report on the commissioning activities

16
ATLAS Plenary, Feb. 1 8th, 05 Commissioning 1 Report on the commissioning activities G. Mornacchi, P. Perrodo and Sub-Systems Collaborators

Upload: carver

Post on 14-Jan-2016

53 views

Category:

Documents


0 download

DESCRIPTION

Report on the commissioning activities. G. Mornacchi, P. Perrodo and Sub-Systems Collaborators. ATLAS components breakdown. Inner Detector. TILES. DCS. MUONS. LARG. View on the ATLAS work packages. MUONS. LARG. Cooling/ Ventilation WPs. DAQ. TILES. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 1

Report on the commissioning activities

G. Mornacchi, P. Perrodo and Sub-Systems Collaborators

Page 2: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 2

ATLAS components breakdown

Inner Detector

LARG

TILES

MUONS

DCS

Page 3: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 3

View on the ATLAS work packages

DAQTILES

LARG

MUONS

Cooling/Ventilation

WPs

Page 4: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 4

Concrete example: Tiles calorimeterWP1:

Detectorand

Modules

FE electronicsat IP

Cooling,Sniffers

WP2:Cables

WP4:FE

Electronicson the truck

WP7: BEelectronics

TTCDAQDB

FE-BEintegration

WP6:Cosmics L1

receivers

Offline

BE LVsystem

WP9: HVsystem

WP8: Cesiumsystem

WP9: Lasersystem

WP11: TILES DCS

Racks,DCS Interlocks

Racks

L1receivers

Lasercalibration

WP5:FE LVPSinsertion WP3:

Rack equipment

Racks,DCS

WP12: minBiais events Updated on 27/01/05

Active WPs

Page 5: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 5

Process Overview

WP SIgn off

WP Execution

WP ElaborationDetail scheduleand resources

Well ahead of execution

WP detailedSystem document

Start end timesTests & expected results

Work PackageBreak down

System AnalysisBreak down

in components

Documents stored in EDMSUnder ATC/commissioning/phase I/

RequirementsWP Schedule -> ATLAS scheduleWP excel sheet, PPSPS document (safety)Agree on WP outcome -> input to sign off

Document resultsPreserve operational information

We are ~ here

Page 6: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 6

Phase 1WP: next 3 monthsSub-system WP Description Start date

Inner Detector Cables PP3->US(A)

PP2 in sector 13

~ installation WP

Pipework on cryostat

~ installation WP

Lar calorimeter F/E on truck Install and commission F/E electronics with detector in “truck position” Active

Racks USA15 lAr rack infrastructure in USA15

Tile calorimeter F/E on the truck Install and commission F/E electronics with detector in “truck position”. Temporary cables, mobydick, MobyDAQ

March

Racks USA15 Install and commission the infrastructure of the USA15 Tile racks March

Cesium source Install and commission the Tile Cs source. Piping will be a subject for an intermediate sign off

Active

Muons system Sector 12-14 Installation of MDT and RPC chambers. No real commissioning yet. Active

Sector 13 Installation and commissioning of sector 13 muon chambers. Validates the full commissioning cycle.

May

Alignment system Install and commission alignment system. Several sub-steps, intermediate sign offs. WP document almost ready for work package analysis.

March

Page 7: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 7

Phase 1WP: next 3 months

Sub-system WP Description Start in

DCS Local DCS USA15 L1 Install and commission local DCS station in USA15. Includes first test with a sub-set of racks in the Tiles area.

March

DSS USA15 Level-1 Commission DSS system in USA15 level-1, stand alone mode.

March

DAQ DAQ infrastructure Install and commission hardware (e.g. servers) and software (e.g. online s/w suite) infrastructure.

March

ROD Crate DAQ Commission RCD software. Multi-step process including one commissioning step per ROD type.

Planning

Magnets MCS/MSS Install and commission Magnet Safety and control system. Multiple steps; first is related to equipment in USA15.

March

All Cables UX15---US(A)15 Test and commission cables upon installation. Involves all sub-systems.

With cables

Page 8: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 8

Sign Off

A number of infrastructure sub-systems have already been commissioned or are in the process of being so: C&V Cryogenics plant on surface Cryogenics in USA15, Magnet equipment Cranes

For these we envisage a sign off procedure only To collect the performance parameters To understand open issues and problems To integrate them in a uniform documentation scheme, easy to

trace back

Page 9: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 9

Sign Off A formal procedure to make sure that:

Installation (if any) has been properly done: e.g. w.r.t. TC procedures (Install. DB, etc…) Proper grounding & safety issues have been taken into account Documentation is available:

Technical and maintenance documentation for H/W and S/W User guides, operational procedures, including the test procedures

Planning for maintenance and responsibilities are defined Performance is according to specifications

Or we understand where, how, possibly why, there is a disagreement We know what are the open problems and issues

And what actions can be defined It is clear who is authorized to use the system once commissioned:

Sensitive items: ID cooling, LARG high voltage, TILES Cesium system,…

The sign-off procedure may occur in several steps: For a complex WP one may envisage intermediate milestones, hence sign offs Associated to a repetitive aspect:

E.g. ROD crates, FE electronics, muon chambers.

Page 10: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 10

Work packages tree:

In the Work packages document: WP outcome:(Agreed before WP activation)

Execution of the WPFollow-up during theCommissioning meetings

Final sign-off procedure

Installation report Inventory, grounding, safety, …

Performance specifications Expected functionality Quantitative performance figures

Test report Checklist of tests and results

Operational documents Indicates who is responsible, who to

contact for problems Maintenance procedures/plan Pointers to relevant documentation

Operational procedures Test procedures Component manuals

List of open issues/problemsEDMS

Archive documents

Sign Off

Page 11: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 11

Weekly meetings at Point 1

Minutes can be found at: Experimental Area Management (EAM):

http://atlas.web.cern.ch/Atlas/TCOORD/Activities/Logistics/G1/EAM_minutes_index.html

Counting Rooms Management (CRM): ATC-C-IM-0001 Inner Detector: ATC-GE-MM-0132 Calorimeters: ATC-GE-MM-0125

Muons: ATC-GE-MM-0126

Make use of sub-system installation meetings to follow phase 1 sub-system specific commissioning Phase 1 has too many

WPs to concentrate their follow up in a single weekly meeting

Avoid proliferation of meetings

Assume that emphasis will shift from installation to commissioning

Weekly meeting The same morning as the

follow-up of the management meetings for UX15 (EAM) & counting rooms (CRM)

Use for topical discussion, sign off, follow sub-systems w/o an installation meeting (e.g. DSS, DCS, DAQ, trigger)

Page 12: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 12

Monthly meetings

Start discussion of phase 2 commissioning - > monthly meeting

Overall status and issues to be escalated: TMB, EB

Monthly meetingsMonday Tuesday Wednesday Thursday Friday

8:009:00 9h30: TMB 9h30: EB

10:0011:0012:0013:0014:00 Commission. TMB/Comm.

15:0016:0017:00

Page 13: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 13

Potential difficulties Elaborating the commissioning work to be done needs

time and some distance with the daily work on site. Collaborators involved in commissioning in the sub-

systems are too often overloaded by many other things (e.g. production/installation tasks).

More effort needed to prepare the “functional work packages” following installation.

The new installation planning is very tight (no float anymore). This can jeopardize the tests and the commissioning. Determine priorities in the tests.

Test programs, software and analysis tools ready in advance is an important asset.

Centralized management of the computers and network at point 1 is mandatory to avoid confusion.

Need of a centralized support for the counting rooms.

Page 14: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 14

Phase II commissioning Define a reasonable “end of Phase I” for the sub-systems. We won’t go sequentially Phase 1-> Phase 2.

System integration: Partitioning the ATLAS detector: Trigger (CTP,LTP), DAQ (RCD), DCS, DB

Integration Sub-detectors + DAQ + DB + Offline data Integration Sub-detectors + central DCS + DBs Operations L1calo + LARG + TILES (Workshop Feb.. 1st 2005, next in April)

Functional tests: Noise tests and Calibration Pulse tests on large scales involving sub-detectors

and L1. Involves ROD crate DAQ. Partial cosmic runs : Tiles + Muon Barrel sector 13 (+ alignment) + LARG (later).

Involves ROD crate DAQ. Toroid tests (after completion) + Sub-systems Infrastructure (cooling, ventilation) + sub-systems (detectors, electronics, TDAQ,

DCS)

Page 15: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 15

Phase II commissioning More local combinations:

LARG + cryogenics Magnets + cryogenics ID + gas system Muons + gas system

Work organization: Many ideas are around and we already feel the pressure to take cosmics asap.

Need a clear formulation (WP) to decide the priorities and build a planning. Working groups being organized :

“L1”, “DAQ” or “DCS” oriented Detector performances and physics coordinators: calibration data, cosmics Elaborate WPs. Monthly meetings to discuss and plan them. Role of commissioning coordination

Need a place to operate the detector being commissioned (proto Control Room) .

can be considered not as Phase II, butas A natural extension of Phase I

Page 16: Report on the commissioning activities

ATLAS Plenary, Feb. 18th, 05

Commissioning 16

Conclusion Continue to initiate the mechanics of WPs with the various

ATLAS systems. Milestone of June, before the barrel calorimeters move to IP.

The success of a well commissioned ATLAS system is the result of the sum of many detailed tasks.They have to be well thought and prepared to be meaningful for the future.This required more collaborators involved in these aspects. The acknowledgment of this work is of importance.

Centralized management of the computers and network at point 1 will become soon mandatory to avoid confusion.

Need of a centralized support for the counting rooms. Start thinking seriously soon to a proto control room.