reply to 11th eac mom dynamic rev 2
TRANSCRIPT
Date: 02.02.2017
To, The Director, Infrastructure and Miscellaneous Projects & CRZ Indira Paryavaran Bhavan Jor Bagh Road, New Delhi - 110 003
Sub: Application for Prior Environmental Clearance for Proposed Residential and Commercial Project at S. NO. 147/8, 147/9, 147/10, 147/11, 148/2, 148/1A, 200/3, 148/1A of village Khidkali, Thane, Maharashtra.
Ref: Minutes of 11P
thP EAC (Infra-II) meeting held on 24.11.2016
(Item no. 11.2.14) (File No. 21-10/2016-IA-III)
Dear Sir,
We are very much thankful to Expert Appraisal Committee (Infra-2) for appraising our above referred project in its 11P
thP Meeting held on 24.11.2016
(Item no. 11.2.14)
As per the minutes of the meeting, we were asked to comply with certain points raised by committee. The point wise reply to the queries raised is enclosed herewith. We hope that reply is in line with your requirement.
Thanking you, Yours faithfully, FOR DYNAMIC BUILDTECH LTD.
Enclosures: 1. As above
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page1
POINTWISECOMPLIANCETOQUIRIESRAISEDDURING11thEAC(Infra‐II)MEETING
PointNo.1: StatusofapplicationoftheprojectproposalinSEIAA,Maharashtra.Compliance: The application is not considered at SEIAA, Maharashtra as the
SEACMMR’stenureisoverandthereisnocommitteeforappraisalof projects. Hence,we have applied toMoEF&CC, Delhi on dated28.10.2016.
PointNo.2: CopyofapplicationsubmittedforclearancefromNBWL.Compliance: Ourprojectsite isabout14kmfromSanjayGandhiNationalpark
(SGNP) i.e. outside of ESZ i.e. (100m); hence clearance from theStanding Committee of the National Board for Wildlife is notapplicabletoourproject.
PointNo.3:Presentlanduseoftheproposedprojectsite.Compliance: Present landuse of proposed project site is for Residential cum
commercial development as per the DP of Thane MunicipalCorporation&thesameisshowninFigureNo.1.
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Pag
Figure1:DevelopmentplanofThaneMunicipalCorporation
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page3
PointNo.4: DistanceofKhidkaLakefromtheprojectsite.Compliance: DistanceofKhidkaliLake from theproject site is about8m&
fromthebuildinglineisabout100m.DistanceofKhidkalilakefrom the project site is superimposed onDevelopment plan&showninFigureNo.2.
FigureNo.2:DistanceofKhidkaliLakefromprojectsite
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page4
PointNo.5: HighestwaterlevelofKhidkaLake.Compliance: As per the HFL Certificate received from Thane Municipal
Corporation,highestwaterlevelobservedis2.80m.Thecopyofcertificatereceivedisattached.
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page5
PointNo.6: Detailsofno.offlooralongwithbuiltupareatobeconstructedineachblocktobefurnished.
Compliance: Detailsofno.offlooralongwithbuiltupareatobeconstructed
ineachblockisgivenbelow.
A
241.76 X 4 = 967.04
------
1 B
C
2
29TH PART. FLOOR
309.87 X 1 = 309.87
384.01 X 1 = 384.01
356.89 X 19 = 6780.91
320.96 X 04 =1283.84
237.42 X 1 = 237.42
295.62 X 01 = 295.62
275.18 X 19 = 5228.42
310.77 X 1 = 310.77
384.01 X 01 = 384.01
356.89 X15 = 5353.35
324.15 X4 = 4538.10
327.90 X 01 = 327.90
311.50 X 22 = 6853.00
279.33 X 5 = 1396.65
60.87 X 1 = 60.87
310.77 X 1 = 310.77
355.40 X 4 = 1421.60
407.23 X 1 = 407.23
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page6
PointNo.7: Commitment that shops and other establishments in
residential blocks with have to conform to residential areanorms in terms of noise pollution and vehicular movementsandshallnotcreateanuisanceforresidentsoftheBlocks.
Compliance: Weherebyconfirmthatshopsintheresidentialblockswillnot
create any nuisance due to noise pollution and vehicularmovements. We have provided separate entry and exit forcommercial as well as residential users. All the shops are ofsmallsizeandforthepurposeofconvenientshoppingneedsoftheresidents.
PointNo.8: Layout plan indicating road, greenbelt, drainage, sewer line,
STP,solidwastehandlingarea,rainwaterharvestingstructure,etc.indifferentcolourtobefurnished.
Compliance: Co‐ordinated drawing showing Layout plan indicating road,
greenbelt,drainage,sewerline,STP,solidwastehandlingarea,rainwaterharvestingstructureetc.withdifferentcolourcodesisshowninFigureNo.3
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page7
FigureNo.3:Co‐ordinateddrawingshowingallservices
ENTRY /EXIT
D.P
. RO
AD
M.I.
D.C
. PIP
E LI
NE
APPROCH ROAD(PROPOSED)
M.I.
D.C
. PIP
E LI
NE
60.00 M WIDED.P. ROAD LINE
INGD LINE
U.G. TANK
30.00 M WIDE D.P. ROAD
6.00 M WIDE DRIVEWAY
9.00
M W
IDE
INTE
RNA
L RO
AD
6.00 M WIDE DRIVEWAY6.00 M WIDE DRIVEWAY
RG 21018.86 SQ.M.
RG 1686.86 SQ.M.
ELEVATED GARDEN
6.00 M WIDE DRIVEWAY
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page8
PointNo.9: Layout of parking plan indicating entry and exit points ofvehicular movement as well as traffic management plan.Highlightthefiretenderpathway.
Compliance: Wehaveprovidedparkingaspertherules.Layoutofparking
plan indicating entry/exit points of vehicular movement aswellastrafficmanagementplanwiththefiretenderMovementisdiscussedbelow.
TableNo.1:Parkingstatementforproposeddevelopment
OCCUPANCY CARPETAREA NO.OFTENAMENTS
REQD.PARKINGS
NO.OFPARKINGS
Residential
Below35.0m2 553 Nil ‐
35.0To50.0m2 56 1P./2
Tenements 28
50.0To75.0m2 48 1P./1
Tenement 48
Above75.0m2 ‐‐ 2P./1
Tenement ‐‐
Total 657 76Add10%VisitorsParking 84Wheeler‐ParkingRequired 84
Commercial
(625.89m2)
1Parkfor25m2inareaupto400m
2 16
1Parkfor50m2inareaexceeding 5
4Wheeler‐ParkingRequired 21Total4WheelerofParkingRequired(Res+Com.) 105Total4WheelerofParkingProvided 115Total2WheelerofParkingRequired 664Total2WheelerofParkingProvided 664
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page9
FigureNo.04:ParkingPlanShowingEntry&ExitforvehicularMovement
4Wheeler 2Wheeler
StiltParking
Bldg1(WingA) 16 19
Bldg1(WingB) 12 24
Bldg1(WingC) 16 18
Bldg2 46 75
OpenParking 25 527
Total 115 663
2Wheelers
4Wheelers
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page10
TRAFFICANALYSISThetrafficsurveywasconductedtoascertainthepresenttrafficscenarioalongKalyan‐ShilphataRoadtoevaluatetrafficimpactthatwillresultfromproposeddevelopment.The twokey componentof study included theassessmentof thepresentScenarioandimpactontrafficduetotheproposeddevelopment.
COMPARISION OF CONGESTION INDICES (V/C RATIOS) ON KALYAN‐SHILPHATAROADTableNo.2:PeakHourPCUCount
TableNo.3:PeakHourPCUCount,LevelofServicesandGeneralOperatingConditions
ROAD YEAR PROJECTEDPCU/hr
CapacityofRoad
V/C LOS
Kalyan‐ShilphataRoad
Present 1457 3600 0.40 B
5 1748 3600 0.49 C
10 1894 3600 0.53 C
Sr.No. Road
2 Wheeler Auto Car LCV Bus Truck Total
1 Kalyan‐ShillPhataRoad (30mWide)
234 553 402 62 129 77 1457
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page11
Present statusof traffic congestion is shownTableNo.02basedon that trafficmanagementhasbeenprepared&givenbelow:
TRAFFICMANAGEMENTPLAN
Proper traffic control measures will be provided to regulate theflowoftraffic/tostreamlinethetrafficflow
Adequatetrafficsignswillbeprovidedtonotifytheresidents. 2 entry gates of 9 m each are planned for the proposed project
whichwillhelpinevendistributionoftraffic. Multiple entries and exits are provided on different roads which
willprovideflexibilitytoenterandexittheproposeddevelopmentduringpeakhours.
Speedhumps/SpeedBreakerswillbeprovided for trafficcalmingandrestrictingtheinternalvehicularspeedto10km/hr.
Trafficwardenswillbeassigned(atparking level) toregulate thetrafficflow.
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page12
FigureNo.4:FireTendermovementPlan
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page13
PointNo.10: Detailsof sourceofwatersupplyalong‐withpermission tobesubmitted.
Compliance: Water Source will be available from Thane Municipal
Corporation.PointNo.11: Excesstreatedsewagedisposalplan/schemetobesubmitted.Compliance: Excess treated water from our project will be disposed in
Municipalsewerlines.PointNo.12: PPshallCommitthatduecareshallbetakentoensurethatthe
recycledwaterdoesnotcomeintocontactofhumansCompliance: Weherebycommittedthattherecycledwaterwillbeusedfor
Flushing&Gardeningpurposesonlytoreducethefreshwaterdemand & the excess treated water will be disposed inMunicipalsewerlines.
PointNo.13: Assessmentofgroundlevelconcentrationofpollutantsdueto
DGset(600KVA).Compliance: Assessmentofgroundlevelconcentrationofpollutantsdueto
DGsetoftotal600KVAisasfollows:
Diesel generator sets operated for back‐up power supply &Emissions from vehicle in parking lots are identified as theonlymajor sources of gaseous and particulate emission. SO2,SPM, NOX and CO emissions are expected due to fuelcombustion in generator sets and vehicular emission.However, use of low sulphur fuels will reduce the impactsconsiderably.
The DG set operation will also contribute towards the airpollution. The total installed capacity of the DG sets for theproposedproject is about total600KVA.TheseDG setshavebeenprovidedtotakecareofpoweravailabilityduringpowerfailurefromtheMSEDCL.HoweverintheThaneCitya24hrselectricity issupplied,butonaprecautionarybasis theaboveDGsetshavebeenproposedincaseofanyemergenciesarisingoutofroutinepowerfailure.TheimpactoftheDGsetsontheenvironmenthasalsobeenstudiedusingmathematicalmodelforascertainingthegaseouspollutantimpact.
It was observed that the predominant wind direction at theprojectsiteisNWandwest.TheAverageWindSpeedwas2.46m/s.WindroseispresentedinFigure6.
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page14
The results of the mathematical model indicate that themaximum incremental increase in the SO2 concentration is0.40 ug/m3 which will not increase any significantconcentrationtotheexistingambientlevels.TheIsoplethsof predicted SO2 concentrations is given in Figure7. This isconfined to a small area of 400m in and around the projectsite.Thepredictedconcentrationsfromthemodelwillnotleadto alter the baseline concentrations as it is well within thenormsstipulated.
Also the attempt has been made to assess the impact ofproposeddevelopment intermsofairqualityonsurroundingareaduetoincreaseinvehicletraffic.
The internal vehicularmovement and entry and exit locationare also strategically planned so as to avoid congestion andensuresafeandcomfortablepassageofthevehicles.FigureNo.6:WindRoseofstudyarea
NORTH
SOUTH
WEST EAST
7%
14%
21%
28%
35%
WIND SPEED (m/s)
>= 11.1
8.8 - 11.1
5.7 - 8.8
3.6 - 5.7
2.1 - 3.6
0.5 - 2.1
Calms: 20.88%
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page15
FigureNo.7:IsoplethsofPredictedConcentrationsforSO2
PointNo.14: EffortshallbemadetoreducecapacityofDGsetupto300KVA
andremainingstandbypowershallbemetfromsolarenergy.Compliance: WewillreducecapacityofDGsetupto300KVAandremaining
standby power will be met from solar energy i.e. Solar PVpanels.
PointNo.15: Treatmentschemeforsewageanditsrecyclingmode.Compliance: Totalwaterrequirementduringoperationalphaseisabout446
KLD.Sewagegenerationisabout416KLDwhichwillbetreatedin450KLDSTPofMBBRTechnology.Weare reusing treatedwater for gardening (10 KLD) & flushing (149 KLD). ExcessTreatedWaterwillbedisposedtoMunicipalSewerlines.
-1000 -800 -600 -400 -200 0 200 400 600 800 1000-1000
-800
-600
-400
-200
0
200
400
600
800
1000
0.10 ug
0.20 ug
0.30 ug
0.40 ug
GLC:Total600kVADGSET
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page16
FigureNo:8:TreatmentschemeforSTP
PointNo.16: Detailsofrainwaterharvestingsystemtobefurnished.Clarity
on recharge pits, storage systems for rain water and use ofappropriate filtration system for collected rain water to bedetailed.
Compliance: TherooftoprainwaterwillbestoredinRainWaterHarvesting
tanks after filtration. The roof top Rain water harvestingpotentialproject is24m3/day&theprovisionof1RainwaterHarvesting tank having capacity 50m3 will be provided. Therooftopwaterwillbefilteredthroughcoarseandfinesandandthen itwillbestored in theTank.Thesectionof the filtrationarrangementisshowninfigureno.9.
1
INLET FROM COMPLEX
416 m³/day
RAW SEWAGE
2
AIR BLOWER
AIR BLOWER
5
9
FILTRATE TORECEIVING
SUMP
SLUDGEUSE ASMANURE
6
NaOCl DOSING
TO FILTER PRESS
TREATED WATERFOR RECYCLING
7
B ACK WASH LINEB ACK WASH LINE
8LEGEND
2 ) AERATION TANK (MBBR TANK)1) RECEIVING SUMP
6) TREATED EFFLUENT SUMP
3 ) FLASH MIXER
4 ) FLOCCULATOR
5 ) SETTLING TANK
9) FILTER PRESS (xx CHAMBER)
7) PRESSURE SAND FILTER
8) ACTIVATED CARBON FILTER
AERATION TANK FILLED WITH MEDIA
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page17
FigureNo9:RWHfiltrationunit
PointNo.17: Amanagement plan for excavation and dewatering to ensurecompliancetotheCGWAguidelinesandregulation.
Compliance: Therearenobasementsproposedresidentialcumcommercial
buildings.Excavationwillbedoneforfoundationpurposeonly.Duringtheexcavationactivity fortheprojectasedimentationtankofsize2mx2mx3.5mwillbeprovidedonsitetoensuresedimentationofthedewateredgroundwater.
Followingmeasureswillbetaken inaccordancetotheCGWAguidelinesduringexcavationfordewateringifthewatertableintersectswiththeexcavation:
1. The dewatered quantum will first be settled in thesedimentation tank. The sedimentation tank is given in thefollowingfigure:
100 MM THK. PCC230 MM THK.
RUBBLE PACKING
GR.LVL.MANHOLE600MM x 900 MM
150 MM Ø PVC PIPEWITH CAP DRAIN OFF
FIRST RAINWATER
PIPE CARRYINGTERRACE
RAIN WATER
MANHOLE450MM x 900 MM
MANHOLE600MM x 900 MM
150 MM THK. RCC WALL
150 MM Ø PIPES (2NOS)WITH CAP CONNECTING
VALVE CHAMBER TOFILTERATION CHAMBER
RCC SLAB
STEEL BARS EMBEDDEDIN RCC WORK FORLADDER PURPOSE
150 MM THK.
MANHOLE600MM x 900 MM
MANHOLE600MM x 900 MM
150 MM Ø PIPE CONNECTINGFILTERATION CHAMBER TO
COLLECTION TANK
SECTION X-X
OVERFLOWPIPE TO S.W.D.
STAINLESSSTEEL (SS) SCREEN PIPE
RCC SLAB
300
GR.LVL.
1ST BASEMENT LVL.
150 MM Ø PVC PIPEWITH CAP DRAIN OFF
FIRST RAINWATER
PIPE CARRYINGTERRACE
RAIN WATER
MANHOLE600MM x 900 MM
230MM THK. BRICKWALL WITH PLASTER
ON BOTH SIDES
350MM THK. BRICKWALL WITH WATERPROOFING & PLASTERON BOTH SIDES
STAINLESSSTEEL (SS) SCREEN PIPE
MANHOLE450MM x 900 MM
MANHOLE600MM x 900 MM
150 MM Ø PIPES (2NOS)WITH CAP CONNECTINGVALVE CHAMBER TOFILTERATION CHAMBER
OVERFLOWPIPE TO S.W.D.
MANHOLE600MM x 900 MM
MANHOLE600MM x 900 MM
150 MM Ø PIPE CONNECTINGFILTERATION CHAMBER TOCOLLECTION TANK
VALVE CHAMBER
STEEL BARS EMBEDDEDIN BRICK WORK FORLADDER PURPOSE
FILTERATION CHAMBER COLLECTION TANK
X X
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page18
FigureNo.5:SedimentationTank
2. The dewatered quantum will be utilized for dust suppressionand/orforartificialrechargetogroundwater.
PointNo.18: Calculation on sizing of solar water heating systems to be
furnished.Compliance: Looking at the long term cost effectiveness, efficiency &
requirementofelectricityratherthanthesolarhotwatersystem,we are producing about 103 kW of energy through solar PVpanels. Hence, the arrangement of solar water heating systemswillnotbepossible.
PointNo.19: At least2solarpowered lightsandone fanshallbeprovided in
eachflat.Solargenerationshallbeconnectedtothegrid.Compliance: Wewillprovidesolarlighting(twolightsandonefan)ineachflat
byconnectingsolargenerationtothegrid.
SOLARPVPANELCALCULATION
TotalTerraceArea 1,207.19m2
PotentialofPVPowergeneration 103kW
Powerrequirementof2lightsand1fanConnectionfor389tenements
80Wx657=53kWapprox.
SolarPowertoGrid/DGBackup 50kW
PointNo.20: Solid waste management plan along with area earmarked for
solidwastemanagementscheme.Compliance:DetailsofSolidWasteManagementisasfollows:
TotalSolidwastegeneration :1,653kg/day Thebiodegradablecomponentis :992kg/day Inert,recyclablewasteis :661kg/day
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page19
Segregationofdryandwetgarbagewillbedoneatsource Thebiodegradable&non‐biodegradablewastewillbesegregatedatsource
Drygarbageasinert/recyclablewastesuchasplastics,glass,metals,rubberwillbesegregatedanddisposedofftorecyclers
Wetgarbage/biodegradablematterasleftoverfood,vegetableswillbecompostedusingmechanicalcomposting (Eco‐Biocompack).
1compostingunitof1000kg/dcapacitywillbeprovided Spaceprovided:40m2
AreaearmarkedforSolidwastemanagementinlayoutisshowninfigureNo.12.
SOLIDWASTEMANAGEMENTPLAN
Domestic Solid Waste
661 kg/d Dry Garbage
Gardening Landscaping
Recycling
Mechanical composting
At Source
991 kg/d Wet Garbage
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page20
AREASEARMARKEDFORSOLIDWASTEMANAGEMENT
Wastestoragearea
Ecobiocompackunit
Recyclablestoragearea
Briquettingplant
Compostcollectionroom
Cartwash
8m
5m
5m
2m
1.5m1.5m
2m
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page21
Figure12:LocationofSolidWasteManagement
ENTRY /EXIT
D.P
. RO
AD
M.I.
D.C
. PIP
E LI
NE
APPROCH ROAD(PROPOSED)
M.I.
D.C
. PIP
E LI
NE
60.00 M WIDED.P. ROAD LINE
INGD LINE
U.G. TANK
30.00 M WIDE D.P. ROAD
6.00 M WIDE DRIVEWAY
9.00
M W
IDE
INTE
RNA
L RO
AD
6.00 M WIDE DRIVEWAY6.00 M WIDE DRIVEWAY
RG 21018.86 SQ.M.
RG 1686.86 SQ.M.
ELEVATED GARDEN
6.00 M WIDE DRIVEWAY
SWMArea
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page22
PointNo.21: Managementof excavated soil.Pollution controlmeasures tobetaken to control fugitive emission during construction phaseincludingmarble/stonecutting.
Compliance: ExcavatedsoilwillbeusedfortheRoadpavement&siteleveling.
Fugitive emission during construction phase will be control byBarricading & plantation along the plot boundary, watersprinkling at regular interval to arrest Air Bourne‐dust, Use ofReadyMixconcrete toavoidexcessivemovementofvehiclesonthesitethatwillreducefugitiveemissionsandnoise.
PointNo.22: Details energy conservation measures to be taken (all points
mentionedintheproposalsuchasorientationtosupportreducedheat gain,useofASHRAE90.1,useofECBC compliant envelopemeasures to be supported through drawings and details in theproposal.
Compliance: Internalandexternallightingdesignwillbeprovidedasrequired
by ECBC which will have Lighting Power Density as per spacerequirements.Theprojectwouldprovide20%lowerLPDthanasspecified inECBC, toachieveenergysaving,whileproviding therequired illumination levels,byusinghighefficacy lighting.Treeplantation is proposed along the periphery of the site ensuringadequatebufferandreducingheatgainbythebuildingsothatthebuildingswillremainnaturallyventilated.Theprojectdesignwillusehighenergyperformingbuildingmaterialswhichwouldhavelow U value (Thermal Conductance) as compared to theconventionalmaterials. The externalwall of buildingwouldusefly ash blocks,whichwill havemandatory SHGC as requiredbyECBC.
The building envelop is proposed to comply with the ECBCguidelinesanditsparametersaregiveninTableNo.6.
TableNo.6:BuildingEnvelop
Wallassembly
‘U’Value– 0.14btu./sq.ft.Hr.FOR0.79W/m20KCanbeeasilyachievedbyusing6”AACblockswithlowerthermalconductivity.
Roofassembly
Roofinsulationentirelyabovedeck,‘U’Value–0.275btu./sq.ft.Hr.FOR1.56W/m20KCanbeeasilyachievedbyusing4”brickbatkoba.ThisiswillbefurtherimprovedbyprovisionofSolarPVPanelonrooftopforElectricitygeneration
Highperformance
‘U’Value ‐ 0.97btu./sq.ft.Hr.FOR5.5W/m20KS.H.G.C. ‐0.56
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page23
fenestration V.L.T. ‐ 51%CanbeachievedbyusingSaintGobainST1506mmhighperformanceglass.
PointNo.23: Layout plan indicating Greenbelt along‐with area earmarked to
beprovided.Compliance: Total RG area required as per rule is 1845.07 m2 & RG area
provided on Ground is 1967.46 m2. Layout plan indicatingGreenbelt along‐with area earmarked is shown in figureNo. 13
DYNAMICBUILDTECHLTD
Replyto11thEACMeeting Page
FigureNo.13:LandscapePlan
30.00 M WIDE D.P. ROAD
6.00 M WIDE DRIVEWAY
RG ON GROUND1075.57 sq.m.
9.00
M W
IDE
INTE
RNA
L RO
AD
GROUND LVL PLAN (+0.00 M LVL)
ELEVATED RG949.29 SQ.M.
Jogging Track
6.00 M WIDE DRIVEWAY
ALBIZIA LEBBECK (SHIRISH)@4.50 M.C/C-(6 NOs.)
MICHELIA CHAMPACA(SONCHAFA )@1.80 M.C/C-(6 NOs. )