report on roadway development technology audit...

77
ACARP Project C17010 Roadway Development Improvement Project Report on Roadway Development Technology Audit June 2010 Gary A Gibson GaryGibson&ASSOCIATES

Upload: hadan

Post on 09-Sep-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

  

  

ACARP Project C17010 Roadway Development Improvement Project       

 

 

 

Report on Roadway Development  

Technology Audit  June 2010 

 Gary A Gibson 

GaryGibson&ASSOCIATES 

Page 2: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

  

DISCLAIMER  No person, corporation or other organisation (“person”) should rely on the contents of this report and  each  should  obtain  independent  advice  from  a  qualified  person  with  respect  to  the information contained in this report.  Australian Coal Research Limited, its directors, servants and agents  (collectively  “ACR”)  is  not  responsible  for  the  consequences  of  any  action  taken  by  any person in reliance upon the information set out in this report, for the accuracy or veracity of any information  contained  in  this  report  or  for  any  error  or  omission  in  this  report.    ACR  expressly disclaims  any  and  all  liability  and  responsibility  to  any  person  in  respect  of  anything  done  or omitted  to  be  done  in  respect  of  the  information  set  out  in  this  report,  any  inaccuracy  in  this report or the consequences of any action by any person in reliance, whether wholly or partly, upon the whole or any part of the contents of this report.  

 

 

Page 3: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

  

 

Table of Contents 

 

  EXECUTIVE SUMMARY  1 

  INTRODUCTION  4 

  FINDINGS  5 

    Utilisation, Effectiveness, and Benefit of Further Research of Technology Elements  5 

    Respondents Comments  6 

    Introduction of New Technology and Processes  7 

  CONCLUSIONS  9 

  RECOMMENDATIONS  11 

  ACKNOWLEDGEMENTS  12 

  TABLES  13 

  1  Process Elements and Technology as Ranked by Utilisation  14 

  2  Process Elements and Technology as Ranked by Effectiveness  15

  3  Process Elements and Technology as Ranked by Likely Benefit of Further Research  16 

  4  Process Elements and Technology Responses – OEMs and Suppliers    17 

  5  Observations Relating to the Utilisation of and Requirement for Further Research of Process Elements and Technologies – as ranked by research priority 

24 

  6  Key Factors Contributing to the Successful Introduction of New Technologies and Processes – Mine Responses 

41 

  7  Factors Contributing to the Successful Introduction of New Technologies and Processes – Mining Contractors 

44 

  8  Key Factors Contributing to the Successful Introduction of New Technologies and Processes – OEMs and Suppliers 

45 

  9  Barriers or Factors Impacting the Introduction of New Technologies and Processes – Mines  47 

  10  Barriers or Factors Impacting the Introduction of New Technologies and Processes – Mining Contractors 

48 

  11  Barriers or Factors Impacting the Introduction of New Technologies and Processes – OEMs and Suppliers 

49 

  12  Major Barriers to the Successful Research, Development and Introduction of New Technologies – Mines 

50 

  13  Major Barriers to the Successful Research, Development and Introduction of New Technologies – Mining Contractors 

52 

  14  Major Barriers to the Successful Research, Development and Introduction of New Technologies – OEMs and Suppliers 

53 

  APPENDICES  55 

  A  Roadway Development Technology Audit ‐ Mines  56 

  B  Roadway Development Technology Audit – OEMS and Suppliers  64 

Faculty of Engineering � 23/6/10 1:35 PMComment: Move to a line above the Table 

Page 4: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

  

  C  Audit Respondents  71 

Page 5: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 1  

Report on Roadway Development Technology Audit – June 2010 

EXECUTIVE SUMMARY 

A  self  reporting  Technology Audit was  completed  across  underground mines, OEMs and  suppliers, and mining contractors with a view to establishing the level of utilisation, effectiveness and need for further research associated with current roadway development related equipment and practices.  

Respondents  were  also  invited  to  identify  key  factors  contributing  towards  the  successful introduction and development of new technologies and processes, and those that were considered to be barriers to their successful introduction and development. 

In overall terms, 63 individual technology elements covering the roadway development process were evaluated,  including continuous miners,  strata support, coal haulage,  face ventilation,  face services (eg; power, water in/out, compressed air, communications), materials handling, panel advance, and personnel transport. Respondents were also invited to comment against each element, particularly if technology elements had previously been trialled and/or installed but were currently not in use.  

Responses  were  received  from  19  longwall  mines  and  7  bord  and  pillar  mines,  16  OEMs  and suppliers, and 6 mining contractors.  

Mines reported that 56% of the 63 technology elements were considered to be somewhat effective or extremely effective, with some 69% of those considered as somewhat or extremely effective also being used regularly or exclusively. Mines also reported that 73% of the technology elements were either  likely  to  or  extremely  likely  to  benefit  from  further  research.  Results  indicate  that  Mines tended  to  adopt  a  simple,  low  technology  approach  to  roadway development, with  “new”,  higher technology elements (such as continuous haulage, auto‐cut facility for sumping and cutting, remote steering systems, machine auto‐reporting systems, self drilling bolts, push button controls on bolting rigs)  not  being  widely  utilised.  Interestingly,  a  number  of  these  low  ranking  “new”  technology elements ranked high in regards to the Likely Benefit of Further. 

Mines and Mining Contractors offered a wide range of comments  in relation to earlier  trials of  the various technology elements, or potential benefits that could arise from further research. A number of observations were developed in respect to these comments, including: 

The operational benefits offered by self drilling bolts are now being recognised, the challenge is  to  develop  a  range  of  competitive  products,  improve  the  understanding  of  potential cost/benefit  relationships,  and  ensure  potential  operational  gains  from  adoption  of  self drilling bolts are not lost in poor process management. 

The  potential  benefits  of  remote  (CM)  steering  systems  are  also  being  recognised,  with further development and application of remote sensing technologies, video monitoring, and self steering systems considered as necessary to underpin the development of an integrated, high capacity roadway development system.    

Push  button  controls  on  bolting  rigs  now  offer  improved  consistency  and  quality  of installation, the challenge is to take that control off the continuous miner and allow bolting rigs to be remotely operated/automated. 

Bolting  is  recognised  as  perhaps  the  largest  limiting  factor  on  improving  roadway development, with concurrent operation of roof and rib bolters seen as critical in respect to improving overall support cycles. Access to and escape from bolting platforms, coupled with the  ergonomics  associated  with  restricted  space  on  the  bolting  platform  appears  to  be limiting the adoption of concurrent bolting practices. The development of automated bolting and meshing  systems  coupled with  development  of  remotely  operated  automated  control system  is  likely  to address  such  issues, as well as providing a more positive solution  to  the challenges posed by compliance with  MDG35.  

Page 6: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 2  

On‐board ducted ventilation systems or possibly the interface between the on‐board systems and roof mounted ducting system appears to be a significant constraint on overall ventilation effectiveness.  The  under‐platform  ducting  system  developed  for  the  Tahmoor  MB610 warrants  close  evaluation,  while  adoption  of  continuous  haulage  systems  (or  monorails) might  eliminate  much  of  the  manual  handling  concerns  and  reduce  potential  space constraints and/or conflicts.  

The  benefits  afforded  by  adoption  of  machine  auto‐reporting  systems  are  again  being recognised, however their broader adoption appears to be constrained by less than state of the art underground communication systems. 

Machine diagnostic display units were seen as being invaluable, although there accuracy was questioned. Development of multiple access levels for operators and trades was identified as an  opportunity,  as  was  the  development  of  a  “black‐box”  style  data  logging  system  to improve diagnostics, particularly in relation to unplanned movements of machinery. 

Maintaining  mine‐wide  explosion  suppression  compliance  was  recognised  as  a  significant challenge in 7 day operations, with the eventual approval of wet dusting systems being seen as a positive outcome. 

In  relation  to  the  research,  development  and  successful  introduction  of  new  technologies  and processes Mines, OEMs  and  Suppliers  reported  a  number  of  consistent  themes,  as  summarised  in Figure 1. As expected perhaps, Mines were critical of the level of support and commitment provided by OEMs in developing and introducing new technologies, whilst OEMs and Suppliers were critical of the lack of buy‐in by Mines to new technologies.  

 Key Factors Identified by Mines  Key Factors Identified by  Mining 

Contractors, OEMs and Suppliers Key Factors in the Successful Introduction of New Technologies and Processes 

Product or project champions Robust change management processes Involvement of personnel Company support and involvement Good planning Demonstrated productivity and safety benefits Reduced manual handling Introductory training 

Champion to push the innovation Personnel taking ownership of system Equipment designed and built fit for purpose Improved operational flexibility and equipment maintenance Test and validation processes prior to going to market Improved performance Reduced manual handling injuries 

Barriers to Successful  Introduction of New Technologies and Processes 

Cost Certification and regulatory issues Lack of OEM support and commitment Lack of operator buy‐in Lack of corporate commitment Lack of management support 

Certification and regulatory issues Lack of operator buy‐in Resistance to change 

Barriers to Successful  Research and Development  of New Technologies 

Funding and costs OEM commitment Research being too “pure” Lack of corporate support for R&D Over‐commitment of R&D funding to longwall operations  Lack of ability or inability to apply technological solutions to roadway development challenges 

Funding and development costs Certification and regulatory issues Low cost sourcing by mines End user acceptance Lack of project champions  

Figure 1: Summary of Key Success Factors and Barriers to New Technology and Processes 

Equipment  certification  and  regulatory  issues  were  also  identified  as  a  major  barrier  to  the introduction of  new  technology  and processes  and  is  expected  to  be  a major  consideration  in  the 

Page 7: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 3  

development and adoption of remotely operated or automated roadway development equipment as is contemplated by this report. 

Unfortunately,  the  Audit  does  not  identify  the  change  management  strategies  adopted  by  mines when introducing new technologies and processes, nor does it reveal a sense of the level of success or  otherwise  achieved  in  regards  to  the  introduction  of  new  technologies  and  processes,  ie;  how often we succeed or fail, or how well we realise the full capability afforded by the new technology or process.  The  wide  disparity  in  roadway  development  performance  levels  between  best  practice mines  and  the  bulk  of  the  industry  suggests  that much  of  the  industry  is  failing  to  realise  the  full capability  afforded  by  available  or  newly  developed  technologies,  whilst  a  review  of  roadway development related technology developments over the past 20‐30 years might suggest that  it  is a long and difficult road from concept development to operational and commercial success. 

Based on the Audit Findings and Conclusions it is recommended that ACARP’s Roadway Development Task Group maintains the general thrust of its CM2010 R&D strategy and where appropriate review R&D priorities in respect to the following key elements: 

1. The  development  of  technologies  that  enable  bolting  (and  meshing)  to  be  undertaken remotely, including:   self drilling bolts (to minimise the number of process steps and components)   bolt, washer, and mesh storage/handling systems and manipulating devices   remotely controlled/automated bolting rigs and manipulators, and  associated sensing and monitoring systems. 

2.  The  development  of  technologies  required  to  support  a  self  steering  remotely  controlled continuous miner including:  remote sensing  seam profiling  video monitoring  machine navigation and steering  communication  protocols  that  facilitate  integration  of  the  differing  technologies  and 

hardware (eg; miners, bolters, manipulators, haulage systems, etc), and  machine supervisory/auto‐reporting systems (including the development of “black‐box” 

data logging systems for machine diagnostics and failure analysis). 

3. Addressing  issues  associated with  on‐board  ventilation  systems,  interconnections  between on‐board  and  auxiliary  ventilation  ducting,  roadway  space  constraints,  and  the  overall effectiveness of face ventilation systems. 

4. The  development  of  shuttle  car  guidance  systems  (potentially  as  an  off‐shoot  to  the development  of  continuous  miner  navigation  systems)  as  a  means  of  improving  the consistency of operations and facilitating the development of a fully remote mining system.   

5. Addressing issues associated with the management of face services, be it via the continuous haulage system or a monorail mounted face services system.  In the latter instance methods need  to  be  developed  to  enable  the  monorail  to  be  extended  remotely  if  a  remotely operated roadway development system is to be employed effectively.  

6. Development  of  strategies  to  address  equipment  certification  and  regulatory  issues, including  consideration of how  the Earth Moving Equipment  Safety Round Table  (EMESRT) design guidelines may be applied in an underground mining context. 

It was also recommended that mines continue to undertake ongoing operational research as a means to optimising face cycle times (ie; matching of cutting, haulage and support cycles), and to consider engagement  of  change management  expertise  as  part  of  any  strategy  to  introduce  new  roadway development technologies and processes. 

Page 8: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 4  

 

INTRODUCTION 

Representatives  from  underground  coal mines,  OEMs  and  suppliers,  and mining  contractors  were invited to complete a self reporting Technology Audit which sought to identify the level of utilisation, effectiveness  and need  for  further  research  associated with  current  roadway development  related equipment and practices. Respondents were also invited to identify key factors contributing towards the successful  introduction and development of new technologies and processes, and those factors that were considered to be barriers to their successful introduction and development. 

An  audit  instrument  was  developed  for  mines  (refer  Appendix  A)  and  circulated  to  mines  by members of ACARP’s Roadway Development Task Group. Minor changes were subsequently made to that  instrument  to  reflect  the  perspective  of  OEMs  and  Suppliers  (refer  Appendix  B).  Mining Contractors were  subsequently  supplied with both audit  instruments  and  invited  to  complete  that instrument which best suited their perspective. 

In  overall  terms,  there  were  some  63  individual  elements  covering  the  roadway  development process, including continuous miners, strata support, coal haulage, face ventilation, face services (eg; power,  water  in/out,  compressed  air,  communications),  materials  handling,  panel  advance,  and personnel transport. Respondents were asked to identify in respect to each element whether: 

individual equipment, technologies or systems were installed and/or available;  their frequency of use;  their relative effectiveness; and,  their likelihood of benefiting from further research. 

A four (4) point scale was provided to rank responses, with a ranking of 1 representing an extremely low  level  of  utilisation,  effectiveness,  or  likelihood  of  benefiting  from  further  research,  while  a ranking  of  4  represented  an  extremely  high  level  of  utilisation,  effectiveness,  or  likelihood  of benefiting from further research.  

Respondents were also invited to comment against each element, particularly if technology elements had previously been trialled and/or installed but were currently not in use. Three further tables were included to enable respondents to identify key factors contributing to the successful introduction and development  of  new  technologies  and  processes,  barriers  to  the  successful  introduction  and development  of  new  technologies  and  processes,  and  major  barriers  to  the  successful  research, development and introduction of new technologies. 

The audit instrument utilised for OEMs and Suppliers asked respondents to identify:  

whether the OEM/Supplier supplied the individual equipment, technologies or systems;  to what extent where their products adopted;  their relative effectiveness; and,  their likelihood of benefiting from further research. 

OEMS  and  Suppliers were  similarly  invited  to  comment  regarding  the  application,  trial  and  use  of their equipment.  

Responses  were  received  from  19  longwall  mines  and  7  bord  and  pillar  mines,  16  OEMs  and suppliers, and 6 mining contractors.  In only two instances were multiple responses received from a mine, OEM and  supplier,  or mining  contractor,  and  in  both  instances were  from a  bord  and  pillar mine. A list of responding Mines, Mining Contractors, OEMS and Suppliers is provided in Appendix C. 

All  responses  were  processed  utilising  a  JMP  statistical  package,  with  an  average  score  being determined  for each element based upon responses  from  individual groups or classes  (ie;  longwall mines,  bord  and  pillar  mines,  OEMs  and  suppliers,  mining  contractors).  Individual  comments  and observations  were  separately  tabulated  by  question  or  element,  again  by  individual  groups  or classes. 

Page 9: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 5  

 

FINDINGS 

Utilisation, Effectiveness, and Benefit of Further Research of Technology Elements 

Key findings in relation to the Utilisation, Effectiveness and Likely Benefit of Further Research of the various technology elements as reported by Mines include: 

Mines  reported  that  56%  of  the  63  technology  elements  were  considered  to  be  used regularly  or  almost  exclusively  (ie;  an  average  score  of  3.00  or  more  across  all  mine respondents).  

Table 1  ranks Utilisation of  the Technology Elements, with  the 20 highest  ranked elements highlighted  in  green  and  the  20  lowest  ranked  elements  highlighted  in  pink.  The  levels  of utilisation  reported  are  perhaps  consistent  with  the  expectations  of  experienced  roadway development operators, however a closer review of the 20 lowest elements suggests that the industry  adopts  a  simple,  low  technology  approach  to  roadway development,  ie;  elements not  being  widely  utilised  include  continuous  haulage,  auto‐cut  facility  for  sumping  and cutting,  remote  steering  systems  (on  continuous miners), machine  auto‐reporting  systems, self  drilling  bolts,  push  button  controls  on  bolting  rigs,  powered  cable  and  hose winders/storage,  monorail  mounted  ducting,  etc.  Interestingly,  a  number  of  these  low ranking  “new”  technology elements  ranked high  in  regards  to  the  Likely Benefit of  Further Research as noted below. 

Mines  similarly  reported  that  56%  of  the  63  technology  elements  were  considered  to  be somewhat effective or  extremely effective  (ie;  an  average  score of  3.00 or more across  all mine respondents) – with some 69% of those considered as somewhat or extremely effective also being used regularly or exclusively. 

Table 2 ranks Effectiveness of the Technology Elements, with the 20 highest ranked elements highlighted in green and the 20 lowest ranked elements highlighted in pink. Again, the levels of effectiveness reported are probably consistent with expectations however, a closer review of the 20 lowest ranked elements identifies a number of manual operations or human factors as  being  somewhat  less  than  effective,  including; manual  loading  of  bolting  consumables, manual loading of mesh sheets onto the continuous miner, overall ergonomic configuration for CM operation, manual tendon/cable tensioning, maintenance accessibility and servicing, face services manually handled.  Interestingly again, except  for  the ergonomic configuration for CM operations these manual operations or human factors did not rank high in regards to the Likely Benefit of Further Research.  

From a statistical perspective there was a moderately strong correlation between low levels of utilisation and  low  levels of effectiveness  (coefficient of  correlation 0.7),  suggesting  that less  effective  elements  were  less  likely  to  be  utilised.  This  was  partially  supported  by  the relationship between higher levels of utilisation and higher levels of effectiveness (coefficient of  correlation  0.4). What  is  somewhat  surprising  is  that  some  “new”  technology  elements such  as  remote  steering  systems  on  continuous  miners  and  continuous  haulage  systems, which have low levels of uptake (utilisation) across the industry, were reported as having low levels of effectiveness.  

Mines  reported  that 73% of  the 63  technology elements were either  likely  to or extremely likely to benefit from further research (ie; and average score of 3.00 or more across all mine respondents). 

Table 3 ranks Likely Benefit from Further Research of the Technology Elements, with the 20 highest ranked elements highlighted in green and the 20 lowest ranked elements highlighted in  pink.  Those  elements  reported  as  being  more  likely  to  benefit  from  further  research include a number of “new” technology elements such as; self drilling bolts, remote steering 

Page 10: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 6  

systems  (on  continuous  miners),  continuous  haulage  mounted  services,  wet  dusting,  and machine diagnostic systems.  

Those elements considered less likely to benefit from further research largely include proven technology elements (eg; bolt washer dispensers, east/west chain and rotating arm/spinner loading configurations, breaker feeders, area lighting, cable and hose boats), with few “new” technology elements. 

When viewing the combined results of Tables 1, 2, and 3, (ie; Utilisation, Effectiveness, and Likely  Benefit  of  Further  Research)  it  was  evident  that  technology  elements  that  were considered  to  be  more  effective  tended  not  to  be  ranked  as  benefitting  from  further research,  although  conversely,  those  considered  to  be  less  effective  were  not  necessarily considered  as  likely  to  benefit  from  further  research.  There  was  a  stronger  correlation however between lower levels of utilisation and likely benefit of further research than there was between the level of effectiveness and likely benefit of further research. 

It  was  not  possible  to  similarly  rank  responses  from  OEMs  and  Suppliers  as  in  most  cases respondents only serviced a  limited range of process elements and technologies,  ie; the number of OEM  and  Supplier  responses  was  statistically  low.  Table  4  details  OEM  and  Supplier  rankings  by process  element  and  technology  (and  also  includes  comments  made  by  OEMs  and  Suppliers  in relation to the application, trial and use of their equipment or services).  

Respondents Comments 

Mine  and Mining  Contractor  respondents  offered  a wide  range  of  comments  in  relation  to  earlier trials of the various technology elements, or potential benefits that could arise from further research and  development.  Table  5  tabulates  these  responses  based  upon  the  Likely  Benefit  of  Further Research ranking, and includes comments from longwall mines, bord and pillar mines, and OEMs and Suppliers. A number of observations are offered in respect to these comments, including: 

The operational benefits offered by adoption of self drilling bolts are now being recognised, the challenge  is  to develop a  range of competitive products,  improve the understanding of potential cost/benefit relationships, and ensure potential operational gains from adoption of self drilling bolts are not lost in poor process management. 

The potential  benefits  of  remote  (CM)  steering  systems are being  recognised, with  further development  and  application  of  remote  sensing  technologies,  video  monitoring,  and  self steering  systems  being  necessary  to  underpin  the  development  of  an  integrated,  high capacity roadway development system.    

While  push  button  controls  on  bolting  rigs  now  offer  improved  consistency  and  quality  of installation, the challenge is to take that control off the continuous miner and allow bolting rigs to be remotely operated/automated. 

Bolting  is  recognised  as  perhaps  the  largest  limiting  factor  on  improving  roadway development, with concurrent operation of roof and rib bolters seen as critical in respect to improving overall support cycles. Access to and escape from bolting platforms, coupled with the  ergonomics  associated  with  restricted  space  on  the  bolting  platform  appears  to  be limiting the adoption of concurrent bolting practices. The development of automated bolting and meshing  systems  coupled with  development  of  remotely  operated  automated  control system is likely to address such issues.  

While improved ergonomics on‐board continuous miners was noted, there was considered to be major opportunities to  further  improve ergonomics, particularly associated with bolting, handling of mesh, access platforms, and cables and hosing. 

While the objectives of MDG35 appear to be well understood and accepted, it appears that there is still substantive work to be done to develop and implement appropriate technologies 

Page 11: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 7  

that  provide  productive  solutions,  including  removal  of  operators  from  the  contact  zone through automation of bolting.  

On‐board ducted ventilation systems or possibly the interface between the on‐board systems and  roof  mounted  ducting  system  appears  to  be  a  significant  issue  in  terms  of  both  a constraint on overall ventilation effectiveness, the interface between the systems and access under or around ducting, and the adoption of larger capacity shuttle cars to balance cutting and support cycles. The under‐platform ducting system developed for  the Tahmoor MB610 warrants  close  evaluation,  while  adoption  of  continuous  haulage  systems  (or  monorails) might  eliminate  much  of  the  manual  handling  concerns  and  reduce  potential  space constraints and/or conflicts.  

While one longwall mine considered it all too hard, a bord and pillar mine which operated a continuous haulage  system  reported  significant advantages  from  installing  face  services on the continuous haulage. 

Machine diagnostic display units were seen as being invaluable, although there accuracy was questioned.  Development  of  multiple  access  levels  for  operators  and  trades  coupled  with improved training were seen as opportunities to improve existing systems. The development of  a  “black‐box”  style  data  logging  system  was  also  seen  as  an  opportunity  to  improve diagnostics, particularly in relation to unplanned movements of machinery. 

The  benefits  afforded  by  adoption  of  machine  auto‐reporting  systems  are  again  being recognised, however their broader adoption appears to be constrained by less than state of the art underground communication systems. 

Maintaining  mine‐wide  explosion  suppression  compliance  was  recognised  as  a  significant challenge in 7 day operations, with the eventual approval of wet dusting systems being seen as a positive outcome. 

A number of mines reported concerns with the overall effectiveness of face/mine ventilation systems, particularly in respect to respirable dust levels, quantity and capacity (distance), and noise levels.  

The  installation  of  6m  long  victaulic  pipes  coupled  with  the  size  and  manoeuvrability  of existing  pipe  installation  equipment  is  an  issue  at  a  number  of mines,  and  is  expected  to warrant  further  research and development  to establish  systems and equipment  to  support higher capacity development systems. 

Introduction of New Technologies and Processes 

Respondents were requested to identify and rank up to five (5) new technologies and processes they consider had been successfully introduced, and to identify the key factors they considered had been instrumental  in  the  successful  introduction  of  those  technologies  and  processes  (respondents  are asked to rank these key factors from 1 to 4, with a ranking of “1” indicating the most positive factor of  those  identified).  Table  6  shows  the  consolidated  responses  from mines,  with  responses  from longwall  mines  being  identified  with  a  highlighted  ranking.  Figure  1  over  summarises  these  key factors. 

While respondents did not consistently complete the table in the manner proposed, Table 6 highlights a number of reoccurring themes  in respect to the successful  introduction of new technologies  and  processes,  including;  product  or  project  champions,  robust  change management processes, involvement of personnel, company support and involvement, good planning,  demonstrated  productivity  and  safety  benefits,  reduced  manual  handling, introductory training. 

These  themes  are  also  reflected  in  Tables  7  and  8  which  detail  the  responses  of  Mining Contractors  and  OEMs/Suppliers  in  relation  to  the  successful  introduction  of  new technologies and processes. 

Page 12: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 8  

Respondents were similarly requested to identify and rank barriers or factors that have impacted the introduction of up to five (5) new technologies and processes that they have been associated with, and  to  identify  root  causes  of  these  barriers  or  impacts  wherever  possible.  Table  9  shows  the consolidated responses from mines, with responses from longwall mines again being identified with a highlighted ranking. Again, Figure 1 summarises these key factors. 

Again  a  number  of  reoccurring  themes  were  evident  in  mine  responses,  including;  cost, certification and  regulatory  issues,  lack of OEM support and commitment,  lack of operator buy‐in, lack of corporate commitment and management support 

OEMs  and  Suppliers  (Table  11)  also  identified  certification  and  regulatory  issues,  a  lack  of operator buy‐in  and  resistance  to  change as barriers  to  the  successful  introduction of new technologies. 

Respondents were similarly requested to identify and rank major barriers to the successful research and development of new technologies. Table 12 shows the consolidated responses from mines, with responses  from  longwall  mines  again  being  identified  with  a  highlighted  ranking.  Again,  Figure  1 summarises these key factors. 

 Themes  evident  in  the  mine  responses  included;  funding,  costs,  OEM  commitment,  cost, research  being  too  “pure”,  lack  of  corporate  support  for  R&D,  over‐commitment  of  R&D funding to longwall operations (the profit maker), or lack of or inability to apply technological solutions to roadway development challenges. 

OEMs and Suppliers (Table 14) again identified funding and development costs, certification and regulatory issues, low cost sourcing by mines, end user acceptance, and a lack of project champions as key barriers to successful research and development of new technologies. 

  Key Factors Identified byMines  Key Factors Identified by  Mining Contractors, OEMs and Suppliers 

Key Factors in the Successful Introduction of New Technologies and Processes 

Product or project champions Robust change management processes Involvement of personnel Company support and involvement Good planning Demonstrated productivity and safety benefits Reduced manual handling Introductory training 

Champion to push the innovation Personnel taking ownership of system Equipment designed and built fit for purpose Improved operational flexibility and equipment maintenance Test and validation processes prior to going to market Improved performance Reduced manual handling injuries 

Barriers to Successful  Introduction of New Technologies and Processes 

Cost Certification and regulatory issues Lack of OEM support and commitment Lack of operator buy‐in Lack of corporate commitment Lack of management support 

Certification and regulatory issues Lack of operator buy‐in Resistance to change 

Barriers to Successful  Research and Development  of New Technologies 

Funding and costs OEM commitment Research being too “pure” Lack of corporate support for R&D Over‐commitment of R&D funding to longwall operations  Lack of ability or inability to apply technological solutions to 

Funding and development costs Certification and regulatory issues Low cost sourcing by mines End user acceptance Lack of project champions  

Page 13: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 9  

roadway development challenges 

Figure 1: Summary of Key Success Factors and Barriers to New Technology and Processes 

While Mines, OEMs and Suppliers reported a number of consistent themes, as summarised in Figure 1, Mine respondents were also critical of the level of support and commitment provided by OEMs in developing and introducing new technologies, as were OEMs and Suppliers critical of the lack of buy‐in  by Mines  to  new  technologies.  This  dichotomy  is  perhaps  fuelled  by  the Mines’  preference  to develop localised solutions to their technology requirements (with perhaps a leaning towards higher level technologies), whereas OEMs seek to develop global products  in order to offset development costs (with perhaps a leaning towards lower or simpler levels of technology). 

Equipment  certification  and  regulatory  issues  have  also  been  identified  as  a  major  barrier  in  the introduction of new technology and processes (and is possibly a factor in OEMs’ preferences towards lower  technology  solutions)  and  is  expected  to  be  a major  consideration  in  the  development  and adoption of remotely operated or automated roadway development equipment. 

Unfortunately,  the  Audit  does  not  identify  the  change  management  strategies  adopted  by  mines when introducing new technologies and processes, nor does it reveal a sense of the level of success or  otherwise  achieved  in  regards  to  the  introduction  of  new  technologies  and  processes,  ie;  how often we succeed or fail, or how well we realise the full capability afforded by the new technology or process.  The  wide  disparity  in  roadway  development  performance  levels  between  best  practice mines and  the bulk of  the  industry  suggests  that  the  industry  is  failing  to  realise  the  full  capability afforded  by  available  or  newly  developed  technologies,  whilst  a  review  of  roadway  development related  technology  developments  over  the  past  20‐30  years  (eg;  Maintel  Development  Machine, Kemcoal  Beaver, Joy 1FCT – 4FCT, Klockner Becorit continuous haulage, Joy Sumps Shearer, Mobile Boot Ends, 12CM20, 12CM30, ABM20, ABM25,) might suggest that it is a long and difficult road from concept development to commercial success. 

Again  unfortunately,  the  Audit  does  not  identify  the  change  management  strategies  adopted  by mines  when  introducing  new  technologies  and  processes.    a  sense  of  the  level  of  success  or otherwise achieved in regards to the introduction of new technologies and processes, ie; how often we succeed 

CONCLUSIONS 

The  Technology  Audit  provides  an  industry  wide  picture  of  the  level  of  utilisation  and  relative effectiveness  of  current  roadway  development  equipment  and  systems.  The  Audit  also  identifies potential areas  for  further research and development together with the challenges associated with the research, development and introduction of new technology and processes into an underground environment. 

The  Audit  clearly  identifies  that  in  overall  terms  bolting  is  perhaps  the most  significant  challenge facing the industry in respect to improving roadway development performance, including: 

self drilling bolts  push button controls on bolting rigs  concurrent operation of roof and rib bolting rigs  improving ergonomics associated with access to and operation of bolting rigs  addressing  issues  associated with  the  adoption  of  and  compliance with  current Guidelines 

(MDG35). 

Whilst  ever  continuous  miners  are  required  to  operate  within  a  5.0–5.4m  wide  2.5–3.5m  high operating envelope, provide effective roof and rib support within metres of the face, be able to break away and mine cut throughs between adjoining roadways, and cut coal at instantaneous rates of 30‐40tpm,  it  is  unlikely  that  designers  and manufacturers  will  be  able  to  incorporate  the  concurrent operation of manually operated bolting and meshing systems within an ergonomically acceptable on‐board work environment.  

Page 14: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 10  

Therefore, future roadway development R&D should, as a priority, focus on developing technologies that enable bolting (and meshing) to be undertaken remotely, including: 

 self drilling bolts (to minimise the number of process steps and components)   bolt, washer, and mesh storage/handling systems and manipulating devices   remotely controlled/automated bolting rigs and manipulators, and  associated sensing and monitoring systems. 

 A continuing focus on the development of technologies required to support a self steering remotely controlled  continuous miner  should  also  be maintained,  including  remote  sensing,  seam  profiling, video monitoring and navigation technologies. These technologies need to be supported by state of the  art  underground  communication  systems,  the  development  of  communication  protocols  that facilitate  integration of  the differing  technologies and hardware  (eg; miners, bolters, manipulators, haulage  systems,  etc),  and  the  development  of  machine  supervisory/auto‐reporting  systems (including the development of “black‐box” data logging systems for machine diagnostics and failure analysis). 

Current research into automated bolting and mesh handling systems has identified significant issues in  regards  to  space  constraints  in  and  around  the  continuous  miner,  particularly  in  respect  to potential conflicts between bolt and mesh storage/handling systems, and on‐board ducting systems and connections to the auxiliary ventilation ducting. Similar constraints were  identified by mines  in the Audit in respect to on‐board ducting systems and connections to the auxiliary ventilation ducts, and between roof/monorail mounted ducting and shuttle cars, with mines also identifying issues in respect to the effectiveness and capacity of current face ventilation systems.  

The development of higher capacity roadway development systems will result  in higher linear rates of  advance  in  gateroads,  which  in  turn  is  likely  to  result  in  increased  rib  emissions  (unless  more extensive  gas  drainage  is  undertaken).  Further  consideration  of  issues  associated  with  on‐board ventilation  systems,  interconnections between on‐board and auxiliary  ventilation ducting,  roadway space  constraints,  and  the  overall  effectiveness  of  face  ventilation  systems  is  warranted  as  an emerging priority. 

Batch  haulage  systems  (eg;  shuttle  cars,  battery/diesel  haulers)  are  unlikely  to  surface  as  a major constraint to improved roadway development performance until such time as self drilling bolts and automated bolting and meshing systems are developed and adopted, and utilised in conjunction with concurrent sumping, cutting, and bolting operations. Further,  the matching of cutting, haulage and support cycles has recently been recognised as a major contributor to improved development rates, with  a  number  of mines  increasing  the  size  of  shuttle  cars  to  optimise  current  face  cycles.  Larger shuttle cars have also  introduced  issues  in  respect  to space constraints  in  roadways, particularly  in regards  to  shuttle  car/ventilation  duct  interferences  and  the  application  of  monorail  mounted services management systems.  Ongoing operational research by mines into the optimisation of face cycles  is warranted (ie; matching of cutting, haulage and support cycles), while the development of shuttle  car  guidance  systems,  potentially  as  an  off‐shoot  to  the  development  of  continuous miner navigation systems, may offer improved consistency of operation and facilitate the development of a fully remote mining system.   

The  introduction  of  continuous  haulage  systems  into  bord  and  pillar  operations  will  provide  an opportunity  for  longwall mines  to evaluate  the potential application of proven continuous haulage systems to gateroad development, not only as a coal clearance system but as a means of mounting face  services  on  the  haulage  system  to  eliminate  manual  handling  of  ducting,  cables,  and  hoses. Monorails are increasingly being utilised to manage face services and are reportedly highly effective however  full  integration  of  the  ventilation  system  has  largely  been  ignored,  with  the  weight  of monorail  segments  understood  to  be  a  limiting  factor.  The  development  of  a  remotely  operated mining system will require means to manage face services, be it via the continuous haulage system or a monorail mounted face services system.   In the latter  instance methods need to be developed to enable the monorail to be extended remotely.  

Page 15: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 11  

The  concept  of  developing  a  high  capacity  roadway  development  system  capable  of  sustained production rates of 10MPOH 20 hours a day as contemplated by ACARP’s CM2010 R&D strategy  is expected  to  reflect  similar  key  success  factors,  and  to  experience  similar  barriers  to  its  successful development  as  experienced  with  existing  technologies. While  the  project  objectives  may  appear visionary,  there  is an emerging  recognition  that adoption of emerging  technologies  such as bolter‐miners,  self  drilling  bolts,  and  continuous  haulage  systems  could,  in  best  practice  mines,  almost realise the 10MPOH objective – the challenge then is to make that rate sustainable, and to minimise or eliminate process downtime. The project also has other key factors in its favour, being the recent highly successful development of  the  longwall automation system under the ACARP banner, with a number  of  the  key  longwall  automation  players  also  being  involved  in  the  Roadway Development Task  Group.  The  Task  Group  also  recognises  the  necessity  of  developing  a  critical mass  to  pursue development  and  adoption  of  the  necessary  technologies,  and  to  gain  OEM  commitment  and support  for  their  commercialisation.  The  successes  achieved  by  Earth  Moving  Equipment  Safety Round Table (EMESRT)  in developing design guidelines for surface mining equipment are also  likely to  be  applicable  in  an  underground mining  context,  and may  become  an  essential  element  in  any strategy aimed at addressing current certification and regulatory issues. 

RECOMMENDATIONS  

It is recommended that ACARP’s Roadway Development Task Group maintains the general thrust of its CM2010 R&D  strategy and where appropriate  review R&D priorities  in  respect  to  the  following key elements: 

1. The  development  of  technologies  that  enable  bolting  (and  meshing)  to  be  undertaken remotely, including:   self drilling bolts (to minimise the number of process steps and components)   bolt, washer, and mesh storage/handling systems and manipulating devices   remotely controlled/automated bolting rigs and manipulators, and  associated sensing and monitoring systems. 

2.  The  development  of  technologies  required  to  support  a  self  steering  remotely  controlled continuous miner including:  remote sensing  seam profiling  video monitoring  machine navigation and steering  communication  protocols  that  facilitate  integration  of  the  differing  technologies  and 

hardware (eg; miners, bolters, manipulators, haulage systems, etc), and  machine supervisory/auto‐reporting systems (including the development of “black‐box” 

data logging systems for machine diagnostics and failure analysis). 

3. Addressing  issues  associated with  on‐board  ventilation  systems,  interconnections  between on‐board  and  auxiliary  ventilation  ducting,  roadway  space  constraints,  and  the  overall effectiveness of face ventilation systems. 

4. The  development  of  shuttle  car  guidance  systems  (potentially  as  an  off‐shoot  to  the development  of  continuous  miner  navigation  systems)  as  a  means  of  improving  the consistency of operations and facilitating the development of a fully remote mining system.   

5. Addressing issues associated with the management of face services, be it via the continuous haulage system or a monorail mounted face services system.  In the latter instance methods need  to  be  developed  to  enable  the  monorail  to  be  extended  remotely  if  a  remotely operated roadway development system is to be employed effectively.  

6. Development  of  strategies  to  address  equipment  certification  and  regulatory  issues, including  consideration of how  the Earth Moving Equipment  Safety Round Table  (EMESRT) design guidelines may be applied in an underground mining context. 

Page 16: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 12  

It  is also recommended that mines continue to undertake ongoing operational research as a means to optimising face cycle times (ie; matching of cutting, haulage and support cycles), and to consider engagement  of  change management  expertise  as  part  of  any  strategy  to  introduce  new  roadway development technologies and processes. 

Page 17: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 13  

 

ACKNOWLEDGEMENTS  

The  contribution  from  participating  Mines,  Mining  Contractors,  OEMs  and  Suppliers  is  greatly acknowledged,  as  is  the  support  of  ACARP’s  Roadway  Development  Task  Group  in  circulating  the audit  instrument  to  Mine  Staff.  The  support  from  Associate  Professor  Ernest  Baafi  and  student Christopher Brunero is also acknowledged, their help was invaluable in compiling and analysing the responses.   Gary A Gibson GaryGibson&ASSOCIATES

Page 18: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 14  

 LIST OF TABLES 

 

Table  Title  Page 

1  Process Elements and Technology as Ranked by Utilisation  14 

2  Process Elements and Technology as Ranked by Effectiveness  15 

3  Process Elements and Technology as Ranked by Likely Benefit of Further Research  16 

4  Process Elements and Technology Responses – OEMs and Suppliers  17 

5  Observations Relating to the Utilisation of and Requirement for Further Research of Process Elements and Technologies – as ranked by research priority 

24 

6  Key Factors Contributing to the Successful Introduction of New Technologies and Processes – Mine Responses 

41 

7  Factors Contributing to the Successful Introduction of New Technologies and Processes – Mining Contractors 

44 

8  Key Factors Contributing to the Successful Introduction of New Technologies and Processes – OEMs and Suppliers 

45 

9  Barriers or Factors Impacting the Introduction of New Technologies and Processes – Mines 

47 

10  Barriers or Factors Impacting the Introduction of New Technologies and Processes – Mining Contractors 

48 

11  Barriers or Factors Impacting the Introduction of New Technologies and Processes – OEMs and Suppliers 

49 

12  Major Barriers to the Successful Research, Development and Introduction of New Technologies – Mines 

50 

13  Major Barriers to the Successful Research, Development and Introduction of New Technologies – Mining Contractors 

52 

14  Major Barriers to the Successful Research, Development and Introduction of New Technologies – OEMs and Suppliers 

53 

 

Faculty of Engineering � 22/6/10 6:28 PMComment: Move to a line above the Table 

Page 19: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 15  

 Table 1: Process Elements and Technology as Ranked by Utilisation 

 

Page 20: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 16  

 Table 2: Process Elements and Technology as Ranked by Effectiveness 

 

 

Faculty of Engineering � 21/5/10 1:33 PMComment: Move to a line above the Table 

Page 21: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 17  

 Table 3: Process Elements and Technology as Ranked by Likely Benefit of Further Research 

 

Page 22: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 18  

Table 4: Process Elements and Technology Responses – OEMs and Suppliers 

No  Process Element and Technology  Supplied  Extent Adopted 

Efficiency  Further Research 

Comments and Responses 

1.00  Continuous Miners           1.01  Remote control operation of CM functions 

(eg; radio) Y  4  4  3   

1.01    Y  4  4  3  Joy is currently working on new generation of handheld remote 1.01    Y  4  4  3  Improve ergonomics of the transmitter 1.02  Concurrent sumping, cutting and bolting  Y  2  4  4  Joy is working on the development our product  for use in the Global arena 1.03  Auto‐cut facility of sumping and cutting 

action Y  1  4  2        

1.03    Y  3  3  2        1.04  Rotating arm/spinner loading configuration  Y  4  3  2        1.04    Y  3  4  2        1.04    Y  4  4  2   1.05  East/west chain loading configuration  Y  2  2  2   1.05    Y  2  3  1  Joy offers the plough exclusively E/W no longer offered 1.06  Plough shovel loading configuration   Y  3  4  2   1.07  Scrolling head assisted loading  Y  2  4  2   1.08  Operator display units (eg; cutting height, 

loads, etc) Y  2  4  2  Works well in Place Change applications so driver knows what is happening on 

the machine when it is under unsupported roof 1.08    Y  3  4  2   1.08    Y  4  3  2        1.09  Machine diagnostic display units  Y  4  3  2        1.09    Y  4  4  3   1.09    Y  4  4  2        1.09    Y  1  4  4  New application, so not widely deployed yet 1.10  Machine auto‐reporting systems  Y  2  3  4  Some issues with mine maintaining infrastructure. Data communications not 

fully developed. Need better data analysis systems 1.10    Y  1  3  4  New application, so not widely deployed yet 1.10    Y  1  4  3   1.10    Y  2  2  3  Problems collecting data via manual downloads. Will only be really effective 

with real time data communications 1.11  Automated lubrication systems  Y  1  3  2   1.11    Y  2  3  3  Issue is that there is no way of checking if lube is getting to where it should get 

to 1.12  Area lighting systems  N                       Only really applicable to bolter miners 1.12    Y  4  4  1  used on miner bolters but not place change machines 1.12    Y  3  4  2   1.13  Operator access and egress  N                       Only really applicable to bolter miner 

Page 23: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 19  

No  Process Element and Technology  Supplied  Extent Adopted 

Efficiency  Further Research 

Comments and Responses 

1.13    Y  4  4  4   1.14  Maintenance accessibility and servicing  Y  4  4  3   1.14    N                       Assume this relates to OEM supplied service contracts 2.00  Strata Support           2.01  Concurrent operation of roof and rib 

bolters Y  2  4  3   

2.02  Push button controls on bolting rigs  N        No but have seen auto bolters at Crinum East and they remove much of the operator dependence making it easier and less variable, using the auto bolters each bolt installation should be identical in terms of spin and hold times. 

2.02    N  1  3  4  Still under development 2.03  Automated bolting systems  N        No but have seen auto bolters at Crinum East and they remove much of the 

operator dependence making it easier and less variable, using the auto bolters each bolt installation should be identical in terms of spin and hold times. 

2.03    Y  1  3  4  Equipment OEM's need to discuss with strata reinforcement company's. Lack of support.  

2.03    Y  4  4  3        2.04  Roof mesh racking system on CM  Y  1  3  4  Initial trails conducted. Requires further investigation. Lack of Industry support 2.04    N        Currently being researched at University of Wollongong 2.04    Y  2  3  3        2.05  Bolt storage cassettes or pods  Y  3  3  2  Pods and Cassettes are fairly commonly 2.05    Y  3  3  2   2.05    Y  3  3  4  Bolt storage systems are generally the last in the design chain. The parameters 

are defined by what available space is left rather then what is actually required. 2.05    Y  3  4  3   2.05    Y                       Used on mobile bolters not bolter miners 2.05    Y  3  4  3        2.06  Tendon/cable tensioners  Y  4  4  3  Involves manual handling. Possible research to reduce weight. Scale of market 

limitations 2.06    Y  3  3  3  Hydraulic tensioners are heavy and can cause strains along with hydraulic 

injection risk. They will always be around for high cable tension so should be made lighter & safer. Lower tension cables (>10t) will not require hydraulic tensioners due to recent developments by Jennmar ToTo device and the Resco threaded end fitting. 

2.06    Y  2  4  3        2.07  Roof fall protection devices  Y  3  4  3  Category too broad. Needs to be broken down into specifics 2.07    Y  2  4  3  Joy offers MGD35 compliant TRS system 2.08  Rib fall protection devices  Y  3  4  3  Category too broad. Needs to be broken down into specifics 2.08    Y  3  4  3        

Page 24: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 20  

No  Process Element and Technology  Supplied  Extent Adopted 

Efficiency  Further Research 

Comments and Responses 

2.10  Self drilling roof or rib bolts  Y  1  4  4  New modifications being trialled in next 3 months. Commercial availability of the SDRB technology expected by end of 2010. 

2.10    Y  1  3  4  This is considered the ultimate product for faster development metres. Yet to develop a product that will achieve the same degree of roof support effectiveness 

2.10    Y        Working with Ground Support Services (Peter Gray) to trial this new technology SDRB on surface and u/g. Most prospective users are very keen to try. Delays are being overcome. Should perform u/g trial by end August. Minova Operations are using Self Drilling  fibreglass bolts for PUR injection on faces etc.  

2.10    Y  3  4  3   2.10    N                       Joy bolting equipment is designed to  3rd party consumables 2.11  Long roof tendons/cables  N                       Joy bolting equipment is designed to  3rd party consumables 2.11    Y  3  4  4  Adopted well , safer & more efficient 2.11    Y  4  4  3   2.11    Y  3  4  4  Lack of industry support in expanding research 2.11    Y        Minova entering this market now. All mines very willing to evaluate. 2.11    Y  3  4  3  There is greater range of groutable long tendons on the market these days. 

Better systems of grouting for "bottom‐up" applications and quality control of grout etc would be good developments 

2.12  Other  Y  2  4  4  New technology in resin anchors has improved the performance of roof bolts systems. Lack of supplier support limited technology introduction 

2.12  Other  Y  2  4  1   3.00  Coal Haulage           3.01  Shuttle car coal haulage systems  Y  4  4  3        3.01    Y  4  3  2        3.02  Battery/diesel hauler haulage systems  Y  2  2  3  Heat and filter life on the diesel Battery life on bad floor conditions and battery 

handling infrastructure 3.02    Y                       not in Australia 3.03  Continuous haulage systems  Y  2  4  3   3.03    N                       System soon to be installed. No experience yet 3.04  Breaker feeders   Y  4  3  2   3.04    Y  4  4  2   3.05  Mobile boot ends  Y  3  4  2   4.00  Face Ventilation            4.01  On‐board ducted ventilation systems  N        Can feed straight into CES monorail mounted vent system 4.01    Y  2  4  3   

Page 25: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 21  

No  Process Element and Technology  Supplied  Extent Adopted 

Efficiency  Further Research 

Comments and Responses 

4.02  Monorail mounted ducting systems  Y  2  4  4  CES Monorail system with flexible vent  ducting reduces injuries from handling elephant trunk and fixed tube lifting, improves advance rate as less need to stop to install ventilation, extremely low maintenance, allows storage of material close to miner that moves with miner, relatively light to handle, recycle rails and long cycle life increases profitability of operations, multiple use applications when left in place. 

4.02    Y  4  4  4  This is relatively new technology and proven results are only just being delivered to the market.  We have had a strong enquiry on this product and believe with more operator awareness it will become more readily adopted. 

4.03  On‐board or fan mounted dust scrubbers  Y  2  3  3   4.03    Y  2  4  2  Extremely effective when set up and operated correctly particularly for a place 

change application. Operators need to be meticulous with spray and screen maintenance. Ventilation needs to be set up to match the scrubber 

4.03    Y  4  4  1   4.04  Flexible ducting  Y  3  4  4  CES Monorail mounted ducting has low damage rate, maintains air flow, 

increases options for mining movements, can be left in place when miner flits/moves, expandable to minimise fixed ducting needed, fans may be mounted on monorail (possible) 

4.05  Auxiliary fans  N                       Not something we supply at this time ‐ might be monorail mounted to increase operational flexibility 

4.06  Face monitoring systems (eg; methanometers) 

Y  3  4  2   

4.06    Y  4  4  2   5.00  Face Services (eg; power, water in/out, 

compressed air, communications, etc)          

5.01  Cable rollers and other devices for manual handling of cables and hoses  

Y  3  3  4  Cable rollers and cable brackets are well accepted in the industry but reinforce the need for manual handling cables and hoses ‐ some of which can be reduced by using monorails.  

5.01    N        Looking at for hard rock mines. Currently use crawler rigs via Minova Operations Division for secondary support. 

5.01    Y  2  3  2  Can be supplied with Alfabs work platforms 5.01    Y  3  4  2   5.02  Monorail systems for mounting of face 

services  Y  2  4  4  It is Worth investigating fixed brackets compared to roller brackets in injury and 

flexibility outcomes. 5.02    y  4  4  4  This is relatively new technology and proven results are only just being 

delivered to the market.  We have had a strong enquiry on this product and believe with more operator awareness it will become more readily adopted. 

5.02    Y  2  3  3   5.03  Cable/hose boats for storage of cables 

and/or hoses Y  3  3  2   

Page 26: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 22  

No  Process Element and Technology  Supplied  Extent Adopted 

Efficiency  Further Research 

Comments and Responses 

5.03    Y  3  4  3   5.03    Y  3  4  2  Can be LHD mounted or fork mounted 5.03    N  2  3  3  Mines that use pipe monorails end up using it extensively as it is light and 

multipurpose ‐ reduces injuries, improves operational effectiveness. Carries ventilation, cables, hoses, stores, pumps, etc 

5.04  Hydraulically powered cable reelers  Y  3  3  3   5.04    Y  3  3  3        5.04    N                       Major safety features for moving injured workers and equipment not 

researched adequately 5.04    Y  3  4  2   5.04    Y  2  4  3   5.04    Y  2  2  2   5.05  Hydraulically powered hose reelers  Y  3  4  2   5.05    Y  3  3  3        5.05    N                       Reduction in cable/ hose damage from better storage practices, improve 

handling risks, and all pits would use them 5.06  Electrical DCB/Gate End Boxes  Y  4  3  2   5.07  Other  Y  3  4  4  Digital based communication and tracking technology used for some years in 

hard rock mines is now finalising I.S. certification for some key components which will see rapid uptake (e.g. I.S. VoIP Telephone handset for two‐way voice & texting). Also Proximity Detection Systems for coal applications will be a growing requirement with more remote control and automation. 

6.00  Materials Handling           6.01  QDS style racking devices for loading 

bolting consumables onto CM Y  3  3  4  The QDS Equipment is designed around the pod design. See previous pod design 

comments in section 2.5      6.01    Y  3  4  2   6.01    N  1  3  3  under development 6.02  QDS style jib devices for loading bolting 

consumables onto CM Y  3  3  4  The QDS Equipment is designed around the pod design. See previous pod design 

comments in section 2.5           6.02    Y  3  3  2  Can be QDS, RAS, KAT etc 6.02    Y  2  3  3   6.03  Boom lifting or racking devices to load 

mesh sheets onto CM N  1  3  3  under development 

6.03    N                       One location uses monorail mesh carrier to act as storage near cm and provide additional rib protection for operators walking past 

6.03    N        Individual mines have developed/trialled different systems to lift mesh sheets onto CM's 

6.04  QDS attachments for the transport of pods or cassettes  

Y  2  3  3   

Page 27: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 23  

No  Process Element and Technology  Supplied  Extent Adopted 

Efficiency  Further Research 

Comments and Responses 

6.04    Y  3  4  2   6.04    Y  3  4  2  Can be designed to suit customer needs 6.04    N  1  3         Monorails with block and tackle enable operators to load cm when mobile 

machinery not available ‐ issue is time effectiveness 6.04    Y  3  3  4  This would need to be included as a part of any future research considerations 

in moving or handling these consumables 6.04    Y  3  3  2   6.05  Material trailers for the transport of 

multiple pods or cassettes Y  2  3  2   

6.05    Y  2  3  3   6.05    N  1  3  3  under development 6.05    Y  3  4  2   6.05    Y  3  4  2   6.05    N                       Under consideration as additional service / supply to facilitate operational 

flexibility 6.05    N  3  3  4  as above 6.06  Face stonedusting systems  Y  3  3  2   6.06    Y  3  4  3   6.07  Bulk stonedusting systems  Y  2  4  2   6.07    N                       Storage system for locating bulk stone dust bags close to face, enabling more 

effective distribution and loading of smaller stone dust system 6.07    Y  3  4  2  Refers to Alfabs Barrier Bag system 6.07    Y  3  2  4  Quickduster was 1st of its type in industry, now Quickduster MKII is expected 

for commercialisation in June/July 2010 6.08  “Wet dusting” systems  Y  3  4  4  Future research is currently underway to prove effectiveness. 6.08    Y  2  4  2   6.08    N                       Theoretical process improvements possible using wet dusting systems. Approval 

to use is limiting application. 7.00  Panel Services           7.01  Conveyor belting reeling/handling devices  Y                       Some items supplied on request ‐ technology in use and incremental 

improvements over time 7.01    Y  3  4  2        7.01    Y  3  3  2   7.01    Y  3  4  2  offered through our conveyor arm of the business CCC 7.01    Y  2  3  3   7.01    Y  3  3  2        7.02  Devices to facilitate installation of 

structure Y  1  3  2  offered on feeder breakers and continuous haulage 

7.02    Y  2  3  3  Pods to carry equipment available 

Page 28: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 24  

No  Process Element and Technology  Supplied  Extent Adopted 

Efficiency  Further Research 

Comments and Responses 

7.03  Purpose designed pipe installation equipment (eg; pipe trailers, QDS attachments) 

Y  3  3  3   

7.03    Y  2  3  3  Pipe handler available as work platform attachment. 7.03    Y  4  3  2        7.03    N                       Suitably installed Monorails may facilitate installation of pipes ‐ more research 

needed on effectiveness / opportunity for improved operating processes 7.03    Y  2  3  4  Pipe trailer designs are limited to "what works elsewhere" there is no room for 

testing or trying new concepts as the market is too small for suppliers to develop and test new concepts unless then end user is willing to risk buying a "white elephant"  

7.03    Y  1  2  4  A pipe trailer unit was sold into Oaky North early 2002, complete with hydraulic grabber claw.  

7.04  Cable reeling/ hanging devices  Y  2  3  3   7.04    Y  3  3  2   7.04    Y  3  4  2  Cable reelers available 7.04    N  3  3  4  Monorail system materially impact on the need for this facility, and cable 

reeling devices can be transported by monorail for use. 7.05  Electrical DCB/Gate End Boxes  Y  4  3  2        7.05    N                       Can be suspended beneath monorails reducing potential damage from 

movements by mobile machinery and integrating their movement with cables along the monorail ‐ operational flexibility and effectiveness increased ‐ more research would define increased productivity improvements. 

7.06  Roadway maintenance vehicles/attachments  

Y  2  3  2   

8.00  Personnel Transport           8.01  PJB/SMV style personnel transporters  Y  4  4  3   8.01    Y  4  4  2   8.03  Purpose designed maintenance support 

vehicles Y  3  3  3   

 

Page 29: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 25  

 Table 5: Observations Relating to the Utilisation of and Requirement for Further Research of Process Elements and Technologies – ranked by research priority 

Score  No  Process Element & Technology  Comments from Respondents 3.77  2.10  Self drilling roof or rib bolts  Longwall 

Three mines noted that they are currently either adapting continuous miners for self drilling bolts (SDB) or are well advanced in respect to potential uptake of SDB, with a fourth noting that they were being used on one continuous miner 

One mine  noted that a Hilti cuttable rib bolt was not far off, while another noted that a SDB trial had been abandoned due to bolts blocking up in soft sheared coal, further noting that SDB need to function in all conditions  

Bord & Pillar  One mine reported trialling Sandvik’s SDB and noted that development rates would if a system of bolting quicker and not having 

as many items to handle can be successfully developed OEMs and Suppliers  Self drilling bolts have been around since the 1960's in many forms. Numerous products exist on today's market but not many 

consider the full requirements of such systems. Lack of industry support for suppliers  This is considered the ultimate product for faster development metres. Yet to develop a product that will achieve the same degree 

of roof support effectiveness  Working with GSS to trial this new technology on surface and underground. Most prospective users are very keen to try. Should 

perform underground trial by end August. Also noted that fibreglass SDB are being used in conjunction with PUR injection on longwall faces  

3.56  1.02  Remote steering systems employed (eg; video) (on continuous miners) 

Longwall   This would enable operators to improve machine visibility whilst cutting and flitting  Use of cameras on larger equipment could be beneficial in reducing blind spots and assisting with operation of equipment such as 

picking up loads, etc   Accuracy of location of drivages is paramount to modern longwall mining. If remote steering could accurately achieve this it would 

be of great benefit   Bord & Pillar  One mine noted that remote steering systems were used on one Eimco  

3.53  2.02  Push button controls on bolting rigs 

Longwall   One mine reported improved consistency/ quality of installation with push button controls while another reported ergonomic 

benefits. Another noted that more technology was required  The machine has the hydraulic capacity but ergonomic and egress issues prevent this occurring simultaneously  Bord & Pillar  One mine reported a frustration that longwall shields can be moved from 200m away and yet still have 4 men on a miner putting 

up bolts!  Two mines reported a preference for levers or handle controls  OEMs and Suppliers  Have seen auto bolters at one mine and they remove much of the operator dependence making it easier and less variable, using 

the auto bolters each bolt installation should be identical in terms of spin and hold times 

Page 30: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 26  

Score  No  Process Element & Technology  Comments from Respondents 3.50  1.11  Machine auto‐reporting systems  

(on continuous miners) Longwall  Communication system not set‐up to allow data reporting from the equipment.  Real time detailed reporting can only be a good 

thing for process coordinators  No fibre network to section expense to business versus return for business  Telemetry not kept up to machine data displayed poorly    Needed as a must, require data cabling and equipment not through supply cables   Have had consistent problems in establishing reliable data link to central facility  Still trying to develop outbye communications  Information difficult to use and get information back to crews. Information needs  to be more user friendly   Reporting system wasn't accurate, currently being looked at again  RTM currently being used as data verification tool. The system has great potential to aid in optimising development cycles  One mine noted that it was currently working through the development of a live data capture package  with the OEM, while 

another noted the software was coming soon and they were excited about implementation of the system, and another noted that it was to be fitted to new continuous miners being currently built 

Bord & Pillar  One mine noted that the JSRP was installed while another noted that the system does not report directly to the surface but can be 

gathered from point underground and brought to the surface OEMs and Suppliers  Some issues with mine maintaining infrastructure. Data communications are not fully developed. Need better 

data analysis systems   New application, so not widely deployed yet  Problems collecting data via manual downloads. Will only be really effective with real time data communications  

3.48  3.07  Overall effectiveness of coal haulage system  

No observations made 

3.45  2.01  Concurrent operation of roof and rib bolters 

Longwall  Access to roof rigs is an issue when rib bolting, therefore operators tend to support roof then rib with 2nd operator assisting to 

install top rib bolt. Have to switch from roof to rib bolters   Concerns regarding the ability of the inbye operator to escape the face in the case of fall or outburst are an issue with concurrent 

bolting.  To leave the bolting on automatic has issues with the rigs jamming up and spitting steels out  Standing in front of rib borer in bad ground (ribs) ‐ no protection for operator using roof bolting rigs   Requires greater ergonomic consideration. Current configurations provide very small working envelope  Emergency escape issues    Use of new technology is proposed (eg; SDB) ‐ new miners being built can use all 6 rigs together Bord & Pillar   Bolting is still one of our biggest delays to production, takes 1 min to cut a metre and 3 minutes to bolt  it ( on minimal support 

level, next level up is 6 minutes)   Two bord & pillar mines and one longwall mine reported that rib bolts were not utilised, and therefore not an issue 

Page 31: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 27  

Score  No  Process Element & Technology  Comments from Respondents 3.42  1.16  Overall ergonomic configuration 

for CM operation Longwall  Onboard mesh carrying system for low seam operations  One mine noted that side platforms were narrow, resulting in poor ergonomics    Hose and cable runs and lay outs are always an after though  One mine noted that ergonomics had improved over the years but could still be further improved, with four other mines also 

noting that further or research work was required to improve on‐board ergonomics Bord & Pillar  Dust and noise and manual handling still large problems even on the most modern machines ‐ more research in to operator 

comfort and reduction in manual handling is required 3.41  2.11  Overall ergonomic configuration 

for strata support Longwall  Additional steps and changes to rig configuration being made to improve the access to bolting rigs  Hard to attain required bolting patterns   When an operator is required to continually install bolts (cut/ bolt) for up to 12 hours the ergonomics of the machines need to be 

greatly improved  Stand on bolting platforms    Good with available room    New miner is improved from the last model, constantly looking options  Bord & Pillar  Still too much manual handling operators putting in 250 bolts each per shift requires a lot of manual handling  Could be improved, potential for issues arising from static constrained postures as a result of 2 handed operation 

3.41  7.04  Purpose designed pipe installation equipment utilised to extend pipe ranges 

Current systems are very unyielding.  Due to the length of the pipes used the equipment is very long.  There needs to be work on finding a better, faster, more flexible joint than Victaulic 

Pipe trailer are high maintenance due to damage incurred in manoeuvring     Always damaged manoeuvring     One mine noted that these units are big ‐ they tie up a LHD, while another noted that a Capricorn/ Mastermyne trailer was very 

unsatisfactory  Two mines reported utilising pipe trailers with a third  reported utilising a pipe pod using MPV trailer  Accepted method of installing pipes. Capacity is an issue  Manual system used, looking into hydraulic system  Bord & Pillar  Pipes advanced from Eimco platform  OEMs and Suppliers      Suitably installed Monorails may facilitate installation of pipes ‐ more research needed on effectiveness / opportunity for 

improved operating processes  Pipe trailer designs are limited to "what works elsewhere" ‐ there is no room for testing or trying new concepts as the market is 

too small for suppliers to develop and test new concepts unless then end user is willing to risk buying a "white elephant"   Pipe handler available as work platform attachment 

Page 32: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 28  

Score  No  Process Element & Technology  Comments from Respondents 3.40  4.01  On‐board ducted ventilation 

system (on continuous miners) Longwall  Mitigation tool against frictional ignition and respirable dust levels  Elephants trunk on the ABM would often fall out or pull down the tubes, was heavy and awkward.  Better design needed for 

transition from Miner to tube  On ABMs the highest restriction in ventilation circuit  Encountering restrictions at miner, being looked into  ABM system had on board system. Current Joy machines only use tubes   Would be fantastic on our miner bolter  (MB30) if it could be engineered   New system fitted to new Sandvik MB610   Size of shuttle cars don’t allow  Working towards getting the system up and running again a hire miner currently being utilised is not fitted with on board 

ventilation    Please research  Bord & Pillar  More can be done to improve these systems 

3.40  5.03  Continuous haulage mounted services  

Longwall   One mine suggested that there would be too much engineering back up required   Bord & Pillar  However, a mine equipped with a continuous haulage system noted that services run along the continuous haulage to the 

continuous miner allow for communication, air, water, etc all to be at the face at all times with no manual handling   Another bord & pillar mine noted the introduction of a Joy 4FCT 

3.36  6.09  “Wet dusting” used for face and outbye dusting 

Longwall  Trial required  Approval issues have prevented the use of this product.  Has a lot of potential in areas with 24/7 and extensive outbye workings  This would be very beneficial for outbye dusting, not sure about advantage in development   One mine requested that this system be further researched, while three mines noted an intention to trial this system when 

available. Another noted that the process had been stopped by DII    Please research  (Mandalong)  One mine noted that this was not the preferred method at this mine  Bord & Pillar  Another (bord & pillar) mine also proposed to undertake trials when available OEMs and Suppliers  Future research is currently underway to prove effectiveness.  Theoretical process improvements possible using wet dusting systems. Approval to use is limiting application. 

3.35  1.10  Machine diagnostic display units  Longwall  One mine reported them as being an invaluable tool  while another questioned the accuracy of information given   Another noted that operators and trades personnel need to be better educated in their use, further noting that the screens and 

layouts need to be intuitive 

Page 33: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 29  

Score  No  Process Element & Technology  Comments from Respondents  On the miner there is the facility to download the event log and downloading on to the computer and then using this information 

to do effective maintenance Bord & Pillar  Systems are there now,  to advance their utilisation requires further introduction of possible delay monitoring s with extra 

sensors, etc  Could be more simpler &/or have multiple access level to assist operators/maintenance more effectively   JNA system better than operators   OEMs and Suppliers  New application, so not widely deployed yet 

3.33  3.05  Mobile boot end   Longwall  Have purchased for future use in mine extension  project  Currently negotiating to purchase MBE   Attempts made using a QDS boot End with PTO hydraulics.  No designs for mobile boot end s are currently available to my 

knowledge 3.31  7.02  Device/s used to separate upper 

and lower belts and facilitate installation of structure 

Longwall  Boot end provides separation of belt to install structure  Not used anymore, but was preferred by operators comfortable with these operations  Will reduce manual handling  Overall belt move system needs improving Bord & Pillar  Boot put in Eimco bucket   Crude manual device utilised OEMs and Suppliers  Offered on feeder breakers and continuous haulage 

3.29  2.12  Level of MDG35 compliance  Two hand operation, shoulder injuries, interaction with rotating parts, this area requires much more research to prevent injuries to operators 

Controls over ridden by operators, due to speeds being to slow   TRS operation interferers with bolting process – continuous miner not configured correctly for our support system  Causes delays and difficulties especially in poor roof   One mine reported a good level of compliance, while another reported that some of the Guideline is in place, full compliance not 

yet achieved   Ongoing program to have bolter operations on machines in Queensland compliant to MDG35   Proposed trials being planned   Roof bolters are digital stations, rib bolters are two handed operation  Simplification Bord & Pillar  Making bolters more difficult to operate is a mechanical engineers method of controlling the issues that MDG35 is trying to 

control. Better to remove the operator from the zone of contact rather than create more complicated systems that they are 

Page 34: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 30  

Score  No  Process Element & Technology  Comments from Respondents tempted to override 

3.29  4.05  Overall effectiveness of ventilation system 

Longwall  One mine reported that conventional ducting was fine, however monorail mounted duct was inadequate    Ventilation is a hot topic with the miner bolter where a number of failed dust samples have been taken   At end of longer gateroad drivages the quantity available is getting low to effectively cut & bolt   Respirable dust failures  Noise is an issue also regulation of supply of air quantity ( ie always flat out)  Bord & Pillar  System requires a lot of maintenance and could benefit from more research to make it more robust  Two mines reported continued use of brattice ventilation 

3.28  1.03  Concurrent sumping, cutting and bolting (on continuous miners) 

Longwall  One mine noted that it was a standard provision with ABM20's and ABM25's, and as it was proven equipment application of the 

technology was not an issue  One mine reported the need to employ a high capacity fan to satisfy ventilation requirements , while two other mines reported 

dust control  as being an issue with concurrent operations  One mine noted that the current system would support while another noted that the current miners being employed did not allow 

for cutting & bolting simultaneously  Bord & Pillar  A mine utilising a continuous haulage system reported that it was still restricted by bolting cycle times, hence coal clearance was 

not an issue 3.28  3.06  Pedestrian interaction measures 

(coal haulage) Longwall  Currently relies on operators   Would greatly reduce the risk of machine pedestrian interaction  LED lighting and no go zones do not provided sufficient protection for pedestrians around shuttle cars  Managers transport roles  No go zones, if done practically  Mine site traffic rule   No Go Zone video produced and comprehensive training   Bord & Pillar  In our shuttle car panels no go zones are used to control movement around shuttle cars ‐ this is a procedural control and is of 

limited effectiveness. The continuous haulage system moves slowly enough that this energy source is greatly reduced and the control is more robust 

3.27  3.01  Shuttle car coal haulage system  Longwall  One mine reported it to be “tried and trusted” technology while another reported that they only use Joy shuttle cars, while 

another considered the current Highlander shuttle cars as ineffective and unreliable  Another mine reported that new 15SCs were ordered for July 2010 delivery, while another noted that a continuous haulage 

system was being considered as part of new suit of mining equipment   With the current focus of 2 cars per cycle the size of the car has increased. With this increased size it has introduced additional 

Page 35: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 31  

Score  No  Process Element & Technology  Comments from Respondents problems of operator visibility and size of intersections required to get car around safely 

Large cars have proven to be extremely unreliable  Operator comfort questionable Bord & Pillar  Same shuttle cars (15SC) for last 30 years   We use shuttle cars in some of our units in combination with the continuous haulage  Remove bottle necks   Some issues arising from electronic foot switches, safety and control   

3.03  3.25  Continuous haulage system  Longwall  The lack of a reliable system has hampered the introduction of continuous haulage systems.  Has a long way to go before it 

displaces the shuttle car  Needs to have more research done to simplify systems for Australian use and address reliability of past systems used in Australia    One mine noted that a continuous haulage was being considered as part of a suite of new mining equipment, while another noted 

that it was too complex for that operation    Current mine conditions would suit, however operator involvement would be essential   Bord & Pillar  Continuous haulage is the key to the future in my opinion ‐ current system carries ventilation, cables, hoses, and supplies,  and 

also hauls coal. System moves in a slow and controlled manner with little or minimum risk of somebody being hit or run over by it. It is the way of the future 

FCT proposed and installed May 2010 OEMs and Suppliers    System soon to be installed. No experience yet 

1.15  3.25  Maintenance accessibility and servicing 

Longwall  Two mines noted that it was difficult to gain access to some parts of the continuous miner, while access to an ABM was noted as 

very difficult at one mine  Machine design with OEM so components are modular and or compartmentalised and swing or slide in or out would help  Could always be better  Bord & Pillar   Two mines noted that access was difficult for maintenance/repair purpose  

4.03  3.25  On‐board or fan mounted dust scrubbers 

Longwall  Cut flit continuous miner in gateroad development  Have used the on‐board scrubber ‐  works very well in the cut and flit process Bord & Pillar  Place change mining system OEMs and Suppliers  Extremely effective when set up and operated correctly particularly for a place change application. Operators need to be 

meticulous with spray and screen maintenance. Ventilation needs to be set up to match the scrubber   

Page 36: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 32  

Score  No  Process Element & Technology  Comments from Respondents 2.09  3.24  Rib fall protection devices  Longwall 

Limited use due to the interaction with the rib bolter   Protection limited due to pinch points between guards and bolter rigs   Currently reviewing design to make them more effective. Have ROP's fitted to miners for rib protection    Needed as added safety device    Needs further development in high rib areas (loss of roof horizon) and when roof and rib bolting together   Rib protection fitted to all miners    Standard OEM system Bord & Pillar  Can still have rib failures as rib bolts are installed behind the roof bolter operators  

1.04  3.23  Auto‐cut facility of sumping and cutting action 

Longwall  This would enable auto profile cut sequences to be installed to enable machine to cut and repeat to the same defined standard 

and sequence. Benefit to operating standards and reduced abuse and damage to machine through operation error   Would help with horizon control    Consistency of roadway conditions    Further training required for operators to be aware of benefits   Geological conditions variable on this site   Two mines noted that such systems were not available on current machines in use, while a third noted  that it was being 

introduced on a new miner Bord & Pillar  Coal seam very variable and needs to be continually checked 

1.09  3.21  Operator display units (eg; cutting height, loads, etc) 

Longwall  Very difficult to read on our current machines. More user friendly displays required    Need better more visible displays.  Displays usually mounted well out of the miner driver’s field of view making it impractical to 

use effectively  Would be of benefit    The more the operators use this the better the cutting system becomes   More technology required  Bord & Pillar  Still have problems with horizon control   If combined with remote steering systems OEMs and Suppliers  Works well in Place Change applications so driver knows what is happening on the machine when it is under unsupported roof 

5.01  3.21  Face services manually handled on cable rollers and other devices 

Longwall  Manual system which requires operator interaction. Need to get operators out of system   Removal of manual handling tasks and risk of cable damage will reduce risk profile  Two different types of cable rollers already trialled to separate CM cable and water line  Rarely used except on some breakaways  

Page 37: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 33  

Score  No  Process Element & Technology  Comments from Respondents Bord & Pillar  Cost and flexibility have hindered acceptance of alternate systems  

7.01  3.20  Conveyor belting pre‐installed in LTU and extended on advance 

Longwall  Belt moves is where we need to improve process ASAP  Tension issues often increase the load required to be pulled by loader on boot end   Have tried however winch does not support process due to technical issues  Not used frequently due to installation standards of conveyor belts  Currently the mine has 2 full capacity LTU systems, with a third to be installed mid‐year which will allow belting to be pre installed 

in the development LTU   No LTU available on 1050mm development conveyor currently in use   Bord & Pillar  One mine reported small LTUs in use (13m capacity) while another reported that no LTU was used  

6.04  3.20  Mesh sheets manually loaded onto CM 

Longwall  Automated systems will reduce manual handling incidents   Risk of injury due to manual handling and pinch point.  Need to find something better    Manual and ergonomic issues    Two mines noted that a low seam height (2.8m) raised issues handling mesh   Roof height raises Bord & Pillar  Have trailed a number of methods but manual loading still quickest and most flexible 

2.04  3.18  Bolt storage cassettes or pods  Longwall   Ergonomics need work.  Still require a lot of man handling  Interaction of loading cassettes onto machine and ventilation system needs to be developed a lot further  Current system does not match process well. Cassettes regularly returned with rib bolts  Improvements would be welcomed    Racker system being introduced   New continuous miners are fitted with them   Roberts Rack system on the continuous miners  More pods required to allow loading off‐site   Cannot hold enough supplies. Mine does not have enough pods to run system   Bord & Pillar  Whilst we don't use cassettes we do load our bolts with a machine. Cassettes restrict the number of supplies the machine can 

carry (currently our machine carries over 100m of supplies ,not including mesh)   Issues with low height/clearance (2.4m) 

6.03  3.17  Boom lifting devices used to load bolting consumables onto CM 

Longwall  Ergonomics need work.  Still require a lot of man handling  Acceptance from operators due to low seam height 2.8m  Mesh carrier being fitted to CM now but is fixed into position and cannot be moved to load machine   

Page 38: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 34  

Score  No  Process Element & Technology  Comments from Respondents  Height is a challenge   Need to review and trial Bord & Pillar  Have tried a number of systems for loading mesh but currently still hand loading it works well  A rudimentary current system, would benefit with further  consideration of low height/clearance environments  (2.4m)  Used by some crews ‐ fairly basic system could be improved  OEMS and Suppliers  One location uses monorail mesh carrier to act as storage near cm and provide additional rib protection for operators walking past  Individual mines have developed/trialled different systems to lift mesh sheets onto CM's 

6.01  3.13  Bolting consumables manually loaded onto CM 

Longwall   Automated systems will reduce manual handling incidents  Pod very high on side of CM ‐ too high  with consumables   Manual loading was consistent, if not the fastest and there were no issues with how the miner was positioned   All bolts loaded on by hand  Some crews prefer to manually load materials   Although our system allows for cassettes to be changed crews still manually load miner as they believe it is safer and more 

effective  Racker system on site and being investigated to get into service   New Darby Pods being trialled  Bord & Pillar  Old fashioned and labour intensive   Cut and flit ‐ bolts not loaded on miner    Flexibility of alternate systems‐variable roof/working heights  

7.03  3.11  Device/s used to install structure  Longwall  Will reduce manual handling    Technology    Two mines noted that all structure is handled manually  as did one Bord & Pillar mine OEMS and Suppliers  Offered on feeder breakers and continuous haulage 

6.05  3.09  Mesh sheets loaded onto CM with boom or racking device 

Longwall  Automated systems will reduce manual handling incidents    Jib onto the mesh carrier.  Room for improvement, particularly on Joy equipment    Roberts jib used very effective    Review and trial needed   

4.02  3.09  Monorail mounted ducting  Longwall  Concertina ducting used on monorail application had higher resistance and provision of sufficient air to the face is problematic   Half assed attempt to introduce the system with a limited number of rails and duct.  Meant that more time spent pulling apart and 

advancing.  Poorly organised and thought through, pretty much killed it before it was born 

Page 39: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 35  

Score  No  Process Element & Technology  Comments from Respondents  Size of shuttle cars doesn’t allow   System is inefficient without 2:4:1 mining. Vent tube extension creates a 30m unventilated stub OEMS and Suppliers  This is relatively new technology and proven results are only just being delivered to the market.  We have had a strong enquiry on 

this product and believe with more operator awareness it will become more readily adopted  CES Monorail system with flexible vent  ducting reduces injuries from handling elephant trunk and fixed tube lifting, improves 

advance rate as less need to stop to install ventilation, extremely low maintenance, allows storage of material close to miner that moves with miner, relatively light to handle, recycle rails and long cycle life increases profitability of operations, multiple use applications when left in place. 

2.08  3.08  Roof fall protection devices  Longwall  In bad roof condition the ABM TRS is difficult to get to roof particularly if the roof cavity has only developed on one side of the 

heading which in our case is usually the case   Not as effective on a Joy as the machine is generally in motion.  Elephant’s feet have minimal impact compared to the ABM TRS 

set‐up  No position monitoring on TRS cylinder while timers built into program slows the operation of cut / bolt sequence  Five mines reported using TRS, ranging from Version 1 to ones meeting MDG guidelines, with another in process of installing TRS 

on miner Bord & Pillar  Becomes ineffective in cavities around faulted areas  Timber jacks on bolting rigs, activities under mesh/supported roof    Canopy on mobile bolter   OEMS and Suppliers  Joy offers MGD35 compliant TRS system 

2.07  3.06  Manual tendon/cable tensioning  Longwall  Would be better if it could be incorporated into the bolt so that the current rigs can be used to pretension without the need to use 

additional equipment     Current systems available to us are manual type tensioners. Although they are effective they are causing our operators a lot of 

injuries due to weight and mode of operation   Manual handling issues need to be addressed, similar to on board set‐ups  Tensioner is heavy   Reduces manual handling   Secondary support completed independent of mining process. it is only if ground deteriorates that secondary support id installed 

from the miner Bord & Pillar  Used in conjunction with hand bolting   New tendon being tested that doesn’t require tensioner  

5.02  3.00  Monorail mounted services  Longwall  Size of shuttle cars don’t allow  

Page 40: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 36  

Score  No  Process Element & Technology  Comments from Respondents  Bord & Pillar 

Basic manual system    Used outbye of boot  OEMS and Suppliers  This is relatively new technology and proven results are only just being delivered to the market.  We have had a strong enquiry on 

this product and believe with more operator awareness it will become more readily adopted   Mines that use pipe monorails end up using it extensively as it is light and multipurpose ‐ reduces injuries, improves operational 

effectiveness. Carries ventilation, cables, hoses, stores, pumps, etc 1.01  3.00  Remote control operation of CM 

functions (eg; radio)  Further research required to provide effective barriers to personnel entering No‐Go Zones during operation  Still development required particularly from a dead man point of view    User friendly units including size    Prefer Pempek system to Joy Jana for reliability and simplicity and avoids costly upgrades at overhaul    Can go flat, chargers underground may help  Bord & Pillar   Currently unable to record keystrokes of the remotes functions. If this information became available, unintended activation events 

could be confirmed as real events or operator error. Saving hundreds of hours of engineering resources, researching problems that may not exist   

Currently having issues with software on the Joy 1232CM giving unplanned movements Still some issues with stuck spools    Still some issues with unplanned movements, ie;  time taken to accurately analyse causes    A lot of issues with remote systems on Joy miner needs to be simpler and more reliable  Make remote control units smaller OEMS and Suppliers   Joy is currently working on new generation of handheld remote  Improve ergonomics of the transmitter 

8.03  3.00  Purpose designed maintenance support vehicles 

Longwall  Utilise conventional SMV dual cab ute with Hiab crane on board    Mainly utes with Hiab    Would be great at mine Bord & Pillar  Maintenance MPV pods used    SMV Utes with Hiab   

2.06  3.00  On‐board tendon/cable tensioning 

Longwall  Light weight tensioning units should be an urgent target for the industry.  The risk associated with the high pressure fluids in close 

proximity to the operators is also an area that could be addressed  Too heavy currently and requires operator to lift the device normally above their head  Hydraulic swap on fittings   Double acting ram required   Improvement in design and weight required  

Page 41: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 37  

Score  No  Process Element & Technology  Comments from Respondents  Unreliable   Reduces manual handling   Secondary support completed independent of mining process. it is only if ground deteriorates that secondary support id installed 

from CM  Bord & Pillar   No problems with this system works well, however tensioner is heavy and can get jammed on bolts. Still a certain amount of 

manual handling in lifting tensioner to bolts, etc 4.04  3.00  Auxiliary fan mounted on mobile 

boot end or monorail Longwall  Need to review and trial   Large, heavy structure once suspension attachments are added to fan structure 

1.08  3.00  Scrolling head assisted loading  Longwall  Unavailable for J35 pick block configuration on centre drums   Joy Miners with scrolled head currently in service and performance is better than the standard cutter heads   Only used on one miner at this time, power requirements higher than standard head    Research for application on ABM    Not available on present machine    Need information before assessing the benefits    Reduced the number of moving parts   

2.03  3.00  Roof mesh racking system on CM  Longwall  Ergonomics need work.  Still require a lot of man handling  Acceptance from operators due to low seam height (2.8m)  Mesh carrier being fitted to CM now but is fixed into position and cannot be moved to load machine     Height is a challenge   Need to review and trial  Bord & Pillar  Have tried a number of systems for loading mesh but currently still hand loading it as it works well  A rudimentary current system, would benefit for low height/clearance environments  (2.4m)  Used by some crews‐fairly basic system could be improved  

1.14  3.00  Operator access and egress (on continuous miner) 

Longwall  Access on and off the machines are regularly damaged during flitting. Egress on and off the machine has caused injuries in the past  Machines are becoming larger and legislation requirements are becoming more stringent (eg; working at heights). Also egress 

from machine on regularly bases difficult but in case of injury or sickness (operators on stretcher) it is almost impossible  Access systems are notorious for damage.  Once damaged they are discarded.   Had a number of injuries with the egress off CM  Access is always a challenge    Incorporate rear step to platforms    Better designs required   Operator platforms fitted to remove men from working on ground and pinch points next to miner if slewed  

Page 42: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 38  

Score  No  Process Element & Technology  Comments from Respondents  Have walking platforms  Platform on ABM  New CMs have big improvements   Most efficient, little interest in research Bord & Pillar  Only site‐added platforms, very basic 

6.08  3.00  Bulka bags used to transport stonedust 

Longwall  No so much the bulk bag but what equipment (bulk dusting and trickle dusting) is used in association with the bulk bag   Loading into dusters only issue  We have manufactured a bulk device for behind the auxiliary fan that holds 4t of stone dust   Pneumatic systems are the way of the future for stone dust handling Bord & Pillar  Lots of wastage due to difficulty of loading duster in low seam   

6.06  2.94  Individual pods or cassettes transported throughout mine 

Longwall  Method of transporting numerous pods   Pods are only for transport ‐ they don’t go on the miners  QDS pods with multiple cassettes transported through the mine   Roberts’s system implementation will eliminate this  Cassette trailers with the ability to carry 4 bolting cassettes   Not the prime method of pod transportation   Bord & Pillar  MPV pods are used with all bolting supplies incl. Mesh loaded into using forklift  

8.01  2.93  PJB/SMV style personnel transporters 

Longwall  Safety aspects and passenger ergonomics required to reduce injuries   Introduced the forward and rear facing seat configuration to be compliant with corporate standards  Good on good roads, suspension not designed for rough going   Availability, ergonomics and performance Bord & Pillar  Converted Mazda utes are used  

6.02  2.93  Racking devices used to load bolting consumables onto CM 

Longwall  Rackers are the preferred method for changing out bolt pods   Working extremely well   The racker requires the CM, LHD and pod to be perfectly aligned.  In the conditions we were in this was never going to happen.  

Was quicker to manually load then waste time with the racker.  Couldn't fit a pod in one pass, had to stop and adjust every time  Used previously, and taken out of service due to damage on cassette frame and maintenance costs on racker jibs   Please research  

5.06  2.92  Powered water hose reels used for storage of hoses 

No observations made 

Page 43: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 39  

Score  No  Process Element & Technology  Comments from Respondents 5.07  2.90  DCB mounted on mobile boot end 

or monorail Longwall  Review and trial  needed    Currently DCB is mounted on QDS sled for LHD management. This has occurred in the last 12 months   Lifting bracket attached to the top for easy repositioning. DCB set up on timber and levelled as per mine Development Standards Bord & Pillar  DCB is mounted on the continuous haulage  Looking at monorail for this  

1.12  2.88  Automated lubrication systems  Longwall  This will improve machine reliability     Trades and operators find this item very useful   Only used on one CM  Would have to prove integrity   When system fails has been hard to find not working until it is too late OEMS and Suppliers   Issue is that there is no way of checking if lube is getting to where it should get to 

6.07  2.87  Trailers used to transport multiple pods or cassettes throughout mine 

Longwall  With rapid advanced required for gate road development this task is drain on operators & resources  Currently looking at this   Pairing frames will be used with the Roberts system  OEMS and Suppliers   Under consideration as additional service / supply to facilitate operational flexibility 

5.04  2.86  Cable/hose boats used for storage of cables and/or hoses 

Longwall  Cable boat system provides good protection    All boats to have QDS   Use cable pullers on cable boats  Only using basic version of boats   If this was in a monorail cassette system / reeler   Review   Bord & Pillar  Use cable boats for main service lines to the DCB (gate end box) which travels on the continuous haulage OEMS and Suppliers   Can be LHD mounted or fork mounted 

3.02  2.78  Battery/diesel hauler haulage system 

Longwall  This type of haulage gives better flexibility and is able to be used on long wheels   Could be used on face road applications  Battery life and DII conditions of use around charging stations need resolution  OEMS and Suppliers   Heat and filter life on the diesel. Battery life on bad floor conditions and battery handling infrastructure 

Page 44: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 40  

Score  No  Process Element & Technology  Comments from Respondents 1.07  2.77  Plough shovel loading 

configuration  Joy 12CM30 with plough and scrolled head currently in service and performing well. Geological conditions have not yet been 

allowed the plough miner to show its true advantages    Bad roof conditions may benefit with a plough ‐ not cleaning up  Shovel angle on ABM25  too steep  Better clean up required ‐ some mods made to shovels to try and correct    Improved shovel design from a cleanup point of view would be useful    Need to be developed to a point where load out rates approached spinner type loading 

1.05  2.77  Rotating arm/spinner loading configuration 

Longwall   Better loading system on CMs – ABM25 shovel too steep    Better clean up required ‐ some modifications made to shovels to try and correct    Good strata supports this operation    ABM access for maintenance very difficult    Used on ABM's and preferred by operators due to their quicker load‐out rates  System is high maintenance and if not managed well is unreliable.  If the seam has stone rolls of bands these jam in the E/W 

chains with regularity  1.13  2.74  Area lighting systems (on 

continuous miners) Longwall  Intrinsically safe LED area lighting would be worthwhile.  Lights on most of our machines have been around for some time. Newer type lights have been observed but need incorporating 

into Coal cutting machines  Has been requested frequently    Any improvement to lighting is welcomed    Adequate Bord & Pillar  Headlights only very basic  

3.04  2.70  Breaker feeder used to size/load coal onto conveyor 

Longwall  Unable to tow breaker feeder with LHD's when moving from panel to panel ‐ Power tram required very slow and expensive   Used solely in mains development with high proportion of stone drivage    Need to match car and conveyor capacity    Used as a tool to provide slower feeds onto under‐performing belts  Soft coal didn't require a feeder  Bord & Pillar  We used a number of feeders as well as a breaker in the throat of the ABM25 continuous miner which works extremely well  Stamler feeder used  

1.06  2.64  East/west chain loading configuration 

Longwall  Closes up the bolt to face distance but struggles in anything other than clean coal  This is a very poor system on Joy 12CMs. It is atrocious at loading out stowed coal and when cutting dyke material. The objective 

of bolting close to the face is achieved by spinner discs much better  Not effective in slurry conditions  

Page 45: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 41  

Score  No  Process Element & Technology  Comments from Respondents  Have worked on CM's with this configuration before ‐ they were very unreliable  Not best option for our current roof support however could benefit with a change in conditions    Had on previous machines and further development would be required in the area of loading out wet clay based material    Used on two JOY 12CM30, but CLA is preferred OEMS and Suppliers   Joy offers the plough exclusively E/W no longer offered 

2.05  2.60  Bolt washer dispensers  Longwall  If the bolting system could be fully automated to self load and drill    More technology required    Not included as considered to be "just something else to break" ‐ simple spike used instead  Metal posts on miners used for storage   Proposed to fit to new CMs Bord & Pillar  Take up a lot of space in the platform area may be able to better utilise   Basic peg system only 

5.05  2.56  Cable/hose boats hydraulically powered as required 

Longwall  Cable pullers on cable boats and hydraulic cable reeler available    Concept took some time to gain acceptance in operations  Currently use storage boats but no hydraulic assistance    Review  OEMS and Suppliers  Reduction in cable/ hose damage from better storage practices, improve handling risks, and all pits would use them 

8.02  2.43  Approved NERZ “troop carriers”  Longwall  These will assist in reducing op costs but increase the electrical control systems around the mine to implement  Bord & Pillar  Hindrance by inspectorate preventing their use  

Page 46: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 42  

 Table 6: Key Factors Contributing to the Successful Introduction of New Technologies and Processes – Mine Responses 

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES RANK  SUCCESSFULLY INTRODUCED TECHNOLOGY &/OR PROCESS  1  2  3  4 

1  Tendon installation of the front of the miners without the use of hydraulics  

Operators involved in the change process 

Operators understood the safety advantages of the introduction of the tendons 

   

1  Waracar (shuttle car)   Planning  Training     1  Cable Winder   Reduce manual handling  Less cable damage  More efficient ( greater 

productivity  

1  Robo Pods for structure   Structure is preassembled ready to be hung off chains 

Easy of handling   Speed of erection  can be loaded on surface off critical path 

1  8mt Spin Bolts   Gradual introduction  Ongoing improvement  Proven increased roof stability  Workforce participation/input 1  Currently introducing racker 

system  (Not fully introduced but being implemented) 

     

 1 

Ergonomics of shuttle car design   Operator comfort       

1  Autocut on ABM   Reception from crews  Method of introduction  Key personnel   1  Two handed bolter operations on 

ABM 20 miners  Imperative to change clearly understood by stakeholders 

Evolutionary improvement from initial concept  

Ability to incorporate improvements into subsequent CM rebuilds 

Technologies incorporated able to be supported at site 

1  Two handed operation on drill rigs         Forced into the industry 1  Onboard ventilation on Joy miner   Reduced frictional ignition risk  Reduction in respirable dust 

samples.    

1  Smaller ventilation ducting (from 720mm to 620mm)  

Ease of flitting miner and no reduction in air quantity to face 

     

1  Longwall Top Coal Caving   Clear economic benefit to be gained from the introduction of the equipment 

Company committment to the project 

Designated team focused on the delivery of the system 

 

1  Mesh handling system  Design and planning  Training package  User input after implementation  Design Improvements 1  Onboard tensioners  Reliability  Less work on men  Availability   1  Continuous haulage system 

(Prairie) in conjunction with ABM25 

Haulage is no longer a restriction to production and men are not at risk of machines such as shuttle cars and ram‐cars coming into contact with them 

All services including ventilation are carried on the machine – requires no manual handling of ventilation tubes, cables or hoses 

Bretby system also reduces the need for a DCB to be handled as it is carried with flexible conveyor 

 

1  Wide‐head continuous miner with on‐board bolting rigs 

Removal of manual handling of hand held roof bolters 

Control of strata with the ability to erect roof mesh to provide safe work place 

Systematic mining process leading to predictable work 

Risk assessments used to remove foreseen hazards prior to introduction of the equipment 

Page 47: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 43  

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES RANK  SUCCESSFULLY INTRODUCED TECHNOLOGY &/OR PROCESS  1  2  3  4 

1  TRS on overhauled Joy 12CM12  “Product Champion” who smooths the path for introduction, explains and persuades the workforce, then arranges training and finally sees it through to successful conclusion 

Employees perceive a genuine benefit. They need to have it explained to them and ideally, feel they are “involved” in the process of introducing the technology 

Management perceives a genuine benefit. Remove or restrict any resource that is required and the technology will “wither on the vine” 

Legally necessary or required to keep the business operating successfully 

1  Monorail cable handling  Desire to reduce cable damage and back injuries 

     

1  Multi‐bank loop   Belt storage  Advance and retraction rates  Maintenance  Flexibility 2  SIL Rated Shuttle Cars   Proven equipment  Use of new technology   Accepted up‐grade  Workforce participation/input 2  Belt structure pod system  Reduce manual handling  Operator acceptance high  More efficient ( greater 

productivity       

2  Darby Pod   Supplies taken to rear of machine   Ease of handling  Can be loaded on surface   2  Development of monorail   Reception from crews  Method of introduction  Key personnel   2  Nitrogen Goaf Seals   Clear safety benefit that was 

readily demonstrated Simple concept that was logical in its application 

Focused individuals working on the project 

Excellent monitoring and analysis to prove the performance of the system 

2  Currently introducing telemetry and visual display  

       

2  Forward and rear facing seat configuration in SMV Driftrunner  

Imperative to change clearly understood by stakeholders 

Concept to implementation planning well conducted 

Detailed engineering to desired specification 

Prototype used to fine tune improvements 

2  Supply system ‐ 24m supply cycle to miner  

       Crews still coming to terms with this process 

   

2  Bulk fan duster behind the auxiliary fan  

1       

2  Panel ute   Supply shortfalls  Work Platform     2  Cameras on shuttle cars  

 increased vision on off side                      

2  Hilti bolts   Positive feedback from all       2  Self drilling rib bolts Hilti  One step function  Quicker  Less exposure to injuries   2  Mobile bolter  “Product Champion” who smooths 

the path for introduction, explains and persuades the workforce, then arranges training and finally sees it through to successful conclusion 

Employees perceive a genuine benefit. They need to have it explained to them and ideally, feel they are “involved” in the process of introducing the technology 

Management perceives a genuine benefit. Remove or restrict any resource that is required and the technology will “wither on the vine” 

Monetary gain to both the business and employees (production bonus) 

2  Auto‐cut sump on CM  Training package  Ongoing training and technical support 

User acceptance  Improved results ‐ visual 

2  Monorail   Manual Handling  Reduced cable damage  Advance and retreat rates  Routine ‐ regular 

Page 48: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 44  

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES RANK  SUCCESSFULLY INTRODUCED TECHNOLOGY &/OR PROCESS  1  2  3  4 

3  Self Drilling bolts   Reception from crews  Method of introduction  Key personnel   3  Monorail Systems   Improvement on manual handling 

of cables and hoses Increased production rates  Reduced injuries  Workforce participation/input 

3  Auto lube pod   Reduce manual handling  Higher staandards in panel  More efficient ( greater productivity 

Less wastage 

3  Adopting good practise and panel standards in development  

Involvement of crew and disputes  Crew presentations, input and feedback 

Building of team environment  With every pair of hands you get a free brain approach 

3  Hydraulic legs on auxiliary fan for levelling‐ hand pump to operate  

  2     

3  Change to man baskets   Ease of having two men in basket concurrently 

     

3  Hydraulic cable boats   Robust construction  View of how being used by others     3  Plough apron          Reduction in support to face 

distance    

3  Equipment designed for process  increase production                      3  Remotely operated outburst 

mining system “Product Champion” who smooths the path for introduction, explains and persuades the workforce, then arranges training and finally sees it through to successful conclusion 

Employees perceive a genuine benefit. They need to have it explained to them and ideally, feel they are “involved” in the process of introducing the technology 

Management perceives a genuine benefit. Remove or restrict any resource that is required and the technology will “wither on the vine” 

Legally necessary or required to keep the business operating successfully 

3  Razor dusters (Bulk)   One man function  Less exposure to injuries  Reliability   3  Concreting travel roads   Travel times  Safety  Standards  Reduced vehicle damage 4  Continuous Miner Platform design 

to compliment the bolt pods – ergonomically designed  

1       

4  Duck Bill Supply Pods  Improvement on manual handling of dust & oil 

Reduced waste   Visible benefits to workforce  Workforce participation/input 

4  Monorail mounted services  Well regarded by operators ‐ makes life easier 

Simple process steps to make work 

Low maintenance   

4  Equipment acceptance by workforce 

Workforce involvement                      

4  RTM monitoring                Ability to compare production reports against actual machine movement 

Potential process mapping and improvement tool 

4  QDS boot ends   Safer job procedure  Less work on men  Quicker process   

Page 49: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 45  

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES RANK  SUCCESSFULLY INTRODUCED TECHNOLOGY &/OR PROCESS  1  2  3  4 

4  Battery powered Una‐haulers  “Product Champion” who smooths the path for introduction, explains and persuades the workforce, then arranges training and finally sees it through to successful conclusion 

Employees perceive a genuine benefit. They need to have it explained to them and ideally, feel they are “involved” in the process of introducing the technology 

Management perceives a genuine benefit. Remove or restrict any resource that is required and the technology will “wither on the vine” 

Benefit of eliminating potentially carcinogenic diesel exhaust fumes and quieter to operate than diesels 

4  Ratio feeder (Joy)   Increased capacity  Improved technology  More robust   5  Belt A frame with retarder    2     5  TRS on miners  Increased safety from roof fall                5  Miner Supply Pods.  Improvement on manual handling 

of supplies Ongoing improvement  Visible benefits to workforce  Workforce participation/input 

5  Control room   Communication  Information and reporting  Mine monitoring  Safety 

 

Table 7: Key Factors Contributing to the Successful Introduction of New Technologies and Processes – Mining Contractors 

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES RANK  SUCCESSFULLY INTRODUCED TECHNOLOGY &/OR PROCESS  1  2  3  4 

1  Cassettes and racker on miner  Few people pushed it       1  Simultaneous cutting/bolting   Good engineering  Good idea     1  Cable handlers  Operator consultation and 

feedback Tradesman initiative  Strong skills base  Management's encouragement to 

increase productivity through design initiative 

2  Machine mounted rib support  Customer buy in  Well engineered     2  Traction overloads on shuttle car  Operator consultation and 

feedback Tradesman initiative  Strong skills base  Management's encouragement to 

increase productivity through design initiative 

3  Lifting bracket attached to DCB  Operator consultation and feedback 

Tradesman initiative  Strong skills base  Management's encouragement to increase productivity through design initiative 

3  Remote operation of miner  Well engineered       4  Jig made up to remove cutter 

motor on miner Operator consultation and feedback 

Tradesman initiative  Strong skills base  Management's encouragement to increase productivity through design initiative 

5  Jig made up to put up 4", 6" and 12" pipes with man basket. 

Operator consultation and feedback 

Tradesman initiative  Strong skills base  Management's encouragement to increase productivity through design initiative 

 

Page 50: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 46  

 Table 8: Key Factors Contributing to the Successful Introduction of New Technologies and Processes – OEMs and Suppliers 

Key Factors Contributing to the Successful Introduction of New Technologies and Processes Rank  Successfully Introduced Technology &/or Process  1  2  3  4 

1  QDS Bolting Platform  Practical substitute for units already in service 

More user friendly  Good operator acceptance  Extensive paperwork packages supplied with equipment. 

1  B&W tensioned TDG cable   Install of the miner  Paid tensioning  Top down post grouting  60t capacity 1  Long Tendons   Ease of instillation  Cost   Improved performance   1  Introduction of the Airo‐duster 

trailer  Equipment designed and built fit 

for purpose The design criteria could be 

maintained without sacrificing the fit for purpose requirements. ie 

Aust standards and MDG's did not change the preferred design 

Large benefits to the end user to try new technology. A borderline new technology is hard to justify  

Buy in from all levels and introduction to site following site 

procedures. 

1  Cassettes and rackers for supplies  Champion to push the innovation  A product that makes it easier for personnel 

   

1  Rapid Advance Development Monorail System   

Personnel taking ownership of system 

Operator Input to all design components 

Operators have full understanding of system benefits 

System design to specific mining conditions/parameters 

1  Optidrive controls on CM   Joy's test and validation process prior to going to market 

Joy Flawless start process applied to all new product development or introduction into new markets 

  Joy's ongoing  service & engineering support 

Joy's parts & component repairs support 

1  ToTo device ‐ Threaded cable bolt fitting tensionable by rotation off a bolting rig. Complete elimination of hydraulic tensioners off the miner, only requires a tightening spanner 

Industry focus on OH&S, being prepared to spend the extra $$ on 

products to reduce injuries 

The product speeds installation of cables at the face. Leading to 

increased use of cables at the face to control very poor roof ‐ 

Geotechs have always wanted but operations have fought them as it 

slows them down 

Price of coal is high, or else is would have been less likely for the industry to adopt a significantly 

more expensive product 

Product sourcing from China is becoming more accepted and can keep the cost of very complex 

components low in comparison to Australian made ‐ unfortunately. 

1  Monorail mounted flexible ventilation ducting 

Reduced manual handling injuries  Changes resupply / operational distruptions to restore air flow 

Improves operational activities with increased advance speed and 

lower costs 

Reduced cost of operations 

1  Remote controlled miners  Initial installations were for place change or where machines were in 

dangerous Areas 

Benefits were recognised in the simplification of the control 

system and better diagonostics improved machine reliability 

Drivers pit area utilised for other    

1  T‐REX  Ease of operation  Manoeuvrability/Versatility   Increased worker safety   1  Tracking Systems  An on‐site "champion" at the mine 

that has the vision and authority to ensure the equipment is 

installed and utilised. 

Technology is fundamentally sound and proven in mine use 

Service and support is provided by OEM and accepted from mine 

Workforce training & acceptance 

1  New Supamix water based resin capsule 

y       

Page 51: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 47  

Key Factors Contributing to the Successful Introduction of New Technologies and Processes Rank  Successfully Introduced Technology &/or Process  1  2  3  4 

2  Cable tensioning  Improved Performance  Operator acceptance     2  New break out fibre glass rib bolts              2  Two‐way mobile communications  Ensuring the communication 

backbone, often the same backbone used for tracking, is well designed, installed and maintained 

An on‐site "champion" at the mine that has the vision and authority 

to ensure the equipment is installed and utilised. 

Service and support is provided by OEM and accepted from mine      

Workforce training & acceptance      

2  Monorail mounted cables and hoses and gate end box 

Reduced manual handling injuries  Reduced cable / hose damage or contamination 

Reduced cost of operations and increased flexibility in operations 

      

2  Long life poly‐sheathed cable in clay 

HDPE Sheathing  Drills for clayey ground  Toe/collar grouting  Tension able 

2  Optidrive shuttle cars  Test and validation process prior to going to market 

Joy Flawless start process applied to all new product development or introduction into new markets 

  Joy's ongoing  Service & engineering support      

Joy's parts & component repairs support      

2  Self Drilling Roof Bolt System  Extremely fast bolting times  Ease of operation  Reduced manual handling   2  Scrubbers on miners  Mine was committed to make it 

work so that place change systems would workat all levels 

OEM committed to improvements   Mine was willing to maintain system 

mine kept working to improve systems 

3  Resin Technology  Improved performance  Cost     3  Quickduster  Improved performance  Ease of maintenance     3  ICM2 2 handed controls   Test and validation process prior 

to going to market Joy Flawless start process applied to all new product development or introduction into new markets 

  Joy's ongoing  Service & engineering support      

Joy's parts & component repairs support      

3  Monorail mounted pumps and equipment  

Improved operational flexibility and equipment maintenance 

Reduced labour needs and reduced manual handling injuries 

Improved access to equipment for maintenance  

 

4  14ED25  Test and validation process prior to going to market 

Joy Flawless start process applied to all new product development or introduction into new markets 

  Joy's ongoing  Service & engineering support           

Joy's parts & component repairs support           

4  High strength bearing plates  Improved Performance  Cost     5  Rapid Face bolters  Test and validation process prior 

to going to market Joy Flawless start process applied to all new product development or introduction into new markets 

  Joy's ongoing  Service & engineering support           

Joy's parts & component repairs support           

5  Cassettes/Pods  Reduced handling  Cost     

 

Page 52: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 48  

 Table 9: Barriers or Factors Impacting the Introduction of New Technologies and Processes – Mines 

BARRIERS OR FACTORS IMPACTING THE INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES  RANK 

IMPACTED TECHNOLOGY AND/OR PROCESS  1  2  3  4 

1  Cable Winder  Cost       1  Machine system approvals around 

electrical and electronic implementation 

Certification and conformity approval 

OEM willingness to embrace new technolgies 

Mine sites and OEM ability to partnership new technologies 

Operator acceptance of new systems 

1  Waracar   OEM going into receivership   Size (getting car into our mine)  Car not fully developed (traction in our road conditions) 

      

1  Remote steering / video  Cost of change across mine  Workforce acceptance  Need Vs practicality  Operational suitability 1  Miner to surface communication  OEM design                      1  Continuous Haulage  Cost high‐ unproven Technology   Resistance to be the first to try     1  Racking system for supplies  Not well suited for the mines 

conditions made it difficult to use.  Was not well accepted by the crews 

Introduction to site did not include engagement with the workforce.  Was just dumped on them. 

   

1  Monorail mounted ventilation  In pratice ventilation outcome did not reach modelled predictions 

Not sufficiently robust for environment 

Operational tolerance too tight wrt current operational controls 

Operator acceptance undermined 

1  Culture Change         1  MBE    Auxiliary fan placement in gate 

roads OEM contract issues   

1  CM cable monorail  Lack of a "Product Champion" who smooths the path for introduction and sees it through to successful conclusion 

Employees do not perceive a genuine benefit 

Lack of genuine management support resented by employees eg because excessively stiff hose not replaced to make the operation physically easier 

      

1  Coal clearance  Reliability  Cost  Geological conditions   1  Cassette rack system  No OEM supprt  Poor design/not suited to miner  Poor quality of implements  Operator acceptance due to 1,2,3 1  Wet stone dusting  DPI  Training  Reliability   2  Automated continuous haulage 

that remove operators from the cutting machine 

OEMs have been approached in 2009 to work on this and it is all too hard 

Corporations willingness to invest  Design, lead time and risk assessments could take 5 years 

Operator acceptance of new systems 

2  Belt structure pod system  Correct design  Operator acceptance poor due to culture and lack of involvement in original design 

Initial training / competency Package was not user friendly 

 

2  Concurrent cut / bolt  Cost of change across mine  Has been trialled but failed  System proven prior to use  Operational suitability 2  Monorail mounted vent duct  Small scale trial meant constantly 

having to move rails.  No benefit was readily apparent 

No way of monitoring if there was a benefit gained from the system 

commissioning issues put the crews off side, never recovered after that 

 

2  Juggernauts  Reliability and noise                      

Page 53: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 49  

BARRIERS OR FACTORS IMPACTING THE INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES  RANK 

IMPACTED TECHNOLOGY AND/OR PROCESS  1  2  3  4 

2  Proven Technology         2  Monorail vent ducting    Flexile tube length  Timely instillation process   2  SMV  Design  Seat restraint  Seating arrangements  Safe speed 2  'TG' Bolts ‐ Secondary support  Design Details  Little OEM support to installers  Process step issues/training   2  Self drilling bolts (roof and rib)  cost       3  Monorail ducting  Fitting into current process  Infra structure required   System proven prior to use  Suitability in wet conditions 3  TG 4m cable bolts  To ridgid for miner installation ‐ 

increased manual handling injuries                     

3  Fully automated bolting system  Self loading cassettes  Bulk of rig systems  Design  Operator acceptance of new systems 

3  Auto lube pod  MDG Guidelines  Supporting services to run  Storage when not in use   3  Approved Processes         3  Fully Automated Bolting on CMs  Cost high ‐ unproven Technology   Resistance to be the first to try     3  Mobile Boot  Tracking  Tensioning  Control of boot end  Lanyard? 3  Road base material  Technology       4  MDG41 2 handed bolting 

operation Increases the risk to exposure of roof fall 

                    

4  DCB onto monorail  Fitting into current process  DCB dimensions & weight  Too many process changes  Monorails to be used / installed 4  Bolt storage BDS  Capacity  Manual handling  Design  Ancillary equipment 4  Automation of machines  Technology  cost     5  23m/3 aux fans / slow speed  Vibration /heating issues and  

decreased mobility                

5  6.5 – Mesh onto CM boom   Low cutting height across mine in comparison to miner height. Limits number of modules on miner while cutting. 

Need for new equipment   Need for revised transport system  Variables with roof support needs if expanding extracted roadway height. 

5  CM Operation  Configuration of remote controls  Visibility  Maintenance of roadway profile (Horizon / alignment) 

 

 

Table 10: Barriers or Factors Impacting the Introduction of New Technologies and Processes – Mining Contractors 

BARRIERS OR FACTORS IMPACTING THE INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES  RANK 

IMPACTED TECHNOLOGY AND/OR PROCESS  1  2  3  4 

1  Flexible conveyors  Cost of trials                      1  Monitoring of equipment 

performance  The lack of an integrated system that included real time data collection and transmission to the surface reduced the effectiveness of the utilisation of the data that was collected. Lesson ‐When introducing new technology look at the complete process. The introduction of only part of the total process may result in the failure of the individual element even if the element itself was effective.  

2  Self drilling bolts  Lack of participants  Lack of supplier support               

Page 54: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 50  

 

Table 11: Barriers or Factors Impacting the Introduction of New Technologies and Processes – OEMs and Suppliers 

BARRIERS OR FACTORS IMPACTING THE INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES  RANK 

IMPACTED TECHNOLOGY AND/OR PROCESS  1  2  3  4 

1    People resistant to change       1  Introducing the Airo‐Dusting 

process Non specific legislation/ regulations for introducing this new technology 

Final approval rests with an organisation that is diffucult to engage and be proactive 

Organisation of a major stake holders to invent new regulatory guidelines as a part of the research project  

Risk of final approval not being granted for reasons not brought to the table during the project 

1  QDS Bolting Platform  MDG Compliance  Acceptance of operators to two handed operation 

Non uniform site requirements from site to  site 

      

1  Longwall recovery mats  Reluctance to chance  Poor understanding of specifications 

   

1  Supamix water based resin capsule         Only two mines adopted new water based Supamix resin system, disappointing. Despite cost saving and benefits, reluctance for mines to change, not sure why. 

   

1  Proximity Detection  Techical barriers in making a coal mine approved system.  Some elements are already approved or simple to do so, but others are technically challenging 

Resource  limitations and other development priorities 

Where interface to large equipment (e.g. c/miners) it takes time to get onto right contact within the OEM and to gain their confidence. 

 

1  B & W tensioned cable  Miner shape unsuitable  Operators unwilling  Operator Fitness   1  Rapid advance development 

monorail system  Low Roadway height                Operator acceptance 

1  Monorail mounted pipe installation 

Operators not following instructions on operation or inadequate instruction on process 

Operator attitude to different method / way of performing activity ‐ need for training and explanation on objective / reason for change  

Adequate compilation and preparation of processes to be followed and training thereon  

 

1  Self Drilling Roof Bolt System  Incomplete underground testing       2  Monorails in development panels  Operators see new equipment as 

another activity to be perfomed, rather than being trained / educated on the benefits from using the monorail and how it reduces their personal risks and workloads 

Benefits from use not explained to operators so they don't appreciate the favourable impact that monorails may deliver on their own work activities 

Lack of Education on how they can utilise the monorail system to reduce their manual handling and associated risks  

  

2  Self Drilling bolts  Cost  Poor understanding of process     

Page 55: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 51  

BARRIERS OR FACTORS IMPACTING THE INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES  RANK 

IMPACTED TECHNOLOGY AND/OR PROCESS  1  2  3  4 

3  Monorail in service support activities  

Lack of education / information on how they can reduce their manual handling risks or improve their work enviroment 

Lack of information on how monorail may improve their operational flexibility or access opportunities 

   

 

Table 12: Major Barriers to the Successful Research, Development and Introduction of New Technologies – Mines 

MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES RANK  PRIORITY RESEARCH ELEMENT 1  2  3  4 

1  Self drilling bolts         Cost and size     1  Timely delivery  Funding  OEM involvement  Mine site buy in  Field trails as these can develop 

resistance as may impact production 

1  Fit for use machinery in the development panel 

Lack of commitment from the OEM's due to various reasons 

     

1  Cable bolting  Miners not designed to install long tendons. 

Effective tensioning of bolts  Transport of bolts around Mine   

1  Self drilling bolts  Cost vs. existing  Operator acceptance (operators are wary of support quality of strata) 

Reliability   

1  Industry involvement         1  Culture of personnel on site         1  We develop our gear as required 

and I work closely with Fleet Welding in the specs and manufacturing 

       

1  Services handling  Multiple variations across every mine 

     

1  Area lighting  Access points on existing machine  Electrical capacity  Human interaction with light directions 

      

1  Requirement to improve onboard ventilation 

       Machine design     

1  Self drilling bolts    Current hydraulic rig compatibility  Weight   1  Continuous Haulage  Cost high ‐ unproven technology   Resistance to be the first to try     1  All  Research is too "pure" as 

researchers are students or others with limited practical experience 

Too difficult to obtain ACARP funding or tax concessions for R&D 

             

1  Modular materials handling systems 

Capital  Availability of equipment to utilise technology 

Local suppliers modularising materials 

      

Page 56: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 52  

MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES RANK  PRIORITY RESEARCH ELEMENT 1  2  3  4 

1  Material handling‐ low height  Mine design  Compnay openess to R&D  Operator training/input  Money 1  Remote control operation of CM  Unplanned movement of CM       1  Bolting and support systems for 

continuous miners can run 300m longwall with 1 man but still can't cut and bolt continuously without having 6 men in the face area?  

 Lack of  research due the false economy that longwall technology makes more money so gets greater amount of reseach, development is the major cost and delay at just about all longwall mines  

     

2  Continuous Haulage  Reliability  Cost     2  Continuous Haulage  Expertise and allotment of 

resource to successfully introduce Cost  Reliability ‐ previous bad 

experiences in Australia with Continuous Haulage 

 

2  Overall effectiveness of coal haulage system 

Constraints in adapting current equipment 

Constraints in capital  In‐disciplined action by crews  Absence of system checks 

2  Access to Miners  No or little access to top of machine for both operational & maintenance tasks 

Removing injuried person from side of machine 

Re‐stocking machine with consumables. 

Flitting machine 

2  Face to surface communications          Current technology               2  Materials handling  Current materials not suitable for 

a continuous process Variation in the mining environment preventing the use of robotics 

   

2  Coal haulage ‐ investigate continuous haulage systems 

       Available technology best suted to individual mine requirements 

   

2  Self drilling pre‐tensioning bolts   Cost high ‐ unproven technology   Resistance to be the first to try     2  Stakeholder buy in at an early 

stage of project        

2  Shuttle car haulage  Foot switch operation       2  Need to be able to drill and bolt in 

1 cycle to reduce time and manual handling, also need to come up with an effective alternative to steel mesh on roof and ribs. 

       

3  Conveyor belt pre‐installed in LTU and extended on advance 

Understanding there is a problem  Achieving "acceptable level of risk"  Achieving standardised work method 

 

3  Ventilation  Ergonomically designed so operators are not required to handle ventilation devices 

Getting required quantites to face to allow rapid face advancement 

   

3  Automated bolting  Reliability. Proving systems prior to introduction 

Operator acceptance operators wary of de‐manning panels 

Cost / productivity benefit   

Page 57: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 53  

MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES RANK  PRIORITY RESEARCH ELEMENT 1  2  3  4 

3  Fully Automated Bolting on CMs  Cost high ‐ unproven technology   Resistance to be the first to try     3  Bolting  interaction between the operator, 

environment, materials and equipment 

Cost of retrofitting the system to a current machine 

   

3  Underground Communication         Current technology               3  Continue to improve ventilation 

systems to working face        Investigate how other mines set 

their ventilation    

3  Vibration, noise, dust and communication is always an issue on continuous miners some research into new helmet designs, airstream type devices that also incorporate noise control and communication.  

       

4  Monorail mounted ducting  Sizing constraints in current environment 

Robustness of construction materials availble 

Number of players in holistic auxillary ventilation stream 

 

4  Operator location identification around large equipment ‐ No Go Zones, pinch points, crush zones all a still significant hazards with no real hard barriers 

Suitably accurate technology within the mine environment 

Cost of retrofitting the system to a current machine 

   

4  Online strata monitoring         Current technology               4  Auto‐cut on Miners   Leave good floor for later vehicle 

access which will not require large quantities of later road works 

Consistent & predicatable rates of advance without human intervention 

   

5  Miner ground automation and mapping 

       Design and cost               

5  Wireless 2 way communication for all operators 

Suitably accurate technology within the mine environment 

Cost of retrofitting the system to a current mine 

The ability to prove the cost benefit of such a system 

 

 Table 13: Major Barriers to the Successful Research, Development and Introduction of New Technologies – Mining Contractors 

MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES RANK  

PRIORITY RESEARCH ELEMENT 1  2  3  4 

1  Maintenance accessibility   OEM buy in                      2  concurrent roof/rib bolting   Cost of new technology  Operator reluctance               3  Roadway maintenance vehicles   Lack of priority from mine owner                      4  Specialised pipe hanging  Lack of acceptance of issue                      5  Shuttle car haulage  Poor engineering in this area  Lack of suitable OEM's  Expensive to design and trial        

 

Page 58: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 54  

Table 14: Major Barriers to the Successful Research, Development and Introduction of New Technologies – OEMs and Suppliers MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES RANK  PRIORITY RESEARCH ELEMENT 1  2  3  4 

1  Self Drilling Roof Bolt System  Financial  Engineering Resources  Legal/Patent        1  Diesel engine system  Cost  FLP electronics  OEM support for engines  Manning 1  General Comments  Resource  limitations and other 

development priorities Techical barriers in making a coal mine approved system.   

Where interface to large equipment (e.g. c/miners) is required, the time it takes to get onto right contact within the OEM and to gain their confidence. 

 

1  Self drilling rock bolts  Bolting rig OEM's need to take on the project of rig designs to pump resin inside a hollow bolt  

Onesteel (our only Australian rebar manufacturer) needs to invest in pierced billet hollow bar technology. Importing such high volumes of steel from china etc  and holding 3 months stock is just not practical. 

The purchasing/ contracts departments of large mining companies are attacking suppliers. The poor margins and low returns limit the potential for private investment into such an important technology 

Current funding into this technology has been into professional researchers. That lives on funding rather than live on profits from inventions because they don't come up with practical solutions!  

1  Pipe Monorail systems ‐ with flexible vent ducting and/or cables mounted thereon (whether or not other components are mounted)  

Lack of understanding /recognition that mounting ventilation and cables onto pipe monorails materially reduces operator risks from manual handling, equipment damage from manual handling, and increases operational flexibility by reducing some resupply requirements for advancing. 

Treating all monorail systems as the same when (a) material weight differences exist between pipe and I‐beam systems (strength comparable), (b) ability to corner and change heights is materially different, (c) fuctional component complexity is different. 

Lack of understanding / recognition that monorail systems can leverage up  manpower opportunities and flexibility 

 

1  Drill rig controls  Controls must be user friendly and easy to maintain 

Controls must be able to report back to mine monitoring sytems to provide cycle and geological data 

There must be systems to analyse this data 

the system must make the job easier for the operator 

1  Roof and Rib support surface  Lack of understanding issues  Cost  Development time  Cost of change 1  Cable testing facility  Testing facility not available  Mines buy cheapest cable  Mines expect supplier to fund 

everything Operators resistance to change 

1  Continuous haulage  Money  Champion to run     1  SDRB         1  Airo‐Dusting  Non specific legislation/ 

regulations for introducing this new technology 

     

1  Underground canopies   Relevant standards  Regulatory constraints  End  user acceptance  Site requirements 

Page 59: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 55  

MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES RANK  PRIORITY RESEARCH ELEMENT 1  2  3  4 

1  Development panel process support equipment ‐ design to align with the panel process map. 

Mining Attachments designs and builds equipment based on customer specs or innovative designs from equipment in the field. Not on what a specific panel requires and or how it would be utilised  

Manufacturer may only see small elements of the bigger panel picture. 

Better ways to do things are rarely brought up as the key information to drive business improvement is not captured and or monitored 

A process of justification, design and implementation of the new technology is time consuming for the process owner 

2  Corrosion (including SCC)  Lack of understanding  Cost     2  CM service support activities    Need to define expected cost 

benefits or operational improvements from a detailed review of the types of service support activites conducted and alternative operation and technoloogies to complete them ‐ often treated as ordinary activities for existing employees 

Need to define incremental benefits (& valuve $) that may be obtained from using new and existing technology for incremental process improvements 

   

3  Braking Systems  OEM Support  Design for environment  User friendly   3  Automation  Cost  OEM and Supplier Support     4  Transmissions  End user perception  Cost  Industry History   4  Long tendon support  Definition on requirements  Cost     5  NVH  Machine Size Constraints  End user perception  In service testing   

 

Page 60: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – May 2010  Page 56  

APPENDICES   

Appendix  Title  Page 

A  Roadway Development Technology Audit ‐ Mines  56 

B  Roadway Development Technology Audit – OEMS and Suppliers  64 

C  Respondents  71   

Page 61: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 57    

APPENDIX A:  ACARP ROADWAY DEVELOPMENT TECHNOLOGY SELF AUDIT – MINES Introduction The following audit has been prepared by the Roadway Development Task Group to evaluate the effectives of existing roadway development technologies and processes and to identify and prioritise areas for further research. Respondents are asked to complete the self audit and return it to Gary Gibson ([email protected]) by 25 February 2010 for reporting at the upcoming Roadway Development Workshop (16, 23 and 24 March 2010). Please note that the audit is designed to be completed electronically and respondents will be required to save their completed audit before returning the completed form by email. Individual audit responses are confidential to ACARP and any details published will be on a consolidated industry basis without detailing individual mine responses or respondent’s details. 

Instructions for Completing Audit Respondents are asked to respond to four basic questions across the roadway development process, namely: 

1. Is the identified technology or process employed or installed at the mine? 2. In the event that such technology or process is employed, how often is that technology utilised in day to day operations? 3. In the event that such technology or process is utilised in day to day operations, how effective is that technology or process in achieving the desired process outcomes? 4. To what extent could the technology or process benefit from further research? 

To respond to the first question respondents are asked to insert either a Y or N in the grey response cell to indicate whether the technology or practice is employed or installed at the mine or not. If the answer is in the affirmative (Y), respondents should then tab to the next column and respond to the second question by inserting a number from 1 to 4, the number representing the heading descriptor which most closely corresponds to their view as to how frequently the technology element is utilised at their mine – ie; number 1 corresponds with extremely rarely whilst at the other extreme number 4 represents used almost exclusively. Respondents can then tab to the next column to similarly respond regarding the effectiveness of that technology or process, and to the fourth question to identify the extent to which such technology or process could benefit from further research (NB: if a negative response (N) is given to the first question respondents should proceed immediately to the next Technology Element or row and continue the audit as above).   Respondents should then tab to the Comments column to make any relevant comments in respect to the use, effectiveness and research potential of the identified technologies and processes, eg; “... technology X previously employed and found to be ineffective due to ..............”, or “... further research warranted on technology Y to overcome issues associated with ...........”  and “... poor operator acceptance of technology Z due to ............”.  Provision has also been included to allow respondents to include other Technology Elements as appropriate by typing in a technology descriptor within the grey descriptor cell, and completing their assessment of that technology as above. Respondents are also invited to complete three other questions relating to the introduction of new technologies and process, namely: 

Key Factors Contributing to the Successful Introduction of New Technologies and Processes – respondents are requested to identify and rank up to five (5) new technologies and processes they consider have been successfully introduced, and to identify the key factors they consider have been instrumental in the successful introduction of those technologies and processes. 

Barriers to the Introduction of New Technologies and Processes – respondents are similarly requested to identify and rank barriers that have impacted the successful introduction of up to five (5) new technologies and processes. 

Barriers to the Successful Research, Development and Introduction of New Technologies – respondents are asked to prioritise the top five (5) “technologies for further research” as reported in their Audit, and to identify what they consider may be major barriers in their successful research, development and introduction.  

Respondents are also requested to complete the Respondent’s Details at the completion of the Audit to facilitate follow up if required. Again, it is noted that individual responses will remain confidential to ACARP. 

Page 62: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 58    

PLEASE ENSURE THAT YOU HAVE READ THE INSTRUCTIONS BEFORE PROCEEDING No  PROCESS ELEMENT AND TECHNOLOGY  INSTALLED  USED  EFFECTIVENESS  FURTHER RESEARCH  COMMENTS 

Installed an

d/or available 

Not installed an

d/or available 

Used rarely if ever 

Used sometim

es 

Used regularly 

Used almost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or installed but are 

currently not in use, eg; why technology is not in use ( operator acceptance, 

safety issues, maintenance requirement, etc) 

1.00  Continuous Miners           1.01  Remote control operation of CM 

functions (eg; radio) 

 

 

 

 

 

1.02  Remote steering systems employed (eg; video) 

 

 

 

 

 

1.03  Concurrent sumping, cutting and bolting 

 

 

 

 

 1.04  Auto‐cut facility of sumping and cutting 

action 

 

 

 

 

 

1.05  Rotating arm/spinner loading configuration 

 

 

 

 

 

1.06  East/west chain loading configuration 

 

 

 

 

 1.07  Plough shovel loading configuration  

 

 

 

 

 1.08  Scrolling head assisted loading 

 

 

 

 

 1.09  Operator display units (eg; cutting height, 

loads, etc) 

 

 

 

 

 

1.10  Machine diagnostic display units 

 

 

 

 

 1.11  Machine auto‐reporting systems 

 

 

 

 

 1.12  Automated lubrication systems 

 

 

 

 

 1.13  Area lighting systems 

 

 

 

 

 1.14  Operator access and egress 

 

 

 

 

 1.15  Maintenance accessibility and servicing 

 

 

 

 

 1.16  Overall ergonomic configuration for CM 

operation    

 

 

 

1.17 

 

 

 

 

 

 2.00  Strata Support           

Page 63: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 59    

No  PROCESS ELEMENT AND TECHNOLOGY  INSTALLED  USED  EFFECTIVENESS  FURTHER RESEARCH  COMMENTS 

Installed an

d/or available 

Not installed an

d/or available 

Used rarely if ever 

Used sometim

es 

Used regularly 

Used almost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or installed but are 

currently not in use, eg; why technology is not in use ( operator acceptance, 

safety issues, maintenance requirement, etc) 

2.01  Concurrent operation of roof and rib bolters 

 

 

 

 

 

2.02  Push button controls on bolting rigs 

 

 

 

 

 2.03  Roof mesh racking system on CM 

 

 

 

 

 2.04  Bolt storage cassettes or pods 

 

 

 

 

 2.05  Bolt washer dispensers 

 

 

 

 

 2.06  On‐board tendon/cable tensioning 

 

 

 

 

 2.07  Manual tendon/cable tensioning 

 

 

 

 

 2.08  Roof fall protection devices 

 

 

 

 

 2.09  Rib fall protection devices 

 

 

 

 

 2.10  Self drilling roof or rib bolts 

 

 

 

 

 2.11  Overall ergonomic configuration for 

strata support    

 

 

 

2.12  Level of MDG35 compliance     

 

 

 2.13 

 

 

 

 

 

 3.00  Coal Haulage           3.01  Shuttle car coal haulage system 

 

 

 

 

 3.02  Battery/diesel hauler haulage system 

 

 

 

 

 3.03  Continuous haulage system 

 

 

 

 

 3.04  Breaker feeder used to size/load coal 

onto conveyor 

 

 

 

 

 

3.05  Mobile boot end  

 

 

 

 

 3.06  Pedestrian interaction measures 

 

 

 

 

 

Page 64: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 60    

No  PROCESS ELEMENT AND TECHNOLOGY  INSTALLED  USED  EFFECTIVENESS  FURTHER RESEARCH  COMMENTS 

Installed an

d/or available 

Not installed an

d/or available 

Used rarely if ever 

Used sometim

es 

Used regularly 

Used almost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or installed but are 

currently not in use, eg; why technology is not in use ( operator acceptance, 

safety issues, maintenance requirement, etc) 

3.07  Overall effectiveness of coal haulage system (eg; matching of cutting, support and haulage cycles) 

   

 

 

 

3.08 

 

 

 

 

 

 4.00  Face Ventilation            4.01  On‐board ducted ventilation system 

 

 

 

 

 4.02  Monorail mounted ducting 

 

 

 

 

 4.03  On‐board or fan mounted dust scrubbers 

 

 

 

 

 4.04  Auxiliary fan mounted on mobile boot 

end or monorail 

 

 

 

 

 

4.05  Overall effectiveness of ventilation system 

   

 

 

 

4.06 

 

 

 

 

 

 5.00  Face Services (eg; power, water in/out, 

compressed air, communications, etc)    

 

   

5.01  Face services manually handled on cable rollers and other devices 

 

 

 

 

 

5.02  Monorail mounted services  

 

 

 

 

 5.03  Continuous haulage mounted services  

 

 

 

 

 5.04  Cable/hose boats used for storage of 

cables and/or hoses 

 

 

 

 

 

5.05  Cable/hose boats hydraulically powered as required 

 

 

 

 

 

5.06  Powered water hose reels used for storage of hoses 

 

 

 

 

 

Page 65: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 61    

No  PROCESS ELEMENT AND TECHNOLOGY  INSTALLED  USED  EFFECTIVENESS  FURTHER RESEARCH  COMMENTS 

Installed an

d/or available 

Not installed an

d/or available 

Used rarely if ever 

Used sometim

es 

Used regularly 

Used almost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or installed but are 

currently not in use, eg; why technology is not in use ( operator acceptance, 

safety issues, maintenance requirement, etc) 

5.07  DCB mounted on mobile boot end or monorail 

 

 

 

 

 

5.08 

 

 

 

 

 

 6.00  Materials Handling           6.01  Bolting consumables manually loaded 

onto CM 

 

 

 

 

 

6.02  Racking devices used to load bolting consumables onto CM 

 

 

 

 

 

6.03  Boom lifting devices used to load bolting consumables onto CM 

 

 

 

 

 

6.04  Mesh sheets manually loaded onto CM 

 

 

 

 

 6.05  Mesh sheets loaded onto CM with boom 

or racking device 

 

 

 

 

 

6.06  Individual pods or cassettes transported throughout mine 

 

 

 

 

 

6.07  Trailers used to transport multiple pods or cassettes throughout mine 

 

 

 

 

 

6.08  Bulka bags used to transport stonedust 

 

 

 

 

 6.09  “Wet dusting” used for face and outbye 

dusting 

 

 

 

 

 

6.10 

 

 

 

 

 

 7.00  Panel Advance           7.01  Conveyor belting pre‐installed in LTU and 

extended on advance 

 

 

 

 

 

Page 66: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 62    

No  PROCESS ELEMENT AND TECHNOLOGY  INSTALLED  USED  EFFECTIVENESS  FURTHER RESEARCH  COMMENTS 

Installed an

d/or available 

Not installed an

d/or available 

Used rarely if ever 

Used sometim

es 

Used regularly 

Used almost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or installed but are 

currently not in use, eg; why technology is not in use ( operator acceptance, 

safety issues, maintenance requirement, etc) 

7.02  Device/s used to separate upper and lower belts and facilitate installation of structure 

 

 

 

 

 

7.03  Device/s used to install structure 

 

 

 

 

 7.04  Purpose designed pipe installation 

equipment utilised to extend pipe ranges 

 

 

 

 

 

705 

 

 

 

 

 

 8.00  Personnel Transport           8.01  PJB/SMV style personnel transporters 

 

 

 

 

 8.02  Approved NERZ “troop carriers” 

 

 

 

 

 8.03  Purpose designed maintenance support 

vehicles 

 

 

 

 

 

8.04 

 

 

 

 

 

              

 

Page 67: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 63    

 

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES Respondents are requested to identify and rank up to five (5) new technologies and processes they consider have been successfully introduced, and to identify the key factors they consider have been instrumental in the successful introduction of those technologies and processes (respondents are asked to rank these key factors from 1 to 4, with a ranking of “1” indicating the most positive factor of those identified).  

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES RANK  SUCCESSFULLY INTRODUCED TECHNOLOGY AND/OR PROCESS  1  2  3  4 

 

 

 

 

 2 

 

 

 

 

 3 

 

 

 

 

 4 

 

 

 

 

 5 

 

 

 

 

 

BARRIERS TO THE INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES Respondents are similarly requested to identify and rank barriers or factors that have impacted the introduction of up to five (5) new technologies and processes that they have been associated with (respondents are asked to rank these barriers or factors from 1 to 4, with a ranking of “1” indicating the barrier or factor with the most significant adverse impact of those identified). Respondents are asked to identify root causes of these barriers or impacts wherever possible – ie; rather than responding “poor operator acceptance”, the response may instead be ”poor operator acceptance due to failure to provide adequate and appropriate training”. 

BARRIERS OR FACTORS IMPACTING THE INTRODUCTION OF NEW TECHNOLOGIES AND PROCESSES  RANK 

IMPACTED TECHNOLOGY AND/OR PROCESS  1  2  3  4 

 

 

 

 

 2 

 

 

 

 

 3 

 

 

 

 

 4 

 

 

 

 

 5 

 

 

 

 

 

BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES Respondents are asked to prioritise the top five (5) technologies for further research as reported in their Audit, and to identify what they consider may be major barriers in their successful research, development and introduction.  

MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES  RANK 

 PRIORITY RESEARCH ELEMENT  1  2  3  4 

 

 

 

 

 2 

 

 

 

 

 3 

 

 

 

 

 4 

 

 

 

 

 

Page 68: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 64    

 

 

 

 

  

Mine: 

  Respondent: 

  Position: 

  Tel No: 

  Email Address: 

 

  Thank you for completing the self audit and forwarding it to the undersigned. Regards, 

Gary Gibson Project Leader ACARP Roadway Development Improvement Project 

Page 69: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 65    

 APPENDIX B:  ACARP ROADWAY DEVELOPMENT OEM/SUPPLIER TECHNOLOGY SELF AUDIT – OEMs AND SUPPLIERS 

Introduction The Roadway Development Task Group proposes to evaluate the effectives of existing roadway development technologies and processes and to identify and prioritise areas for further research. Separate self audits have been prepared for both mines and OEM/suppliers with OEM/supplier respondents being asked to complete the self audit and return it to Gary Gibson ([email protected]) by 24 February 2010 for reporting at the upcoming Roadway Development Workshop (16, 23 and 24 March 2010). 

Please note that the audit is designed to be completed electronically and respondents will be required to save their completed audit before returning the completed form by email. Individual audit responses are confidential to ACARP and any details published will be on a consolidated industry basis without detailing individual responses or respondent’s details. 

Instructions for Completing the Audit Respondents are asked to respond to four basic questions across the roadway development sector, namely: 

5. Has the OEM/supplier supplied or installed the identified technology at Australian underground coal mines? 6. In the event that such technology has been supplied, how broadly has that technology been adopted at mines? 7. In the event that such technology has been supplied and is utilised in day to day operations, how effective is that technology being employed by mines – ie; are mines fully utilising 

the installed capacity/capability of the technology, and/or are they realising the full potential of the technology? 8. To what extent could the technology benefit from further research? 

To respond to the first question respondents are asked to insert either a Y or N in the grey response cell to indicate whether the OEM/supplier supplies the technology to the industry or not. If the answer is in the affirmative (Y), respondents should then tab to the next column and respond to the second question by inserting a number from 1 to 4, the number representing the heading descriptor which most closely corresponds to their view as to how broadly that technology is adopted at mines – ie; number 1 corresponds with extremely rarely whilst at the other extreme number 4 represents used almost exclusively. Respondents can then tab to the next column to similarly respond regarding how effectively that technology is being employed, and to the fourth question to identify the extent to which such technology could benefit from further research (NB: if a negative response (N) is given to the first question respondents should proceed immediately to the next Technology Element or row and continue the audit as above).   

Respondents should then tab to the Comments column to make any relevant comments in respect to the development, introduction, and adoption, of the identified technologies, and the need for further research, eg; “... introduction and uptake of technology X was impacted by ..............”, or “... further research warranted on technology Y to overcome issues associated with ...........”  and “... poor operator acceptance of technology Z due to ............”.  

Provision has also been included to allow respondents to include other Technology Elements as appropriate by typing in a technology descriptor within the grey descriptor cell, and completing their assessment of that technology as above. 

Respondents are also invited to complete three other questions relating to the introduction of new technologies, namely:  Key Factors Contributing to the Successful Introduction of New Technologies – respondents are requested to identify and rank up to five (5) examples of where new technologies 

have been successfully introduced at mines, and to identify the key factors they consider were instrumental in the successful introduction of those technologies.  Barriers to the Introduction of New Technologies – respondents are similarly requested to identify and rank barriers that have impacted the successful introduction of new 

technologies at mines in up to five (5) instances or examples.  Barriers to the Successful Research, Development and Introduction of New Technologies – respondents are asked to prioritise the top five (5) “technologies for further research” as 

reported in their Audit, and to identify what they consider may be major barriers in their successful research, development and introduction.  

Page 70: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 66    

Respondents are also requested to complete the Respondent’s Details at the completion of the Audit to facilitate follow up if required. Again, it is noted that individual responses will remain confidential to ACARP.

Page 71: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 67    

 PLEASE ENSURE THAT YOU HAVE READ THE INSTRUCTIONS BEFORE PROCEEDING 

No  PROCESS ELEMENT AND TECHNOLOGY  SUPPLIED?  EXTENT ADOPTED?  EFFECTIVENESS?  FURTHER RESEARCH?  COMMENTS 

Supp

lied an

d/or available 

Not sup

plied an

d/or available 

Mines use rarely or if ever  

Mine use sometim

es 

Mines use fa

irly exten

sively 

Mines use alm

ost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or supplied but are 

currently not adopted, eg; why technology is not in use (lack of industry support, operator acceptance, safety issues, maintenance requirement, lack 

of profitability, scale of market, economies of scale or supply, lack of 

OEM/supplier support, etc) 

1.00  Continuous Miners           1.01  Remote control operation of CM 

functions (eg; radio) 

 

 

 

 

 

1.02  Concurrent sumping, cutting and bolting 

 

 

 

 

 1.03  Auto‐cut facility of sumping and cutting 

action 

 

 

 

 

 

1.04  Rotating arm/spinner loading configuration 

 

 

 

 

 

1.05  East/west chain loading configuration 

 

 

 

 

 1.06  Plough shovel loading configuration  

 

 

 

 

 1.07  Scrolling head assisted loading 

 

 

 

 

 1.08  Operator display units (eg; cutting height, 

loads, etc) 

 

 

 

 

 

1.09  Machine diagnostic display units 

 

 

 

 

 1.10  Machine auto‐reporting systems 

 

 

 

 

 1.11  Automated lubrication systems 

 

 

 

 

 1.12  Area lighting systems 

 

 

 

 

 1.13  Operator access and egress 

 

 

 

 

 1.14  Maintenance accessibility and servicing 

 

 

 

 

 1.15 

 

 

 

 

 

 2.00  Strata Support           2.01  Concurrent operation of roof and rib 

bolters 

 

 

 

 

 

Page 72: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 68    

No  PROCESS ELEMENT AND TECHNOLOGY  SUPPLIED?  EXTENT ADOPTED?  EFFECTIVENESS?  FURTHER RESEARCH?  COMMENTS 

Supp

lied an

d/or available 

Not sup

plied an

d/or available 

Mines use rarely or if ever  

Mine use sometim

es 

Mines use fa

irly exten

sively 

Mines use alm

ost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or supplied but are 

currently not adopted, eg; why technology is not in use (lack of industry support, operator acceptance, safety issues, maintenance requirement, lack 

of profitability, scale of market, economies of scale or supply, lack of 

OEM/supplier support, etc) 

2.02  Push button controls on bolting rigs 

 

 

 

 

 2.03  Automated bolting systems 

 

 

 

 

 2.04  Roof mesh racking system on CM 

 

 

 

 

 2.05  Bolt storage cassettes or pods 

 

 

 

 

 2.06  Tendon/cable tensioners 

 

 

 

 

 2.07  Roof fall protection devices 

 

 

 

 

 2.08  Rib fall protection devices 

 

 

 

 

 2.09  Chemical roof and rib bolts and/or 

anchors          

2.10  Self drilling roof or rib bolts 

 

 

 

 

 2.11  Long roof tendons/cables 

 

 

 

 

 2.12 

 

 

 

 

 

 3.00  Coal Haulage           3.01  Shuttle car coal haulage systems 

 

 

 

 

 3.02  Battery/diesel hauler haulage systems 

 

 

 

 

 3.03  Continuous haulage systems 

 

 

 

 

 3.04  Breaker feeders  

 

 

 

 

 3.05  Mobile boot ends  

 

 

 

 

 3.06 

 

 

 

 

 

 4.00  Face Ventilation            4.01  On‐board ducted ventilation systems 

 

 

 

 

 4.02  Monorail mounted ducting systems 

 

 

 

 

 4.03  On‐board or fan mounted dust scrubbers 

 

 

 

 

 4.04  Flexible ducting 

 

 

 

 

 4.05  Auxiliary fans 

 

 

 

 

 

Page 73: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 69    

No  PROCESS ELEMENT AND TECHNOLOGY  SUPPLIED?  EXTENT ADOPTED?  EFFECTIVENESS?  FURTHER RESEARCH?  COMMENTS 

Supp

lied an

d/or available 

Not sup

plied an

d/or available 

Mines use rarely or if ever  

Mine use sometim

es 

Mines use fa

irly exten

sively 

Mines use alm

ost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or supplied but are 

currently not adopted, eg; why technology is not in use (lack of industry support, operator acceptance, safety issues, maintenance requirement, lack 

of profitability, scale of market, economies of scale or supply, lack of 

OEM/supplier support, etc) 

4.06  Face monitoring systems (eg; methanometers) 

 

 

 

 

 

4.07 

 

 

 

 

 

 5.00  Face Services (eg; power, water in/out, 

compressed air, communications, etc)          

5.01  Cable rollers and other devices for manual handling of cables and hoses  

 

 

 

 

 

5.02  Monorail systems for mounting of face services  

 

 

 

 

 

5.03  Cable/hose boats for storage of cables and/or hoses 

 

 

 

 

 

5.04  Hydraulically powered cable reelers   

 

 

 

 

 5.05  Hydraulically powered hose reelers 

 

 

 

 

 5.06  Electrical DCB/Gate End Boxes 

 

 

 

 

 5.07 

 

 

 

 

 

 6.00  Materials Handling           6.01  QDS style racking devices for loading 

bolting consumables onto CM 

 

 

 

 

 

6.02  QDS style jib devices for loading bolting consumables onto CM 

 

 

 

 

 

6.03  Boom lifting or racking devices to load mesh sheets onto CM 

 

 

 

 

 

6.04  QDS attachments for the transport of pods or cassettes  

 

 

 

 

 

6.05  Material trailers for the transport of multiple pods or cassettes  

 

 

 

 

 

Page 74: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 70    

No  PROCESS ELEMENT AND TECHNOLOGY  SUPPLIED?  EXTENT ADOPTED?  EFFECTIVENESS?  FURTHER RESEARCH?  COMMENTS 

Supp

lied an

d/or available 

Not sup

plied an

d/or available 

Mines use rarely or if ever  

Mine use sometim

es 

Mines use fa

irly exten

sively 

Mines use alm

ost e

xclusively 

Extrem

ely  ineffective 

Somew

hat ine

ffectiv

Somew

hat e

ffectiv

Extrem

ely  effectiv

Extrem

ely un

likely to ben

efit 

Unlikely to ben

efit 

Likely to

 ben

efit 

Extrem

ely likely to ben

efit 

   

Y  N  1  2  3  4  1  2  3  4  1  2  3  4 

Please include comments particularly if technology elements have previously been trialled and/or supplied but are 

currently not adopted, eg; why technology is not in use (lack of industry support, operator acceptance, safety issues, maintenance requirement, lack 

of profitability, scale of market, economies of scale or supply, lack of 

OEM/supplier support, etc) 

6.06  Face stonedusting systems 

 

 

 

 

 6.07  Bulk stonedusting systems 

 

 

 

 

 6.08  “Wet dusting” systems  

 

 

 

 

 6.09 

 

 

 

 

 

 7.00  Panel Services           7.01  Conveyor belting reeling/handling 

devices 

 

 

 

 

 

7.02  Devices to facilitate installation of structure 

 

 

 

 

 

7.03  Purpose designed pipe installation equipment (eg; pipe trailers, QDS attachments) 

 

 

 

 

 

7.04  Cable reeling/ hanging devices 

 

 

 

 

 7.05  Electrical DCB/Gate End Boxes 

 

 

 

 

 7.06  Roadway maintenance 

vehicles/attachments  

 

 

 

 

 

7.07 

 

 

 

 

 

 8.00  Personnel Transport           8.01  PJB/SMV style personnel transporters 

 

 

 

 

 8.02  Approved NERZ “troop carriers” 

 

 

 

 

 8.03  Purpose designed maintenance support 

vehicles 

 

 

 

 

 

8.04 

 

 

 

 

 

 

 KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES  

Page 75: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 71    

Respondents are requested to identify and rank up to five (5) examples of where new technologies have been successfully introduced at mines, and to identify the key factors they consider were instrumental in the successful introduction of those technologies (respondents are asked to rank these key factors from 1 to 4, with a ranking of “1” indicating the most positive factor of those identified).  

KEY FACTORS CONTRIBUTING TO THE SUCCESSFUL INTRODUCTION OF NEW TECHNOLOGIES RANK  SUCCESSFULLY INTRODUCED TECHNOLOGY   1  2  3  4 

 

 

 

 

 2 

 

 

 

 

 3 

 

 

 

 

 4 

 

 

 

 

 5 

 

 

 

 

 

BARRIERS TO THE INTRODUCTION OF NEW TECHNOLOGIES  Respondents are similarly requested to identify and rank barriers that have impacted the successful introduction of new technologies at mines in up to five (5) instances or examples with which they have been associated with (respondents are asked to rank these barriers or factors from 1 to 4, with a ranking of “1” indicating the barrier or factor with the most significant adverse impact of those identified). Respondents are asked to identify root causes of these barriers or impacts wherever possible – ie; rather than responding “poor operator acceptance”, the response may instead be ”poor operator acceptance due to failure to provide adequate and appropriate training”. 

BARRIERS OR FACTORS IMPACTING THE INTRODUCTION OF NEW TECHNOLOGIES   RANK 

 IMPACTED TECHNOLOGY   1  2  3  4 

 

 

 

 

 2 

 

 

 

 

 3 

 

 

 

 

 4 

 

 

 

 

 5 

 

 

 

 

 

BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES Respondents are asked to prioritise the top five (5) technologies for further research as reported in their Audit, and to identify what they consider may be major barriers in their successful research, development and introduction.  

MAJOR BARRIERS TO THE SUCCESSFUL RESEARCH, DEVELOPMENT AND INTRODUCTION OF NEW TECHNOLOGIES  RANK 

 PRIORITY RESEARCH ELEMENT  1  2  3  4 

 

 

 

 

 2 

 

 

 

 

 3 

 

 

 

 

 4 

 

 

 

 

 5 

 

 

 

 

 

 

Company: 

  Respondent: 

  Position: 

  Tel No: 

  Email Address: 

 

Page 76: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 72    

  Thank you for completing the self audit and forwarding it to the undersigned. Regards, 

Gary Gibson Project Leader ACARP Roadway Development Improvement Project 

Page 77: Report on Roadway Development Technology Audit …undergroundcoal.com.au/roadway/pdf/Report_on... · Report on Roadway Development Technology Audit – June 2010 Page 1 ... high capacity

Report on Roadway Development Technology Audit – June 2010  Page 73    

 APPENDIX C:  RESPONDENTS  TECHNOLOGY AUDIT  RESPONSES ‐ MINES MINE  LONGWALL  BORD & PILLAR Airly     Angus Place     Baal Bone     Blakefield South     Broadmeadow     Clarence     Cook     Cornwall     Crinum     Dendrobium     Donaldson     Integra     Kestrel     Mandalong     Metropolitan     Myuna     Narrabri     Newlands North     North Goonyella     Ravensworth     Springvale     Tahmoor     Wambo North     West Cliff     West Wallsend      

  TECHNOLOGY AUDIT RESPONSES ‐ CONTRACTORS COMPANY  CONTRACTOR Mastermyne   Resco   SBD Delta   Sondaren   UGM   Walter Diversified Services    TECHNOLOGY AUDIT RESPONSES – OEMS AND SUPPLIERS  COMPANY  MAJOR OEM  MINOR OEM  SUPPLIER Alfabs       Alminco       Bucyrus       Conveyor Equipment Specialists 

     

Dywidag       Jenmar       Joy Mining Machinery       Macquarie       Megabolt       Mine Site Technologies       Mining Attachments       Minova       OneSteel       Resco       Valley Longwall ‐ Diesel