report 4 revised

Upload: gurtar-kaur

Post on 08-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/7/2019 report 4 revised

    1/15

  • 8/7/2019 report 4 revised

    2/15

    compare the two alternatives and see which alternative would have the highest number. The

    highest number outcome would be the recommendation of the alternative.

    D. Design Goals and Weights

    This was our rank ordering of goals from report 3

    Rank Ordering of Goals

    Performance

    Sustainability Acceptability

    Safety Economic

    Performance - 0.5 1.0 0.0 0.5 2.0

    Sustainability 0.5 - 1.0 0.0 1.0 2.5

    Acceptability 0.0 0.0 - 0.5 0.5 1.0

    Safety 1.0 1.0 0.5 - 1.0 3.5

    Economic 0.5 0.0 0.5 0.0 - 1.0

    Next we weighted our goals on a scale from one to one hundred. We then divided it

    into three parts

    being optional (1-30), important (31-70), and critically important (71-100). The

    results are as follows:

    Performance 75

    Sustainability 85

    Acceptability 55

    Safety 95

    Economic 50

    E. Method Used to Generate Alternative:

    Water Supply source:

    Alternative 1:

    a.) Description:

  • 8/7/2019 report 4 revised

    3/15

    Extend the Southern Nevada water distribution system via water main extensions: The South

    Valley Lateral water providers have identified a selected alternative to supply approximately

    130,000 gallon / day to Utopian homes. The Horizon Ridge Reservoir alternative is selected

    because it is in 20 mile reach and water delivery will be effective and efficient. The system shall

    have sufficient capacity to maintain 40 psi at the building entrance for one- and two-family

    dwellings. For other development provide minimum pressure of 35 psi at the building side of the

    meter during periods of maximum use, and to provide sufficient volumes of water at adequate

    pressures to satisfy the expected daily consumption plus fire flows of 20 psi. Normal working

    pressure in the distribution system should be approximately 60 psi with a range of 40 psi to 100

    psi. Where installation of dead-end water mains cannot be avoided, a hydrant or a valve of

    adequate size for flushing shall be installed at the terminal end of the line. The flush valves shall

    have an above ground discharge and shall be protected from contamination. Trenching, pipe

    laying, and backfilling shall be accomplished in a manner to prevent damage and misalignment

    of the pipe. Water mains shall be buried to a depth below the frostline or to a depth sufficient to

    provide a minimum of 30 inches cover, whichever is greater. There are many benefits of a

    existing system it is a reliable source of water, assured quality of water, better overall

    management, and more skilled technical operational capabilities. This water system meet all goal

    of sustainability. This project will not produce any CO2, will meet the goals of environmental

    sustainability of potable water supply and no waste or pollution will be produced.

    b.) Goal Achievement and Ranking factor:

    This Alternative will satisfy all goal of water supply system. This system will have better

    performance than water well and it will also be cost-effective.

    Sustainability 4

    Safety 6

  • 8/7/2019 report 4 revised

    4/15

    Acceptability 2

    Economic 7

    Performance 8

    Alternative 2:

    a.) Description:

    Install and develop Pumping stations: The location of the pump station and intake structure, and

    the anticipated heads and capacities are the major factors in the selection of pumps. Main

    pumping stations which supply water to the distribution system will be located near the water

    treatment facility or a potable water storage facility and will pump directly into the piping

    system. Booster pump stations will also be located in the system to increase the pressure in the

    pipeline. Major planning factors are: availability of electric power, roadway access for

    maintenance and operation purposes, and adverse impact, if any, upon surrounding occupancies.

    Pump drives for water supply and distribution pumps will be electric motors. Diesel or other

    fuels will be considered as a power source only for emergency use. The total energy consumption

    charges associated with a pump operation can be decreased by improving the efficiency of

    individual pumps or combination of pumps. However, such measures have little impact on

    reducing the costs associated with time of day energy rate schedules. A pump operating policy is

    a schedule of water levels that should be maintained and a series of rules that dictate when

    different pumps should be operated in response to different system conditions. The pumping

    equipment will be located so as not to be subject to flooding. The site will be graded to drain

    surface water away from structures. Roadway access for maintenance vehicles will be provided

    at all equipment locations with space provided for vehicle turn around. Pumping station can be

    sustained by limiting the drawdown of ground water level only to level that will be replenished

    by future recharge.

  • 8/7/2019 report 4 revised

    5/15

    Undergr

    ound Reservoir And Pump Station

    Above figure shows the pump supplying the distribution system

    b.) Goal Achievement and ranking factor:

    This alternative will meet the performance goal but it is inadequate to meet the Economic and

    Sustainability goal which is the aim of the system.

    Sustainability 3

    Safety 5

    Acceptability 3

    Economic 5

    Performance 7

    Water Treatment facility:

    Alternative 1: Onsite Treatment (Primary, Secondary, and Tertiary)

  • 8/7/2019 report 4 revised

    6/15

    Fig 1

    a.) Description

    With this alternative, we suggest to build a treatment facility onsite. The treatment facility will

    include three stages of treatment, which are the Primary, Secondary, and Tertiary stages. Primary

    treatment includes those components that are designed to remove solids and oils from the waste

    stream. This could include bar screens, grit chambers, and primary sedimentation tanks. When

    the wastewater stream leaves this treatment area, it is assumed that the wastewater is relatively

    free of solids. Secondary treatment is a biological process designed to remove soluble,

    biodegradable wastes from the water. Tertiary wastewater treatment is used after the secondary

    units to clean the wastewater prior to its final discharge. This area of the process may include

    further solid removal through sand beds, or even further reduction of organic matter through an

    activated carbon system.

    b.) Goal Achievement and Rating Factors

  • 8/7/2019 report 4 revised

    7/15

    This alternative will fulfill all the goals and requirements of the system as stated in report three,

    but is unsatisfactory in an economic standpoint. This will be discussed more in depth in the

    tradeoff analysis section of this report. Rating factors that were considered when evaluating this

    alternative include its ability to meet the relevant laws, the acceptability to the stakeholders, and

    the cost of the facility. We rated on a scale of 1 to 10, with 10 being superior, in each of the goals

    from report three. The results are as follows;

    sustainability 7safety 9acceptability 4economic 2

    performance 9

    Alternative 2: Use existing treatment facility

    Fig 2

    a.) Description

    Las Vegas has an existing treatment facility for all waste water that runs constantly. In this

    alternative we assume that we attach to the existing system which will allow for use of the

    pretreated water. It is located at 6005 East Vegas Valley Drive (see picture above). In regard to

  • 8/7/2019 report 4 revised

    8/15

    treatment, the facility treats 100 million gallons of wastewater on a daily basis, through

    physical, biological, and chemical treatment systems, to be reused or returned to the Las Vegas

    Wash.(CCWRD)

    b.) Goal Achievement and Rating Factors

    This alternative will satisfy all goals and excel in some. It will be able to perform at the rate that

    is needed as well as save money over alternative one. When evaluating and rating this alternative

    we found must better results. They are as follows;

    sustainability 7safety 9

    acceptability 9economic 10performance 9

    Water Storage Facility:

    Alternative 1: Ground Level Storage:

    b) Description

    Water ground storage tanks shall be provided with a light-proof and insect-proof cover of

    concrete, steel or equivalent material approved by the Division. The construction joints between

    side walls and the covers of concrete tanks or reservoirs shall be above ground level and above

    flood level; except that clearwells constructed below filters may be excepted from this

    requirement when total design, including waterproof joints, gives equal protection. The access

    manholes for finished water storage tanks or reservoirs shall be framed at least four inches above

    the tank or reservoir covers at the opening and shall be fitted with solid covers of materials that

    overlap the framed openings and extend down around the frames at least two inches. The covers

    for the openings shall be hinged at one side and fitted with a locking device. The tanks or

    reservoirs shall have vents with screened, downward directed openings. The vent and screen

  • 8/7/2019 report 4 revised

    9/15

    shall be of corrosion resistant material. Water supply inlets and outlets of storage tanks and

    reservoirs shall be located and designed to provide circulation of the water. All tanks and

    reservoirs shall be equipped with drain valves. Ground Storage tanks have lower initial cost of

    construction, a lower maintenance cost, the ease with which water quality can be tested, greater

    safety, and a greater aesthetic value.

    A plan of the reservoir with all dimensions as shown in Figure 9. This plan shows a top, side andend view.

    b.) Goal Achievement and ranking factor:

    If the storage facility is needed then ground level storage will be the one to choose. It will able to

    fulfill the goal of performance, safety with being cost-effective.

    Sustainability 6

    Safety 9

    Acceptability 4

    Economic 6

    Performance 9

  • 8/7/2019 report 4 revised

    10/15

    Alternative 2: Elevated Storage Tank:

    a) Description

    The specifications for elevated tanks, stand-pipes, towers, paints, coatings and other

    appurtenances shall meet the appropriate ANSI/AWWA Standards D 100 84 and D 101-53(R86)

    of the American Water Works Association, Inc., which are hereby incorporated by reference

    including any subsequent amendments and editions. Elevated tanks do not require the continuous

    operation of pumps. Short term pump shutdown does not affect water pressure in the distribution

    system since the pressure is maintained by gravity. And strategic location of the tank can

    equalize water pressures in the distribution system. However, precise water pressure can be

    difficult to manage in some elevated tanks. The optimal pressure is achieved at only one depth.

    http://water.me.vccs.edu/courses/ENV110/lesson10.htm

    The length of the standpipe causes continual and highly unequal pressures on the distribution

    system. In addition, a significant quantity of the water in a standpipe is required to produce the

    necessary water pressure. The water below a certain level is therefore used only as a support,

    unless booster pumps are available for emergency use of this water.

    b.) Goal Achievement and ranking factor:

    This alternative will not satisfy the performance goal of this system.

    http://water.me.vccs.edu/courses/ENV110/lesson10.htmhttp://water.me.vccs.edu/courses/ENV110/lesson10.htm
  • 8/7/2019 report 4 revised

    11/15

    Sustainability 4

    Safety 6

    Acceptability 2

    Economic 6Performance 5

    F. Evaluation

    1. Decision Matrix

    Water Supply Alternative:

    sustainability(85)

    safety(95)

    acceptability(55)

    economic(50)

    performance(75)

    DF=WF*RF

    Existing

    System 340 570 110 350 600Water Well 255 475 165 250 525

    Treatment Alternatives

    Sustainabilit

    y (85)

    Safety

    (95)

    Acceptabilit

    y (55)

    Economic

    (50)

    Performance

    (75)

    DF=WF*RF

    Onsite Facility 595 855 220 100 675 2445

    Existing

    Facility

    595 855 495 500 675 3120

    Storage Alternative:

    sustainability safety acceptability economic performance DF=WF*RF

    Ground Level

    ElevatedStorage

    These numbers were achieved by multiplying the goal weights from report three by each of the

    alternatives ratings in that category. The result was then added in each alternative to reveal the

    numbers on the far right of the table. These numbers will allow a decision in regard to which

    alternative is best suited to this project.

  • 8/7/2019 report 4 revised

    12/15

    2. Rankings for Treatment Alternatives

    The table above shows that the existing facility came out above that of building an onsite

    facility. The results show how each alternative is equal with respect to sustainability, safety, and

    performance. The difference lies within that of acceptability and economic. The reason for this

    will be discussed in the tradeoff analysis section of this report.

    G. Tradeoff Analysis

    1. Sustainability Vs Performance and Economic Goals for Treatment

    Alternatives

    In regard to treatment the important factor to look at is that of economics. Since each of the

    alternatives is relatively similar in regard to performance, cost will be the biggest factor. There is

    an existing facility in Las Vegas that treats all water and is most beneficial to the proposed

    system. So the only cost for that alternative will be that of materials and construction. On the

    other hand, if the alternative that proposes a new facility is constructed is chosen, the costs will

    be significantly higher.

    2.The Top Ranking Alternative Versus Other Alternative:

    3.Sensitivity of Result to Design:

    H. Preliminary Design Study Recommendations

  • 8/7/2019 report 4 revised

    13/15

    1. Achievement of Sustainable Design

    For this project we recommend using alternative two (the existing facility) for its ability to

    achieve sustainability, performance, and economic goals. By implementing this alternative, no

    new materials will be needed which can save money. The savings from this alternative can allow

    research and use of new water conservation techniques.

    2. Achievement of Performance

    Water Supply Source: Alternative 1 Water supply from existing source was the

    recommended alternative. The advantages of this alternative in relation to the others are:

    a. Provides residents access to the highest quality water available,

    b. Can be implemented relatively quickly,

    c. Eliminates homeowner operation and maintenance responsibility,

    d. Offers the highest level of fire protection,

    e. Protects public welfare,

    f. Minimizes environmental impact on and would be the most protective

    against any potential future impacts to the existing aquifer supply.

    g. Provides a redundant, reliable water supply.

    Treatment Facility: If using the existing treatment facility to supply clean water to the

    community, performance can be expected to match that of existing communities of Las Vegas.

    Water Storage Facility: The alternative is generally non-structural. The construction of new

    storage facilities will not be required. The only construction anticipated is associated with a new

    ditch for pipe installation.

    3. Achievement of Economic and Other Goals

  • 8/7/2019 report 4 revised

    14/15

    Assuming the existing water system is a viable water system, there are obvious economies of

    scale both initially and ongoing which generally results in less overall cost to consumers of the

    new system. The total capital cost of Horizon Ridge Reservoir and related pumping station and

    pipeline is estimated to range between approximately $33.6 million and $46 million. We

    anticipate that energy costs for this alternative would be about $18 for 325 851 gallon of water

    pumped to the reservoir. Alternative two promotes use of the existing treatment facility. By using

    this alternative, the cost of the project will be significantly lower than that of alternative one.

    4.Strengths and Shortcomings of the Preliminary Design Study:

    6. Summary of Further Research, Analysis and Design Needs

    Over the last three reports, the water team has been researching a proposed water system so that

    the needs of the decision maker are met. The next step in the category of further research will

    include the things such as the quantity of materials needed, location of materials for construction,

    and the design plans from the remaining teams. Water conservation techniques should also be

    researched for the future in order to better meet sustainability goals. Design considerations and

    project costs require updating. Also, an assessment of on-site environmental conditions is

    needed.

    References:

    Hornby, Lawrence E., Devising Wastewater Treatment Strategies.

    4/27/2010.http://www.p2pays.org/ref/02/01336.pdf

    Clark County Water Reclamation District. 4/27/2010.

    http://www.cleanwaterteam.com/home.html

    http://www.cleanwaterteam.com/home.htmlhttp://www.cleanwaterteam.com/home.html
  • 8/7/2019 report 4 revised

    15/15

    City of Las Vegas. Wastewater treatment. 4/27/2010.

    http://www.lasvegasnevada.gov/information/5397.htm

    Fig 1. From google/images. 4/27/2010.

    http://saferenvironment.files.wordpress.com/2008/11/image2.gif

    Fig 2. CCWRD. 4/27/2010. http://www.cleanwaterteam.com/aboutus_rev.html

    http://saferenvironment.files.wordpress.com/2008/11/image2.gifhttp://saferenvironment.files.wordpress.com/2008/11/image2.gif