report ok geophysical survey tabor lake property · 2017-01-17 · tabor lake property february...

14
52F89SWTO41 2.2927 TABOR LAKE 010 REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys were carried out by the author in February and March, 1979> to accumulate data to assist in the interpretation of the structure on claims K-502044 and K-502045 on the Tabor Lake property, Kenora Mining Division. SUMMARY. CONCLUSIONS AKD RECOMMENDATIONS; In February and March, 1979, work was carried out on two claims of the Tabor Lake property, K-502044 and -045. The claims are 26 miles SE of Dryden, Ontario, in the Kenora Mining Division and are accessible by road from Borups Corners (5 miles northeast) on Highway 1? in summer and by foot or snow machine in winter. The area is relatively flat and has been cut-over with minor stands of timber remaining. Three miles of linecutting, 16,635 feet of magnetometer and 10,971 feet of electromagnetic surveys were carried out. Anomalies were located in both surveys. Because of the small area surveyed and the lack of detailed mapping data available little can be concluded except that it is probable that much of the low area

Upload: others

Post on 25-Jul-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

52F89SWTO41 2.2927 TABOR LAKE 010

REPORT OK

GEOPHYSICAL SURVEY

TABOR LAKE PROPERTY

February 26-March 8. 1979

INTRODUCTION;

Linecutting, magnetometer and electromagnetic surveys were

carried out by the author in February and March, 1979> to accumulate

data to assist in the interpretation of the structure on claims

K-502044 and K-502045 on the Tabor Lake property, Kenora Mining

Division.

SUMMARY. CONCLUSIONS AKD RECOMMENDATIONS;

In February and March, 1979, work was carried out on two claims

of the Tabor Lake property, K-502044 and -045. The claims are 26

miles SE of Dryden, Ontario, in the Kenora Mining Division and are

accessible by road from Borups Corners (5 miles northeast) on

Highway 1? in summer and by foot or snow machine in winter. The

area is relatively flat and has been cut-over with minor stands of

timber remaining.

Three miles of linecutting, 16,635 feet of magnetometer and

10,971 feet of electromagnetic surveys were carried out.

Anomalies were located in both surveys. Because of the small

area surveyed and the lack of detailed mapping data available little

can be concluded except that it is probable that much of the low area

Page 2: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

- 2 -

is filled with conductive clay overburden.

Prospecting and geological mapping should be carried out.

If structure does not become apparent after the mapping, it is

recommended that lines be cut at 200 foot intervals and both

magnetometer and electromagnetic surveys be carried out on the

new lines. It is also recommended that the remainder of the

property be surveyed on at least a 400 foot grid and that prospecting

and geological mapping be done,

PROPERTY. LOCATION AND ACCESS

The two claims covered by the survey are part of a larger

group covering and surrounding Tabor Lake. The two claims are in

the northeastern corner of the group and are numbered K-502044 and

K-502045. The group is located near the north central part of the

Tabor Lake Hap Area and lie south of Helgund Township in the Kenora

Mining Division. Tabor Lake lies some 5 miles southwest of fiorups

Corners on Highway 1? and 26 miles southeast of Dryden.

Direct access can be made to the property by car or four-

wheeled vehicle in moderate seasons and by snow vehicle or snowshoe

in winter from plowed secondary roads three and four miles to the

east and west respectively.

The access road passes through the southern parts of both

claims.

The Canadian Pacific Railway station of Dyment lies two miles

north of Borups Corners, connected by secondary highway, and major

Page 3: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

- 3 -

power lines pass east-west between the two villages.

ENVIRONMENT

The area has been generally cut-over but some stands of pulp

and timber spruce and jackpine are still extant. The remainder of

the area is predominantly covered with second-growth alder, poplar,

balsam and birch with some young spruce and jackpine bush beginning

to return.

The topography is relatively flat with gently sloping ridges

separated by swamp and sub-swamp type bush. On the claims the maximum

relief is 50 to 70 feet. Tabor Lake itself is a head-water lake

fed only by very local small swamps and springs.

The soil probably has a high clay content as evidenced by the

amount of poplar and aspen second-growth, although a small gravel

pit has been developed just west of the shaft on claim K-502044.

As mentioned previously, a road passes east-west through the

southern portion of the claims, giving access from both sides to

the shaft. The headframe erected in 1958 is still standing but

except for one out-house, all the other buildings have either been

dismantled or have collapsed.

HISTORY AND PREVIOUS WORK

Most of the previous work, except for some prospecting and

trenching, was carried out on claim K-502044 between 1937 and 1959.

The companies involved in this work were Clark Gold Mines Limited,

Page 4: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

Tabor Lake Gold Mines and Pantan Mines Limited. Work carried out

included extensive surface trenching, channel and bulk sampling,

shaft sinking to 280 feet, levels established at 125 feet and

250 feet, more than 600 feet of drifting and cross-cutting, and

7,312 feet of diamond drilling in twenty-two holes.

The work located several gold bearing veins, the main vein

carrying over one ounce values over narrow widths. A modest shoot

was outlined in the underground work and diamond drilling intersected

high grade values below the deepest level of up to 29 oz. Au/ton.

The patents and leases taken out on the claims during the

working period were allowed to expire in 1977 and 1978 and the

ground was restaked as it came open.

GEOLOGY AND MIMERALIZATION

The claims lie in an area of Keewatin volcanics of andesitic

and dacitic composition intruded by diorite dikes and aplitic to

porphyritic acid intrusives. The rocks were subsequently faulted

and sheared and quartz veins were introduced along generally east-

west trending structures which contain pyrite, galena, some

tellurides and gold.

The main, or No. 1 vein on claim K-502044, dips at some 45

south and the ore shoot appears to pitch some 45 to the southwest.

CURRENT WORK

, Linecutting and geophysical surveys were carried out by the

Page 5: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

- 5 -

author during the period February 26 to liarch 8, 1979* Much less

ground was covered than anticipated because very soft snow

conditions slowed the lineexttting drastically.

Linecutting

A grid of picket lines with north-south cross lines at 400 foot

intervals was cut from a OfOO base line at the south of claim

K-502044 and from IfOON base ine on claim K-502045. The north

boundary was straightened, brushed and chained to use as a tie line.

Pickets were placed at 100 foot intervals along the lines.

A total of 16,635 feet or 3.15 miles of line were cut.

Magnetometer Survey

A magnetometer survey was carried out on all the lines using a

McPhar M-700 fluxgate magnetometer. Readings were taken at 100 foot

intervals with 50 foot readings where anomalous gradients were

encountered. Readings were taken with tie-ins to base stations

established on the base lines at approximately one hour intervals

and the readings corrected for diurnal changes and plotted on the

map.

Electromagnetic Survey

An electromagnetic survey was done using a Crone Radem VLF

electromagnetic unit. The remote signal source used in the survey

was the marine communications radio at Seattle, Washington, as

being the source most in line with the strike of the gold bearing

Page 6: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

- 6 -

zones. Readings were taken at 100 foot stations along the north-

south lines only, with 50 foot readings where anomalous changes

indicated the necessity.

RESULTS OF SURVEYS

The magnetometer survey indicates a system of banded rocks

with contrasting magnetics in all except the southeast half of claim

K-502045. The western responses range from lows of minus 1898

gammas to highs of plus 1349 gammas. The most continuous of these

anomalies appear to strike between NE and ENE but the serpentine

shape in some cases may indicate fault offsetting, or folding.

Several of the anomalies are found on single lines and true attitudes

can only be assumed. The extreme low reading (-1898) on line 4W

associated with only a moderate high (368) may indicate the presence

of polarized pyrrhotite.

The magnetic uniform low in the SB of K-502045 indicates a

homogenous rock which may be acid intrusive.

The sudden change between these areas, corresponding with the

scarp-edge of the outcrop area, indicates a probable contact,

possibly by faulting.

The electromagnetic survey, although it located four true

cross-overs, may not have found any worthwhile conductors. The high

south dip build-ups toward Tabor Lake and north build-ups toward

flat swampy ground and the fact that all the anomalies occur close

Page 7: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

- 7 -

to the edge of outcrop areas probably indicate that the area has

conductive clay overburden in the low ground and lake bottom. The

anomalies may merely indicate the edges of the conductive overburden.

However, because the area covered was small end complete profiles

could not be read, there may be true conductors present. The anomaly

at 1350N on line 0 may be a true bedrock conductor. This anomaly

coincides with a weak but long magnetic high.

Respectfully submitted,

March 20, 1979

Page 8: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

21'M

Page 9: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

titnUg

' . * I W . I r 1'I '."H""- J v<<

y cOariifijo\m\ MO .j uffi im \\m\w\tim 1 075 *

'ffi.fflt?ff.'ffl-JH vW1*«r«ilii89

Page 10: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

Minis

Ontario TECHNU 3VED52F09SW0041 2.2927 TABOR LAKE 900

AN APPENDIX TO TECHNICAL REPORT ^ NtE£> NOT BE REPEATOD IN RETORT ';" :; CONTAIN I^r^ERPRETA riON ) CONCLUSIONS El

9

; of Survey(s).

Township or Area.

Claim Holder(s)_

"fa*

Survey Company

Author of Report

Address of Anthnr /

Covering Dates of Survey.

Total Miles of Line Cut_

2 & ~~/*?*frcA/&> /$73(linecutting to office) ^

SPECIAL PROVISIONS CREDITS REQUESTED

ENTER 40 days (includes line cutting) for first survey.

ENTER 20 days for each additional survey using same grid.

DAYS

Geophysical

Electromagnetic

per claim -. ̂

ic \ ^

-Other_

Geological.

AIRBORNE CREDITS (Special provision credits do not apply to airborne surveys)

Magnetometer .Electromagnetic. . Radiometric

DATE :

(enter days per claim)

>'-^*0/'?3 SIGNATURE :Author of Report or Agent

Res. Geol.. . Qualifications.

Previous Surveys File No. Type Date Claim Holder

MINING CLAIMS TRAVERSED List numerically

AT(prefix) (number)

TOTAL CLAIMS.

Page 11: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

GEOPHYSICAL TECHNICAL DATA

GROUND SURVEYS If more than one survey, specify data for each type of survey

Number of Stations

Station interval

Profile

/ OQ

Contour interval /A"7-J--» >t. c

Number of Readings

Line spacing ___ ' C/Cx

/ " si

- t

ulInstrument __

Accuracy Scale constant

Diurnal correction method

Base Station check-in interval (hours)__

Base Station location and value ' '

/

/ £ <,<3sAf.

H 2J

<

O

oh-j

Tn Strnment C

>il configuration

Coil:

Accuracy.

Method:

Z. Os

CU Fixed transmitter

«-«a^ot

d Shoot back CH In line CH Parallel line

Parameters measured.

(specify V.L.F. station)

<

O

Instrument.

Scale constant

Corrections made.

station and location.

Elevation accuracy-

Instrument

H

N

C

C

CO

Pi

Method I I Time Domain

Parameters On time ___

- Off time ___

Delay time.

Integration time.

Power

Electrode array _

Electrode spacing.

Type of electrode

I I Frequency Domain

_ Frequency _____

__ Range ________

Page 12: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

92°30'

49° 37' SO'^—n

ro(0to CM

UJ*<

o oQ. LU_J

o:

49° 30'—•

WABI600N INDIAN RESERVE \

SATTERLY TWRFOR STATUS REFER TO TWP PLAN

No. M.2035

--59M.

MELGUND TWRFOR STATUS REFER TO TWP PLAN

UJ>UJ (T

tt o

trt 2Z3

inK Ou.

56M

-86M

|4«I48

44084844884«448847~ " ~ ~ ~ " " ~"

Low try

Lakt 44t«»4 | 449B4Jl44»«4« 44*841i ! i

58M

Z <

£1H

87M

£ *»~ (M

-i S|_l fc s1.1 CC

27' 26 23 21 20 19 18 17' 16*

S006aF«96»»84l 2.2827 TABOR LAKE

KAWASHEGAMUK LAKE M.2573

92°IS'I

rr-49°37 1 30"

37'

36

35'

m CD

LU

34'

33

32'

31'

-49°30'

92°I5'

495922

AREA OF

TABOR LAKEDISTRICT OF KENORA

KENORA MINING DIVISION

SCALE: 1-INCH = 4O CHAINS

LEGEND

PATENTED LANDCROWN LAND SALELEASES

LOCATED LANDLICENSE OF OCCUPATIONMINING RIGHTS ONLY

SURFACE RIGHTS ONLYROADSIMPROVED ROADS

KING'S HIGHWAYSRAILWAYSPOWER LINES

MARSH OR MUSKEGMINES

CANCELLEDPATENTED S R 0.

*

c.

NOTES400' surface rights reservation along the shores of all lakes and rivers.

Roadt indicated PRIVATE may t>« used by prospectors only after permission it obtained from Dryden Paper Co , Drydtn, Ontario

Ar«at withdrawn from staking und«r Section 43 of the Mining Act. ( RSO'70)

Order No F ile Daft Disposition

(5) W36/78 115978 10 July'78 M. R 0

DATE OF, ISSUE

APR -91979

SURVEYS AND MAPPING

NATIONAL TOPOGRAPHIC SERIES 52 F 9

PLAN NO. MONTARIO

MINISTRY OF NATURAL RESOURCESSURVEYS AND MAPPING BRANCH

Page 13: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

B2F9B8WM11 2 .3827 TABOR UAKE

it ffr-u ****** SVAVer M*P

/" *

Page 14: REPORT OK GEOPHYSICAL SURVEY TABOR LAKE PROPERTY · 2017-01-17 · TABOR LAKE PROPERTY February 26-March 8. 1979 INTRODUCTION; Linecutting, magnetometer and electromagnetic surveys

S

'*!

^

-•'/!-.A

"•I *•

V N

* \ ^\

•____V

«

\*»>s

sI8>

°5

N

n5fVJ

n»^ K̂1

s«uS

!S.

*•? J