleshoot and repair lobby camera
165 troubleshoot and repair parking lot camera
166 nogotiate/verify next years natural gas pricing
167 make digital copies of passenger elevator schematics
168 troubleshoot and repair internet issues (found bad attenuator on the cable modem)
169 determine signage needed in elevator car to cover holes from old e-light fixture and order
170 run new conduit on freight elevator for new e-light
171 missing two screws in hall call stations. get new SS screws and install
172 get plastic anchors need to mount new elevator/fire warning signs
173 make punch list for elevator
174 ensure Vertical Lift has completed all the punch list items
175 run conduit in passenger elevator hoistway for new fire alarm system and future network cabling
176 replace furniture and rugs in lobby and install artwork (lobby committee)
177 review the HOA application form and update
178 replace emergency light fixture in the freight elevator
179 order new light diffusers for the passenger elevator (current one broken)
180 repair loose trim in the north hallway
181 repair wall at back (north) door
182 renew no-ip account for 2015
183 scrape peeling paint at front entry and repaint
184 make repairs to 4th floor hallway wall (damage from unit 4G)
185 write trash rules (break down boxes, no Styrofoam in recycle, do not set recycle outside of can)
186 clean the dryer vents in the laundry room and replace filter screens
187 remove piping systems that have been abandon-in-place in the boiler room
188 demo old boiler heat exchanger
189 rewrite the bylaws and rules
190 build a routine maintenance plan for the building
191 replace light fixture at the back door with track lighting
192 finish wiring can lights above mail boxes
Page 14 of 16
193 finish sofit above mail boxes
194 build a a desk for the HOA office
195 move new computer to the HOA office
196 Add Chuck to the front door directory
197 Add Alice Ball to the fron door directory
198 Troubleshoot the call system for the front door
199 Order replacement call system for the front door call system
200 Program the replacement front door call system
201 Replace the call box system for the front door that was damaged by electrical storm
202 Troubleshoot the East camera
203 Ask Been to get Alice Ball's window repaired
204 Make proxie ballots for annual meeting
205 Make ballots for annual meeting
206 Build budget with Tom for annual meeting
207 Fix front door not latching again
208 Troubleshoot West camera
209 Repair West camera
210 Inspect work in unit C1 (bike shop)
211 remove abandoned in place emergency light in passenger elevator and cover w/warning sign
212 install warning signs for elevator on each floor
213 clean the inside of the remaining freight elevator doors
214 paint the inside of the freight elevator doors and stencil with the floor number
215 make copies of all HOA keys that we do not have duplicates for
216 clean / strip wax buildup in elevator
217 make repairs to stairway walls
218 paint stairway walls
219 paint stairway trim
220 paint stairway floors
221 look into getting LED fixtures/bulbs in the lobby (lobby committee)
222 replace lighting in the lobby (lobby committee)
223 replace ventilation louvers on west side of building with brick
224 replace bicycle room doors
225 replace utility room door
226 review control panel for freight elevator and AutoCAD schematic and panel layout
227 install under voltage relay on the freight elevator to protect motor against single-phase loss
228 write a briefing documents for new owners/tenants
229 build a database of all units/owners/tenants
230 schedule preventative roof maintenance
231 install light fixture in the front door call box
232 troubleshoot receptacles in the lobby
233 replace receptacles and covers in the lobby
Page 15 of 16
234 relocate the electrical outlet located in storage unit 103 to next to the phone demarcation
235 update building elevation drawings to reflect correct window sizes and placement
236 make a new cardboard backing for the front call box directory
237 scrape and paint laundry room
238 diagram the phone systems, internet, DVR and fire alarm monitoring system (use Visio)
239 look into putting the front entry lights on the same timer used for the lobby lights
240 come up with a west door latch system
241 replace the outside freight entrance door
242 relocate camera on west side of building toward the south end of the west side
243 remount camera in lobby
244 add camera to lobby (channel no.8)
245 trace hot and cold water piping that goes into the slab
246 make plan to upgrade plumbing in phases
247 the front garden watering system needs to be repaired
248 replace all light bulbs with LED bulbs
249 replace mailboxes (relocate to lobby)
250 replace flooring in hallways
251 replace lighting in hallways
252 replace drop ceilings in hallways
253 repaint hallways
254 replace front door
255 replace parking lot door
256 remove split rail fence and have proper wall/fence built
257 resurface parking lot
258 secure parking lot (gates)
259 upgrade building plumbing
260 rewire electrical in common spaces
261 investigate card access system
262 look into adding a roof deck
263 write scope of work for building manager (include a fee schedule)
264 hire a building manager
265 add on to or replace hallway baseboard trim (contract out)
266 add crown molding to hallways to hide edge of drop ceiling (contract out)
267 trim around doors in the hallways (contract out)
268 relocate vestibule pull station on 2nd floor
269 relocate vestibule pull station on 3rd floor
270 relocate vestibule pull station on 4th floor
271 relocate vestibule pull station on 5th floor
272 flush mount hallway pull stations/ horns/e-lights and receipts on 2nd floor
273 flush mount hallway pull stations/ horns/e-lights and receipts on 3rd floor
274 flush mount hallway pull stations/ horns/e-lights and receipts on 4th floor
Page 16 of 16
275 flush mount hallway pull stations/ horns/e-lights and receipts on 5th floor
276 flush mount hallway pull stations/ horns/e-lights and receipts on 6th floor
277 install camera software on the HOA computer
278 test new camera and POE switch with the HOA computer
279 install new camera in the lobby
280 install new a/c grates in front of building
281 Get all the other Board members setup to receive emails from the [email protected]
282 Build storage in the boiler room
283 Power wash the West side of the building and sidewalks
284 Repaint the stripes in the parking lot
285 Repaint the unit numbers in the lot
286 Repaint the yellow on the curbs
287 renew no-ip account for 2016