redispatch and countertrade costs - thema.no€¦ · leading to relatively high redispatch and...

26
Redispatch and Countertrade Costs The Impact of German Bidding Zones Final Report

Upload: others

Post on 26-Sep-2020

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

1.png 1.bb

Redispatch and Countertrade CostsThe Impact of German Bidding ZonesFinal Report

Page 2: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

Project infoClientStatnett

Project numberSTN-19-04

Project nameBidding zones and redispatch

Report infoReport availabilityPublic

THEMA report number2020-01

Date of publicationJanuary 2020

About the projectTheGerman Energiewende has led to grid congestion in Germany, which is currently handled bymeans of redispatchand countertrade. This report evaluates to what extent bidding zones may be used as an alternative measure toaddress and handle grid congestion, and how the introduction of bidding zones may impact market prices, trade,and redispatch costs and volumes.

Project teamProject managerArndt von Schemde

Contributors (alphabetically)Anders L. EriksrudJulian HentschelArndt von Schemde

Page 3: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

Contents

Contents

1. Executive Summary 4

2. Background 62.1. Scope of work and mandate . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62.2. Grid congestion in Germany . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62.3. Options to address internal congestion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 7

3. The effect of potential bidding zones 83.1. Description of analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 83.2. Current HVDC projects address issues in 2025, but may not suffice for 2030 and beyond . . . . . . . 93.3. Bidding zone delimitation can address grid bottlenecks . . . . . . . . . . . . . . . . . . . . . . . . . . 113.4. Bidding zone delimitation may be an efficient way to manage congestion . . . . . . . . . . . . . . . . 15

A. Appendix: Model and Methodology 19A.1. Methodology . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19A.2. Models applied in the analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21A.3. Key assumptions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 21

A. Acronyms 24

©THEMA Consulting Group (2020) 3

Page 4: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

1. Executive Summary

Background

The Energiewende in Germany has resulted in regionalimbalances in the German electricity system. Whilethere is modest electricity demand in northern Germany,there is a vast amount of installed wind power capacity.In the south of Germany, electricity demand normallyexceeds generation. Large flows of electricity fromnorthto south are therefore needed to supply the demandcenters in the south.

This imbalance has, in recent years, led to an in-crease in redispatch costs in Germany (Figure 2.1). Inlight of this development, the Transmission System Op-erators (TSOs) in Germany are planning High VoltageDirect Current (HVDC) lines between north and southGermany.

Findings

In this report, we analyse internal German grid conges-tion, and towhat extent the introduction of bidding zoneswithin Germany may address future grid congestion andreduce redispatch costs. Our main findings from theanalysis are summarised below.

Even with HVDC grid investments, bottlenecks willincrease again towards 2030 Most of the congestionwithin the German grid will be resolved by 2025 ifthe planned HVDC investments are in place. In thiscase, the simulation results show a substantial drop inredispatch costs up until 2025 (Figure 3.5). If biddingzones are introduced, we estimate relatively small pricedifferences between the zones in 2025 in this scenario(Figure 3.9).

However, by 2030, with further expansion of offshorewind in the north, and additional changes in the Germangeneration mix, the simulation results show that redis-patch costs begin rising again. This indicates that theplanned transmission investments may be sufficient for2025, but may not be sufficient for the situation in 2030.

In case grid development is delayed, we expect signi-ficant congestion If the HVDC lines are delayed, thesimulation results show significant internal congestionin the German system. This is reflected by highredispatch costs if Germany keeps the single biddingzone configuration. If German bidding zones areintroduced in this situation, there will be significant pricedifferences between zones, which is another indicatorof the severity of the bottlenecks (Figure 3.10).

Bidding zones are a potential measure to addressbottlenecks and reduce redispatch costs The simula-tion results show that the introduction of bidding zonescan contribute to a significant reduction in redispatchcosts. In general, the finer the bidding zone granularity,the smaller the redispatch costs (if bidding zones wereconfigured on a nodal level, redispatch costs would bezero).

Our simulations show a substantial reduction in re-dispatch costs if moving to an appropriate two-zoneconfiguration, where the wind-heavy northernmost partof Germany is separated from the rest of the country.Further reductions in redispatch costs from introducingeven more zones are rather limited. A two-zone config-uration with a small southern zone consisting of Bayernand Baden-Württemberg is less effective at reducingredispath costs – themain challenge is a surplus of windgeneration in northern Germany.

Evaluation

Bidding zone delimitation would clearly contribute toa reduction in redispatch costs. In addition, it wouldprovide more efficient price signals, which are importantboth for the long and short-term efficiency of the electri-city market. Even though it may be difficult (or even im-possible) to find an ”optimal” bidding zone configuration,we find that a configuration that reflects major existingimbalances yields significant reductions in redispatchcosts. An inability to identify an ”optimal” solution is nota valid argument against implementing a better solutionthan the current market design.

4 ©THEMA Consulting Group (2020)

Page 5: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

1. Executive Summary

At the same time, there are also valid argumentsagainst bidding zone delimitation. Potential effects onfinancial market liquidity and long-term investor confid-ence should be considered in this context. There mayalso be some regulatory challenges related to the designof the German support system for renewable generationand for other regulation.

However, severe grid congestion must be addressedsomehow. Ignoring grid bottlenecks in the day-aheadmarket implies that they have to be resolved outside ofthe market. With internal grid congestion increasing,using these alternative means is likely to become moreand more challenging.

©THEMA Consulting Group (2020) 5

Page 6: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

2. Background

2.1. Scope of work and mandate

This report studies the effects of introducing biddingzones in theGermanelectricitymarket, with an emphasison redispatch and countertrade costs. The study wascommissioned by Statnett.

The study is based on THEMA assumptions, andpublicly available data, e.g. data from the German griddevelopment plan and planned transmission lines.

2.2. Grid congestion in Germany

The Energiewende in Germany has resulted in regionalimbalances in the German electricity system. Whilethere is modest electricity demand in northern Germany,there is a vast amount of installed wind power capa-city. In southern Germany, electricity demand normallyexceeds generation. Large flows of electricity fromnorthto south are therefore needed to supply the demandcentres in the south.

Figure 2.1.: Development of Redispatch Volumes in TWh inGermany. Sources: Bundesnetzagentur and BDEW.

Since the resulting internal grid congestion is notfully accounted for in the day-ahead market, redispatchcosts and volumes have increased substantially in re-cent years. This is illustrated in Figure 2.1, which shows

developments in redispatch volumes in Germany since2013. Increasing redispatch volumes drive up the costsof congestion management, which amounted to around1.4 billion Euros in 2017. Furthermore, internal Germancongestion results in loop flow issues with neighbouringcountries.

The issues related to congestion are addressed inGermany’s grid development plan. The planned HVDClines between north and south Germany play an im-portant role in handling these regional imbalances, andshould be in place by 2025, according to the grid devel-opment plan. These lines are meant to transport largevolumes of wind power from the north, to areas withhigh demand in southern Germany. This is illustratedin Figure 2.2, in which the red-dotted lines illustrate theplanned HVDC lines.

Figure 2.2.: Illustration of the currentgrid development plan. Source: ht-tps://www.netzausbau.de/leitungsvorhaben/de.html

All but one of the planned HVDC projects are under-ground cables:

6 ©THEMA Consulting Group (2020)

Page 7: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

2. Background

Brunsbüttel – Großgartach (SuedLink)

Wilster – Grafenrheinfeld (SuedLink)

Emden Ost – Osterath (A-Nord)

Wolmirstedt – Isar (SuedOstLink)

The only overhead HVDC project is the line betweenOsterath and Philippsburg (Ultranet).

2.3. Options to address internalcongestion

Internal grid congestion can be addressed by a numberof measures, or a combination of these.

If the day-ahead market clearing solution resultsin grid congestion, the Transmission System Operator(TSO) may resolve this through redispatch measures.That is, it can oblige a generator to increase generationon one side of the bottleneck, and another generator todecrease generation on the other side, compensatingboth accordingly. Another possibility to tackle conges-tion is to compensate foreign generators (or consumers)for adjusting their output (or demand), in order to adjustinterconnector flows. We refer to this as countertrade.

To mitigate any grid congestion from the day-aheadmarket schedule, the TSO may limit the transmissionflowson interconnectors. In some instances, lower inter-connector flows will result in less congestion. However,from 2020, new EU regulation obliges TSOs to make atleast 70% of cross-zonal transmission capacity avail-able to the market. There will therefore be less room tolower transmission capacity below 70% as a means tohandle internal grid congestion.

Bidding zone delimitation can also address bottle-necks in the grid if designed appropriately. When thetransmission grid is congested, zonal prices diverge inorder to balance the system and relieve any congestion.The benefit of bidding zone delimitation is that gridcongestion is handled in the market, and that marketparticipants face a price that signals the marginal valueof electricity in their location. This leads to more effi-cient market clearing and reduces the need to performredispatch and countertrade. In addition, bidding zonedelimitation may provide better locational price signalsfor investments in new generation capacity or consump-tion. Diverging zonal prices may, for instance, give

an industrial company the necessary incentive to sitenew consumption in a region with cheap and abundantelectricity generation.

There is, however, no objective way of defining theoptimal bidding zone configuration. Even though ad-dressing future bottlenecks should be the overall object-ive, no objective method to design the optimal set ofbidding zones exists, both in terms of number of zonesand their borders. Though more bidding zones mayhelp reduce congestion management costs, they mayalso reduce efficient hedging opportunities, and therebyincrease the cost of hedging.

Note that other countries like Norway, Sweden andDenmark already use bidding zones in order to addressbottlenecks. In Norway, the Norwegian TSO Statnetthas a dynamic approach to handling grid bottlenecks.Statnett not only alters the number of bidding zones fromtime to time, but also occasionally moved the biddingzone borders in order to reflect changes in physicalbottlenecks, e.g. after new lines are completed.

©THEMA Consulting Group (2020) 7

Page 8: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

3. The effect of potential bidding zones

3.1. Description of analysis

This chapter presents the results from the analysis of theeffects of introducing bidding zones in Germany.

We first find the day-ahead market clearing solutiongiven a certain bidding zone configuration. Then, wefind the optimal dispatch on a nodal level. Finally, wecompare the two solutions, and the difference repres-ents the estimated redispatch and countertrade costsand volumes. The methodology and model frameworkis described in more detail in Appendix A.

Note that in our analysis, we assume that the TSOscan always achieve the nodal-optimal solution via re-dispatch and countertrade measures, independent ofthe starting point that the day-ahead market solutionprescribes. We do therefore not investigate the impacton total economic welfare, since one always ends upwith the same (nodal-optimal) dispatch eventually.

Instead, redispatch and countertrade costs andvolumes serve as an indicator of:

a) how good or bad a specific bidding zone configura-tion is, and

b) how severe the internal bottlenecks are.

High redispatch volumes and costs can be seen asan indicator of high internal congestion and an inefficientbidding zone design. While one may argue that TSOscan eventually achieve the same nodal solution via redis-patch, in real life, the TSOs may not be able to achievethis solution in a cost-effective manner. In addition,spot prices that do not account for bottlenecks may beinefficient, not just in terms of short-term dispatch andtrade, but also in terms of their impact on long-terminvestment signals.

We do not model any market imperfections or issuesrelated to market power. We have consciously decidedto leave these topics outside our fundamental model.Trying to account for these issues in the quantitative ana-lysis makes the results somewhat arbitrary, as there is a

strong danger of over-parameterising and over-fitting theresults. Instead, we discuss these issues in a qualitativemanner later in the report.

In the analysis, we study the following two scenarios:

Case 1 – No grid delay: In the default case, weassume that all prospective grid investments are im-plemented as planned and as outlined by the currentGerman grid development plan.

Case 2 – Three year grid delay: In this scenario, weassume that all grid projects are delayed by threeyears. This affects the HVDC projects in particu-lar. According to recent statements by Bundesnetza-gentur representatives, a delay of some HVDC linesseems to be highly likely. As most of the HVDC linesare planned to start operation in 2025, this meansthat none of these lines are included in 2025 in thisscenario. The choice of a three year delay for allgrid development projects is somewhat arbitrary andmight be overstated, but this assumption provides atransparent scenario outlining the effects of substan-tial delays in grid development.

In our analysis, we investigate the effects of intro-ducing up to four bidding zones. An illustration of thebidding zone topologies used is shown in Figure 3.1.As discussed in Chapter 2, there is no objective way ofdesigning the optimal bidding zone configuration. Thus,our assumptions represent potential configurations, butwe do not claim or argue that any of our suggestions isoptimal. However, as we will see, some of the resultstend to be robust across alternative bidding zone config-urations.

In defining the four-zone configuration, we have star-ted with the zonal configuration from the ’Big CountrySplit 2’ scenario in the first edition of the bidding zonereview by ENTSO-E.1 The zones DE1d and DE3d aredirectly adopted from ENTSO-E, and two more zones(DE2d and DE4d) in the north and north-east of Germanyare introduced to arrive at our four-zone configuration.1https://www.entsoe.eu/news/2018/04/05/first-edition-of-the-bidding-zone-review-published/

8 ©THEMA Consulting Group (2020)

Page 9: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

3. The effect of potential bidding zones

(a) Two-zone configuration. (b) Three-zone configuration. (c) Four-zone configuration.

Figure 3.1.: Bidding zone configurations in the analysis.

The two and three-zone configurations contain dif-ferent subsets of the four-zone configurations. In thetwo-zone configuration, the northernmost zone (DE4d)is kept, and zones DE1d, DE2d and DE3d are mergedinto one, whereas in the three-zone configuration, thenorthernmost (DE4d) and southernmost (DE1d) zonesare kept, while DE2d and DE3d are merged to one.

Figure 3.2 shows the generation per bidding zonein 2025 by week. The northernmost zone (DE4d) isdominated by wind power, and has a large surplus ofgeneration. The southernmost zone (DE1d), on the otherhand, is a deficit zone. Supply and demand are morebalanced in the zones DE2d and DE3d.

3.2. Current HVDC projects addressissues in 2025, but may notsuffice for 2030 and beyond

Our simulations indicate that the costs for redispatchand countertrade will remain high in the coming decade.Figure 3.3 shows the simulated level of redispatch andcountertrade compensation in the one-zone configura-tion (status quo).2

The simulated redispatch and countertrade com-pensation in 2020 is significantly higher than historical2The source for the historical values (before 2020) is Bundesnet-zagentur, and includes counter trading, redispatch and feed inmanagement.

values, and reflects increases in grid congestion over thecoming years. However, in 2022 the simulated redis-patch and countertrade compensation decreases mod-erately due to some underlying changes in the thermaland nuclear capacity mix in that period.

For 2025, we run two scenarios with very differentresults. In the scenario without grid delays, the redis-patch and countertrade compensation is low, indicatingthat there are few severe bottlenecks in the transmissiongrid. That implies that planned grid development up to2025 would address the most important bottlenecks inthe grid.

However, in the event of three-year delays in all Ger-man transmission grid development, more congestion isto be expected in the grid relative to both today and 2020.This is mostly attributable tomore onshore and offshorewind capacity.

Our simulations show significant grid congestionleading to relatively high redispatch and countertradecosts in the simulations by 2030. In the 2030 sim-ulations, we assume that projects in the current griddevelopment plan are built, including all the plannedHVDC lines. By 2030, wind power generation in northernGermany, particularly from offshore wind farms, furtherexpands, which exacerbates grid congestion. We as-sume 15GW of offshore wind by 2030, reflecting thecurrent German target. Note that there is currently adebate on whether the offshore wind target for 2030should be increased.

©THEMA Consulting Group (2020) 9

Page 10: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

Figure 3.2.:Weekly generation per bidding zone in 2025 in the four-zone configuration.

10 ©THEMA Consulting Group (2020)

Page 11: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

3. The effect of potential bidding zones

Figure 3.3.: Simulated redispatch and countertrade com-pensation paid by the German TSOs in the one-zone config-uration (real 2019 EUR).

In short, should the HVDC lines be delayed, our es-timates for redispatch indicate significant bottlenecksby 2025. In the event that the HVDC lines are built, theysolve the bottleneck issue in 2025, but increasing windvolumes towards 2030 will increase internal congestionyet again. This implies the need for a proactive approachto transmission investments beyond what is currentlyplanned and outlined. Note that the TSOs are also awareof this fact, which iswhy they are planning to increase thetransmission capacity through the planned HVDC lines.

3.3. Bidding zone delimitation canaddress grid bottlenecks

Our simulations show that the chosen bidding zone con-figurations reduce redispatch and countertrade costs.Furthermore, the simulated power price differencesacross the German bidding zones are a clear indicator ofsubstantial bottlenecks. Aswewill see further below, theprice differences are markedly higher in hours with highwind feed-in in northern Germany. Both the reduction inredispatch costs and the price gap when assuming thezonal delimitation are clear indicators that bidding zonesare a viable instrument to address internal bottlenecks.

3.3.1. Redispatch and countertrade costsare reduced through bidding zonedelimitation

Our simulations show that the cost for redispatch andcountertrade is reduced if bidding zones are introduced.This is a common observation across the alternativebidding zone configurations tested. Figure 3.5 showstwo sets of redispatch costs in the grid delay scenarioin 2025. Figure 3.5a shows how much total generationcosts increase in order tomove from the day-aheadmar-ket dispatch to the redispatch solution. This indicatorcan be interpreted as the redispatch cost in a perfectpay-as-bid solution. Figure 3.5b shows the redispatchand countertrade compensation that TSOs must pay togenerators for redispatch and countertrade, assuminga perfect pay-as-cleared solution. The latter is higher,because this indicator also includes profits for somegenerators. In terms of overall economic welfare, how-ever, this simply constitutes a redistribution from TSOs(or consumers) to producers.

Figure 3.4.: Reduction in redispatch costs (pay-as-bid) in2025 with grid delays.

Both indicators show a significant reduction in re-dispatch costs if bidding zones are introduced. Themajority of the reduction comes from splitting off thenorthern zone. In the two-zone configuration, the pay-as-bid compensation (increase in generation cost) isreduced by almost 60% compared to the one-zone con-figuration. In the four-zone configuration, the compens-ation is further reduced to 28%. The pattern is similar forthe pay-as-cleared results, but the percentage reductionis somewhat smaller.

Note that it is not just the number of bidding zones

©THEMA Consulting Group (2020) 11

Page 12: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

(a) Redispatch and countertrade compensation in pay-as-bidmechanism (Increase in generation cost).

(b) Redispatch and countertrade compensation in pay-as-clearedmechanism.

Figure 3.5.: Redispatch and countertrade results in the grid delay scenario in 2025 for different bidding zone configurations(real 2019 EUR).

that is important for the redispatch costs, the config-uration matters too. We also analysed alternative con-figurations. If only southern Germany is split from therest of the country (zone DE1c and DE1d in the threeand four zone configurations of Figure 3.1, which givesa bidding zone configuration suggested by the ENTSO-E bidding zone review), redispatch costs only decreaseby around 20%, see Figure 3.4. It is thus more efficientto isolate the north, because the main issue is a surplusof generation in the north, not a deficit in the south,as discussed further below. Bidding zone delimitation

Figure 3.6.: Simulated redispatch and countertrade com-pensation paid by the German TSOs without grid delays (real2019 EUR).

reduces redispatch costs – this effect isn’t just a featureof the grid delay scenario in 2025. As discussed inSection 3.2, if the projects in the grid development planare implemented as planned, there will be significantlyless congestion in the German grid in 2025. However,by 2030, more grid congestion can be expected. Oursimulations show that bidding zone delimitation alsoreduces redispatch costs in 2030, as shown in Figure 3.6.Hence, even if grid development goes according to plan,it is likely that bidding zones would help to alleviate gridcongestion in the long term.

The introduction of bidding zones affects the gen-eration implied by the day-ahead market in Germany.However, actual generation after redispatch is identicalin all bidding zone configurations in this analysis, as allsimulations arrive at the efficient nodal solution after re-dispatch and counter trade measures. Figure 3.7 showshow the generationmix implied by the day-aheadmarketsolution changes if four bidding zones are introduced.The figure shows that more wind power (in the north)is curtailed through the market, whereas more gas-firedgeneration (in the south) is dispatched. This reduces theneed for redispatch and countertrade.

12 ©THEMA Consulting Group (2020)

Page 13: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

3. The effect of potential bidding zones

Figure 3.7.: Change in day-ahead market dispatch per fuelin Germany in 2025 from the one-zone configuration to thefour-zone configuration with grid delays.

3.3.2. Prices in northern Germany drop ifbidding zones are introduced

Bidding zone delimitation may have a significant impacton power prices in some German areas. Figure 3.9shows how annual prices develop to 2030 in the casewithout grid delays. The spread between zonal pricesreflects grid congestion. The price in DE4d (the north-ernmost zone) is significantly lower than the price inthe other zones in years with severe grid congestion.The price level in DE2d is similar to the price in theone-zone configuration. The prices in the consumption-heavy zones DE1d and DE2d are higher than in the one-zone configuration (DEa), but the difference is smallerthan the difference between DE4d and the one-zoneconfiguration price.

In the grid delay scenario, the price differences aregreater in 2025. Figure 3.8 shows the annual prices indifferent zonal configurations. In all cases, the price inthe northernmost zone is significantly lower than in theone-zone configuration.

Figure 3.10 shows the simulated prices in the four-zone and one-zone configurations. The weekly pricesshow that certain weeks have very low prices in DE4d,i.e., weeks with high wind power generation.3

3In the simulations we base the wind and solar generation pro-files and the demand profiles on one historical year to capturethe volatility of intermittent generation and consumption on anhourly level.

Figure 3.8.: Simulated annual prices in 2025 in differentzonal configurations with grid delays (real 2019 EUR).

Figure 3.9.: Simulated annual prices per bidding zone in four-zone configuration and one-zone configuration without griddelays (real 2019 EUR).

Figure 3.10b shows the price duration curves foreach bidding zone. The price duration curves show thatthe price in DE4d drops to −75EUR/MWh in more than1000 hours during the year. In these hours, there is asurplus of generation in the zone, leading to curtailmentof wind power. The price difference is greatest duringwinter, when the wind generation in the north is high, andsolar generation in the south is low.

In the simulations, we assume that wind powergeneration will be curtailed when the price goes to−75EUR/MWh. Note, however, that if bidding zones areintroduced, and negative prices become that frequent,

©THEMA Consulting Group (2020) 13

Page 14: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

one would expect market participants to react in sucha way that the scale of negative prices is reduced. Forone thing, the support scheme is changing and morewind power operates on merchant terms. For another,frequent negative prices may trigger investments in newsources of flexibility. Hence, one might expect the priceto be rather close to zero in many of the hours withsurplus generation.

The fact that the northernmost zone is where theprice reacts most to the introduction of bidding zonesshows that themain issue in Germany today ismanaginga surplus of generation in the north. In particular, thisregion has a very large share of wind power. Figure 3.11ashows the relationship between the hourly price differ-ence between DE1d and DE4d and residual load in DE4d.The price difference grows when the residual load falls,i.e. when wind power generation is high and demand islow.

The residual load in southern Germany does not driveprice differences to the sameextent. Figure 3.11b showsprice differences versus residual load in DE1d (the south-ernmost zone). There is a weak relationship, showinghigher residual load causes slightly higher price differ-ences. However, the relationship is much less strongthan that for residual load in the north. The main driverbehind price differences (and hence grid congestion) isnot the deficit in the south, but rather the surplus in thenorth.

3.3.3. Bidding zone delimitation redis-tributes welfare from generators toconsumers

With lower prices in northern Germany when using mul-tiple bidding zones, the income of power generatorsfalls. Meanwhile, with less grid congestion and morecongestion rent, German electricity consumers benefitfrom a lower grid tariff. The estimated redistributionaleffects of introducing four bidding zones are shownin Table 3.1. The table shows the model results forproducer and consumer surplus in 2025, in the scenariowith delayed grid development.

As power prices fall in the north of Germany, the pro-ducer surplus of power generators in the region drops.Generation in northern Germany is dominated by windpower, and the price in the northern zone drops to zero

Table 3.1.: Redistributional effects of the four-zone configura-tion, compared to a one-zone configuration in 2025 with griddelays (real 2019 Euros).

Change in producer surplus:Day-ahead market −3 532 MEURRedispatch −70 MEURTotal −3 602 MEUR

Change in consumer surplus:Day-ahead market −230 MEURReduced grid tariff 3 509 MEURof which reduced redispatch cost 1 080 MEURof which reduced countertrade cost 409 MEURof which increased congestion rent 2 020 MEUR

Total 3 279 MEUR

or less in many hours, as wind power must be curtailed.One should note that due to the dominance of windpower, a large share of the generation will be com-pensated through existing support mechanisms. Hence,parts of the reduced producer surplus shown wouldbe compensated by payments from the Government orTSO. Generators in the south, on the other hand, be-nefit from the bidding zone delimitation, as the powerprice in southern Germany is slightly higher comparedto the one-zone configuration. In general, flexible powergenerators would loose some income from redispatchactivities.

Electricity consumers benefit from the introductionof bidding zones in our simulations. Even though theprice in northern Germany drops, the majority of con-sumption is located further south, and the consumersurplus in the day-ahead market for Germany as a wholeis reduced slightly in the simulations, due to higher pricesin southern Germany. However, this impact is more thanoffset by lower grid tariffs, as the cost for the TSOs fallif bidding zones are introduced.

The TSOs will need to use less redispatch and coun-tertrade with bidding zone delimitation, which reducestheir costs significantly. Furthermore, if bidding zonesare introduced, congestion rents increase, both becausecongestion rent is generated on the internal borderswithin Germany, and because congestion rents on someinterconnectors increase. The latter is true for intercon-nectors connected to the northernmost zone (DE4d), be-cause the price difference between DE4d and the Nordic,Polish and Dutch zones is significantly higher, comparedto the one-zone configuration. In Table 3.1, we attributethe entire savings of the TSOs to consumers, as they paythe grid tariffs, and the income of the TSOs is regulated.

We would like to point out that the numbers in

14 ©THEMA Consulting Group (2020)

Page 15: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

3. The effect of potential bidding zones

(a)Weekly prices. (b) Price duration curves.

Figure 3.10.: Simulated day-ahead market prices in 2025 in the four-zone configuration and one-zone configuration with griddelays (real 2019 EUR).

(a) Price difference DE1d-DE4d versus residual load in DE1d. (b) Price difference DE1d-DE4d versus residual load in DE4d.

Figure 3.11.: Price difference versus residual load (consumption - wind generation - solar generation) in 2025 with grid delays(real 2019 EUR).

Table 3.1 need to be taken with some caution. This alsorelated to the fact that some of the countries in Europein this setup were modelled exogenously (with givenprices), which also influences results. We would notgo as far as to conclude that the overall welfare effectfor Germany (sum of producer and consumer surplus)would be negative. In this respect, please also note thatwe assume that redispatch and countertrade is carriedout in an optimal matter by the TSOs. If this is not thecase, theremay be an additional welfare gain associatedwith redcuing the need for redispatch and/or counter-trade (see discussion below). However, this effect is not

included in the estimated values shown in Table 3.1.

3.4. Bidding zone delimitation maybe an efficient way to managecongestion

We have seen in the previous sections that there are:

a) significant bottlenecks if the HVDC lines are delayed,and

©THEMA Consulting Group (2020) 15

Page 16: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

b) that these bottlenecks can be addressed by the intro-duction of bidding zones.

The effect on the resulting price spreads and on redis-patch costs are clear indicators of these impacts.

3.4.1. Efficiency of day-ahead markets

In a theoretical world, the TSOs could achieve the sameoptimal nodal dispatch solution through efficient redis-patch after the clearing of the spot markets. There are,however, real-life limitations to the overall efficiency ofusing redispatch instead of the market.

Efficient redispatching by a TSO would require addi-tional information Efficient redispatching by a TSOwould require additional information in order to makesure that the redispatch is cost-efficient. While theremay be options to adjust the market design in order tomake redispatch more efficient, it is likely that it will beless efficient than handling the bottlenecks directly inthe spot market in the first place.

Price distortion Even if redispatch itself were cost effi-cient, not addressing bottlenecks in the spot market dis-torts market signals. The spot market price signal influ-ences dispatch, trade, and investment decisions. Long-term hedging is done based on spot forward markets.Inaccuracies in the spot price signal provides inefficientsignals for all these key decisions. It is unsurprisingtherefore that the EU Commission emphasises the im-portance of spot market efficiency for the successfulintegration of European power markets. In this respect,the role of providing efficient trade signals should notbe underestimated. If the trade signals provided by spotprices are ”wrong”, the resulting cross-border flows willaggravate the internal bottleneck situation. It is unlikelythat redispatch markets can be designed with the abilityto provide efficient signals for both short-term and long-term decisions in power markets while the spot priceremains unable to signal local surpluses or shortagesof power. Note also that the feasibility of meeting the70 percent rule for availability transmission capacities,to be introduced in 2020, must be seen in this context.

Efficiency of Flow Based Market Coupling (FBMC)The current market design, using flow-based marketcoupling, also accounts for internal bottlenecks. It hasbeen argued that, under this approach, one therefore

does not need bidding zones. However, bidding zonedelimitation is fundamental for the efficiency of flow-based market coupling. In a flow-based system, thebalance in a zone determines the cross border flowsused in the clearing algorithm. But, the larger the zone,the less precise this approximation between impliedflows and physical flows. This is because the thedistribution of injections and withdrawals within a zoneis crucial for the physical flow. The larger the zone andthe larger the internal bottlenecks, the more guessworkis required of TSOs when calculating efficient PTDFsand CBCOs for the clearing algorithm.

Impact on trade The use of bidding zones will supportmore efficient trade and the more efficient use of flexib-ility. In particular, the future deployment of additional in-termittent generation capacity increases the importanceof using cross-border lines efficiently to help providethe system with required flexibility. Interconnection withNorway will play an important role given Norway’s flex-ible hydro resources. During hourswhere there is ”lockedin” generation in northern Germany, it would be efficientto export this excess power to Norway. Without efficienttrade signals however, as determined by the spot mar-ket price, the new NordLink cable between Norway andGermany, as well as other interconnections, will not beefficiently utilised.

3.4.2. Additional considerations aroundbidding zones

From a technical and TSO perspective, a finer biddingzone granularity would certainly improve market effi-ciency. However, there are some arguments againstmarket splitting that deserve further discussion and cla-rification.

The ideal bidding zone configuration One argumentthat has been raised against the use of multiple biddingzones is that it is difficult to find an optimal bidding zoneconfiguration, and that one should therefore not split theGerman market. But this is an argument for inactionrather than a defence of the use of a single biddingzone, which is itself an arbitrary design. We see fairlyrobust results and implications for redispatch costs forthe alternative bidding zone configurations analysed. Aslong as the major bottlenecks are accounted for by thebidding zone delimitation, any market split is likely to be

16 ©THEMA Consulting Group (2020)

Page 17: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

3. The effect of potential bidding zones

more efficient than today’s setup. Not being able to finda first-best solution should not prevent the adoption of abetter second-best system.

Impact on liquidity Zone splitting would reduce thesize of the respective zones, and may also reduce long-term liquidity. Decreasing liquidity in forward markets isbecoming an increasing issue, in particular for theNordiccountries. However, it is important to note that recentdeclines in forward market liquidity are not really attrib-utable to changes in the bidding zone setup. Instead, fin-ancial regulation, reduced hedging needs, the increasingrole of PPAs and other factors are likely to have been themain drivers. Nevertheless, the implications for forwardmarkets should be taken into account, and could, inthe event of market splitting, justify remedies, such asthe presence of market makers, aimed specifically ataddressing these issues.

Impact on investor confidence The introduction ofbidding zones could harm investor and market parti-cipants’ confidence in the underlying market conditions.Markets have, in recent years, been hit by somesignificant policy and regulatory changes (e.g. policieson coal phase-out, renewable targets, nuclear exit, EU-ETS reform, and changes inmarket design for renewablegeneration). Splitting the market would add to the longlist of policy and regulatory changes that stakeholdershave had to endure and could thereby harm investorconfidence. However, the real problem here is not theintroduction of bidding zones itself, but rather that theissue of bottlenecks has been ignored for such a longtime that introducing bidding zones now would exposethe market suddenly to quite a severe impact.

Market power The argument of market power issometimes used in the context of bidding zones. If abidding zone becomes too small, market players couldexercise that market power. But, if this is the case, themarket player could anyway exercise market power, ifnot in spot markets, then in intraday or reserve markets,or in redispatch. Furthermore, there are supervisory en-tities such as the competition authorities and regulatorswhose role it is to supervise markets and to identifypotential abuses of market power.

3.4.3. Final commentary

Bottlenecks in the transmission grid cannot be ignoredforever. They have to be addressed in one way or an-other. Ultimately congestion can only be fundamentallyalleviated through network investments, but even withinvestment, the network will never be a copper plate inwhich there is no congestion. Therefore, trade-offs needto be made to respect the physical limits of the network.

These trade-offs can be made through the market,by reflecting the network constraints inmarket design, orby correcting the flawedmarket outcome through centralplanning undertaken by a planning body, in this case theTSOs. In practice, the system uses some combinationof both and the key question is what would be the rightbalance between the two.

The failures of the current German market systemhave become truly staggering as the market structurehas become increasingly abstracted from the economicand technical fundamentals of the system and, increas-ingly, system dispatch is planned centrally by the TSOs(with the TSOs even effectively commissioning their owngeneration assets). This is likely to harm efficiencythrough the absence of proper price signals in the spotmarket and to prevent Germany’s efficient integrationinto a liberalised European energy market.

Changing the system now is of course very challen-ging politically, because it would have significant distri-butional impacts and bring scrutiny to the scale of trans-fers currently taking place outside of view. In order tomitigate the impact on consumers, one could introducea hybrid system, like the Italian bidding zone model, inwhich bidding zones apply to producers but consumerprices are uniform at a national level. Since consumersare not normally very price sensitive in the short-term,this compromise would not significantly harm short-term socio-economic efficiency. The downside, how-ever, would be the lack of efficient long-term price sig-nals for consumption and the fact that the resultant mar-ket designmight be challenging to apply to batteries andother sources of flexibility that can act both as producersand consumers.

In hindsight, it is unfortunate that Germany did nothave bidding zones in place before the current conges-tion got so out of control, as the earlier introduction ofbidding zones could have been achieved with less polit-ical controversy and then helped to counteract some of

©THEMA Consulting Group (2020) 17

Page 18: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

the current problems faced by the network, by stimulat-ing early action and investment to address the underlyingcongestion.

If the current set of HDVC connections do, as ex-pected, provide a short period of respite, Germany maywell wish to avoid the mistakes of the past by using thiswindow to revise its market structure and adopt one thatis more resilient to expected future congestion issues.

18 ©THEMA Consulting Group (2020)

Page 19: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

A. Appendix: Model and Methodology

A. Appendix: Model and Methodology

A.1. Methodology

In this study, we use both a grid model with nodal resolu-tion and amarketmodel with zonal resolution. The nodalis a DC Optimal Power Flow (OPF) model, simulatingflows between nodes in the transmission grid basedon physical properties of the grid. The market modelwe applied, the The Market Analyzer (TheMA) powermarket model clears supply and demand with hourlyresolution, taking hourly availability, start-up costs, partload efficiencies and other inter temporal constraintsinto account.

A.1.1. The TheMA model framework

THEMA’s power market model TheMA applied in thiscontext is an advanced, fundamental power marketmodel of European markets. The model is activelydeveloped by THEMA Consulting Group and has beenapplied for a variety of purposes including the prepar-ation of price forecasts, scenario analysis and invest-ment evaluations. A wide range of energy market act-ors license the model for direct use and the model’suserbase includes public authorities, energy utilities,portfolio managers and funds. The model is constantlyupdated,maintained and improved in close collaborationwith these licensees. In this project, we applied a versionof the model that simulates FBMC, as currently appliedin Central Western Europe.

The grid model is based on the same modellingplatform as the TheMA model, but is set up with a nodalresolution. The model simulates generation patternsand physical power flows in the meshed AC network ata nodal level. It is applied to identify grid bottleneckswithin or across bidding zones, and is used to estimatethe Power Transfer Distribution Factor (PTDF) relevantto the modelling ofFBMC.

The two models are described in more detail in Sec-tion A.2.

A.1.2. The interaction between the models

The grid model gives the optimal dispatch on a nodallevel, when accounting for all constraints in the trans-mission grid. The zonal model represents the day-aheadmarket solution, applying flow based market couplingmethodology, using PTDF derived from the grid model.

The day-ahead market solution, even though de-rived with flow-based market coupling which accountfor internal bottlenecks, does typically violate some gridconstraints. This is why TSOs apply redispatch andcountertrade measures to move from a zonal day-aheadsolution to a (nodal) solution that is in line with all gridconstraints.

A.1.3. Estimation of redispatch and coun-tertrade

In our setup, redispatch and countertrade are estimatedas the difference between the zonal model and the nodalmodel. That is, the necessary redispatch and counter-trade measures are the steps needed to move from theday-ahead dispatch to the dispatch that is optimal on anodal level.

We calculate indicators for redispatch and counter-trade costs based on the fundamental approach, as illus-trated in Figure A.1. The figure gives a simple illustrationof the effects of redispatch, in the case of two nodes.Imagine that there is congestion between node 1 and 2in the day ahead market solution. In order to relieve thecongestion, one could ramp up generation in node 1 by𝛥𝑔, and ramp down generation correspondingly in node2.

We use two different indicators for redispatch andcountertrade costs, pay-as-bid and pay-as-cleared costs:

Pay-as-bid redispatch and countertrade: The redis-patch costs are in this case estimated as the differ-ence between the increased cost in node 1 (area inA under the supply curve), minus the saved cost in

©THEMA Consulting Group (2020) 19

Page 20: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

node 2 (area B under the supply curve). The methodabove provides redispatch costs from a welfare eco-nomic perspective.

Pay-as-cleared redispatch and countertrade: Redis-patch activities may also have additional redistribu-tional effects. The TSOs must compensate gener-ators (and consumers) to carry out the redispatch.The fundamentally correct compensation in the illus-tration from Figure A.1 would be 𝛥𝑔(𝑝𝐷𝐴𝑀 + 𝛥𝑝1) −𝛥𝑔(𝑝𝐷𝐴𝑀 −𝛥𝑝2), or simply𝛥𝑔(𝛥𝑝1+𝛥𝑝2),assuminga well-functioning pay-as-cleared redispatch mech-anism, and where 𝑝𝐷𝐴𝑀 is the day ahead marketprice.

Both measures are used as indicators for how far thedispatch solution is from the perfect nodal solution.Both measures are strongly correlated, and we use bothmeasures in this report. The latter pay-as-cleared re-dispatch estimate is in addiiton used to estimate theredistributional effects of redispatch (fromTSOs to othermarket participants).

One could instead argue that a bidding zone delimit-ation associated with high redispatch and countertradecosts may indicate an economic welfare loss, comparedto a delimitation with lower redispatch and countertradecosts. The simulated redispatch and countertrade coststherefore serve as an indicator for economic efficiency.

Figure A.1.: Illustration of redispatch calculations.

We distinguish in our report between redispatch andcountertrade. The different as follows:

Redispatch: Wiht redispatchwe refer to all measuresto arrive in the efficient nodal solution that are per-formed within a country or bidding zone.

Countertrade: With countertrade we refer to all

measures to arrive in the efficient nodal solutionthat are performed outside a country or respectivebidding zone.

A.1.4. Commentary on the redispatchmeasures

Our approach assumes that redispatch and countertrademeasures always result in the same dispatch, regardlessof the starting point from zonal solution. That is, weassume that the TSOs are always able to make optimaldecisions to handle any grid congestion.

The implication of this assumption is that the eco-nomic efficiency is independent of the bidding zonedelimitation in the simulations. Nomatter howmuch thezonal dispatch differs from the nodal-optimal dispatch,redispatch and countertrade measures ensure that thecost-optimal solution is achieved in the end.

This assumption may not be reasonable. Actualredispatch and countertrade measures may differ fromthe optimal solution. For example, the TSOs may prefera few large generation adjustments, rather than manysmall ones. In addition, TSOs may not have the neces-sary information in order to select those generators thatmay be would be efficient to redispatch from a welfarepoint of view, andmay hence end up in suboptimal nodalsolution. We would also like to mention that TSOs mayin reality procure less redispatch abroad (countertrade)than what our model results suggest - in our setup themodel performes welfare efficient redispatch withoutany preferences for whether this is domestic or abroad.And we do not model or estimate the long-term benefitsof bidding zones that derive from more efficient long-term price signals for investments.

All in all, we are likely to underestimate the actualredispatch costs needed to get into balance. We are wellaware of the implications of our approach. Neverthelessdid we consciously opt for this method for estimatingredispatch and countertrade costs. The reason for this isthat it is very challenging, so say the least, to account forimperfections in the redispatch and countertrade meas-ures. Any attempt to model imperfections or even stra-tegic bidding behaviour in redispach would eventuallymake the results in-transparent and in a way arbitrary, asone would need to make a wide range of assumptionson how to model and parametrise the imperfections and

20 ©THEMA Consulting Group (2020)

Page 21: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

A. Appendix: Model and Methodology

the strategic bidding behaviour.

We therefore opted for using the approach outlinedabove, which provides a transparent and cost-optimalestimate for redispatch costs and countertrade.

We only consider the short-term effects, that is, howthe dispatch is affected by the introduction of biddingzones, with given generation capacities and consump-tion. We do not estimate the long-term effects of intro-ducing bidding zones. Investments in new generationcapacity, and the location of demand, are also affectedby price signals. Bidding zones may hence providemore efficient locational price signals for where newgeneration capacity is needed, and where it is beneficialto locate new electricity consumption.

A.2. Models applied in the analysis

As explained in Section A.1, we apply two different mod-els in the study, with the same set of power plants.

The grid model

The grid model uses a DC Optimal Power Flow (OPF)approach. This approach finds the cost-optimal dis-patch on a nodal level, taking transmission constraintsinto account. The flows on the transmission lines arelinearised by neglecting active power losses.

The grid model simulates around 500 transmissionnodes in Germany. The dataset is based on the opensource SciGRID dataset and data from theGermanTSOs.In addition, developments from the grid developmentplan are included in the analysis. All transmission linesof 220 kV and above are included in the model. Othercountries than Germany are represented with one nodeper country, with the exception of Western Denmark,where all transmission nodes at the 400 kV level areincluded.

The available capacity on AC lines in the grid modelis set to 90% of the estimated thermal capacity of eachline. Hence, we subtract a safety margin of 10%. Wedo not account explicitly for the n-1 criteria in the gridmodel, the safety margin represents an approximation.Furthermore, themodel does not include voltage stabilityconstraints, but such considerations accounts for less

Table A.1.: Assumed fuel and carbon prices (real 2019 values).Type Unit 2020 2022 2025 2030Gas EUR/MWh 19.0 17.3 20.0 24.0Coal USD/t 73.1 73.1 73.9 64.7CO2 EUR/t 26.3 26.0 23.1 26.0

than 10% of redispatch volumes. Overall, our estimateson 90% ability is a rather non-conservative assumption.

The zonal model

The zonal model represents the day-ahead market,where nodes are aggregated into bidding zones. Thezonal model uses FBMCmethodology. The zonal PTDFsare calculated as weighted average of the nodal PTDFs,where the absolute value of the nodal balances are usedas Generation Shift Keys (GSK) (weighting factors).

All transmission lines from the grid model are alsoincluded in the zonal FBMC model. That is, even thoughthe market model is run with a zonal resolution, alsointernal transmission constraints within each biddingzone are represented in the model.

Due to the aggregation into zones, the flow on eachtransmission line approximated from the zonal modelis not as accurate as the flows from the grid model.This is the reason why bottlenecks arise from the zonaldispatch, and hence the need for redispatch and coun-tertrade.

The approach we apply and the interaction betweenthemodels mimics in principle the current market setup.First, TSOs estimate PTDFs and Reliable Available Mar-gins (RAM) on Critical Network Elements (CNE). Theymay also account for contingencies and critical out-ages. In addition, they calculate Net Transfer Capacities(NTC) for trade with markets outside the flow baseddomain. These parameters are then used as constraintsin themarket clearing optimisation. For reasons outlinedabove, this market solution typically violates grid con-straints, which creates the need for redispatch.

A.3. Key assumptions

The simulations are based on THEMA’s Best Guessscenario as of August 2019. The fuel and carbon pricesare shown in Table A.1.

©THEMA Consulting Group (2020) 21

Page 22: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

Table A.2.: Assumed gross electricity consumption in Germany(TWh).

2020 2022 2025 2030548 549 551 549

We assume a fairly flat development of electricityconsumption, as depicted in Table A.2.

The assumed capacity development in Germany isshown in Figure A.2. Note that these capacities are avail-able in the market, capacity in reserve is not included inthe simulations.

Figure A.2.: Capacity assumptions in Germany.

All nuclear plants are decommissioned by the end of2022. Our coal and lignite capacity assumptions followthe suggestion by the Coal Commission (the WSB re-port). Hard coal capacity falls to 8GW by 2030 whereaslignite capacity drops to around 9GW. We do not as-sume market-driven investments in gas-fired capacity,even though some new reserve capacity may come.

We assume that German offshore wind capacity in-creases to around 11GW by 2025 and 15GW by 2030.Note that raising the offshore wind target for 2030 isunder discussion, and that the latest German Grid De-velopment Plan (NEP) assumes between 17 and 20GWof offshore wind by 2030. Our assumption for onshorewind power is in line with scenario B from the NEP,i.e., 70.5GW by 2025 and 81.5GW by 2030. We alsofollow scenario B for solar Photo-Voltaic (PV) capacity,at 73GW by 2025 and 91GW by 2030.

We assume that wind is curtailed at a negative priceof −75EUR/MWh. This assumptions has in implication

for the magnitude of price differences between zones,and on the estimate for redistpach and welfare. Wetested the model with alternative values for wind cur-tailment thresholds. While this changed the magnitudeof the results, it did not change the overall picture andconclusions. The same applies to the so called 6 hourrule in Germany, which we have not explicitly modelledin this project.

We modelled single years with hourly resolution forthe assessment. The analysis is based on one historicweather year (2016), with consistent values for wind,PV, and demand, accounting for observed correlationbetween countries and between variables. The wind, PV,and demand valueswere normalized such that the seriesdo not lead to any volume bias. Modelling differentweather years would of course change the results forselected hours, days, and weeks, but would not changethe overall conclusion.

A.3.1. The geographic scope of the modelanalysis

Germany, its neighbouring countries as well as the UKare modelled endogenously. The endogenous modelscope is shown as the light blue ares in Figure A.3. As forGermany, the assumptions around generation mix anddemand for neighbouring countries and UK are based onour Best Guess scenario as of August 2019.

The dark areas in the figure are modelled with anexogenously given price, and trade capacity. The endo-genously modelled areas can therefore trade with thesezones based on the price and trade capacity. We alsomodelled the Nordic countries (except Denmark) withexogenous prices.

Ideally, we would have modelled the entire Europeanpower market endogenously for this project. However,the grid model is computationally very complex. Ex-tending its scope to the entire European market wouldbe a challenge in itself. What would make this exten-sion even more challenging is the hydro portfolio in theNordics, where many reservoirs and hydro assets areinter-temporally optimised between hours and betweenseasons. Combining all these complexities into onesimultaneousmodelling optimisation is computationallyinfeasible.

22 ©THEMA Consulting Group (2020)

Page 23: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

A. Appendix: Model and Methodology

Figure A.3.: Endogenously modelled region.

©THEMA Consulting Group (2020) 23

Page 24: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

The Impact of German Bidding Zones

A. Acronyms

CNE Critical Network Elements

FBMC Flow Based Market Coupling

GSK Generation Shift Keys

HVDC High Voltage Direct Current

NTC Net Transfer Capacities

PTDF Power Transfer Distribution Factor

PV Photo-Voltaic

RAM Reliable Available Margins

TheMA The Market Analyzer

TSO Transmission System Operator

24 ©THEMA Consulting Group (2020)

Page 25: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

Disclaimer

THEMA Consulting Group AS (THEMA) expressly disclaims any liability whatsoever to any third party. THEMAmakes no representation or warranty (express or implied) to any third party in relation to this Report. Any releaseof this Report to the public shall not constitute any permission, waiver or consent from THEMA for any thirdparty to rely on this report. THEMA acknowledges and agrees that the Client may disclose this Report (on anon-reliance basis) to the Client’s affiliates, and any of their directors, officers, employees and professionaladvisers provided that such receiving parties, prior to disclosure, have confirmed in writing that the disclosure is ona non-reliance basis. THEMA does not accept any responsibility for any omission or misstatement in this Report.The findings, analysis and recommendations contained in this report are based on publicly available informationand commercial reports. Certain statements contained in the Report may be statements of future expectationsand other forward-looking statements that are based on THEMAs current view, modelling and assumptions andinvolve known and unknown risks and uncertainties that could cause actual results, performance or events to differmaterially from those expressed or implied in such statements.

Page 26: Redispatch and Countertrade Costs - thema.no€¦ · leading to relatively high redispatch and countertrade costs in the simulations by 2030. In the 2030 sim-ulations, we assume that

About THEMA:THEMA Consulting Group is a consulting firmfocused on electricity and energy issues, andspecializing in market analysis, market design andbusiness strategy.

Øvre Vollgate 60158 Oslo, Norwegen

THEMA Consulting Group

[email protected]://www.thema.no/

Friedrichstrasse 6810117 Berlin, Deutschland

Berlin office