recovery procedure for western region - srldc · starting of motor of power plant auxiliaries like...
TRANSCRIPT
Recovery Procedure for Western Region-Dec 2013 1
Power System Operation Corporation Ltd.
(A wholly owned subsidiary of Power Grid Corporation of India Ltd.) WESTERN REGIONAL LOAD DESPATCH CENTRE
F-3, MIDC Area, Marol, Andheri(E),
Mumbai- 400093.
Recovery Procedure
For
Western Region
December - 2013
Recovery Procedure for Western Region-Dec 2013 2
TABLE OF CONTENTS
Chapter Title Page No.
1. Introduction .............................................................. 4
2. System restoration approaches and
General guidelines ........................................................... 6
3. Recovery Procedures –An overview .............................. 11
4. Restoration Procedures for Gujarat ................................. 22
Exhibits ....................................................................
5. Restoration Procedures for Madhya Pradesh............... 37
Exhibits ...............................................................
6. Restoration Procedures for Chhattisgarh.................... 52
Exhibits ................................................................
7. Restoration Procedures for Maharashtra ..................... 66
Exhibits ..................................................................
8. Restoration Procedures for Goa .................................. 87
9. Restoration Procedures for Total black out in
Western Region........................................................... 88
10. Training Drills and Exercises....................................... 95
11. Power Map of Western Region .................................... 97
Recovery Procedure for Western Region-Dec 2013 3
ANNEXURES
Sl. No. Title Page No.
Annexure-I List of Generating Stations
With Black-start facilities ...……………………… 99
Annexure-II Minimum Survival/Auxiliary
Power Requirement of Generating Stations ………… 101
Annexure-III Sub-stations provided with
Synchronization facilities .…………………………. 104
Annexure-IV(a) Traction Substations in WR ........................................ 106
Annexure-IV(b) Power Supply to Traction Substations Format ……… 109
Annexure-IV(c) Power Supply Arrangement Diagram of SEBs to 110
Traction sub-stations (TSS) of Western Railway………
Annexure-IV (d) Power Supply Arrangement Diagram of SEBs to 111
Traction sub-stations (TSS) of South East Railway
(Nagpur Division) …………………………………
Annexure-V List of Bus/Tertiary Reactors .....................…………. 112
Annexure-VI Line Charging Guidelines During Restoration……….. 114
Annexure-VII Restoration Procedures for Tata Power system …….. 117
Annexure-VIII Monitoring Performance of Restoration Plans ..…….. 136
Annexure-IX(i) Report on Black Start Mock Drill at Indira Sagar 146
Hydro Power station
Annexure-IX(ii) Report on Black Start Mock Drill at Bargi 152
Hydro Power station
Annexure-IX(iii) Report on Black Start Mock Drill at SSP 157
Hydro Power station Annexure-IX(iv) Report on Black Start Mock Drill at Bango 160
Hydro Power station
Annexure-IX(v) Report on Black Start Mock Drill at Pench 165
Hydro Power station
Annexure-IX(vi) Report on Black Start Mock Drill at CCPP Vatva 171
Annexure-X Ready Reckoner on Reactive Power Management…… 173
Acknowledgement ………………………………………………………… 175
Bibliography ………………………………………………………… 176
Recovery Procedure for Western Region-Dec 2013 4
CHAPTER – 1
1.1 INTRODUCTION
Western Regional Electrical Power Grid covers geographically the states of Maharashtra,
Gujarat, Madhya Pradesh, Chhattisgarh and Goa, union territories of Daman and Diu &
Dadra and Nagar Haveli. The central government companies primarily NTPC and NPC
Ltd. own and operate many power stations in the western grid. The inter state
transmission system is owned and operated by POWERGRID also declared as the
Central Transmission Utility (CTU) of India. The region also has a significant portion of
generation, transmission and distribution network belonging to the private sector.
1.2 SCOPE
This document describes the procedures to be followed / implemented by WRLDC,
SLDCs and other constituents of western region for the restoration of grid following a
system disturbance. This document has been prepared in consultation with regional
constituents. This document is being issued in pursuance to clause 5.8(b) of Revised
Indian Electricity Grid Code (IEGC-2010) and supersedes the existing document titled
'Black Start facilities in Western Region', issued in Jan 2012.
1.3 OBJECTIVE
The objective of Recovery Procedures is to achieve restoration of total system in the
shortest possible time, taking into account the generation securing (i.e., stabilization of
saved units), extension of start-up power to thermal and nuclear units, traction and other
essential loads, core sector industrial loads keeping in view of the generator capabilities
and the transmission constraints etc. and to achieve re-synchronization of the constituent
systems which have separated from each other as a result of the disturbance.
1.4 HIERARCHY OF RESPONSIBILITIES
WRLDC as the apex body in operation of the Western Regional Grid, supervises and
controls all the grid operations and ensures integrated operation of the regional grid. The
regional power system is operated as a loose power pool with ample autonomy to the
state utilities. The region has computerized Load Dispatch Centers at the regional level
(WRLDC) top of the hierarchy and State Load Dispatch Centers (SLDCs) & Area Load
Dispatch Centers (ALDCs) at the state level. The National Load Dispatch Centre
(NLDC), exercises supervision over WRLDC and the other four Regional Load Dispatch
Centres(RLDCs). While WRLDC is directly involved in the restoration of the central
sector transmission and generation, it directs, supervises and monitors the restoration of
the facilities owned by the states and coordinates the resynchronization/reintegration of
the islands that are restored around the generating units with black start facilities or
sources of power energized through inter regional interconnections. Restoration of the
loads is under the control of the state utilities and priorities are set by them. More the
number of sources, faster the restoration process. WRLDC would try to get emergency
assistance from the neighboring regions at the earliest to speed up restoration provided
no constraints are experienced in getting inter regional assistance. The RLDC is
authorized during the restoration process following a black out, to operate at reduced
Recovery Procedure for Western Region-Dec 2013 5
security standards for voltage and frequency as necessary in order to achieve the fastest
possible recovery of the grid. (Section 5.8(d) of IEGC-2010).
1.5 DEFINITIONS OF THE IMPORTANT TERMS
Total System Black Out: The system is said to be under total black out when all
Regional utility generation has ceased to operate and there is no supply from external
interconnections to the (WR) grid and it is not possible for the total system to function
again without black start.
Partial System Black out: Blackout of a particular constituent system either partially or
fully or that of more than one constituents‟ systems is termed partial system blackout.
System Islanding: In case, part of the system gets separated from the grid due to system
splitting or through operation of any defense mechanism/scheme and operates
independently, the phenomenon is called System Islanding.
Normal System Conditions: System will be declared to be normal when all islands are
re-connected, all emergency and essential loads are restored and adequate transmission
system is restored enabling all the constituent states to draw their scheduled power from
ISGS.
1.6 CONTENTS: This document contains, inter alia, the following aspects:-
(i) Generation securing
(ii) Generation build-up
• Survival and Start-up Power of Power Plant(s).
• Power Station(s) with Black-start facility.
(iii) Build-up of islands
(iv) List of Units with black start facilities, inter-state/regional ties, synchronizing
points and essential loads to be restored on priority.
(iv) Detailed State/Utility-wise Restoration plans.
1.7 UPGRADATION
As per IEGC-2010(5.8.a), detailed plans and procedures for restoration of the regional
grid under partial/total blackout shall be developed by RLDC in consultation with all
regional constituents/RPC Secretariat and the same shall be reviewed / updated annually.
The important inputs required for revision shall include the performance of restoration
plans during previous grid disturbances and critical analysis of the shortfalls along with
recommendations/suggestions for future. Keeping this in view, Annexure -VIII has been
included with tables from I to VII. Some of the information concerns restoration plans
and the rest on actual experience of restoration. The constituents may fill up these tables
for inclusion in the next report. As per IEGC-2010 (5.8.b), detailed plans and procedures
for restoration after partial /total blackout of each Constituent‟s system within a region
will be finalized by the concerned constituent in coordination with the RLDC. The
procedure will be reviewed, confirmed and revised annually. Mock drills are to be
carried out by the constituents at least once every six months under intimation to the
RLDC.
Recovery Procedure for Western Region-Dec 2013 6
CHAPTER – 2
SYSTEM RESTORATION APPROACHES
AND
GENERAL GUIDELINES
2.1 SYSTEM RESTORATION APPROACHES
Restoration of the system on black start is generally done through the following two
approaches:
1. Bottom-Up Approach -Systems with a fair dispersal of Generating units with black
start facilities:
Those generating stations, where black start facilities are available, should be started up
and islands be formed around them by connecting essential loads. These islands are then
interconnected at predefined locations where synchronizing facilities are available. The
speed of restoration enhances with increase in number of black start facilities and their
dispersal. Gujarat, Chhattisgarh, Madhya Pradesh and Maharashtra have considerable
number of generators with black start facilities and these should be utilized to the
maximum extent. It is required to carefully monitor the operations of the islands (before
re-integration with rest of the grid) due to small stiffness in islands. One well conversant
engineer must be specifically assigned at the SLDC level to monitor each island.
Utmost care should be taken, while adding loads, to ensure step-by-step addition,
keeping strict vigil of the load characteristics, i.e. variation of load with respect to
voltage and frequency and stiffness of the islands. During cold load pick up, sudden
starting of motor of power plant auxiliaries like BFP, ID & FD fans, pulverizing mills,
long conveyors etc., can cause voltage dips due to drawing of high starting currents.
Essential loads can be restored in steps smaller than 5 MW. While starting the power
station auxiliaries, it is preferable to start the largest motor first, if the startup sequence
permits. When the next largest motor is started, the running motor acts as an induction
generator and helps in controlling the starting current. Further, larger motors along with
their rotating loads may act as flywheel and prevent jerks to the generators. It is also
preferable to connect some radial loads to black started units before extending startup
power to other stations. It is also preferable to restore rotating type loads, which
contributes to inertia of the island. In all cases, load pick up should be restricted so as to
avoid frequency excursions by more than 0.5 Hz in the island.
2 Top-Down Approach -Systems with no / less generating units with black start
facilities:
The second approach could be followed in case self start facilities are available at only a
few power stations or the start up power has to be imported from neighboring
areas/regions at one or two points. In this case, the start up power is required to be
extended to all the generating stations on priority basis while restoring few loads and
transformers/reactors for voltage control. The start up power available from neighboring
regions at various interconnections has to be seriously explored since considerable
Recovery Procedure for Western Region-Dec 2013 7
assistance can be availed and the restored system is likely to be connected to a stable
external system. These procedures are to be well planned for the earliest and quickest
harnessing of the facilities.
The restoration through this approach could be delayed due to problems in charging the
lines viz. high-voltage, lack of synchronizing facilities at certain substations etc. and
high probability of system disturbance during restoration. These guidelines are derived
from actual operational experience gained in Western Region. Great deal of care has to
be exercised while restoring the grid and the following guidelines must be kept in mind
while restoration of a collapsed system:-
(i) Reactive Power Balance
During early stages of the restoration process, it is of utmost importance to keep the
system voltage within the allowable range. This can be accomplished through the
following energizing the lower voltage lines with priority with well exercised plan by
energization of minimum number of lines to get maximum area covering, operating
generators at minimum voltage levels (at lagging pf.), switching off capacitor banks and
use of bus reactors, wherever available, using the line reactors as bus reactors wherever
provision is available, charging the shortest lines, charging transformers and taking
tertiary reactors in service, operating synchronous condensers, wherever feasible.
Charging of lines with series capacitors is to be avoided and filter-banks at HVDC
stations may be used for voltage control.
It may be kept in mind that in isolation, the fault level of the buses may reduce abruptly
and the effect of MVAR injection or absorption in a bus will be much more in increasing
or decreasing the voltage respectively than the normal condition which may damage
CVTs and LAs and further aggravating the problem.
(ii) Active Power Balance
This can be achieved by maintaining proper load generation balance by restoring
minimum and essential loads only, restoring load in small steps keeping in view the load
characteristics, by getting adequate inductive loading to compensate capacitive effect of
charging long high voltage lines and releasing concentrated load of large town/city along
with that of Railways. The major precautions in carrying out this step are:
(a) Load connected should preferably be balanced on all three phases.
(b) Bypassing the U/F relays initially until sufficient loads are connected and
frequency stabilizes and is maintained close to 50 Hz.
(c) Paying special attention for traction and other fluctuating loads.
(d) Power number, which is 2500-3000MW in the integrated N-E-W grid of above
1,00,000 MW, may come down to even below 50 MW in the isolated grid and any
addition or removal of even 5 – 10 MW may seriously affect the frequency and
stability of the system. Primary response from generating units becomes
particularly important at that time.
(e) Charging of any faulty line may cause tripping of the surviving generators.
(iii) Coordination and priorities
The main priorities are to restore power supply to the generating stations and load
dispatch centers, formation of self-sustaining islands around the generating stations for
Recovery Procedure for Western Region-Dec 2013 8
which procedures are being laid down well in advance , to supply start up power to hydro
and gas units and finally for providing back up / survival / start up power to thermal and
nuclear units.
(iv) Communication and Real time data availability at control centres
It is most important to establish and maintain communication between RLDC, SLDCs,
generating stations and major substations if at all there is any disturbance in this area. All
important substations are to be kept in touch and links with less-important substations
may be cut off to avoid draining of batteries. All communication channels required for
restoration process shall be used for operational communication only, till grid-normalcy
is restored (IEGC-2010, sec- 5.8.e). General experience suggests that BSNL, MTNL and
private landline and mobile networks are useful alternatives to PLCC channel, especially
during disturbance. The contact numbers of all the concerned officials are to be
essentially maintained in the Control Rooms and updated regularly. Internet (e-mail) also
is to be used as a backup communication.
In case of non-availability / failing of battery backup, portable DG sets of suitable
capacity are to be arranged by the respective departments on priority to keep the
communication links operative. Apart from operating personnel at WRLDC/SLDCs
availability of personnel responsible for real time data and communication is also
important.
e) Protective Systems
The synchronizing facilities (of line / bus coupler) may not be available or may not be in
working condition at generating station or important substation(s) along the restoration
route. Hence the strategy should be modified accordingly. Problems in closing the
breaker due to low gas/air pressure or fault in closing/tripping circuit may cause delay in
restoration which may be sorted out suitably. Paralleling or interconnection of surviving
or restored islands through weak ties must be avoided. Faulty equipment / line, suspected
on the basis of physical observation, relay indications or any other related information
from site must not be energized. High voltage has to be controlled during restoration to
avoid damage of LAs, CVTs etc.
f) Survival Power
Availability of backup power supplies in the form of batteries, battery chargers, and DG
sets are to be ensured to avoid non-operation of circuit breakers, communication systems
etc., since this may cause unnecessary delay in restoration of the system.
g) Awareness of Restoration Plans
Training and necessary documentation is to be provided to all the system operators, load
dispatchers and concerned officials by respective LDCs.
h) Exchange of Information
Exchange of information among SLDCs and between NLDC, RLDC and SLDCs is
essential for proper co-ordination.
Recovery Procedure for Western Region-Dec 2013 9
2.2 OPERATIONAL GUIDELINES.
(i) Each SLDC of Western Region will coordinate synchronization of units and
transmission lines in its system in consultation with WRLDC. For ISGS power
stations, WRLDC will be coordinating for their synchronization. WRLDC will
coordinate interstate/ inter-regional startup power availability and also inter-
state/inter-regional synchronization of the system.
(ii) Priorities for usage of Black start generation are as under:-
a) Providing startup power to hot units
b) Providing startup power to units that are cool, but capable of rapid restart
like hydro and gas units.
c) Restoring station auxiliary service to generating stations and substations.
d) Picking up essential loads.
(iii) Transmission corridors being used for startup power should be isolated from any
damaged/faulty equipment and should be of minimum length and minimum voltage
level to avoid excess line charging VAR and consequent voltage rise.
(iv) The constituent receiving assistance from neighboring area/region during restoration
process should restrict drawal to the agreed quantum of power only since exceeding
this quantity may have an adverse impact on the healthy system extending the
assistance and there by further deteriorating the condition.
2.3 GENERAL GUIDELINES
While each disturbance would be different and may require a different plan,
nevertheless, it would be useful to formulate general guidelines for the benefit of the load
dispatchers. These may be described as below:
i. The operators at generating stations and substations should have the training and
knowledge of planned synchronizing locations and synchronizing procedures.
ii. Switching procedures should be clearly laid down and periodically reviewed.
iii. Once disturbance occurs and dead bus situation comes in, all the circuit breakers
are to be opened except those specifically mentioned. Further action should be
started only after getting instruction from RLDC / SLDC.
iv The part systems should be reintegrated only after adequate stabilization.
v. The transformer taps should be checked for desired settings to minimize voltage
difference. Initially, it is advisable to be kept at the middle i.e. at tap position 9
for a transformer with typical 17 tap provision.
vi. The substation operators and load dispatchers should make a through scrutiny of
the capacitor banks and reactors in service and accordingly carry out the
switching operations for voltage control.
Recovery Procedure for Western Region-Dec 2013 10
vii. Energizing long high voltage lines and cables should be avoided until adequate
generating capacity is available on bar.
viii. Provision of islanding schemes with varied strategies (viz. area-wise, power
station-wise and unit wise) would enable the operators to restore the system
faster. These provisions wherever available should be fully exploited.
ix. Provision of extending power supply to nuclear plants should be given top most
priority irrespective of cold or hot shutdown status of plant from safety
consideration.
x. In case of failure of main communication channels, guidelines for decision-
making should be given to all the major substations and generating stations.
xi. Developing of islands at power stations, wherever small units are available, could
help in faster restoration. One small unit at these power stations can be islanded
with radial loads and/or house load.
xii. Synchronization of the systems to be carefully done when the restoration is
carried out from two different sources.
xiii. DRs/SERs shall have to be provided at all the power stations and major sub-
stations. The outputs of these have to be made available to WRLDC.
xiv. No constituent shall refuse to extend start up power to other constituents(s) and
WRLDC directions should be complied with.
xv. Some of the generating units might have been saved due to successful islanding.
Stabilization of such surviving generation is of top most priority.
***
Recovery Procedure for Western Region-Dec 2013 11
CHAPTER – 3
RECOVERY PROCEDURES –An Overview
3.1 INTRODUCTION
The following recovery procedures are laid down based on the operating experience
gained in restoration of the systems during major grid disturbances that took place in the
region in particular and other regions in general in the past few years. Multi scenario
approach has been adopted while formulating the restoration procedures. The various
scenarios are listed for each state.
3.2 Existing Black Start Facilities in Western Region
List of all power stations having black start facilities is enclosed at Annexure-1.
3.3 Requirement of survival power / auxiliary power
Survival power means the power needed for avoiding the damage to the equipment in
case of supply failure. This power is required for:
• Turbine emergency oil pump
• Jacking oil pumps
• Barring gear of the turbine
• Lubricating oil pumps
• Compressors for ABCB operation
• Emergency lighting
• Battery chargers of Units, Stations, Communication & Telemetry system.
• Ensuring cooling of nuclear reactor and its auxiliaries
The survival power required by a 120 MW unit is of the order of 250-350 kW while the
requirement of 210 MW unit is of the order of 350kW and for 500 MW unit, it is of the
order of 1250 kW – 1500 kW. As a general rule, the survival power requirement would
be around 0.25 – 0.30% of the unit capacity. Stand-by diesel generator (DG) sets are
normally available at all power stations to provide survival power. As leaving the
equipment safety entirely to these DG sets for an extended period of time is not
desirable, extending alternate sources of supply to a power station becomes important.
For ensuring long term cooling of reactor and its auxiliaries, and safe containment of
radio activity, nuclear units need “Off-site power” at the earliest. Therefore, top most
priority would be given to nuclear units.
3.4 Requirement of start-up power
The start-up power is the power required for the unit auxiliaries for restoration of the
generating unit. The requirement of start-up power by various units is as follows:-
Thermal Units: 7 to 8% of the unit capacity.
Nuclear units: 10% of the unit capacity
Recovery Procedure for Western Region-Dec 2013 12
Hydro Units: 0.5 to 1% of the unit capacity.
Gas Units : 1.5 to 2% of the unit capacity.
The start up power requirement for starting the thermal unit is considerably high as the
major auxiliaries like Boiler Feed Pump (BFP), Induced Draft (ID) Fan, FD (Forced
Draft) Fan, Cooling Water (CW) Pumps etc., are of bigger size and the starting torque is
considerably high. In case of hydro units, the requirement of start-up power is not
significant as there are very few auxiliaries. The details of minimum survival / auxiliary
power required for the power stations in Western Region along with the capacity of
Diesel sets wherever installed are indicated at Annexure-2.
3.5 Synchronizing facilities at power stations / major sub-stations
The generating stations and major sub-stations having synchronizing facilities are
indicated in Annexure-3. For minimizing the time for restoration, it is imperative that all
lines of all the substations should be equipped with the synchronizing facilities in proper
working condition.
3.6 Supply to traction loads
(i) Constituent-wise priorities of load which are to be connected in steps should be
well documented and while restoring loads, essential loads such as railway
traction loads, underground coal mines/deep gassy mines, Air Port, TV station,
Telephone exchange, hospital, pumping stations etc., should be given priority
depending on available generation on bar.
(ii) Prior coordination with Railways is to be done to co-ordinate shifting of loads
between two Railway feeding points.
(iii) While extending power supply to the traction network during the system
restoration process, phase balancing should be kept in mind. Also the quantum of
actual load released from the sub-station should be known before the process of
restoration.
(iv) Railways should ensure that power supply should be used for only mobilizing the
rakes held up in between stations.
(v) Negative phase sequence currents, unbalanced voltages should be monitored to
avoid untoward incidents.
(vi) While releasing supply to traction some urban/city loads (inductive) should also
be simultaneously released so as to check the high voltages, jerks and
unbalancing.
(vii) Details of traction sub-stations in Western Region are enclosed at Annexure-
4(a).
(viii) The traction requirements have to be furnished by the constituents as per the
format enclosed at Annexure-4(b).
Recovery Procedure for Western Region-Dec 2013 13
3.7 Bus reactors
List of Bus reactors available in the Western Grid are enclosed in Annexure-5.
3.8 Line Charging Guidelines
Guidelines for charging lines are enclosed at Annexure-6.
3.9 Start up power from Non Utility Generators (Captive & IPP)
Maharashtra : At present, non utility / captive power plants are not in a position to
supply start-up power as their capacity is small and it is either completely used for their
own system or in most cases it is not feasible to be extended to other power stations.
Chhattisgarh : M/s. BALCO have agreed for supply of 10 MW power to cater to the
survival power requirement of units at Korba (E) for about one hour duration. No other
non-utility sector /captive power plant is able to supply start up / survival power.
Gujarat: Black start facilities are available in GIPCL, CLPIPL, and AECo. And Sugen
(Torrent) Power stations located near Vadodara, Bharuch, Ahmedabad and Surat
respectively.
• Islanding scheme is available for all the units at GIPCL power station.
• In the event of failure of islanding scheme, the units can be started through the D.G sets
available. The time taken would be of the order of 40 minutes. It was informed by
GIPCL that the gas at required pressure is available directly from the gas fields. As such,
further compression / pumping are not needed. Hence, even in the event of power supply
failure to the gas fields, the gas is readily available in the usable form at the power
station up to 12 hours.
Madhya Pradesh: Non-utility / CPPs are not having start-up power facility.
Goa: Reliance Power station at Sancole (48 MW) is the only generating unit in Goa.
Details of black start capability of the units are not available.
3.10 RESTORATION PROCEDURES
The black start/restoration procedures to be adopted depend upon the gravity of the grid
disturbance and the sources from where the startup power could be
expeditiously provided. Different approaches and procedures will be needed to be
adopted in case the whole grid is affected by the disturbance or the disturbance is
restricted to a limited area. The following black start procedures are laid down based on
the operating experience gained in restoration of the systems during major grid
disturbances that took place in the region in the past few years. Multi-scenario approach
has been adopted while formulating the restoration procedures. The various scenarios for
each state and region as a whole are listed below:-
Recovery Procedure for Western Region-Dec 2013 14
3.10.1 RESTORATION PROCEDURES FOR GUJARAT SYSTEM
To facilitate black start, D.G. sets are available in Gujarat System as mentioned below:
Sl. No. Power station Fuel Type DG set capacity
1 Ukai Hydro 500kVA
2 Mini hydro Hydro 50kW
3 Kadana Hydro 500kVA
4 Dhuvaran Gas/Thermal 2x1600kVA+700kVA
5 CCPP Vatva Gas 500kVA
6 CCPP Vatva Thermal Unit C:125kVA and Unit D,E,F:500kVA
each(Unit C islands during disturbance )
7 Kawas Gas 2850 kW
8 Gandhar Gas 2975 kW
9 GIPCL-II Gas/Steam 500 kVA
10 CLPIPL(Earlier
called GPEC)
Thermal 3000 kVA
11 Sugen Gas 2x6000 kVA
12 SSP Hydro 2x1000 kVA
PROCEDURES:
Detailed restoration procedure for Gujarat system is given at Chapter 4. Exhibits showing the
schematic scenarios are also enclosed along with Chapter 4. The salient points covered are :
(i) Scenario # 1 : All existing black start facilities of the state are made use of.
(ii) Scenario # 2 : Black start facility is not available at any location and start up power is
availed from Maharashtra through 220 kV Nasik-Navsari D/C or 220 kV TAPS(1&2)-
Vapi or TAPS(1&2)-Bhilad feeders. Alternatively 400 kV Boisar(PG)-Vapi-Sugen path
can also be used for availing start up power from Maharashtra.
(iii) Scenario #3 : Black start facility is not available at any location and start up power is
availed from M.P through 400 kV Indore-Asoj-Wanakbori or 400 kV Indore-Asoj-Ukai
paths.
3.10.2 RESTORATION PROCEDURES FOR M.P SYSTEM
To facilitate black start, D.G sets are available in M.P system as mentioned below:
Sl. No. Power station Fuel Type DG_set capacity
1 Indira Sagar Hydro 2x1000 kVA
2 Omkareshwar Hydro 2x1010 kVA
3 Bansagar Stage-I Hydro 250 kVA
4 Pench Hydro 250 kVA
5 Gandhisagar Hydro 100 kVA
6 Bargi Hydro 250 kVA
7 Bansagar Stage -III Hydro 250 kVA
8 Medikheda Hydro 250 kVA
9 Rajghat Hydro 250 kVA
10 Birsinghpur Hydro 220 Volt Battery
Recovery Procedure for Western Region-Dec 2013 15
Black start facility is available at Gandhi Sagar generating station, but due to the remote location
of this station and the requirement of charging long lines to extend the start up power to other
generating stations and inability of the machines to absorb reactive power while charging long
lines, these machines would not be available practically for providing black start facility.
Similarly, black start facility of Birsinghpur hydel station is not very reliable. Start up power
from Rajghat station also cannot be extended to thermal power stations as the hydro units are
small and cannot handle high starting current while energizing thermal auxiliaries. These plants,
thus, can be used to form small islands around them and act as a base for grid formation and
supplying emergency power to the nearest areas.
PROCEDURES
Detailed Restoration procedures for MP System are given at Chapter 5. Exhibits showing the
schematic scenarios are also enclosed along with Chapter 5. Possible scenarios are given below:
(i) Scenario # 1: Availing start up power from own black start sources.
(ii) Scenario # 2: Availing start up power from Chhattisgarh via Korba(W)-Kotmikala-
Amarkantak or 132 kV Dongargarh-Balaghat-Seoni-Pench path or through 400 kV
Bhilai-Seoni path.
(iii) Scenario # 3 : Availing start up power from Gujarat via 400kV Asoj-Indore-Burwaha
(220kV) - Itarsi- Satpura path or 400 kV SSP-Rajgarh-Nagda-Indira Sagar path.
(iv) Scenario # 4: Availing start up power from Maharashtra via 132 kV Kanhan-Pench
path or through Khaparkheda-Kalmeswar-Pandurna-Satpura path.
(v) Scenario # 5: Availing start up power from NR via 132 kV Rihand-Singrauli-
Vindhyachal or using 400 kV AC bypass link at Vindhyachal or through 132 kV Anpara-
Morwa-Amarkantak or by 132 kV R P Sagar -Gandhi Sagar lines or by 220 kV Auraiya-
Malanpur and Auraiya-Mehgaon lines.
3.10.3 RESTORATION PROCEDURES FOR CHHATTISGARH SYSTEM
Black start facilities are available at Hydro stations at Hasdeo Bango (250kVA DG Set).
PROCEDURES:
Detailed Restoration procedures for Chhatisgarh system are given at Chapter 6. Exhibits
showing the schematic scenarios are also enclosed along with Chapter 6. The possible scenarios
are as enumerated below:
Scenario # 1 : Availing start up power from own black start sources i.e. Hasdeo Bango hydro
power station.
Scenario # 2 : Availing start up power from Madhya Pradesh through 220 kV Amarkantak-
Kotmikala-Korba(W) or through 220 kV Amarkantak-Manendragarh-Bango or through 400 kV
KSTPS-Korba(W) S/C line.
Scenario # 3 : Availing start up power from Eastern Region through 220 kV Budhipadar-
Korba(E) path or through 400 kV Rourkela-Raigarh path.
Recovery Procedure for Western Region-Dec 2013 16
3.10.4 RESTORATION PROCEDURES FOR MAHARASHTRA SYSTEM
To facilitate black start, D.G. sets are available in Maharashtra System as mentioned below:
MAHARASHTRA:
Sl. No. Power station Fuel Type DG set capacity
1 Koyna I and II Hydro 2-MVA
house generator
2 KDPH Hydro 310 kVA
3 Eldari Hydro 6 kW
4 Ghatghar Hydro 1250 kVA
TATA POWER COMPANY (TPC):
Sl. No. Power station Fuel Type DG set capacity
1 Khopoli Hydro
2 Bhivpuri Hydro
3 Bhira Hydro 500 kVA
4 Bhira PSS Hydro 500 kVA
5 Trombay-7 Gas 2.5 MW
Action to provide black start facilities (DG set) at Koyna-IV may be initiated.
The following scenarios are considered.
Scenario # 1 : From own Black Start Facilities
Black start facilities at Koyna (Hydro) and Tata (Hydro) power stations are utilized.
Scenario # 2 : From Gujarat The black start facilities are not available and start up power is available from Gujarat through
220kV Vapi(G)-TAPS(1&2) and Bhilad-TAPS(1&2) lines and 220kV Navsari-Nasik D/C lines.
Power can also be received on 400 kV Vapi - Boisar line.
Scenario # 3 : From Madhya Pradesh
The black start facilities are not available and start up power is available from M.P grid through
220kV Pandurna-Kalmeshwar S/C line and 132kV Pench-Kanhan D/C lines.
Scenario # 4 : From Southern Region
The black start facilities are not available and start up power is available from Karnataka and
A.P of Southern Region through 220kV Chikodi- Kolhapur D/C lines and AC bypass link at
HVDC Bhadravati from SR.
Detailed Restoration procedures are given at Chapter 7. Exhibits showing the schematic
scenarios are enclosed along with Chapter 7.
Recovery Procedure for Western Region-Dec 2013 17
3.10.5 RECOVERY PROCEDURES IN TPC SYSTEM
Scenario # 1
In case of survival of Mumbai system through the islanding scheme for Mumbai area, TPC
system would be in a position to extend start up power to the power stations in Western
Maharashtra. In the event of failure of the islanding scheme, the hydro units would island at 45
Hz. The hydro units, two sets at Khapoli and three sets at Bhivpuri are equipped with black start
facilities in addition to the sets at Bhira and GT at Trombay. These hydro stations can be used
for black start requirements.
Scenario # 2
In the event of failure of the hydro islanding scheme of TPC and problems in black starting the
above units, TPC could avail start up power assistance from Maharashtra at the three tie points
of Borivali, Trombay and Kalwa interconnecting TPC and Maharashtra systems in Western
Maharashtra. Guidelines have been laid down and are in force for restoring the consumer loads
in Mumbai area. Detailed black start procedures for restoration of the generating stations as well
7as complete restoration of the lines and consumer loads is discussed at Annexure-7.
As a special case considering the importance of Mumbai city, the procedure for restoration of
the lines and consumer loads in Mumbai has also been dealt with separately. It would be of
utmost importance to resume city loads in Mumbai as early as possible to avoid loss of industrial
production and other law and order problems.
3.10.6 TOTAL WESTERN REGION
In case of total blackout in Western Region, assistance could be availed from neighbouring
regions in addition to utilization of black start facilities within the region. The scenarios for
availing black-start facilities within the region have been discussed in cases of restoration of
individual constituent‟s systems. The various possibilities of availing start-up power from
outside sources are described below.
Scenario # 1 Availing start-up power from NR through any of the following paths -
(a) 400kV AC bypass link at HVDC Vindhyachal substation.
(b) 132 kV Anpara-Morwa-Amarkantak
(c) 132 kV R.P. Sagar- Gandhi Sagar lines
(d) 220 kV Kota-Badod or Modak-Badod lines
(e) 220 kV Auraiya-Malanpur or Auraiya-Mehgaon lines
(f) 400 kV Bhinmal- Zerda or Kankroli- Zerda lines
(g) 400 kV Agra- Gwalior D/C
Scenario # 2 Availing start-up power from SR through 400kV Ramagundam-Bhadrawati lines
and 400 kV AC bypass link at HVDC Bhadrawati substation. 220 kV Chikodi- Kolhapur D/C
can also be used to avail start-up power from SR.
Scenario # 3 Availing start-up power from ER through any of the following paths-
(a)220 kV Budhipadar-Korba(E) D/C and Budhipadar-Raigarh S/C lines.
(b)400 kV Rourkela-Raigarh D/C lines.
(c)400 kV Ranchi-Sipat D/C lines.
Recovery Procedure for Western Region-Dec 2013 18
Detailed Restoration procedures are given at Chapter 9. Exhibits showing the schematic
scenarios are enclosed along with Chapter 9.
3.11 PRESENT CONSTRAINTS AND ACTIONS TO BE TAKEN TO OVERCOME
THE SAME.
Various constraints in the previous document for Recovery Procedures were discussed in past
and the following suggestions emerged:
1. Since Sikka station is located remotely, it would be difficult to extend startup power over
long distances till the rest of the Gujarat grid stabilizes. This would cause delay in
restoration of units at this power station. To speed up restoration, islanding scheme could
be designed for Sikka. Sikka units can be islanded either with Bhatia or Jamnagar.
Further, synchronizing facilities need to be provided at 220kV Anjar and Jamnagar to
facilitate integration of Sikka and Panandro with the rest of the grid in case of islanding
of these power stations. The islanding scheme for Sikka was dropped due to constraints
in opening of number of lines.
2. 220 kV Satpura-Kalmeshwar S/C line is made LILO at Pandurna and is in service and
this line would facilitate in extending start up power to Satpura, Khaperkheda, Koradi
power stations as well as to Pench HEP if required. This line helped in reducing the
problems faced while extending power from Pench units.
3. 220kV Ujjain-Badod-Modak and Ujjain-Badod-Kota lines are brought into service and
can be used for extending black start power to and from Rajasthan(NR) whenever
required. This would help in extending start up power upto Satpura power station
through 220kV Ujjain – Barwaha – Itarsi - Satpura D/C path. By simultaneously running
Gandhisagar hydro units, start up power can also be extended through 132 kV Gandhi
Sagar- Garoth– Badod-Ujjain – Makshi-Shujalpur – Shajapur – Bhopal – Itarsi –
Satpura. This was successfully used earlier after the grid disturbance on 30.07.2002.
4. The existing islanding scheme for Panandro is now kept out of service. This scheme
requires review as Akrimota power station is in close vicinity of Panandro.
5. Out of the several islanding schemes proposed in the existing recovery procedures, some
of the schemes were discussed and finalized by the islanding subcommittee. Out of these,
scheme for Uran was already implemented while islanding scheme for Bhusawal was
dropped. The islanding scheme for Korba(E) was approved by the islanding sub-
committee and is to be implemented. The islanding scheme for Nasik and Tarapur
stations were under finalization.
6. Out of the Islanding schemes using radial load at power stations as proposed in the
existing recovery procedures, islanding schemes for Amarkantak power station was
cleared by the islanding sub committee and is yet to be implemented. However, islanding
scheme for Satpura was dropped and the islanding scheme for Parli would be discussed
in the next meeting of islanding subcommittee.
7. There is no need to provide black start facilities at Vaitarna, Bhira TR and Tillari power
stations.
Recovery Procedure for Western Region-Dec 2013 19
8. No D.G set or battery is available at SGTPS, Korba (W), Korba (E) etc. to supply
survival power. The constituents were requested to inform the availability of DG sets.
9. The MPPTCL representatives confirmed that the second 63 MVA, 220/132 kV ICT at
Amarkantak was taken back into service and at present both 2x63 MVA ICTs are in
service.
10. Tripping of breakers by the operators at all the dead buses takes time and delays
restoration process. This could be done automatically using under voltage/no voltage
relays.
11. All the constituents should fix up targets (time required for restoration) for various
activities and this could be compared with the actual time taken during restoration so as
to understand the reasons for delays. The NTPC representative stated that the problem of
delay in restoration due to puncturing of LP turbine diaphragms was examined at their
end. Earlier it used to take 8 hours for replacement of diaphragms and now the same can
be done in 3-4 hours due to some modifications works done by NTPC. It was suggested
that the representatives from power station of the constituents would interact with NTPC
on the above and spare diaphragms should be made available at all the power stations.
13. Field tests to be conducted to study the feasibility of using one unit at Pench for
restoration of Maharashtra system and the other unit for restoration of M.P system.
Khaperkheda & Koradi power stations should be able to get start-up power from Pench
without any difficulties.
14. Some of the islands during restoration might collapse due to tripping of units or load
restoration in large amounts compared to response rate of units or frequency prior to pick
up of loads being too low (below 49 Hz) etc.. If the islands are built around gas based
power plants, a constraint might arise in respect of restriction on multiple start-up and
shutdowns. Documentation of number of startups and shutdowns, load and duration
between two startups for emergency conditions is essential. The constituents may furnish
this information for inclusion in the Recovery Procedures.
15. On 30.7.2002 occurrence, problems with some DG sets were observed. Healthiness of
DG sets has to be ensured through weekly trial runs.
16. Field trials in the form of Mock Drill on all the black start facility generating stations are
planned to done on regular basis. As on date Nine Balckstart mockdrill has been
completed in Western region out of which Details of the Moackdrill at ISP, Bargi, SSP,
Bango, Pench and CCPP Vatva are included in Annexure-IX.
17. 220kV Kolhapur-Chikkodi D/C lines between WR & SR grids are now in service and in
healthy condition and can be used for black start.
18. Field trials are to be conducted to overcome the hunting problem faced by Bargi and
Pench. The following procedure was agreed upon:
(i) By starting one unit keeping AVR out of service keeping the excitation around 0.85 pu
(as low as possible). AVR to be taken into service only after the machine is loaded upto
10% to 15% at frequency around 50 Hz.
Recovery Procedure for Western Region-Dec 2013 20
(ii) At the remote end, one transformer with load of around 10% capacity of the machine (i.e
5 MW for Bargi machines or 7 MW for Pench machines) is to be kept closed so that if
the line is charged, the load immediately comes on the machine. It is generally found that
hydro machines have good response rates.
(iii) It is to be observed if any hunting occurs in active power, voltage or reactive
power. If no hunting is observed, the AVR is to be taken into service. If hunting is
still observed more load is to be added at the remote end (i.e Jabalpur for Bargi
units and Kanhan/Seoni for Pench units) tills the hunting stops and then the AVR is
to be taken in auto mode. As the load is picked up on the machine, the excitation
should be increased gradually.
iv) With AVR in service throughout, it can be tested whether hunting occurs as it is
suspected that the hunting occurs mainly due to activation of exciter modes. The
response rates of the machines are also to be tested by recording frequency change for
different load increments. The observation on MW/Hz to be recorded. The response rates
should be recorded as below:-
Sl No Initial M/c Loading
(MW)
Load Increment in
MW (preferably @
5% steps)
Change in
frequency (Hz)
Response
MW/Hz
1
2
3
4
19. Updates are constantly required from the experience of the past grid disturbances. It has
been decided after discussions with the constituents that the recovery procedures has to
be updated based on experience gained from each of the grid disturbance. It was agreed
that after a grid disturbance, all the constituents shall report to WRLDC/WRPC the
restoration process adopted in detail along with the formats enclosed at Annex-VIII and
thereafter a meeting will be arranged along with the following OCCM to discuss the
difficulties faced in restoration and to suggest measures to improve the restoration
performance. It is stressed that updating of recovery procedures should be a continuous
ongoing activity and the constituents would provide suggestions and updates on a
continuous basis so that WRLDC can consider the information while updating the
recovery procedures as per the provisions in Grid Code.
20. Review of facilities and new units/transmission lines commissioning:-
A new hydro station of 2x125 MW has been commissioned at Ghatgar near Igatpuri.
This sub-station could ideally provide start up power to Nasik. The details of evacuation
facilities from Ghatgar shall be provided by MSETCL to identify the start up paths. One
black start DG set of 1250kVA is available at Ghatghar to provide start up power to the
units. To overcome high voltage problems during the black start process it is considered
worthwhile to provide facilities to run the hydro units in synchronous condenser mode. It
was therefore recommended that the up-coming hydro projects should have the facility to
operate in synchronous condenser mode. It was informed that synchronous condenser
mode of operation is proposed to be provided for Omkareshwar hydro units. The
information regarding Maheshwar hydro power station would be furnished by MPPTCL
with the necessary details.
Recovery Procedure for Western Region-Dec 2013 21
21. SSP units are already being used in synchronous condenser mode and one / two
machine(s) may be used during the initial start up for charging and connecting suitable
and sustainable load in addition to house and local loads through a line.
22. The Detailed Recovery Procedure for new plants viz. Sipat, Jindal, Lanco, NSPCL,
Jaigad, Wardha Power, Essar (Mahan), ACBL, Balco etc. are to be prepared in priority.
23. The Black Start facilities to be extended by new gas plants like RGPPL, Sugen etc. are to
be worked out in details. RGPPL has recently procured a black start generator in the form
of a gas turbine of 35 MW capacity which can be started with both gas & liquid fuel. The
turbine is under testing and soon will be ready as a black start source for the generationg
station.
***
Recovery Procedure for Western Region-Dec 2013 22
CHAPTER – 4
RESTORATION PROCEDURES
FOR
GUJARAT SYSTEM
4.1 INTRODUCTION
In case of total Black out in Gujarat power system, the following possible scenarios are
recommended for restoration of the supply in the state based on black start facilities available in
the state and sources of power available from outside the state. Enclosed Exhibits show the
schematic diagrams for scenarios and restoration plans based on island approach.
4.2 SCENARIOS OF BLACK START AT GUJARAT
4.2.1 SCENARIO # 1: FROM OWN BLACK START SOURCES
A. Kawas Gas Power Station (NTPC) (4 X 106 MW (GT) + 2 x 116 MW (ST))
(i) Kawas gas power station is equipped with DG sets adding to 2.85 MW capacity.
The auxiliary power requirement is 2.5MW for one GT.
(ii) The DG set cuts in automatically with black out and synchronizes to 6.6kV bus within 30
seconds.
(iii) The availability of DG set is being checked weekly by synchronizing with 6.6kV and
running the DG set for half an hour.
(iv) Kawas is having synchronizing facilities for units as well as lines.
(v) After auxiliary power is made available, the GTs can come up and deliver power to
220kV bus within half an hour.
(vi) In normal case with proper communication between Kawas and Ichhapur, 220kV
Kawas-Ichhapur S/C shall be charged and load is provided to Kawas units
commensurate with ramp up and response rate requirements of the GTs. The loads
of ONGC and GAIL, Hazira to be restored on priority to maintain gas pressure of
HBJ pipeline.
(vii) The preference for extending power from Kawas is Ichhapur, Navsari and Vav in that
order under normal restoration. However, in case of any problem between Kawas &
Ichhapur or in case of total failure of supply at Tarapur, 220kV Kawas-Navsari line may
be charged instead of 220kV Kawas-Ichhapur S/C line so that off-site power to Tarapur
can be extended. In case of problems in extending power supply to Ichhapur and
Navsari, extension to Vav can be considered.
(viii) SLDC, Gujarat shall instruct Ichhapur sub-station and Kawas sub-station to make
available suitable load in small increments and not to connect excess load as the units
Recovery Procedure for Western Region-Dec 2013 23
may trip. Gujarat shall initially connect 220kV/66kV and then 66/11kV transformers
without any load on their secondary. Further, the 11kV feeders shall be switched ON one
by one in steps of 2 MW each. The loading rate shall not exceed 7.2 MW per minute. In
case Gujarat requires to extend start up power to another power station, Kawas units on
bar shall preferably be loaded upto 50% of their capacity. The exact loading rates – ramp
up/ramp down in MW per minute and response rates in MW/Hz shall be informed by
NTPC.
(ix) If frequency is less than 49.5 Hz, load should not be connected and in case frequency is
greater than 50.2 Hz, load should not be disconnected and restoration of loads shall be in
small steps such that the frequency change is not more than 0.5 Hz.
(x) 220 kV Ichhapur - Vav line is to be charged in consultation with Kawas and start up
power is to be fed to Utran CCPP through 66 kV Vav - Utran line to start generation of
Utran and release supply to essential services like Railways and essential loads of Surat
city through 66 kV Vav - Bhestan lines.
(xi) One circuit of 220 kV Vav-Kakrapar D/C (43km) line is to be charged to feed survival
power to Kakrapar Nuclear Power Station. In case of no power available at Vav, this
power can be availed from Ukai(Th.) by charging 220 kV Vav - Kakrapar - Ukai (Th)- 1
(Teed line) (63 KM) to feed survival power to Kakrapar.
(xii) By Charging 220 kV Vav - Kim - Zagadia - Haldarwa line and feeding start up power to
Jhanor, CLPIPL & GSEG more and more generation to the growing up network can be
availed.
(xiii) Extend power available at Halderwa to Jambua via 132 kV Haldarwa - Karjan - Jambua
(56 KM) line and there after charge 220 kV Haldarwa - Jambua line. Supply power to
Railways and Vadodara city.
(xiv) Extend start up power to GIPCL if required or if generation is available at GIPCL due to
islanding, synchronise it at Jambua and get more generation.
(xv) The available power at Jambua may be extended to Dhuvaran and Wanakbori.
(xvi) In case of failure of DG to start, start up power to Kawas to be extended as per the
procedures under sec 4.2.2 & 4.2.3.
B. Jhanor CCPP (144MW X 3 GTs+225 MW ST)
Selecting the gas turbine first to be started as per following preferences:-
a) GT-1 or GT-3 when all three gas turbines/ only GT-1 & GT-3 are available
b) GT-1, when GT-1 & GT-2 are available
c) GT-3, when GT-2 & GT-3 are available.
The actions may be initiated as described below:
(i) Start 2975 kW DG set to feed start up power to the GT unit to be started. After start up of
one of the GT unit, station load to be put on operating gas turbine.
(ii) Isolate both 220kV buses by opening all feeders connected to them.
Recovery Procedure for Western Region-Dec 2013 24
(iii) Start another gas turbine.
(iv) One of the 220kV buses is to be charged as per existing condition and convenience.
(v) One of the 220kV Jhanor-Haldarwa D/C lines (13km each) is to be charged through one
gas turbine which is not connected to station load, in consultation with Haldarwa sub-
station.
(vi) Then build up load upto 50 MW at Haldarwa sub-station in consultation with SLDC
Jambua, WRLDC and NTPC-Jhanor as per approved procedure of loading within
capability of gas turbine at a rate of 7.2 MW/min. Power supply to Bharuch town,
Railways and ONGC Gandhar gas fields (to maintain adequate gas pressure)has to be
extended on priority basis. Loading procedure is to be drawn by SLDC,Gujarat in
consultation with WRLDC and NTPC.
(vii) Start up power to CLPIPL to be extended through 220kV Haldarwa-CLPIPL line.
However, charging 400 kV Jhanor-CLPIPL line may not be feasible till sufficient load
(approx.50MW) is available on the unit as it requires charging through ICT.
(viii) 132 kV Haldarwa - Karjan - Jambua line (56 Kms) is to be charged to feed Railways and
Vadodara city.
(ix) 220 kV Haldarwa - Jambua line to be charged and power available at Jambua to be
extended to GIPCL, Dhuvaran and Wanakbori.
(x) After checking the generation capacity available at Jhanor, CLPIPL and GIPCL, extend
start up power to Kadana (Hydro), AECo and Gandhinagar to start generation.
(xi) By charging 220 kV Haldarwa - Kawas line (81 Kms) start up power to Kawas may be
taken.
(xii) By charging 220 kV Kawas - Ichhapur line (3 Kms), supply to ONGC and GAIL Hazira
may be availed to be extended to maintain gas pressure of HBJ pipe line.
(xiii) By charging 220 kV Icchapur - Vav line (34 Kms), start up power to Utran CCPP
through 66 kV line and then to Kakrapar, Ukai (Th) and (Hydro) via 220 kV Vav –
Kakrapar line (43 Kms) is to be availed.
(xiv) As mentioned earlier restoration of loads shall be in small steps such that the frequency
change is not more than 0.5 Hz. In case of failure of DG set to start, start up power to
Jhanor shall be provided as per the procedures described under 4.2.2 & 4.2.3. If power is
available at CLPIPL, then through 400kV CLPIPL-Jhanor S/C and then from 220kV
Haldarwa by charging 220kV Jhanor-Haldarwa lines.
C. Ukai hydro Power Station (75 MW x 4 Units)
(i) D.G. Set of 500 kVA is available at Ukai main hydro power station. This set can be
started and auxiliaries to any one of 4 units can be fed, thereby main unit can be started
immediately. Simultaneously 50 KW house set of Mini Hydro station is to be used to
start 2.5 MW x 2 sets and charge 66kV line to main hydro station. Main unit can be
started either through its own DG or through power extended from Mini Hydro
Recovery Procedure for Western Region-Dec 2013 25
whichever comes first. Once the main unit is started, it can give start up power to Ukai
Thermal Power Station on one of the 220 kV Ukai Hydro-Ukai Thermal Tie lines. The
75 MW unit requires minimum 40 MW load for normal running, the same can be made
available by 66kV radial feeders from 50 MVA, 220/66 kV transformer installed at 220
kV main hydro switch-yard and 66kV lines feeding Songadh, Vyara, Nizar and Sagbara,
which is 25 to 30 MW.
(ii) By charging 220kV Ukai (Th) - Vav - Kakrapar from Ukai, keeping the breaker at Vav
open and observing the voltages within operating limits, Kakrapar is to advised to draw
survival power/ start-up power.
(iii) After charging 220 kV Bus of Vav substation, power to essential services like Railways
(through 66kV line to Bhestan) and Surat City may be catered.
(iv) Also start up power to Utran CCPP is to be extended through 66kV Vav – Utran line to
start the station and add generation.
(v) If generation at Kawas is available due to operation / survival of any of the unit on
house load, the system may be strengthened by charging 220 kV Vav - Ichhapur line (34
km) and 220kV Ichhapur - Kawas line (3 km) with addition of more generation.
Extension of power to essential services like ONGC Hajira for maintaining gas pressure
of HBJ pipe line feeding to Kawas and other important industries located on the
upstream may be explored and carried out.
(vi) Power to be extended to Navsari via 220kV Vav-Navsari line (33 km) to feed Railways
and Navsari town by ensuring adequate inductive loading to compensate capacitive
effect while charging long line. A concentrated load of town / city may be released along
with that of Railways after taking into due consideration of frequency and stiffness of the
island.
D. Kadana Hydro Power Station (60 MW x 4 units)
DG set of 500 kVA is available at Kadana Hydro Power Station. This set can be started
to feed the auxiliaries of any one of 2 units. Once main unit is started it can give start up
power via 220 kV Kadana-Godhra and from Godhra to Wanakbori.
E. A.E.Co. (Torrent Power), Sabarmati Gas Station (32.5 MW x 2 GT +35 MW ST)
(i) 500 kVA DG set to be taken into service to feed start up power to one GT unit. With
availability of sufficient gas pressure, GT unit is to be taken up. Once one GT unit is
started, auxiliary power to be extended to C,D,E and F units.
ii) Power to be fed to ONGC Kalol to help maintain gas pressure to operate second GT unit.
(iii) Once any of C,D,E,F units starts generation, restoration of power to Ahmedabad and
Gandhinagar may be initiated.
(iv) Auxiliary power to Gandhinagar and Wanakbori TPS can be restored subsequently.
F. GIPCL CCPP (32 MW X3 Units and 105 MW Unit)
DG set of 500 kVA capacity is available.
Recovery Procedure for Western Region-Dec 2013 26
(i) If GIPCL CCPP is successfully islanded and survived, power to be extended to Jambua
through GIPCL Nandesari- Jawaharnagar- Jambua lines to feed to Railways, Vadodara
City and GAIL Wagodia.
(ii) To extend power to Haldarwa substation via 132 kV Jambua - Karjan line (21km) and
132 kV Karjan - Haldarwa line (35km) to feed to railways and Bharuch city.
(iii) If generation at Jhanor is available due to operation of one of its three units in house
load, 220 kV Haldarwa - Jhanor line (13kms) may be synchronised (at Jhanor) to add
more generation and strengthen the network.
(iv) Start up power to CLPIPL may be taken via 220 kV Haldarwa - CLPIPL line and on
starting generation at CLPIPL, loads to be slowly resumed and network to be expanded
and built up.
(v) Further expansion of network may be done by Charging 220 kV Haldarwa - Kawas line
(81kms) and synchronizing Ukai - Kawas system with GIPCL - Jhanor system at Kawas.
(vi) Extend power of GIPCL to Dhuvaran, if Dhuvaran can not start its DG set to start GT
unit, via 132 kV GIPCL - Nandesari - Jawaharnagar - Fertiliser - Gotri - Dhuvaran lines
and start GT unit to feed auxiliaries of other units.
(vii) From Dhuvaran feed power to Gandhinagar via 132 kV Dhuvaran - Vatva - Ranasan and
220 kV Ranasan - Gandhinagar lines.
(viii) Extend power available at Jambua to Asoj and then Wanakbori via 220 kV Jambua -
Asoj - Wanakbori lines. From Wanakbori extend power first to Godhra and Kadana via
220 kV Wanakbori - Godhra – Kadana lines and start Kadana units to add generation to
the expanded network. Restore Railway supply from Asoj, Godhra and Dahod.
(ix) Power available at Dhuvaran can be fed to Railways from Anand, Mahemdawad via 132
kV Dhuvaran - Karamsad - Ode line and 132 kV Karamsad - Nadiyad - Mahemdawad
line.
(x) Power available at Haldarva or Jambuva can be extended to Zagadia through 220kV
Haldarva-Zagadia-Mangrol S/C or through 220kV Jambuva-Zagadia-Mangrol S/C.
(xi) Power available at Wanakbori/Gandhinagar/Ranasan can be extended to Sikka through
220kV Wanakbori/Gandhinagar-Ranasan-Karamsad-Limdi-Jetpur & 220kV Jetpur-
Jamnagar and 132 kV Jamnagar-Sikka.
(xii) Start up power to Panandro can be extended from Sikka via 132kV Sikka-Wanakner-
Anjar S/C and 220/132kV ICT at Anjar and 220kV Anjar-Kukma-Panandro D/C.
G) SUGEN(3 GTs of 382.5 MW each):
2-DG sets of capacity 6 MVA each are available at Sugen power plant(3x382.5MW)
from which power supply can be extended to GSEC via 220 kV Sugen-Kim-GSEC D/C.
Recovery Procedure for Western Region-Dec 2013 27
4.2.2 SCENARIO # 2: FROM MAHARASHTRA
In order to start at least one unit each at Kawas and Ukai about 10 MW power is required.
WRLDC would arrange about 10 MW power from Maharashtra either on 220 kV TAPS –
Bhilad- Navsari or on 220 kV Nasik - Navsari D/C whichever route is feasible at that moment to
supply power. Following action are to be taken from Navsari end.
1. Navsari would be advised to make necessary arrangements for getting power supply
from TAPS / Nasik.
2. Navsari would extend the supply to Kawas on 220 kV Navsari- Kawas D/C and to Vav
on 220 kV Navsari - Vav D/C.
3. Kawas would be advised to make necessary arrangements to receive the power on 220
kV Navsari- Kawas D/C and extend the same to Kawas Gas power station to start at
least one unit at Kawas.
4. Once the unit at Kawas start generating power, Power can be extended to Haldarwa on
220 kV Kawas - Haldarwa D/C. Essential loads in Bharuch can be restored and power
can be extend to Karamsad on 220 kV Haldarwa-CLPIPL-Karamsad D/C if sufficient
amount of power is available at Haldarwa end.
5. Vav would be instructed to make necessary arrangements to receive the power on 220
kV Navasari - Vav D/C.
6. Vav would extend the power to Ukai and Kakrapar on 220 kV Vav- Ukai and Vav -
Kakrapar respectively.
7. Ukai and Kakrapar would be advised to avail the power received from Vav to start the
units at Ukai (T) and for providing survival power and start-up power to the units at
Kakrapar respectively.
8. Once the units at Kakrapar & Ukai (T) start generating power, the power can be
extended to central Gujarat area on 220 kV Kakrapar - Haldarwa D/C, 220 kV Ukai -
Achhalia and 400 kV Ukai - Asoj to restore the essential loads and to extend the power
supply to start other thermal generating units in Gujarat.
9. 400kV Padghe- Boiser(PG)- Vapi(PG)- Sugen- Jhanor line can also be used to extend
supply from Maharashtra.
4.2.3 SCENARIO #3: FROM MADHYA PRADESH
All efforts to be made to start the thermal generating units by getting the supply from Ukai (H),
Kadana (H), Kawas, Dhuvaran, A.E.Co. C, GIPCL, Sugen where black start facilities are
available. In case of non availability of DG Sets at Ukai and Kadana Hydro power station and
Kawas and unsuccessful operation of islanding scheme of A.E.Co. `C` station /Dhuvaran - II /
GIPCL, LD Jambuva will contact WRLDC to arrange the assistance from other constituents. In
order to start at least one unit each at Wanakbori and Ukai (Th) power station, about 25 MW
power is required. WRLDC would arrange about 30 MW power from Madhya Pradesh on 400
Recovery Procedure for Western Region-Dec 2013 28
kV Indore - Asoj lines. One of the Indore - Asoj lines can be charged depending upon the bus
voltage at 400 kV Indore S/S.
Following actions are to be taken from Asoj end.
1. SLDC,Gujarat would advise Asoj to make necessary arrangements for getting power
supply from Indore and taking into service 400 kV Indore - Asoj lines. Use bus reactors
at Asoj and tertiary reactors at Indore to control the high voltage problem.
2. Asoj would extend the supply to Wanakbori and Ukai on 400 kV Asoj - Wanakbori and
Asoj - Ukai lines.
3. SLDC,Gujarat would advise Ukai(T) to make necessary arrangements to take the supply
from Asoj.
4. Wanakbori would extend supply to start one unit at power house. Once one unit is started
all other units can be started sequentially.
5. Depending upon the power assistance possible from Madhya Pradesh, Wanakbori would
charge the 400/220 kV ICT and supply can be extended to start the other units at
Wanakbori.
6. 220kV Wanakbori S/S would extend the supply to Gandhinagar thermal power station on
220 kV Wanakbori - Ranasan - Gandhinagar lines.
7. Gandhinagar would make the necessary arrangements to receive the power from Ranasan
and would extend the supply to start the units at Gandhinagar.
8. Once the units at Gandhinagar start generating sufficient amount of power, the same can
be extended to Mehsana on 220 kV Gandhinagar –Nardipur-Mehsana.
9. Mehsana would extend the supply to start the units at KLTPS on the route 220 kV
Mehsana – Anjar –Kukma- Panandro.
10. Mehsana, Anjar and Panandro would be advised to avail the power and extend the same
to start the units at KLTPS and Akrimota.
11. Ukai would be advised to extend power to Ukai (T) to start one unit by availing the
supply from Asoj. After starting one unit, supply can be extended to start the other units.
12. Ukai would extend the supply to Kakrapar on 220 kV Ukai (T) –Vav-Kakrapar feed line
for survival power and to start the unit at KAPS.
13. Ukai would extend the supply to Vav on 220 kV Ukai(T) - Vav and essential load in
Surat town can be restored to the limit of availability of power.
14. Vav would extend the supply to Kawas Gas power station to start the units at Kawas.
15. Vav and Kawas would extend the supply to Navsari to restore the loads in Navsari and
Vapi and also to extend the supply to TAPS and Nasik in case of failure of supply in
Maharashtra system.
Recovery Procedure for Western Region-Dec 2013 29
16. Extending supply to Sikka TPS can be done through the path 220kV Wanakbori- Gandhi
Nagar-Ranasan-Karamsad-Limdi-Jetpur and 132kV Jetpur- Jamnagar-Sikka.
4.2.4 SCENARIO #3: FROM NORTHERN REGION (NR)
If Rajasthan(NR) system is intact startup power may be availed from NR over 400 kV
Kankroli-Kansari and 400 kV Bhinmal-Kansari and then power can be extended via 400
kV Kansari-Soja-Wanakbori to Wanakbori Thermal Power Station(TPS).Wanakbori
would use the start up power to start one unit and extend power to start other units
sequentially.
Depending upon the system condition 400/220 kV ICT at Wanakbori may be charged
and power supply may be extended to Gandhinagar TPS via 220 kV Wanakbori-
Ranasan-Gandhinagar and sub-systems can be gradually built up as described in earlier
sections.
4.3 GUJARAT SYSTEM – IDENTIFIED GRID PATH FOR START UP POWER
TO POWER STATIONS WHERE STARTUP SOURCE IS NOT AVAILABLE
Kakrapar
Path I - Ukai(H) / LBC(H) / via Ukai(T) – Vav 220kV circuitI -Teed connector at
Kakrapar
Path II - From 220kV Kawas-Haldarwa-Kakrapar D/C
Path III - From 220kV Jhanor-Haldarwa-Kakrapar D/C
Path IV - Kawas-Vav-Kakrapar D/C
Path V - 220kV Kawas-Navsari-Vav-Kakrapar
Ukai (Thermal)
Path I - 220kV Ukai (H) – Ukai (T) D/C (From Ukai(H) or LBCH)
Path II - 220kV Kawas-Vav D/C and 220kV Vav-Ukai(T) D/C
Path III - 132kV GIPCL – Nandesari-Asoj and through 132/220/400kV ICT at Asoj to
Ukai on 400kV path.
Path IV - 400 kV SSP- Asoj – Ukai(T)
Sikka (Thermal)
Path I - From RPL on 132kV RPL-Khambalia - Sikka S/C
Path II - 132kV Wankaner-Sikka
Path III - 132kV Jamnagar-Sikka
Path IV - 220kV Wanakbori / Gandhinagar- Ranasan-Karamsad-Limdi - Jetpur –
Jamnagar &132kV Jamnagar- Sikka
Recovery Procedure for Western Region-Dec 2013 30
Dhuvaran (Thermal)
Path I - 132kV AE Co.- Sabarmati – Ranasan-Watwa-Dhuvaran D/C
Path II - 132kV GIPCL-Jawahar Nagar-Jambua - Gotri-Dhuvaran
Path III - 132kV AE.Co(gas),Watwa- Watwa(Gujarat)-Dhuvaran
Gandhinagar
Path I - 132kV AE.Co- Sabarmati – Ranasan D/C – 220/132kV
ICTs at Ranasan-Gandhinagar D/C.
Path II - 220kV Wanakbori-Ranasan-Gandhinagar D/C-Wanakbori
Path I - Kadana-Godhra-Wanakbori
Path II - 132kV AE.Co–Sabarmati-Ranasan D/C – 220/132kV ICTs at Ranasan-
Wanakbori D/C
Path III - 132kV GIPCL – Nandesari – Asoj through 132/220kV ICT at Asoj and
220kV Asoj - Wanakbori D/C
Path IV - SSP – Asoj - Wankabori
Panendro
Path I - 220kV Anjar-Kukma-Panendro D/C
Path II - 400 kV Gandhar-Dehgam-Sami-APL Mundra-N‟Khakar-Nakhatrana-
Panendro
Essar
Path I - 220kV Kawas-Ichhapur-Essar
Path II - 220kV KAPS/ Jhanor/CLPIPL-Haldarwa- Kawas-Ichhapur-Essar
Path III - 220kV KAPS-Vav-Sachin-Essar
Path IV - 220kV Ukai(T)-Vav-Sachin-Essar
SLPP
Path I - 220kV Utran-Kim-Zagadia-SLPP(Mangrol)
Path II - 132kV Dhuvaran-Gotri-Jambua & 220kV Jambua-Zagadia-SLPP
Path III - 132kV GIPCL-Jawaharnagar-Jambua & 220kV Jambua-Zagadia-SLPP
Path IV - 220kV KAPP/Kawas/Jhanor/CLPIPL-Haldarwa - Zagadia-SLPP
Path V - 132kV A.E.Co.-Ranasan-Karamsad- Jambua & 220kV Jambua-
Recovery Procedure for Western Region-Dec 2013 31
Zagadia-SLPP
Utran
Path I - 220kV Ukai/Kawas/Kakrapar-Vav & 66kV Vav-Utran
Path II - 220kV SLPP-Zagadia-Kim-Utran
Path III - 220kV GSEC-Kim-Utran
Path IV - 220kV Kawas/Jhanor/CLPIPL/KAPP – Haldarva-Kim-Utran
GSEG, Hazira
Path I - 220kV Utran-Kim-GSEG- CLPIPL
Path I - 400kV Jhanor-CLPIPL
Path II - 220kV Jhanor-Haldarwa-GPEC
Path III - 220kV Gandhinagar-Karamsad-CLPIPL
Path IV - 220kV Wanakbori-Ranasan-Karamsad - CLPIPL
Path V - SSP-Kasor-CLPIPL
Akrimota
Path I - 220 kV Panandro- Akrimota- D/C
Path II - 220 kV Nakhatrana- Panandro-Akrimota D/C
APL,Mundra
Path I - 220 kV Panendro-Nakhatrana–Nanikhakar – APL, Mundra
Path II - 400 kV SSP-Asoj-Chorania-Hadala-220kvHadala-Varsana-APL,Mundra
Path III - 400 kV Gandhar-Dehgam-Sami-APL,Mundra
CGPL(UMPP),Mundra
Path I - 400 kV Gandhar-Dehgam-Ranchodpura-Bachchao-CGPL,Mundra.
Path II - 400 kV SSP-Asoj-Choronia-CGPL
***
Recovery Procedure for Western Region-Dec 2013 32
13
LE
GE
ND
:
Sta
tion t
o s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
LE
GE
ND
:
Sta
tion t
o s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
Guja
rat
Se
lf S
tart
LE
GE
ND
:
Sta
tion T
o S
elf
- S
tart
Hyd
ro
Therm
al
Nucl
ear
Sub-S
tatio
ns
400 K
V
220 K
V132 K
V
66 K
VA
ltern
ate
Path
Godhra
Uka
i (H
)
Kadana(H
)
Ste
p N
o0
12
34
Uka
i (T
)
Wanakb
ori
Ranasa
n
Anja
rM
ehsa
na
56
Jaw
ahern
agar
Jam
buva
Ach
halia
AE
CO
.(G
)G
andhin
agar
Nard
ipur
Panandro
Sabarm
ati
Jetp
ur
Palia
dD
huva
ran
GIP
CL
Gandhar
Kaw
as
Gondal
Jam
nagar
Sik
ka
Wanka
rer
Lim
di
Vav
Vapi
Hald
arv
a
Kakr
apar
Navs
ari
Aso
jN
andesa
ri
Kim
Zagadia
Sura
t Lig
nite
Utr
an
GP
EC
Gotr
i
Kara
msa
d
Karjan
Ichhapur
Wagodia
Bhila
d
Tara
pur
Vatw
a
GS
EC
Akr
imota
SS
P
Kaso
r
Fe
rtili
zer
Na
ga
r
Meh
sana
Sa
nkh
ari
Sh
ivle
kha
We
lsp
un
An
jar
Ku
kma
N
'Kh
akk
ar
N
akh
atr
ana
Pa
ne
nd
ro
De
hga
mS
am
iG
and
ha
rS
uge
n
AP
L(M
un
dra
)
Ra
nch
od
pu
raC
GP
L(M
un
dra
)B
ach
chao
2.5
8
34
73
7
80
35
47
19.8
2.1
9.2
19.8
830.2
13 81
34
6289
49
74
117
81
10.3
21
27
16
55
2249
35
21
12.9
35
98
7318
548
27.5
124
Dar
ol27
92
138
26
106
106
50
152
64
59
282
157
16.3
75
3
100
41
Dha
ndhu
ka
96
82
108
(Fig
ure
show
s lin
e le
ngth
in K
m)
62
280
Exh
ibit
- 1
/Sce
nario
1
30
146
26
10.2
7.1
Recovery Procedure for Western Region-Dec 2013 33
LEG
END
:
Stat
ion
to s
elf-s
tart
Hyd
ro
Ther
mal
Nuc
lear
Subs
tatio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rnat
e Pa
th
(Fig
ure
show
s lin
e le
ngth
in K
m)
Exhi
bit -
1 /S
cena
rio 2
Scen
ario
- II
Jam
bua
Acha
lia
Kaw
asN
avsa
ri
Uka
i( T
)
Step
No
01
23
45
6
Guj
arat
: Sta
rt up
from
Mah
aras
htra
Kakr
apar
Vav
Asoj
Wan
akbo
ri
GPE
CG
andh
arH
alda
rwa
Tara
pur
Kar
amsa
d
Gan
dhin
agar
Nas
ik
Mah
aras
htra
Vapi
7
Bhila
d
Bois
er
(PG
)
Uka
i( H
)
Vapi
(PG
)
Ran
asan
Suge
n
81
117
33 8962
171
90
64 118
2.5
81
43
140
7637
10.2
9
19.8
49
13
6383
774825
95
66
71
47
Recovery Procedure for Western Region-Dec 2013 34
Recovery Procedure for Western Region-Dec 2013 35
LEG
EN
D:
Sta
tion
to s
elf-s
tart
Hyd
ro
Ther
mal
Nuc
lear
Sub
stat
ions
400
KV
220
KV
132
KV
66 K
V
Alte
rnat
e P
ath
(Fig
ure
show
s lin
e le
ngth
in K
m)
(San
khar
i-Shi
vlek
ha-W
elsp
un-A
njar
)
Exh
ibit
- 1/ S
cena
rio 3
Sce
nario
- III
Akr
imot
aA
njar
Vav
Guj
arat
:
Sta
rt up
from
Mad
hya
Pra
desh
.
Ste
p N
o1
23
45
67
Indo
r
eA
soj
Wan
akbo
riR
ansa
nG
andh
inag
arM
ehsa
naP
anen
dro
Kaw
asN
avsa
ri
Kak
rapa
rU
kai(T
)
Mad
hya
Pra
desh
Hal
darv
a
Gan
dhar
80
Tara
pur
Vap
i
Nas
ik
Kar
amsa
dLi
mdi
Jetp
urJa
mna
gar
Sik
ka
Kuk
ma
Had
ala
Bhi
lad
Zaga
dia
289
70
76 140
19.8
63S
oja
185
16 Sal
ejav
a
3571
166
7316
124
27.5
115
9227
7775
6649 13
37 55
3362
22
171
81
5543
74
Recovery Procedure for Western Region-Dec 2013 36
LE
GE
ND
:
Sta
tion to s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
(Fig
ure
sh
ow
s lin
e le
ng
th in
Km
)
(Sa
nkh
ari-S
hiv
lekh
a-W
els
pun
-Anja
r)
Exh
ibit
- 1
/ S
cena
rio 4
Sce
na
rio -
IV
Akr
imo
taA
nja
r
Va
v
Guja
rat
:
Sta
rt u
p f
rom
N
ort
hern
Reg
ion
.
Ste
p N
o1
23
45
67
Bh
inm
al
Aso
jW
ana
kbori
Ra
nsa
nG
and
hin
agar
Meh
sana
Pa
ne
nd
ro
Ka
wa
sN
avs
ari
Ka
kra
pa
rU
kai(T
)
NR
.
Ha
ldarv
a
Ga
nd
har
80
Ta
rap
ur
Va
pi
Na
sik
Kara
msa
dL
imdi
Jetp
ur
Jam
nag
ar
Sik
ka
Ku
kma
Ha
dala
Bh
ilad
Za
ga
dia
Ka
nsa
riS
oja
Ka
nkr
oli143
234
70
76
140
19.8
63
So
ja
185
16
Sa
leja
va
35
71
166
73
16
124
27.5
115
92
27
77
75
66
49 13
37
55
33
62
22
171
81
55
43
74
Recovery Procedure for Western Region-Dec 2013 37
CHAPTER – 5
RESTORATION PROCEDURES
FOR
MADHYA PRADESH
In case of total black out in Madhya Pradesh system, the following possible scenarios are
recommended for system restoration in the state based on black start facilities available in the
state and sources from outside the state. Enclosed Exhibits show the schematic diagrams for
scenarios and restoration plans based on island approach.
5.0 SCENARIOS OF RESTORATION
5.1 SCENARIO # 1: FROM OWN BLACK START SOURCES
A. Bargi Hydro power station (2 x 45 MW)
A DG set of 250 KVA is available at Bargi hydro power station. This set can be started and
auxiliaries to one or both sets can be fed thereby both units can be started immediately. Once the
main units are started, start up power to Amarkantak power station can be extended on 132 kV
Bargi-Jabalpur and 220 kV Jabalpur-Amarkantak line. After sufficient generation is available,
power supply to the essential load will be restored. Start up power supply can also be fed from
Bargi HP to Satpura TPS through 132 KV Bargi-Lakhanodone- Seoni-400 kV Seoni-Satpura
feeder.
B. Pench hydro power station (2 x 80 MW)
Start up facility in the form of 250 KVA DG set is available at Pench hydro power station.
Auxiliaries to any one of the two sets can be fed and the main unit can be started immediately.
Once the main unit is started, start up power can be extended to Satpura power station through
132 kV Pench-Seoni-Amarwara- Chindwara-Satpura line up to 132 kV & 220 kV Satpura
substation and then to 220 kV Satpura PH Bus. Generating units at Satpura can be started and
after sufficient generation is available power supply to the essential load can be restored. In this
case considerable voltage and power hunting is expected as experienced earlier. Voltage hunting
is controlled by putting some load at Seoni, Chindwara & Satpura 132 kV substation. Start up
power can also be extended to Khaperkheda / Koradi power stations. In case MP & Maharashtra
grids have to be restored without parallelling, then Pench units can be connected to MP &
Maharashtra through separate buses at Pench by opening bus-coupler.
C. Bansagar-I (Tons) hydro power station (3 x 105MW)
250 kVA DG set is available at Bansagar-I (Tons) hydro power station. No DG sets are available
at 2x15 MW Bansagar-II (Silpara) and 3x20 MW Bansagar-III (Devlone). To start units at
Bansagar-II and Bansagar-III, 220kV Bansagar (Tons)-Rewa D/C, 132kV Rewa-Bansagar-II
D/C and 132kV Rewa-Bansagar- III S/C lines can be taken into service. After starting the DG
Set, auxiliary power to any one of the three units can be fed. Once the unit is started start up
power to Sanjay Gandhi Thermal Power Station can be extended on 220 kV Bansagar- I (Tons)-
Satna line and 220kV Satna-Birsinghpur line. After starting unit at Sanjay Gandhi TPS and
when sufficient generation is available, essential load can be restored. However due to load -
generation balance, voltage hunting was observed and Tons HPS unit got tripped 2-3 times
Recovery Procedure for Western Region-Dec 2013 38
during restoration on 30.07.2002. Proper co-ordination among the power house personnel and
sub station staff is essentially required during such activities to save valuable time and resources.
D. Birsinghpur Hydro power station(1x20 MW)
Unit can be started using 220 Volt batteries and power can be extended to Birsinghpur thermal
station to start one unit with essential auxiliaries required for start up. Other units can be started
after the stabilization of the first unit. However utmost care is required to be taken to connect
only selective loads to ensure stability of small hydro unit of 20 MW size against heavy jerks
coming from starting up of high capacity thermal auxiliaries like boiler feed pump etc.
E. Indirasagar Hydro power station (8x125 MW)
In the condition of system collapse, one unit of Indira Sagar (ISP) can be started immediately
with the help of D G Set of 2x1000 KVA.Then 400 kV Indira Sagar-Indore (80km) one circuit
can be charged and an island can be built up with restoration of some load at 220 kV Indore-
II(Jetpura) 220/132/33 kV S/S.The ISP-Indore-Jetpura is-land had been successfully created
during a black start mock exercise on 22nd
May,2011(annex-IX).Based on the prevailing
condition and stiffness of the island formed around Indira Sagar, start up power can be provided
to Satpura TPS through 400 kV ISP- Satpura line.
F. Gandhisagar Hydro power station (5x23 MW)
110 KVA DG set at Gandhisagar can be used to black start Gandhisagar units and power supply
can be extended to Satpura power station through 132kV Gandhisagar-Garoth-Badod-Ujjain-
Makshi-Shajapur-Shujalpur-Bhopal-Itarsi link up to Itarsi and then 220 kV supply may be
extended through 220 kV Itrasi- Satpura.
G. Omkareswar Hydro power station (8 x 65 MW)
2 x 1010 KVA DG Set is available which can be used to start up the units. Then power can be
extended to Satpura via Omkareswar-Burwaha – Itarsi – Satpura 220 KV link. Essential and
traction loads of Khandwa, Ratlam, Indore etc. also can be restored through the respective 220
KV links depending upon water availability.
H. Bansagar stage –III Hydro Power Station (3x20 MW)
Start-up power in the form of 250 kVA DG set is available. All three units can be started one by
one with help of DG sets immediately and 132 kV supply to Bansagar stage II and IV can be
extended to Rewa 220kV sub-station and then this supply may be extended to Rewa 220 kV
sub-station and then this supply may be extended to Amarkantak Thermal power Station through
220 kV Rewa-Sidhi-Amarkantak.
I) Marhikheda (3x20 MW)
One DG set of 250 KVA is available at Marhikheda.All three units can be started one by one
with help of DG set. Supply to Gwalior area can be extended through 132 kV Marhikheda-
Karera-Gwalior link.Supply to Gwalior and Datia railway traction point can also be extended.
J) Rajghat Hydro Power Station(3x15 MW)
Recovery Procedure for Western Region-Dec 2013 39
Start-up facility in the form of 250 kVA DG set is available .All three machines can be
started with help of DG sets immediately and supply to Pichhore, Bina and Sagar area can be
extended through 132 kV Rajghat-Bina-Sagar link. Supply to Bina and Makronia Railway
traction point can also be extended.
5.2 SCENARIO # 2: FROM CHHATTISGARH
Start up power through 220kV Korba (W) –Kotmikala-Amarkantak line can be availed from
Korba (W). The generating units at Amarkantak would be started. Once the units at Amarkantak
are started, the power can be fed to Birsinghpur on 220kV Amarkantak-Birsinghpur lines.
Alternatively start up power can be availed via 132 kV Dongargharh-Balaghat path or 132 kV
Bango-Manendragarh path. 400 kV Bhilai-Seoni or 400 kV KSTPS-VSTPS path can also be
explored based on the condition and convenience.
5.3 SCENARIO # 3: FROM GUJARAT
Indore can make necessary arrangements to receive the power from Asoj through any one of 400
kV Asoj - Indore D/C. Indore can then extend the power to Satpura PS through 400/220 kV ICT
at Indore and 220 kV line from Indore – Burwaha - Itarsi - Satpura to start the units at Satpura.
Once the units start, power can be extended to other power stations and esseintial loads. This
option can be tried in the least due to involvement of long line sections and associated high
voltage. Start up power can be extended from SSP through SSP- Nagda- Indirasagar line to
Indirasagar power station which can be further extended to Satpura.
5.4 SCENARIO # 4 : FROM MAHARASHTRA
A. Through 220 kV Kalmeshwar -Pandhurna
1. Pandhurna makes necessary arrangements to receive the power from Kalmeshwar and
extends to Satpura.
2. Satpura extends the power to start the units at Satpura power station.
3 Once the units at Satpura are started, depending on the availability, Satpura extends the
power to 220 kV Itarsi on 220 kV Satpura - Itarsi.
4 Itarsi extends the supply to 220 kV Jabalpur on 220 kV Itarsi - Jabalpur line. Jabalpur
makes necessary arrangements to receive the same.
5 Jabalpur extends the supply to Amarkantak on 220 kV Amarkantak - Jabalpur line to start
1 or 2 units at Amarkantak depending on the power availability.
6 Amarkantak after having sufficient quantum of generation, extends supply to SGTPS on
220kV Amarkantak-Birsinghpur.
7 Jabalpur also extends the power supply to Bargi hydel power station. through 220/132 kV
ICT & 132 kV Jabalpur - Bargi line to start the units at Bargi.
B. Through 132 kV Pench-Kanhan D/C
1 Pench makes necessary arrangements to receive the power from Kanhan through 132 kV
Pench - Kanhan D/C to start the units at Pench hydel power station.
Recovery Procedure for Western Region-Dec 2013 40
2 Once the units at Pench are started power can be extended to start the other thermal units.
5.5 SCENARIO # 5 : FROM NORTHERN REGION
A. Through 400 kV HVDC bypass link
Startup power as a first source can be taken through 400 kV HVDC bypass link from Northern
Region. Operating staffs at HVDC Vindhyachal shall initiate actions to extend start up power
from NR to WR after receiving necessary codes from both NRLDC & WRLDC. Western
Region can draw around 200 MW of power from NR after due consent of NRLDC / NLDC as
per the existing arrangement (100 MW for VSTPS and 100 MW for KSTPS). Vindhyachal back
to back station shall request Singrauli to extend start up power from NR through HVDC bypass
link. The start up power will then be extended to KSTPS. Detailed Procedures are enclosed at
Chapter-9.
In case of high voltage problem in charging Vindhyachal-Korba line, loads at Waidhan &
Morwa can be restored using 132kV Vindhyachal-Waidhan D/C. This may require more
assistance from NR. Further power can be extended to Amarkantak for start up through 132 kV
Waidhan-Amarkantak S/C or 132 kv Waidhan-Morwa single circuit. Based on availability of
assistance from NR, start up power from Amarkantak can be extended to Birsinghpur on 220kV
Amarkantak-Birsinghpur line.
B. From Rihand through 132 kV Singrauli - Vindhyachal - Rihand to start VSTPS.
Startup power can be taken from NR through 132 kV lines (Singrauli -Vindhyachal - Rihand).
However the available power on 132 kV would be optimum for Vindhyachal only and power
cannot be catered to Korba NTPC through this route.
C. From 132 KV Anpara – Amarkantak Line
Start-up power can be availed from Anpara TPS of U.P through 132kV Anpara-Morwa-
Amarkantak lines.
D. From 220 KV Auriya- Malanpur and 220 KV Auraiya-Mehgaon
The 220 KV network of MP in this area i.e Auraiya – Malanpur/Mehgaon – Gwalior – Bina –
Damoh – Katni – Birsinghpur and Bina – Bhopal – Itarsi – Satpura etc. can be explored as per
situational requirement.
E. From 132 KV R P Sagar-Gandhi Sagar
The 132 KV RP Sagar-Gandhi-Sagar-Ujjain and Gandhi Sagar-Neemuch-Nagda paths can also
be explored as per situational requirement.
F. From Kota through 220 kV Badod – Kota and Badod-Modak lines
Past experience showed that this link is not useful for availing start up power from NR due to
longer line length and higher voltage level.
Recovery Procedure for Western Region-Dec 2013 41
5.6 MADHYA PRADESH SYSTEM - IDENTIFIED GRID PATH FOR
STARTUP POWER TO POWER STATIONS WHERE STARTUP SOURCE IS
NOT AVAILABLE
SGTPS (Birsinghpur)
Path I - Birsinghpur hydel power station (20 MW) through 220kV inter connector
Path II - Tons hydel project through 220kV Bansagar- Satna-Birsinghpur D/C
Path III - 220kV Amarkantak-Birsinghpur D/C from Amarkantak.
Path IV - 400 kV Indirasagar-Satpura-220 kV Satpura- Itarsi-Jabalpur-
Amarkantak – Birsinghpur D/C
Amarkantak:
Path I - Bango HEP through 132kV Amarkatak- Manendragarh- Bango line (S/C)
Path II - Korba(W) TPS through 220kV Korba (W) –Kotmikala- Amarkantak
D/C.
Path III- Bargi hydel power station through 132kV Bargi-Jabalpur-Amarkantak
lines (D/C)
Path IV- Tons power station through 220kV Bansagar-Satna-Birsinghpur-
Amarkantak S/C
Path V- From Pench HEP through 132kV Pench-Seoni-Lakhnadone-Bargi-
Jabalpur D/C line and 220kV Jabalpur - Amarkantak D/C line.
Path VI- From Satpura TPS through 220kV Satpura-Itarsi-Jabalpur-Amarkantak
D/C
Path VII- Vindhyachal STPS through 132kV Vindhyachal-Waidhan-Morwa-
Amarkantak path.
Path VIII- Anpara TPS of U.P through 132kV Amkantak-Anpara- Morwa lines. One
circuit goes from Waidhan to Amarkantak and other circuit goes to
Morwa.
Path IX- 400 kV Indira Sagar -400kV Satpura- 220kV Satpura -220kV Itarsi-
Jabalpur-Amarkantak
Satpura
Path I - Pench hydel project through 132kV Pench- Seoni-Amarwara-
Chindwara-Satpura line.
Path I I- From Maharashtra via 132kV Kanhan-Pench-Seoni-Amarwara-
Chindwara- Satpura line.
Recovery Procedure for Western Region-Dec 2013 42
Path III- Koradi TPS of Maharashtra through 400kV Koradi- Satpura (S/C) and
220kV Satpura- Kalmeshwar-Ambazari-Koradi
Path IV- From Gandhisagar or Kota to Ujjain through 220kV Ujjain-Burwaha-
Itarsi-Satpura line
Path V- From Gujarat through 400kV Asoj-Indore D/C, 220kV Indore-Burwaha-
Itarsi-Satpura line OR 132kV Gandhisagar-Garoth-Ujjain-Makshi-
Shujalpur- Shajapur-Bhopal-Itarsi-Satpura.
Path VI- 400kV Asoj-Indore-Indirasagar-Satpura
Path VII- From Bargi hydel project through 132 kV Bargi-Lakhanodone-Seoni-
Amarwara-Chhindwara-Sarni feeder.
Path VIII- 400 kv Indirasagar-Satpura-220 kV Satpura
VSTPS*
Path I - 400kV AC by-pass at Vindhyachal HVDC
Path II - 132kV Rihand -Singrauli- Vindhyachal
Path III- From Amarkantak on 132kV Amarkantak- Morwa-Waidhan-Vindhyachal
D/C
Path IV- From KSTPS on 400kV KSTPS-VSTPS D/C
* The above start up sources are in the order of priority. In case VSTPS gets start up power
using paths II & III, it is not possible to extend start up power from VSTPS to KSTPS till some
units are brought up on bars at VSTPS.
Jaypee Bina
Path I - From 400 kV Satpura-Itarsi-Bhopal-Bina-Jaypee Bina
Path II - From 400 kV Birsingpur-220 kV Damoh- Bina-Jaypee Bina
***
Recovery Procedure for Western Region-Dec 2013 43
Exh
ibit
- 2
/ Sce
nario
1
Sce
nario
- I :
Fro
m o
wn
Bla
ck S
tart
Sou
rces
Ban
saga
r T
ons
Sat
na
LEG
EN
D:
Bar
giS
tatio
n T
o S
elf -
Sta
rt
Hyd
ro
The
rmal
Pen
chB
lack
Sta
rt
Seo
niC
hhin
dwar
Sat
pura
Sub
-Sta
tions
400
KV
Gan
dhis
agar
220
KV
132
KV
Alte
rnat
e P
ath
Indi
rasa
gar
Sat
pura
Kor
adi
VS
TP
SK
ST
PS
Kor
ba (
E )
Am
arka
ntak
Ste
p N
o1
23
45
67
Mad
hya
Pra
desh
Birs
ighp
ur (
H)
Jaba
lpur
Kor
ba(
W )
8
Man
endr
agar
h
Birs
ighp
ur (
T)
Ban
go
Mor
wa
Wai
dhan
Kor
adi
Kha
perk
heda
Ujja
inS
hahj
apur
Shu
jalp
urB
hopa
lIta
rsi
Kha
perk
heda
Kot
mik
ala
Lakh
nado
ne
Mak
shi
Am
arw
ara
G'S
agar
Gar
oth
Bad
od
Ujja
in
Om
kare
swar
Bur
wah
aIta
rsi
76
Nar
sing
hpur
18
233
2210
0
158
61
51
215
1016
5
71
74
71
66
154
2718
2
26
101
14
8
65
7936
149
10
2482
8550
1931
77
5176
77.6
3171
190
149
13
188
(Fig
ure
show
s lin
e le
ngth
in K
m)
Recovery Procedure for Western Region-Dec 2013 44
Recovery Procedure for Western Region-Dec 2013 45
LE
GE
ND
:
Sta
tion t
o s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
Exh
ibit
- 2
/S
cen
ari
o 2
Sce
na
rio-
II :
Sta
rt u
p f
rom
Ch
ha
ttis
ga
rh
Ch
ha
ttis
ga
rh
Ste
p N
o1
23
45
67
Ma
dh
ya P
rad
esh
0
Sa
tpu
raC
hh
ind
wa
raS
eo
ni
Don
ge
rga
rh
Bir
sin
gh
pu
r
Am
ark
an
tak
Ko
rba
(W)
Ko
rba
(E)
Ba
ng
o
Ma
ne
nd
rag
arh
Bh
ilai
Ba
lag
ha
t
Pe
nch
KS
TP
SV
ST
PS
Birsi
ngh
pu
r J
aba
lpur
Na
rsin
gh
pu
r I
tars
i S
atp
ura
Ko
tmik
ala
Am
arw
ara
61
15
47
41
36
86
66
657
7
75
23
02
2
71
71
21
5
14
22
10
0
51
8
10
1
(Fig
ure
sh
ow
s lin
e le
ng
th in
Km
)
Recovery Procedure for Western Region-Dec 2013 46
Recovery Procedure for Western Region-Dec 2013 47
LE
GE
ND
:
Sta
tion t
o s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
Exh
ibit
- 2
/S
cen
ari
o 3
Sce
na
rio-
III
: S
tart
up f
rom
Gu
jara
t
Ma
ne
nd
rag
arh
Ko
rba
( w
)
Am
ark
an
tak
Ste
p N
o1
23
45
67
Aso
jIn
do
reB
urw
ah
aIt
ars
iS
atp
ura
Jab
alp
ur
Bir
sin
gp
ur(
T)
Ko
rba
( E
)
Ma
dh
ya P
rad
esh
Pe
nch
KS
TP
S
Gu
jara
tC
hh
ind
wa
ra
0
Se
on
i
SS
PN
ag
da
Ind
ira
sag
ar
Ra
jgarh
Ko
tmik
ala
Ba
rgi
10
41
88
74
15
4
27
65
28
97
7
45
66
17
8
86
Am
arw
ara
19
0
71 1
88
Na
rsin
gh
pu
r1
82
14
10
171
61
(Fig
ure
sh
ow
s lin
e le
ng
th in
Km
)
Recovery Procedure for Western Region-Dec 2013 48
Recovery Procedure for Western Region-Dec 2013 49
LE
GE
ND
:
Sta
tion t
o s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
Exh
ibit
- 2
/ S
cen
ari
o 4
Sce
na
rio-
4 :
Sta
rt u
p f
rom
Ma
ha
rash
tra
Mo
rwa
Wa
idh
an
Pe
nch
VS
TP
SK
ST
PS
Bir
sin
gh
pu
r
Se
on
i
Ba
nsa
ga
r
Ko
rba
( E
)
Am
ark
an
tak
Na
rsin
gh
pu
rJa
ba
lpu
r
Ste
p N
o1
23
45
67
Ka
nh
an
Sa
tpu
ra
Kh
ap
erk
he
da
La
khn
ad
on
e
Ka
lme
shw
ar
Ko
rad
i
Ita
rsi
Ko
rba
( W
) Sa
tna
Ma
ne
nd
rag
arh
8
Ma
ha
rash
tra
Ba
rgi
Ba
ng
o
0
Ch
hin
dw
ara
Am
beja
ri
Ko
tmik
ala
Ma
dh
ya P
rad
esh
36
27
18
2
8 23
3
22
10
1
74
15
4
66
65
77
71
79
61
10
0
51 76
Am
arw
ara
71
16
52
61
0
14
21
5
52 20
43
68
85
13
14
9
Pa
nd
urn
a
LE
GE
ND
:
Sta
tion t
o s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
Exh
ibit
- 2
/ S
cen
ari
o 4
Sce
na
rio-
4 :
Sta
rt u
p f
rom
Ma
ha
rash
tra
Mo
rwa
Wa
idh
an
Pe
nch
VS
TP
SK
ST
PS
Bir
sin
gh
pu
r
Se
on
i
Ba
nsa
ga
r
Ko
rba
( E
)
Am
ark
an
tak
Na
rsin
gh
pu
rJa
ba
lpu
r
Ste
p N
o1
23
45
67
Ka
nh
an
Sa
tpu
ra
Kh
ap
erk
he
da
La
khn
ad
on
e
Ka
lme
shw
ar
Ko
rad
i
Ita
rsi
Ko
rba
( W
) Sa
tna
Ma
ne
nd
rag
arh
8
Ma
ha
rash
tra
Ba
rgi
Ba
ng
o
0
Ch
hin
dw
ara
Am
beja
ri
Ko
tmik
ala
Ma
dh
ya P
rad
esh
36
27
18
2
8 23
3
22
10
1
74
15
4
66
65
77
71
79
61
10
0
51 76
Am
arw
ara
71
16
52
61
0
14
21
5
52 20
43
68
85
13
14
9
Pa
nd
urn
a
(Fig
ure
sh
ow
s lin
e le
ng
th in
Km
)
Recovery Procedure for Western Region-Dec 2013 50
Recovery Procedure for Western Region-Dec 2013 51
215
LE
GE
ND
:
Sta
tion to s
elf-
start
Hyd
ro
Therm
al
Nucl
ear
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rnate
Path
Exh
ibit
- 2
/S
cen
ari
o 5
Sce
nario-
V :
Sta
rt u
p f
rom
Nort
hern
Reg
ion(N
R)
Ma
dh
ya P
rad
esh
Ste
p N
o1
23
45
67
0
Sin
gra
uli
Rih
an
d
NR
Bu
s a
t
HV
DC
Vin
dh
yach
al
An
pa
raM
orw
aWa
idh
an
Am
ark
an
tak
VS
TP
S
KS
TP
S
NR
Bir
shin
gh
pu
r(T
)
Mala
npur
G
walio
r B
ina D
am
oh K
atn
iA
ura
yia
Sa
tpu
raIt
ars
iB
ho
pa
l
Ko
ta
Mo
da
k
Ba
do
dU
jjain
Ind
ore
Ind
ira
Sa
ga
r
3
71
14
86
1
71
24
6
13
5
16
5
44
10
98
19
915
18
07
81
88
37
85
38
11
5
11
7
15
8
26
Sa
ga
r
(Fig
ure
show
s lin
e le
ngth
in K
m)
21
5
Recovery Procedure for Western Region-Dec 2013 52
CHAPTER – 6
RESTORATION PROCEDURES
FOR
CHHATTISGARH
In case of total Black out in Chhattisgarh system, the following possible scenarios are
recommended for system restoration based on black start facilities available in the state and
availing start up power from outside the state. Enclosed Exhibits show the schematic diagrams
for scenarios and restoration plans based on island approach.
Black start facilities are available at Hydro stations at Hasdeo Bango (250 kVA DG Set) and
Korba(E) phase-I. The scenarios include importing of start up power from the neighbouring
states or neighbouring regions. In case of total Black out in Chhattisgarh the following modes of
system activation are recommended to be taken up for early restoration of the state system.
6.1 SCENARIO # 1 : FROM OWN BLACK START SOURCES
A. Hasdeo Bango hydro power station (3 x 40 MW)
250 kVA DG set is available at Hasdeo Bango hydro power station. After starting the set,
auxiliary power to any one of the three units can be fed. The start-up power to Korba (E) shall
be extended through 132 kV Hasdeo Bango- Korba (E) line and to Korba (W) through 220 kV
Korba(E)-Korba(W) lines. After starting of Korba (E) unit (s) and picking up sufficient
generation, start up power to Korba (W) generating station and essential loads including start up
power to BALCO (BCCP) units can be extended.
B. Korba(E) stage-I
1500 kVA DG set is reported to be available at the retired power station of Korba(E) stage –I.
This can be used as an alternative if the above mentioned option (6.1 (A)) fails. After starting of
DG set, the power can be extended to Bango units through 6 MVA 3.3/132kV transformer.
Regular trial runs are reported to be carried out on the DG set.
6.2 SCENARIO # 2 : FROM MADHYA PRADESH
A. Through 220kV Amarkantak-Kotmikala-Korba(W) D/C.
Power can be availed from Amarkantak through 220kV Amarkantak-Kotmikala-Korba (W) line
to start the units at Korba(W) and also extends the same to Korba (E) and KSTPS. In spite of
difficulties like high voltage problem, the path can be utilized as an important option during
recovery stage.
6.3 SCENARIO # 3 : FROM EASTERN REGION
A. Through 220 kV Budhipadar-Korba(E) D/C or 220 kV Budhipadar-Raigarh S/C
Korba(E) will make the necessary arrangements to receive the power from Orissa through
220kV Tarkera-Budhipadar-Korba(E) path or from IB-TPS through 220kV IB-Budhipadar-
Recovery Procedure for Western Region-Dec 2013 53
Korba(E) lines or from Vedanta TPS through 220kV Vedanta-Budhipadar-Korba(E) lines in
case ER survives. Start up power can be extended from Budhipadar to Korba(E) on one of the
220kV Budhipadar-Korba(E) D/C lines and Budhipadar-Raigarh-Korba(E) S/C with resuming
some load at Raigarh along the path if voltages are high. Once the units at Korba(E) start
generating power, the start up power can be extended to Korba(W), KSTPS, Sipat and
BCPP(Balco). Reasonable loads should be connected at Raigarh before extending power from
Korba(E) to Korba(W) to avoid over voltage condition.
B. Through 400kV Rourkela-Raigarh D/C
When ER grid is surviving and voltage at 400kV Rourkela is within permissible limit, power
can be availed from Rourkela to Raigarh through 400 kV link and then to Raipur -Bhilai-
KSTPS or through 220 KV Raigarh-Korba (E) – Korba (W) route or 220 kV Raigarh –
Budhipadar – Korba (E) – Korba (W) route or 400 KV Raipur –Pathadi – KSTPS route. Before
this operation, suitable loads should be connected at Raigarh, Raipur, Urla, Bhilai & Bhatapara
by charging 220kV lines to bring Raipur voltage to safe limits and provide enough anchoring.
During this course, survival power to Sipat, KSTPS, and other IPPs in that area like
JPL(Tamnar), Pathadi, NSPCL etc. can be catered depending upon the quantum of power
available. 400 kV Ranchi – Sipat lines can also be used in similar manner as per the condition of
availability of power and voltage condition at Ranchi end.
6.4 SCENARIO # 4 : FROM NORTHERN REGION THROUGH VINDHYACHAL
HVDC (when MP grid is also under partial/total blackout)
Korba(E) and Korba(W) will avail power from KSTPS (out of NR assistance as indicated in
para 9.2.1 of Chapter 9.
6.5 SCENARIO # 5 : START UP POWER FROM SOUTHERN REGION
A. Through AC Bypass link at Bhadravati HVDC Back-to-back
WRLDC shall arrange for 100 MW start up power from SR on HVDC bypass link at
Bhadravati. 70 MW start up power can be extended to Chandrapur power station of Maharashtra
and 30 MW to Bhilai on 400kV Bhilai-Bhadravati line. Both 400/220kV ICTs at Bhilai will be
charged from 400kV side and 220kV bus charged. 220kV Bhilai would extend power to
Korba(E) and then it can be further extended from Korba(E) to Korba(W). In case of high
voltage problem in charging 400kV Bhilai-Bhadravati, power can be taken on 400kV
Bhadravati-Raipur-Bhilai path taking 80 MVAR bus reactor at Raipur into service.
B. Through HVDC Barsoor - L.Sileru link
There are 220kV D/C lines between Barsoor and LowerSileru (AP) through which minimum 50
MW can be availed in black start condition. However, assistance from AP on this line can only
be availed after availability of AC supply at Barsoor end from other sources. This path can be
used to feed loads connected to Barsoor, but it would be difficult to extend startup power further
to any power stations of Chhatisgarh. Further, this HVDC link is not operational and this path
has not ben tried.
Recovery Procedure for Western Region-Dec 2013 54
6.6 CONCLUSION:
Priority No.1: Startup power from Bango hydel plant and extending same to Korba(E) on
132kV path and to Korba(W) on 220kV path from Korba(E).
Priority No.2: Startup power from Budhipadar through Korba(E)- Budhipadar line and taking
Raigarh loads to control overvoltage conditions.
Priority No.3: Startup power to Korba(W) can be extended from KSTPS after availing power
from VSTPS (power extended from NR). Korba(E) may be extended power after atleast one
210MW unit at Korba(W) comes on bar.
Priority No.4: Power can be availed from Amarkantak through 220 kV Amarkantak-Kotmikala-
Korba West line. Korba West receives the power to start the units at Korba West and extend the
same to Korba East.
6.7 CHHATTISGARH SYSTEM - IDENTIFIED GRID PATH FOR START-UP
POWER TO POWER STATIONS WHERE STARTUP SOURCE IS NOT
AVAILABLE
KSTPS
Path I 400kV Vindhyachal-Korba D/C
Path II 132kV Bango-Korba(E)-through 132/220kV ICT at Korba(E) – 220kV
Korba(E)-Korba(W) and then through ICT and 400kV Korba(W)-
Korba(NTPC) S/C
Path III 220kV IB-Budhipadar-Korba(E)-Korba(W) and then through ICT and
400kV Korba(W)-Korba(NTPC)
Korba (E)
Path I From Bango HEP through 132kV Bango-Korba(E) or preferably
through 132kV Bango-Jamnipali-Korba(E).
Path II Korba(W) TPS through 220kV Korba(W)-Korba(E) inter connector
feeders (three circuits)
Path III Amarkantak TPS through 132kV Amarkantak-Manendragarh-Bango-
Korba(E) lines
Path IV 220kV IB-Budhipadar-Korba(E)
Path V 220kV BALCO(BCPP)-Korba(East) D/C
Korba (West)
Path I Hasdeo Bango - Korba(E) to Korba(W)
Recovery Procedure for Western Region-Dec 2013 55
Path II Korba East TPS through 220kV Korba(E)-Korba(W) inter- connector
(three circuits.)
Path III Amarkantak(TPS) through 220kV Amarkantak-Kotmikala-
Korba(W).
Path IV 220kV IB-Budhipadar-Korba(E)-Korba(W)
Path V KSTPS(NTPC) through 400kV KSTPS(NTPC)-Korba(W) line
Lanco(Pathadi):
Path I 400kV Korba(NTPC)-Pathadi S/C
Path II 220kV Budhipadar-Raigarh(Chhattisgarh)-Raigarh(PG)-400 kV
Raigarh-Raipur-Pathadi.
JPL(Tamnar):
Path I 220kV IB-Budhipadar- Raigarh(Chhattisgarh)-JSPCL-JPL(Tamnar).
Path II 400 kV KSTPS-Pathadi-Raipur-JPL(Tamnar)
Path III 400 kV KSTPS-Bhatapara-Raipur-JPL(Tamnar)
NSPCL:
Path I 400 kV KSTPS-Pathadi-Raipur-NSPCL
Path II 400 kV KSTPS-Bhatapara-Raipur-NSPCL
Sipat :
Path I 400 kV Raipur-Sipat
Path II 400 kV Ranchi-Sipat
Path III 765 kV Seoni-Bilaspur-Sipat
ACBIL :
Path I 765kv Sipat-Bilaspur-ACBIL
Path II 765 kV Seoni-Bilaspur-ACBIL
***
Recovery Procedure for Western Region-Dec 2013 56
Recovery Procedure for Western Region-Dec 2013 57
Exhi
bit -
3 /
Scen
ario
1
Stat
ion
to S
elf -
Sta
rt
Scen
ario
- I :
Blac
k St
art S
ourc
es
Hydr
o
Ther
mal
Sub-
Stat
ion
400
KV
220
KV
132
KV
Alte
rnat
e Pa
th
Step
No
12
34
56
7
Chha
ttisg
arh
80
Bang
oKo
rba
( E )
Korb
a(W
)
Amar
kant
ak
Birs
ighp
ur(T
) Satn
a
Bans
agar
Jaba
lpur
Balco
(BCC
P)
Kotm
ikala
(Fig
ure
show
s lin
e le
ngth
in K
m)
51
810
161
71
233
76
3
182
Recovery Procedure for Western Region-Dec 2013 58
Recovery Procedure for Western Region-Dec 2013 59
LEG
EN
D:
Sta
tion
to s
elf-
star
t
Hyd
ro
The
rmal
Nuc
lear
Sub
stat
ions
400
KV
220
KV
132
KV
66 K
V
Alte
rnat
e P
ath
Exh
ibit
- 3
/ Sce
nario
2
Sce
nario
- II
: S
tart
up
from
MP
Kor
ba (
E )
Am
arka
ntak
Ste
p N
o1
23
45
67
Chh
attis
garh
Kor
ba(
W )
Man
endr
agar
h
8
Mad
hya
Pra
desh
Ban
go
KS
TP
S
0
Kot
mik
ala 10
161
14
8
51
2210
0
(Fig
ure
show
s lin
e le
ngth
in K
m)
Recovery Procedure for Western Region-Dec 2013 60
Recovery Procedure for Western Region-Dec 2013 61
LE
GE
ND
:
Sta
tion to s
elf-
start
Hyd
ro
Therm
al
Nucl
ear
Subst
atio
ns
400 K
V
220 K
V
132 K
V
66 K
V
Alte
rnate
Path
Exh
ibit
- 3
/ S
cen
ari
o 3
Sce
na
rio I
II :
Sta
rtu
p p
ow
er
fro
m E
ast
ern
Reg
ion
Ko
rba
(E)
Ch
ha
ttis
ga
rh
ER
KS
TP
SR
aig
arh
Bu
dh
ipa
da
rK
orb
a(W
)V
ST
PS
Am
ark
an
tak
Bir
sin
gh
pu
r
Mo
rwa
Ta
rke
ra
Ste
p N
o1
23
45
67
0
Ib T
PS
Vedanta
BA
LC
O(B
CC
P)
Rou
rke
laR
aig
arh
Bh
ata
pa
ra
Wa
idh
an
Kotm
ikala
Raip
ur
Mo
pka
Pa
tha
di
Sip
at
Ran
chi
1812
0
10
77
11
08
14
21
51
0
26
61
10
1
16
5
40
5
71 15
8
83
64
10
02
32
12
14
93
9
3
(Fig
ure
show
s lin
e le
ngth
in K
m)
Dom
a
21
7
16
0
Recovery Procedure for Western Region-Dec 2013 62
Recovery Procedure for Western Region-Dec 2013 63
LE
GE
ND
:
Sta
tio
n t
o s
elf-s
tart
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bsta
tio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
Exh
ibit -
3 /
Sce
na
rio
4
Sce
na
rio I
V:
Sta
rtu
p p
ow
er
fro
m N
ort
hern
Reg
ion
Ch
ha
ttis
ga
rh :
Ste
p N
o1
23
45
67
0
Sin
gra
uli
Rih
an
d
NR
Bu
s a
t
HV
DC
Vin
dh
ya
ch
al
An
pa
raM
orw
a
Am
ark
an
tak
VS
TP
S
KS
TP
S
NR
Ko
rba
(W)
Ko
rba
(E)
Wa
idh
an
Ko
tmik
ala
(Fig
ure
sh
ow
s lin
e le
ng
th in
Km
)
10
44
15
8
26
16
5
61
10
1
21
53
8
Recovery Procedure for Western Region-Dec 2013 64
Recovery Procedure for Western Region-Dec 2013 65
LE
GE
ND
:
Sta
tion t
o s
elf-
sta
rt
Hyd
ro
Th
erm
al
Nu
cle
ar
Su
bst
atio
ns
400
KV
220
KV
132
KV
66 K
V
Alte
rna
te P
ath
Exh
ibit
- 3
/ S
cena
rio 5
Sce
na
rio V
: S
tart
up p
ow
er
fro
m S
outh
ern
Reg
ion
Chhattis
garh
:
Ste
p N
o1
23
45
Bh
ad
rava
ti
Ra
ipur
Bh
ilai
Bh
atp
ara
Ko
rba
(W)
KS
TP
S
Ko
rba
(E)
SR
Ba
ng
o
Mo
pka
Ba
raso
or
L'S
ileru
(AP
)
(Fig
ure
sh
ow
s lin
e le
ng
th in
Km
)
16
64
8
14
83
10
0
23
21
33
3
32
2
Do
ma
51
Gu
nu
r6
518
5
Recovery Procedure for Western Region-Dec 2013 66
CHAPTER – 7
RESTORATION PROCEDURES
FOR
MAHARASHTRA
7.1 INTRODUCTION
In case of total Black out in Maharashtra power system, the following possible scenarios are
recommended for system restoration and restoration of the supply in the state based on black
start facilities available in the state and sources of power available from outside the state.
Enclosed Exhibits show the schematic diagrams for scenarios and restoration plans based on
island approach. Considering the availability of black start facility available with TATA
POWER independent simultaneous action need to be taken for utilising the facilities with TATA
POWER and restoration of TATA POWER system (which is enclosed at Annexure- VII). These
procedures are meant for the case of failure of the TPC islanding.
7.2 SCENARIOS
7.2.1 SCENARIO #1 : FROM OWN BLACK-START FACILITIES
A. From Koyna Hydro Power Station:-[Koyna stage I-(4x65MW) and stage-II
(4x75MW)].
Two house generators of 2 MVA and 310 kW are available at Koyna and KDPH power stations.
One unit at Koyna stage-I & II can be started with the help of the house generator & DG sets
and auxiliaries of all other units at these power stations can be supplied. Once the units are
started, the power can be extended to thermal power stations over the transmission lines. The
step by step procedure along with schematic is described below. The transmission paths for
extending start up power are shown in relevant annexures.
Extension of Power supply using Black Start facility at Koyna Power Station
Following steps may be followed to extend power supply using black start facility at Koyna
power station:
1) To hand trip all 220kV outgoing feeders at Koyna (Pophali) sub-station.
2) To start house generator of 2 MVA capacity at Koyna (Pophali) sun-station.
3) To charge auxiliary bus at Koyna power station, start one unit & charge 220kV Bus.
(This will take around 30-40 minutes).
4) To charge 220kV Pophali-Pedambe one circuit (11.3 km).
5) To charge 220/33kV T/F at Pedambe and release 30MW load of Ratnagiri &
Kharepatan.
6) To extend supply to 220kV New Koyna on 220kV Pedambe-New Koyna (11 km)
line and release local load (@10MW).
7) To take second unit on bar at Koyna Power Station.
8) To extend supply to 220kV Lote(P) by charging 220kV New Koyna-Lote(P) line (44
km) and release 20MW load at 220kV Lote s/s.
9) To charge 400/220kV ICT I (315 MVA) at 220kV New Koyna from LV side &
charge 400kV New Koyna Bus.
Recovery Procedure for Western Region-Dec 2013 67
10) To extend supply to 400kV Koyna Stage-IV S/S. by charging 400kV New Koyna-
StageIV one circuit (14 km). Once the supply is extended to 400kV Stage-IV, 4X250
MW hydro units are available and one of the units can be immediately taken on
condenser mode operation which will be helpful for controlling voltages by
regulating the reactive power requirement.
11) Take one unit at 400kV Koyna Stage-IV on generation mode. The unit can be kept
on minimum (50MW) for about 30-40 minutes and the generation can be increase as
per the requirement.
12) To extend supply to 220kV Dasturi by charging 220kV Lote(P)-Dasturi(29 km) line
and release 20MW load at 220kV Dasturi S/s.
13) To extend supply to 220kV Kandalgaon by charging 220kV Dastruri-Kandalgaon
(44 km) and release load 220kV Kandalgaon as per the requirement.
14) To extend supply to 400kV Dabhol S/S. by charging 400kV New Koyna-Dabhol one
circuit (60 km). This will make available auxiliary supply for RGPPL Generation and
any one of the unit (GT) can be taken in service within one hour.
15) To extend supply to 400kV Jaigad S/S. by charging 400kV New Koyna-Jaigad one
circuit (57 km). This will make available auxiliary supply for Jaigad Power Station.
16) To charge 220kV Koyna (Pophali)-Kandalgaon Circuit and then extend supply to
220kV Kharghar by charging 220kV Kandalgaon-Top Worth-Kharghar Citcuit
17) To take more units on bar at Koyna (Pophali) and charge 220kV Koyna (Pophali)-
Pedambe second circuit.
18) To extend supply to 220kV Uran s/s. by charging 220kV Kharghar-Uran one citcuit
(28 km). Auxiliary supply will be available to Uran (Gas) Power Station.
19) To extend supply to 220kV Karad S/s. by charging 220kV Koyna (Pophali)-Karad
circuit. Loads can be picked up at 220kV Karad as per the requirement to control the
frequency of the energized network.
20) To extend supply to 220kV Kalwa-I S/S.,by charging 220kV Kharghar-Kalwa line
(25.66km).
21) Extend supply to 400kV Karad by charging 400kV New Koyna-Karad one circuit
(60 km) and take 400/220kV 315 MVA one ICT in service.
22) Further 400kV network with single circuit shall be built in Nagothane, Karad,
Lonikand, Kalwa & Padghe substations.
The island so formed, can be controlled using hydro generation of Koyna I & II
@600MW and Koyna Stage-IV @ 560MW (considering two units taken on generation
mode and two units are taken on condenser mode). Based on the availability of units at
Uran, Dabhol & Jaigad Power stations, network shall be further expanded on 220kV &
400kV level which will make the island more strong and stable.
Recovery Procedure for Western Region-Dec 2013 68
LEGEND:
Transformer:
Generating
station:
400 kV line:
220 kV line:
Stage-IV
Dabhol
Tambati
New Koyna(220kV)
Finolex
ONGC(Panvel)
Kalwa
Colrchem
Padghe
Jindal
Washala
RAYMOND
Nasik
Apta
Kophali(Taloja)
OCIL
Kharghar
HOC
Uran
KhandelgaonDasturi
Lote(P)
IPCL
SPCL
Nagothane
Mahad
KHPTN
KOYNA-3(Pedambe)
New Koyna(400kV)
(4x65MW+4x75 MW) Koyna-1&2
(Pophali)
Karad
220kV
Restoration of Network using Black start facility at Koyna Power
Karad
Ghatghar
Jaigad
Temghar
MalharpathKDPH
Nivlift
PawasONI
(4x80 MW)
(4 x 60MW + 4x108MW +2x120MW)
44
29
72
30
12
16
(60)
26
136
16
25
29
60.3
4523
75
40
13.36.4
37
93
0.7
160
83
59.4
26
11
(14) (72) (120)
11
25
5
79
60
37
29
56
2.8
44
9
67
113
43
4.528
23
88
85
11
66
Recovery Procedure for Western Region-Dec 2013 69
7.2.2 SCENARIO #2 : FROM GUJARAT
In case of total black out, SLDC Kalwa will contact WRLDC for providing assistance for
auxiliary supply to generating units at Nasik power stations from Navsari on 220 kV Navsari -
Nasik lines. WRLDC will arrange the same by contacting SLDC, Gujarat. Auxiliary supply to
generating units at Tarapur will be availed by TAPS in consultation with WRLDC/LD Jambua
on 220 kV Bhilad – Tarapur / Vapi-Tarapur lines. In order to start the generating units at Nasik,
Tarapur, Uran and Trombay (TPC), about 100 MW power is needed to meet the auxiliary power
requirement.
A) Following actions are to be taken from Tarapur end :
1. It is essential to extend survival/start up power to Tarapur within half an hour of loss of off-
site power supply.The start up path is identified as 220kV Kawas-Navsari-Bhilad-Tarapur. In
case of total power failure at Tarapur (failure of islanding), charging of 220kV Kawas-
Navsari
one circuit should get precedence over 220kV Kawas- Ichhapur S/C line. Start up power has
to
be further extended to TAPS(3& 4) through 220 kV interlink.
2. In case of problems with on-site power sources at Tarapur, it is extremely imperative to
supply survival power to Tarapur to enable controlled and safe shut down of reactors. About
1 MW power is required for this purpose and high priority has to be accorded in supplying
the survival power.
3. Gujarat should ensure the communication healthiness (PLCC) for Kawas- Ichhapur S/C and
Kawas-Navsari D/C lines at Ichhapur,Navsari and Kawas ends.
4. If Maharashtra/Gujarat require start up power, TAPS shall extend start up power.
5. It is also required to keep facilities available at 220kV Boisar substation to connect with
Dahanu in readiness for use under emergency conditions such as for start up power extension
to Tarapur from Dahanu or vice-versa.
6. After availing supply from Navsari, Tarapur would extend about 10 MW to Tarapur Atomic
Power Station (TAPS) for starting their units.
7. Start up power shall be extended to TAPS (3&4) power station through 220 kV line between
TAPS(1&2) and TAPS(3&4).
8. The alternative path could be 220 kV TAPS(1&2) - Boisar(Maharashtra) - Boisar(PG)-
TAPS(3&4).
9. Attempts shall be made to avail start up power from Gandhar through 400 kV Gandhar-
Sugen-Vapi-Boisar-TAPs(3&4). For voltage control, radial load shall be taken at Vapi &
Boisar. With TAPS(3&4) auxuliaries fed as indicated in steps 7 & 8 and 400 kV TAPS-(3
&4) charged, TAPS(3&4) can inject power to the grid.
10. Tarapur(1&2) would extend the supply to Borivali on 220 kV Tarapur - Borivali line.
11. Borivali would be advised to make arrangements for getting supply from Tarapur(1&2).
Recovery Procedure for Western Region-Dec 2013 70
12. Borivali would extend the supply towards Kalwa on 220 kV Borivali - Kalwa line.
13. Kalwa would be advised to make arrangements for getting supply from Borivali.
14. Kalwa would extend supply to 100 kV side through 220/100 kV ICTs at Kalwa to extend
supply to SLDC Kalwa.
15. Kalwa would extend supply to Apta and Kandalgaon on 220 kV Kalwa - Apta and 220 kV
Kalwa –Kharghar- Kandalgaon lines.
16. Apta and Kandalgaon would be advised to make arrangements for getting supply from
Kalwa.
17. Kalwa would extend supply to Trombay as second source of supply to TATA POWER on
220 kV Kalwa-Trombay lines.
18. Kalwa would extend supply to Nasik on 220 kV Kalwa-Padghe-Nasik line.
19. Apta would extend about 5 MW to Uran.
20. Uran would be advised to make arrangements to avail supply from Apta on 220 kV Uran –
Apta line and gas turbines units at Uran should be started one after another.
21. Kandelgaon would extend supply to Koyna stage I and II to give auxiliary supply to Koyna
hydro units on 220 kV Kandalgaon – Koyna line. Power of about 5 MW should be extended
to Koyna.
22. Instructions should be given to Koyna stage I & II (Pophali) to make arrangements for
availing supply from Khandelgaon to start hydro units one after another. Start up power
would be extended to 220kV New Koyna over 220kV Pophali-New Koyna S/C and then
extended to Koyna-IV over 400kV New Koyna-Koyna-IV line. For voltage control, one of
the Koyna-IV units can be run in synchronous condenser mode(if required).
23. Kandelgaon would extend supply to Bhira Tail Race(TR) to start the unit.
24. Apta would extend supply to Koyna stage-III (Pedambe) for starting the units, if possible.
25. Instructions would be given to Koyna stage-III to avail supply from Apta on 220 kV Apta –
Pedambe line and units should be started if possible. In case power from Pophali is readily
available, then the same should be availed to start Koyna stage III units.
26. If sufficient generation is available at Uran and Koyna, Apta would extend supply to
Chinchwad on 220 kV Apta - Chinchwad line.
27. Instructions would be given to Chinchwad for availing supply from Apta and essential loads
in Pune city like Hospitals, Railways, Water works etc. may be taken into service.
28. Koyna would be advised to extend supply to Karad on 220 kV Koyna - Karad lines. Karad
would make necessary arrangements for availing the supply.
29. Karad would be advised to extend supply to Kolhapur. In case sufficient generation is
Recovery Procedure for Western Region-Dec 2013 71
available essential loads in Kolhapur city be taken into service.
30. Kolhapur would be advised to extend supply (over 220 kV Kolhapur-Mumbevadi-Halkarni-
Tillari) of about 2 to 3 MW to run Tillari Hydro station, if possible.
31. Karad would be advised to extend supply to Sholapur. In case sufficient generation is
available, essential loads in Sholapur city be taken into service.
B) Following actions are to be taken from Nasik end:
As stated above, WRLDC will arrange supply to Nasik power station via 220 kV Navsari -
Nasik D/C lines by contacting SLDC, Gujarat. The requirement of auxiliary power at Nasik for
one 210 MW unit will be about 20 MW.
1. On getting auxiliary supply from Navsari, units at Nasik would be brought into service. Nasik
would be advised to charge 220/132 kV ICTs at Nasik and extend the supply to Vaitarna
hydro power station.
2. Vaitarna HPS would bring the machine on bar.
3. If sufficient generation at Nasik and Vaitarna is available, then essential loads in Nasik city
should be taken into service.
4. Nasik would be advised to extend supply to Bableshwar on 220 kV Nasik - Bableshwar line.
5. Bableshwar would avail supply from Nasik and 400/220 kV ICT from 220 kV side should be
charged.
6. Padghe would be advised to charge the 400/220 kV ICT at Padghe from 220 kV side and
charge 400 kV Padghe - Bableshwar line from Padghe end.
7. Bableshwar would be asked to synchronise the 400 kV Padghe - Bableshwar line from
Bableshwar end.
8. Bableshwar would extend the supply to Aurangabad. Aurangabad should make arrangements
for getting supply from Bableshwar. If sufficient generation is available, then essential loads
in Aurangabad area should be taken into service.
9. Bableshwar should extend the supply to Chalisgaon. Chalisgaon should make arrangements
for getting supply from Bableshwar. If sufficient generation is available, then essential loads
in Chalisgaon area would be taken into service.
10. Chalisgaon would extend the supply to Bhusawal on 220 kV Chalisgaon - Bhusawal line and
by charging the 220/132 kV ICTs at Bhusawal, an alternate source of auxiliary supply to
Bhusawal could be made available.
7.2.3 SCENARIO # 3(a): FROM M ADHYA PRADESH
In order to start the generating units at Koradi, Khaperkheda, Chandrapur and Parli, WRLDC
will arrange to avail start-up power from Madhya Pradesh (approx. 80MW) to meet the auxiliary
power requirement of these units.
Recovery Procedure for Western Region-Dec 2013 72
1. WRLDC will contact SLDC, Jabalpur for supply of power from 220 kV Satpura station
on 220 kV Pandurna - Kalmeshwar line or 400kV Koradi-Satpura line based on the
system condition.
2. Kalmeshwar would make necessary arrangements for getting supply from Pandurna. On
getting the supply, Kalmeshwar should extend the same to 220 kV Khaperkheda for
auxiliary power to Khaperkheda units. Khaperkheda would then extend the power to
Koradi for starting the units at Koradi.
3. Koradi should be advised to run 1 or 2 units first and subsequently other units would be
taken into service one after another. Power supply can also be extended to 220kV
Ambazari substation either from Koradi or Khaperkheda.
4. Koradi would be advised to charge one 400/220 kV ICT at Koradi from 220 kV side.
5. If Chhattisgarh is in a position to assist by about 300 MW, then avail the power from
400 kV Bhilai substation on 400 kV Bhilai - Koradi line or on 400 kV Bhilai
Bhadrawati- Chandrapur line .
6. Khaperkheda or Koradi would extend supply to Akola and then to 220kV Wardha
substation.
7. Wardha would make necessary arrangements for getting supply from Koradi or
Khaperkheda and extend the same to 220kV Warora. Warora should arrange to extend
the supply to Chandrapur.
8. Chandrapur would extend the supply to Chandrapur thermal power station(TPS) and one
Chandrapur unit should be brought on bar. By utilising this power, the other units could
be brought into service one after another.
9. Chandrapur would charge the 400/220 kV ICT from 220 kV side and arrangements for
charging 400 kV Chandrapur - Parli should be kept ready.
10. Wardha would make arrangements to extend supply to Pusad on 220 kV Wardha - Pusad
line.
11. Pusad would make arrangements for getting supply from Wardha and extend the same to
Parli on 220 kV Pusad - Parli line.
12. Parli would make arrangements for getting supply from Pusad and extend the same to
Parli TPS for running the units at Parli. With the help of this power, other units at Parli
can be brought into service.
13. Parli would be advised to charge the Western Maharashtra system on 220 kV Parli
Osmanabad- Solapur line.
14. Parli would be advised to charge 400/220 kV ICT at Parli from 220 kV side and then
charge one 400 kV Parli - Chandrapur line.
15. Parli would be advised to charge 400 kV Parli –Solapur- Karad line.
Recovery Procedure for Western Region-Dec 2013 73
16. Koradi would be advised to synchronise 400 kV Koradi – Bhusawal line.
17. Bhusawal would be advised to charge 400 kV Bhusawal – Bableshwar line from
Bhusawal end.
18. Koradi would be advised to charge the 400 kV Koradi –Khaperkheda line from Koradi
end.
19. Khaperkheda would be advised to charge 400 kV Khaperkheda-Chandrapur line
followed by synchronization at Chandrapur end.
20. Chandrapur would be advised to extend supply to Lonikhand through 400 kV
Chandrapur- Parli - Lonikhand and subsequently 400kV Karad - Lonikhand line to be
charged achieving full normalcy in the system.
21. If supply is available at Itarsi substation , supply may be extended to Dhule on 400kV
Itarsi-Khandwa-Dhule path and some load can be taken at Dhule after observing the
voltage profile. Then Dhule-Bableshwar-Padghe section may be charged.
22. Then Chandrapur-Padghe HDVC lines can be taken into service.
7.2.4 SCENARIO # 3(b): FROM MADHYA PRADESH
1. SLDC, Jabalpur would take initiative to black start Pench units (2x70 MW). If
simultaneous restoration of Madhya Pradesh & Maharashtra systems is desired, one unit
for each state can be used for extension of start-up power.
2. Charge 132kV Pench-Kanhan one circuit. Charge 220/132kV ICT at Kanhan. Supply
some local load of low pf (lag) to control high-voltage problem.
3. Charge 220kV Kanhan-Khaperkheda and energise auxiliary of one unit at Khaperkheda
(preferably unit capable of hot start).
4. Charge 220kV Khaperkheda-Koradi and energise auxiliaries of one unit at Koradi
(preferably unit capable of hot start and of 120 MW capacity.)
5. After synchronisation of one unit at Koradi and one unit at Khaperkheda, it is advisable
to supply some radial loads at Ambazari.
6. Then steps 6 to 22 from section 7.2.3 are to be followed.
7.2.5 SCENARIO # 4 : FROM SOUTHERN REGION
WRLDC will arrange start up power from Southern Region through SRLDC Bangalore to
Maharashtra system through the two possible routes mentioned bellow:
A. Through 400 kV Ramagundam- Bhadravati(HVDC By pass Link)- Chandrapur
Detailed procedures for using AC bypass at Bhadravati HVDC BTB are available at Bhadravati
HVDC. The minimum auxiliary requirement for Chandrapur TPS is 20 MW for each 210MW
unit and 40MW for each 500MW unit. WRLDC will arrange about 40 to 50 MW power from
Southern Region through 400 kV Ramagundam – Bhadrawati(HVDC by pass link)-Chandrapur
Recovery Procedure for Western Region-Dec 2013 74
path. Once the unit is started at Chandrapur, the rest of the units at Chandrapur and the
neighbouring power stations could be supplied with auxiliary power. In case sufficient power is
available from Southern Region, then about 90/100MW power shall be arranged by WRLDC
from Southern Region and one unit each at Chandrapur, Koradi, Khaperkheda and Parli shall be
provided with auxiliary power simultaneously.
B. Through 220 kV Kolhapur - Chikodi line
In case of non availability of house generator set at Koyna HPS, the minimum power for start-up
may have to be extended from Karnataka. The installed capacity of Tillari and Koyna stage I and
II (Pophali), are 60 MW and 560 MW respectively. Thus considering the auxiliary requirement
of about 0.5%-1% for hydro units, the requirement of auxiliary power for Tillari unit would be
approximately 1 MW and for each stage of Koyna-(I and II), it will be about 1.5 MW.
1. SRLDC would be requested for assistance of about 10 MW power for supplying
auxiliaries of Tillari/Koyna generating units from 220 kV Chikodi substation on 220 kV
Chikodi - Kolhapur line.
2. Kolhapur would be advised to make arrangements for getting supply from Chikodi.
Kolhapur should further extend the same to Karad.
3. Kolhapur would be advised to make arrangements for extending supply to Tillari hydro
station. If possible, Tillari units could be brought into service.
4. Karad would be advised to make arrangements for getting supply from Kolhapur and
extend the same to Koyna Hydro station.
5. With the help of this power 1 or 2 units at Koyna stage I and II should be brought into
service and other units would be brought one after another.
6. Koyna would be advised to extend supply to Pedambe (Koyna stage III) to start Pedambe
machines, if possible. In case it is not possible due to water level problems to start
Pedambe machines, extend supply to Apta. Simultaneously Koyna should be instructed
to extend supply to Khandalgaon on 220kV Koyna-Khandalgaon line. Koyna-stage-IV
units can be taken into service by availing start up power from Koyna-I & II on 220kV
Pophali-New Koyna line and 400kV New Koyna-Koyna-stage-IV line.
7. Khandalgaon would extend the supply to Bhira T.R. to run the unit, if possible. Also
Kandalgaon should extend supply to Trombay via Kharghar-Kalwa-Trombay feeder.
8. Apta would be advised to make arrangements for getting supply from Koyna stage-III.
9. Apta would be advised to extend supply to Uran Gas Station.
10. With the help of this power 1 or 2 units at Uran could be brought into service and other
units would be brought into service one after another.
11. Apta would be advised to extend supply to Kalwa on 220kV Apta- Kalwa line.
12. Kalwa would be advised to make arrangements for getting supply from Apta.
13. Tata(LD) would be advised to avail the supply from Maharashtra Trombay on 220kV
Maharashtra -Tata(1&2)Tie-lines and 220/100kV ICTs.
Recovery Procedure for Western Region-Dec 2013 75
14. If sufficient generation is available with Tata, essential loads of Bombay city like
Hospitals, Railways and Airport would be taken into service.
15. Kalwa would be advised to make arrangements for getting supply form Apta.
16. Kalwa would extend supply to 100kV side through 220/100 kV ICTs at Kalwa to extend
supply to SLDC Kalwa.
17. Kalwa would extend supply to Trombay as second source of supply to TATA POWER
on 220 kV Kalwa-Trombay lines.
18. Kalwa would extend supply to Nasik on 220kV Kalwa-Padghe-Nasik
line.
19. Padghe would extend supply to BMC Water works.
20. Nasik would extend supply to Nasik Thermal Power Station for running 1or2 units at
Nasik. Other units would be run one after another. If sufficient generation is available
essential loads in Nasik city can be taken into service.
21. Kalwa would extend supply to Borivali.
22. Borivali would make available this supply on 100kV side for TPC as third source of
supply.
23. Nasik would extend supply to Bableshwar on 220kV Nasik - Bableshwar line.
24. Bableshwar would avail supply from Nasik and charge 400/220kV ICT from 220kV
side.
25. Kalwa would be advised to charge the 400/220kV ICT at Kalwa from 220kV side and
charge 400kV Kalwa-Padghe line from Kalwa and synchronise at Padghe end.
26. After charging 400kV Padghe-Bableshwar line from Padghe end Bableshwar would be
asked to synchronise from Bableshwar end.
27. Bableshwar would extend supply to Chalisgaon on 220kV Bableshwar- Chalisgaon
line.
28. Chalisgaon would avail supply from Bableshwar and extend the same to Bhusawal.
29. If sufficient generation is available, Karad would be advised to extend the same to
Sholapur.
30. Sholapur would be advised to keep ready 220kV Sholapur-Osmanabad-Parli line for
extending supply to VKM system.
31. Bhusawal would extend supply to Bhusawal Thermal Power Station for running one unit
at Bhusawal. With this power, the other units at Bhusawal may be brought in service.
Recovery Procedure for Western Region-Dec 2013 76
32. Karad would be advised to charge 400/220kV ICT from 220kV side and energise 400 kV
Karad-Sholapur-Parli line from Karad end.
7.3 RESTORATION PROCEDURE FOR TATA POWER SYSTEM
Detailed restoration procedures for Tata Power system is enclosed at Annexure-VII.
Alternative power supply to Tarapur can be given from 100kV Borivali(TATA) substation in
case Tata system is not separated(islanded) or Tata system is already connected to the grid. The
path available is through 100kV Borivali(Tata) to 100kV Borivali (Maharashtra) and then to
220kV Borivali(Maharashtra). From 220kV Borivali to Tarapur through 220kV Borivali-
Tarapur S/C line. This option has the least priority due to the conditions described above.
7.4 MAHARASHTRA SYSTEM - IDENTIFIED GRID PATH FOR START UP
POWER TO GENERATING STATIONS WHERE STARTUP SOURCE IS NOT
AVAILABLE
TAPS(1&2)
Path I - 220kV Kawas-Navasari-Bhilad-TAPS
Path II - 220kV Borivali-TAPS or 220kV Boisar-TAPS
TAPS(3&4)
Path1 - 400 kV Gandhar-Sugen-Vapi-Boisar- TAPS-3&4
Path II - 220kV TAPS(1&2)-Boiser(Maharashtra)-Boiser(PG)-TAPS(3&4).
Path III - 220 kV Tarapur 1&2 – Tarapur 3&4
Koradi
Path I - From Pench through 132kV Pench- Kanhan- Ambazari D/C and
220kV Ambazari-Koradi D/C.
Path II - Paras through 132kV Paras-Akola- Amaravati-Ambazari-Koradi
Path III - Satpura Power Station through 400kV Satpura-Koradi S/C.
Path IV - Khaperkheda Power Station through 220kV Koradi-Khaperkheda
D/C.
Path V - Chandrapur 400kV S/S through 400kV Chandrapur-Khaperkheda-
Koradi S/C.
Path VI - Bhusawal through 400kV Bhusawal- Koradi / Bhusawal-Akola-
Koradi.
Path VII - Chandrapur 220kV S/S through 220kV Chandrapur-Warora-Wardha D/C
and Wardha-Koradi S/C.
Recovery Procedure for Western Region-Dec 2013 77
Path VIII - Korba STPS through 400kV Korba STPS-Bhilai- Koradi -
Khaperkheda .
Chandrapur
Path I - Ramagundam TPS through 400kV Bhadravati-Chandrapur- HVDC
Bypass link and 400kV Bhadravati-Chandrapur Q/C
Path II - Koradi through 220kV Koradi-Wardha- Warora-Chandrapur
Path III - From K'kheda through K'kheda-Ambazari-Wardha-Warora-
Chandrapur.
Path IV - Koradi through 400kV Koradi-Chandrapur path.
Path V - KSTPS through 400kV KSTPS-Bhilai-Bhadravati-Chandrapur path.
Path VI - Parli through 400kV Parli-Chandrapur T/C.
Parli
Path I - Eldari through 132kV Eldari-Jintoor-Parbhani-Parli.
Path II - Nasik through 220kV Nasik-Bableshwar-Ahmednagar and 132kV
Ahmednagar-Khandke-Pathardi-Raimoh -Beed-Parli route.
Path III - From Koradi on 220kV Koradi-Wardha-Pusad-Parli line
Path IV - From Khaperkeda 220kV K'kheda-Ambazari-Wardha-Pusad-Parli
Path V - From Chandrapur on 220kVChandrapur-Warora-Wardha-Pusad-
Parbhani-Parli
Path VI - Koyna through 220kV Koyna-Karad-Sholapur-Parli
Path VII - From Tillari through 220kV Tillari-Kolhapur-Karad-Vita-Sholapur-
Parli
Path VIII - KEB through 220kV Chikodi-Kolhapur-Karad-Vita-Pandharpur-
Sholapur-Parli
Path IX - Chandrapur through 400kV Chandrapur-Parli T/C
Bhusawal
Path I - Paras through 132kV Paras-Malkapur-Bhusawal D/C
Path II - Nasik through 132kV Nasik-Manmad-Chalisgaon-Pachora-Bhusawal D/C
or through 220kV Nasik-Bableshwar-Chalisgaon-Bhusawal
Recovery Procedure for Western Region-Dec 2013 78
Path III - From Nasik on 220kV Nasik-Bableshwar D/C line and 400kV
Bableshwar-Aurangabad-Bhusawal line (or direct line)
Path IV - Koradi through 400kV Koradi- Bhusawal S/C or 400 kV Koradi-Akola-
Bhusawal or 132kV Koradi-Ambazari-Amravati-Akola-Paras-Malkapur-
Bhusawal.
RGPPL(Dabhol)
Path I - 220 kV Koyna-NewKoyna-400 kV New Koyna-RGPPL(Dabhol)
Nasik
Path I - Koyna through 220kV Koyna-Kandalgaon-Kalwa-Padghe-Nasik
Path II - From Uran through 220kV Uran-Apta-Kalwa-Padghe-Nasik.
Path III - Bhusawal through 132kV Bhusawal-Pachora-Chalisgaon-Manmad-
Nasik or through 220kV Bhusawal-Chalisgaon-Bableshwar-Nasik
Path IV - Navsari through 220kV Navsari-Nasik
Path V - Tarapur through Tarapur-Bhilad-Navsari-Nasik
Path VI - Vaitarna through 132kV Vaitarna-Igatpuri-Nasik
Uran
Path I - Koyna through 220 kV Koyna-Apta-Uran
Path II - 220 KV Koyna-Kandalgaon-Kharghar-Uran.
***
Recovery Procedure for Western Region-Dec 2013 79
Recovery Procedure for Western Region-Dec 2013 80
Exh
ibit -
4 /
Sce
na
rio
1
Scenario-
I
Pa
dg
he
Na
sik
LG
EN
D:
Sta
tio
n T
o S
elf -
Sta
rt
Hyd
ro
Th
erm
al
Bla
ck S
tart
Su
b-S
tatio
ns
40
0 K
V
22
0 K
V1
10
or
13
2 K
VA
lte
rna
te P
ath
Tro
mb
ay(
T )
Tro
mb
ay 7
A
N.K
oyn
a
Ko
ya
na
-IV
Kh
an
de
lga
on
Tro
mb
ay(M
SE
B)
Ka
lwa
Ste
p N
o1
23
45
67
Ma
ha
rash
tra
:
S
elf S
tart
8
Ura
n
Bo
riva
liT
ara
pu
r
Sh
ola
pu
rP
arl
i
Pu
sa
dW
ard
ha
Till
ari
Po
nd
a
Pa
rbh
an
i
Giraw
li
Ko
rad
iK
'kh
ed
a
Wa
roo
raC
ha
nd
rap
ur
KD
PH
Ko
yn
a-3
Ap
ta
Ka
rad
Ko
lha
pu
r
Eld
ari
Bh
ira
Dh
ara
vi
Jin
tur
Ya
wa
tma
l
Pu
rti
Sa
lse
tte
Bo
riva
li(T
)A
rre
yV
ers
ova
Gh
od
bu
nd
er
Da
ha
nu
09
Vita
(O
sm
an
ab
ad
)
Kh
arg
ha
r
Ta
mb
ati
Da
bh
ol
Kh
op
oli
Bh
ivp
uri
Gh
atg
ha
r
Bu
tib
ori
Kolh
apur
Mum
bevadi H
alk
arn
i T
illari A
mona P
onda
113
44
357
30
64
82
85
26
25.6
45
56
15.4
96
23
160
136
93
46
56
80
56
262
457
Ko
yn
a-(
1&
2)
0.8
Sh
ola
pu
r(P
G)
299
178
11
24
985
49
37
16
11
152
56
80
151
85
17
45
14
16
62
59
20
14
29
29
52
21
12
11
109
29
51
182
Pa
rbh
an
i
(Fig
ure
show
s lin
e length
in K
m)
Recovery Procedure for Western Region-Dec 2013 81
Recovery Procedure for Western Region-Dec 2013 82
LE
GE
ND
:
Sta
tion to s
elf-
start
Hyd
ro
Therm
al
Nucl
ear
Subst
atio
ns
400 K
V
220 K
V
132 K
V
66 K
V
Alte
rnate
Path
Exh
ibit
- 4 /
Sce
nario 2
Sce
na
rio
- II
Vaita
rna
Ste
p N
o0
12
34
56
Ma
ha
rash
tra
:
Sta
rt u
p f
rom
Guja
rat
7
Navs
ari
Gu
jara
t
89
10
Bhila
d
Vapi
Bois
or(
MS
EB
)
Dahanu
Tro
mbay
Nanded
Pusa
d
Ward
ha
Waro
raP
arli
Beed
Ahm
ednagar
Kaw
as
Padghe
Kandalg
aon
Tara
pur(
1&
2)
Nasi
k
Boriva
liA
pta
Koyn
a-3
Kara
dT
illari
Bhira
K'k
heda
Kora
di
Bhusa
wal
Chalis
gaon
Bab
lesh
war
Ura
n
L'k
hand
Chandra
pur
(To G
oa)
Kalw
aK
olh
apur
11
12
13
Sola
pur
Purt
i
Bois
or(
PG
)
Tara
pur(
3&
4
Vapi
Gandhar
Tam
bhati
Hin
goli
Nasi
k -
Pach
pct
a -
Bhanderd
hara
-Igatp
uri -
Vaita
rna
Mum
beva
di H
alk
arn
i
T
rom
bay
S
onkh
er
N
eru
l K
harg
har
Khandalg
aon
(132 k
V A
hm
ednagar-
Khandke
-Path
ard
i-R
aim
oh-B
eed)
62
89
96
15.4
56
45
66
23
136
160
11
11
299
182
49
178
21
56
26
56
357
149
92
138
137
80
151
182
244
69
285
35
72
24
115
44
Koyn
a-1
&2
Sola
pur(
PG
)
Parb
hani
Parg
aon
Ale
phat
115
Ako
la
35
40
32
80
3
118
64
18
91
21
31
0.7
320
30.4
171
174
Sugen
26
14
22
85
35
38
101
50
113
81
105
52
49
29
10
816
93
(Fig
ure
show
s lin
e le
ngth
in K
m)
Recovery Procedure for Western Region-Dec 2013 83
Recovery Procedure for Western Region-Dec 2013 84
LE
GE
ND
:
Sta
tion to s
elf-s
tart
Hydro
Therm
al
Nucle
ar
Substa
tions
400 K
V
220 K
V
132 K
V
66 K
V
Altern
ate
Path
Exhib
it -
4 /
Scenario
3
Sce
na
rio
- I
II
Pandurn
aS
atp
ura
Ma
ha
rash
tra
Sta
rt u
p f
rom
M.P
.
Ste
p N
o0
12
34
5
Pench
Ma
dh
ya
Pra
de
sh
Kora
di
Malk
apur
Kalm
eshw
ar
Badnera
Akola
Para
sK
'kheda
Kanhan
Bable
sw
ar
Chandra
pur
Am
bazari
Bhusaw
al
Ward
ha
Waro
ra
Pusad
Parli
Kara
d
Butib
ori
67
8
Chalisgaon
Am
ravati
Osm
anabad
Sola
pur
Vita
9
Parb
hani
Purt
i56
220
115
115 4
480
95
21
13
85
149
68
244
156
357
96
26
30
182
Akola
30
85
80
14
56
16
151
44
152
178
299
62
182
46
Giraw
ali
Sola
pur(
PG
)
64
14
52
24
25
26
(Fig
ure
show
s lin
e length
in K
m)
Recovery Procedure for Western Region-Dec 2013 85
Recovery Procedure for Western Region-Dec 2013 86
LE
GE
ND
:
Sta
tion to s
elf-s
tart
Hydro
Therm
al
Nucle
ar
Substa
tions
400 K
V
220 K
V
132 K
V
66 K
V
Altern
ate
Pa
th
Exh
ibit -
4 /
Sce
na
rio
4
Sce
na
rio-
IV
Ste
p N
o1
23
45
67
Ma
ha
rash
tra
: S
tart
up f
rom
Ka
rna
taka
8
Ko
lha
pu
rT
illa
ri
Ka
rad
Ko
yn
a-3
Ka
nd
alg
ao
n
Bh
ira
TR
L'k
ha
nd
Ba
ble
sh
wa
r
Bh
usa
wa
l
Ap
taU
ran B
ori
va
liT
ara
pu
r
Pa
dg
he
Nasik
Ka
lwa
Ko
rad
iS
ho
lap
ur
Ka
rna
taka
Th
rou
gh
22
0 K
V K
olh
ap
ur
-C
hik
od
i D
/C
Cha
lisg
ao
n
Kh
arg
ha
r
Pa
rli
Cha
nd
rap
ur
Chik
od
i
0
Tro
mb
ay
Chin
ch
wa
d
Bh
osa
ri
Pu
sa
dP
arb
hani
Nan
de
d
Wa
rora
Wa
rdh
a
Kh
ap
erk
he
da
91
0
Pa
nd
ha
rpu
r
Osm
an
ab
ad
149
Ya
wa
tma
lH
ing
oli
Am
ba
za
ri
Mum
bevadi
Halk
arn
i
Vita
Ta
mb
atiB-D
yin
g
sahara
Urs
e
Cha
ka
n
(Fig
ure
show
s lin
e length
in K
m)
52
56
160
24728
28
22
30
24
69
35
66
24
21
178
49
150
29
105
Pa
rga
on
Ale
ph
at
15
174
62
56
26
96
30
113
80
115 26
85
138
156
56
120
60
16
182
14
357
30
92
82
137
80
151
56
299
110
10
115
Giraw
ali
Khapark
heda
Sh
ola
pu
r(P
G)
Ko
yn
a-1
&2
11
136
11 9
3 28
Recovery Procedure for Western Region-Dec 2013 87
CHAPTER – 8
RESTORATION PROCEDURE FOR GOA
8.1 Following grid disturbance in Western region, part of Goa connected to Western region
would be affected while part of Goa connected to Southern region would not be affected. As
such, Goa could take more assistance from Karnataka and transfer some of the loads from
WR side to SR side depending upon the size of the assistance.
8.2 Sancole power station would black start their 48 MW GT and feed radial loads. Charge 33kV
Sancole-Verna D/C and restore loads at Verna. Charge 110kV Verna-Ponda D/C and Ponda-
Xeldem S/C. At 110kV Xeldem S/S, supply from Sancole can be paralled with supply from
SR side. This would help in stabilising the area fed by Sancole power station. After
connecting to SR grid, some loads at Xeldem could be restored.
8.3 Since Madgaon is in SR side, power supply to Railways can be ensured.
***
Recovery Procedure for Western Region-Dec 2013 88
CHAPTER – 9
RESTORATION PROCEDURE
FOR
WESTERN REGION
9.1 INTRODUCTION
In case of total blackout in Western region, assistance could be availed from neighbouring
regions in addition to utilising black start facilities within the region. The various possibilities of
availing start up power from outside sources are described below:
9.2 SCENARIOS
9.2.1 SCENARIO #1: From Northern Region(NR)
A. Through 132kV Vindhyachal-Rihand and 132kV Vindhyachal- Singrauli lines
In case of tripping of all the units at VSTPS and tripping of Vindhyachal- Jabalpur Q/C and
Korba-Vindhyachal D/C lines, supply of start up power from Western region to VSTPS would
be difficult as charging of 400kV lines may not be possible. The requirement of start-up power
of VSTPS is approximately 35 MW for starting station auxiliaries and reviving one unit of 210
MW. The requirement for startup for 500 MW unit is 50 MW. This assistance could be availed
through 400kV HVDC bypass or 132kV Vindhyachal-Singrauli-Rihand lines in case of non
availability of 400kV HVDC bypass. VSTPS would make use of 35 MW to provide survival
power for all the units at VSTPS and starting of one unit. Once one unit at VSTPS starts
generating, other units can be started. If power is available, revival of multiple units can be
attempted depending on the available quantum of power. Depending upon the voltage levels and
availability of machines, 400kV lines from VSTPS can be charged to evacuate the generation
from VSTPS with at least two units synchronized at VSTPS and closing of Vindhyachal-
Jabalpur line should then be attempted.
UTILISATION OF AC BY-PASS LINKS
Inter-regional tie points especially strong inter-connections enable import of substantial amount
of power which can be used to provide start-up power to several power plants in the shortest
possible time. Based on the quantum of assistance, power supply to some essential loads could
also be restored. Other advantage over black start facilities would be stable operation of the
restored part since the same would be connected to strong healthy external system. Two such
major options are through bypass AC links at HVDC back to back stations at Vindhyachal &
Bhadravati. The start up power could be availed within 30 minutes. Further, experience of
restoration from these tie points has been highly encouraging. The core approach has been
followed rather than island approach. The operational procedures for closing and opening of
bypass links are discussed in ensuing paragraphs.
I) 400kV Vindhyachal AC by-pass link
a) Closing of A.C. Bypass link.
Recovery Procedure for Western Region-Dec 2013 89
In the event of a total blackout in the Western Region, start up power would be obtained
from the Northern Region on Vindhyachal A.C bypass link. As per the existing arrangement
with Northern Region, Western Region can draw 200 MW power from Northern Region
(100MW for VSTPS and 100MW for KSTPS) on this link consequent to a total blackout. The
quantum of power can be increased subsequently on mutual consent. Since this link connects the
two regions using line isolators only, due care is to be taken before its operation while
connecting or disconnecting the two regions. The schematic diagram depicting the set up of
400kV Vindhyachal A.C bypass link is shown at Exhibit-I. The sequence of operation of this
link is as follows:-
1.1 Vindhyachal back-to-back shall initiate action to extend start up power to VSTPS through
the A.C. bypass link as soon as it receives a request from VSTPS. However, the A.C bypass
link shall be closed after receiving confirmation from either of RLDCs.
1.2 VSTPS shall open breakers AWL2-Q and AWL1-Q and confirm the same to HVDC
Vindhyachal.
1.3 HVDC Vindhyachal shall isolate HVDC Block-I and Block 2 by opening breakers Nos.
BIQ11-Q, BIQ21-Q, B211-Q and B2Q21-Q.
1.4 HVDC Vindhyachal shall open breaker ARI-Q of reactor if it is connected to HVDC Bus I
B.
1.5 HVDC Vindhyachal shall ensure that North Bus IA is in energized condition.
1.6 HVDC Vindhyachal shall bypass interlocking scheme of D11 & D21 isolators of bypass
link.
1.7 HVDC Vindhyachal shall close D21 isolator of bypass link.
1.8 Close D11 isolator manually.
1.9 HVDC Vindhyachal shall intimate VSTPS to draw start up power by one of the HVDC
feeders to bus 1B.
1.10 In case of any problem in opening of VSTPS end breakers of HVDCVSTPS feeders,
VSTPS shall request HVDC to open AWL3Q. This procedure shall be followed only under
exceptional conditions. Breaker AWL3-Q shall be opened by HVDC station after getting
clearance from NRLDC. After opening AWL3Q, HVDC station shall close isolators D21
followed by D11 (manually after bypassing interlock). Close AWL3Q thus charging North
bus 1A and West Bus 1B. Then VSTPS shall be asked to take one feeder on West bus 1B
and draw 100 MW start up power.
1.11 VSTPS shall extend startup power to KSTPS by charging one of the 400kV Vindhyachal-
Korba D/C lines.
b) Opening of bypass link
Once the VSTPS-KSTPS part system of WR connected to NR grid is running with the
synchronization of two generating units ( with one preferably 500 MW set) in KSTPS/VSTPS, it
shall be disconnected from N.R by disconnecting bypass links. Active power flow on the bypass
link should be brought to floating condition to the extent possible before opening. Reactive
Recovery Procedure for Western Region-Dec 2013 90
power import from N.R should also be reduced to bare minimum (by increasing MVAR
generation on KSTPS/VSTPS units) before disconnecting the bypass link. For making the line
floating, generation of KSTPS/VSTPS shall be modulated and if required Vaidhan loads can be
connected on VSTPS.
In case N.R is drawing power on the bypass link from WR, WRLDC shall take the help of
NRLDC for controlling flow on the bypass link alongwith generation reduction on
KSTPS/VSTPS units.
2.1 HVDC Vindhyachal shall obtain permission from NRLDC and WRLDC for disconnection
by opening breaker AWL3Q.
2.2 HVDC station shall open isolator D21 followed by D11.
2.3 HVDC station shall close AWL3Q. The island after separation from N.R shall be
quickly connected to the rest of the W.R grid.
The switching diagram of HVDC back to back substation at Vindhyachal is given below:-.
Recovery Procedure for Western Region-Dec 2013 91
Recovery Procedure for Western Region-Dec 2013 92
II. Other options from NR:
a. Through 132kV R.P.Sagar- Gandhisagar lines.
b. Through 220kV Kota-badod and Modak-Badod lines.
c. Through 132kV Anpara(U.P)-Morwa-Amarkantak lines.
d. Through 400kV Bhinmal-Zerda and 400 kV Kankroli-Zerda lines.
e. Through 400 kV Agra-Gwalior D/C lines.
9.2.2 SCENARIO #2 : From Southern Region( S.R.)
a) Through 400kV AC bypass at HVDC BhadraWati and 400 kV Bhadrawati-Ramagundam
D/C lines.The detailed procedures for using AC bypass at Bhadrawati HVDC Back-to-back
station are available with HVDC Bhadrawati sub-station.
Action shall be initiated at HVDC Bhadrawati after receiving intimation from WRLDC,
SRLDC and NLDC.
After receiving request for start-up power from WRLDC,and concurrence of SRLDC and
NLDC for the same,Bhadrawati shall make the following arrangements.
1) Ensure that the line side breakers of Bhadrawati-Chandrapur-quadruple
circuit (Q/C),Bhadrawati-Raipur T/C,Bhadrawati-Bhilai S/C are open from both ends.
2) HVDC system is to be completely isolated from both west and south bus.
3) All filter isolators are to be kept open.
4) South bus at HVDC Bhadrawati has to be in charged condition.
5) Ensure that all the AC bus isolators are closed.
6) Then AC bypass isolators are to be closed.
7) Then one circuit of Bhadrawati-Chandrapur-Q/C has to be charged after consultation
with WRLDC.This will supply startup power to one of the 210 MW units at
Chandrapur power station.
8) Then start-up power can be extended to other units with gradual connection of loads and
build-up of subsystem around Chandrapur station.
9) After Maharashtra system develops into a stable island A/C inter-connection at Bhadrawati
will be opened after reducing the flow on the inter-connection into a minimum value by
adjusting the load and generation of the island.
The schematic diagram of HVDC Bhadrawati substation is given below:-.
Recovery Procedure for Western Region-Dec 2013 93
Recovery Procedure for Western Region-Dec 2013 94
B) Through 220kV Kolhapur-Chikodi D/C :-
Detailed procedure for availing start-up power by this route has been described in Chapter- 7
(Sec. 7.2.5(B)) .
9.2.3 SCENARIO # 3: From Eastern Region(ER)
a) Through 220kV Budhipadar-Korba(E) and Budhipadar- Raigarh lines.The detailed procedure
is described under Section 6.3.
b) Through 400kV Rourkela-Raigarh D/C lines. The detailed procedure is described under
Section 6.3.
***
Recovery Procedure for Western Region-Dec 2013 95
CHAPTER – 10
TRAINING, DRILLS & EXERCISES
Training:
1. Annual workshops on Restoration Procedures, sharing of experience has to be
continuously conducted to increase awareness among all the players in the regional
power system.
2. To understand the restoration process, usage of black start facilities, load build up,
priorities of load restoration, coordination with other agencies, SLDCs will also have to
conduct necessary training.
3. Training at regional level is required to build up coordination, foster team work and
optimize effectiveness and to ensure efficient communication and data transfer.
4. RLDCs are required to conduct role-play sessions and meetings immediately
following an occurrence to identify constraints as well as for SWOT
(Strength,Weakness,Opportunity,Threat) analysis.
Drills:
1. Drills will enable confidence in the preparedness and expose any deficiencies in the
restoration plans.
2. Drills also help in estimating the time required for restoration.
3. Feedback of the drills shall help in improving the restoration plans.
Routine Mock-Exercises:
1. The objective of routine mock-exercises as mandated in the grid cide is to check black
start facilities available in the system for their readiness to function at the time of need.
2. In case black start facilities are not fully ready, then the expected time by which those
facilities will be available for system has to be estimated and intimated.
3. The expected time taken to bring the facility into operation incase of contingency has to
be noted after every mock-drill.
4. Load to be connected at 132kV sub stations can be estimated so as to evolve restoration
plans.
5. Actual time for extension of start up power to generating units can be verified during the
mock-exercises, in case black start facilities in a particular generating station is not
available.
6. Readiness on the part of HVDC stations to use bypass for extending supplies from other
regions can be checked during the mock-exercises.
Recovery Procedure for Western Region-Dec 2013 96
7. It also helps to check the functioning of relays for islanding schemes at Mumbai, other
nuclear power stations like KAPS/TAPS and other power stations. Availability of UF
relays and other settings in different constituent system are also checked.
8. The availability of inter state and inter regional lines which are not frequently utilized are
also checked during the exercise.
9. Meetings of all constituents have to be conducted routinely to ascertain their
preparedness for black-start and for taking suitable actions as and when required.
***
Recovery Procedure for Western Region-Dec 2013 97
Recovery Procedure for Western Region-Dec 2013 98
ANNEXURES
Recovery Procedure for Western Region-Dec 2013 99
Annexure-I
POWER STATIONS WITH BLACK START FACILITIES
Sl.
No.
Power Station Installed Cap.
(MW)
Unit Type Black Start
Source
Capacity
GUJARAT
1 Ukai (H) 4 x 75 Hydro Diesel 500 kVA
2 Mini Hydro 2 x 2.5 Hydro Diesel 50 KW
3 Kadana 4 x 60 Hydro Diesel 500 KVA
4 Dhuvaran
1 x 107 (68+39)
+ 1 x 112 (72+40)
Gas
Details to
be
furnished
by Gujarat
Details to be
furnished by
Gujarat.
5 GIPCL-I 3 x 32
+ 1 x49
Gas /
Steam
Diesel 141 KW
6
**A.E.Co.
Stn. C
Stn.- D,E,F
and CCPP-
Vatva
StnC:2x30
StnD:120
Stn.E,F(110MW
each)CCPP-
Vatva:100MW
Thermal
(Units-
C,D,E,F)/
Gas(CCPP)
Stn-C
islands
Diesel
Stn.C:15kVA;
Stn.D,E ,F and
CCPP(500 kVA
each)
7 CLPIPL 3x138+1x241 Thermal Natural Gas 3000 kVA
8 Sugen 3x382.5 MW Gas Diesel 2x6MVA
MADHYA PRADESH
9 Gandhisagar 5 x 23 Hydro DG set 100 kVA
10 Birsinghpur 1 x 20 Hydro Battery 220 Volt Battery
11 **Pench 2 x 80 Hydro DG set 250 kVA
12 **Bargi 2 x 45 Hydro DG set 250 kVA
13 Bansagar
Stage-I
3 x 105 Hydro DG set 250 kVA
14 **Indira
Sagar
8x125 Hydro DG set 2x1000 KVA
15 Omkareshwar 8x65 Hydro DG set 2x1010 kVA
16 Bansagar Stage
-III
3x20 Hydro DG set 250 kVA
17 Marhikheda 3x20 Hydro DG set 250 kVA
18 Rajghat 3x15 Hydro DG set 250 kVA
CHHATISGARH
19 **Hasdeo
Bango
3 x 40 Hydro DG Set 250 kVA
20 Korba(E)-
phse-I
Power plant retired but Black start
DG set available and on- load trial
is reported to be carried out
regularly
DG Set 1500
kW(3.3kV)
MAHARASHTRA
21 **Koyna I
& II
4 x 65
4 x 75
Hydro House
generator
2 MVA
22 KDPH 2 x20 Hydro DG set 310 KW
Recovery Procedure for Western Region-Dec 2013 100
23 Eldari 3 x 7.5 Hydro DG set 6 KW
24 **Uran
(Gas)
4 x 60 (GT)
+ 4x108 (GT)+
2x120 WHR
Gas DG set 4 MW
PH1:412kVA
PH2:450kVA
WH:520kVA
Sl.
No.
Power Station Installed Cap.
(MW)
Unit Type Black Start
Source
Capacity
25 RGPPL Block 1:
640MW+Block 2:
663.54MW+Block
3: 663.54MW
Gas Gas
Turbine
(Frame-6)
35 MW (Under
testing): Details
to be provided
by RGPPL.
26 **Ghatghar 2x125 Hydro DG set 1x1250 kVA
27 Khopoli 3x24+2x12 Hydro DC
Governor &
bearing oil
pumps
DC power (self
start)
28 Bhivpuri 3 x 24 +
2 x 1.5 +2x12
Hydro DC
Governor &
bearing
-do-
29 Bhira 6 x 25 Hydro 1 No.of
500 KVA
house
generator
with water
turbine
500 kVA
30 Bhira PSS 1 x 150 Hydro DG set 500 kVA
31 Trombay 1 x 120 Gas Turbine DG Set 2.5 MW
1 x 60 Steam
Turbine
NTPC
32 Kawas 4 x 106
2 x 116
Gas Diesel 2850 KW
33 Gandhar 3 x 144
+ 1x225
Gas Diesel 2975 KW
NCA
34 **SSP(RBPH
& CHPH)
6x200+5*50 Hydro Diesel 2x1000kVA
** Unit successfully undergone black start mock drill during last one year.
Annexure-II
MINIMUM SURVIVAL / AUXILIARY POWER REQUIREMENT
Recovery Procedure for Western Region-Dec 2013 101
Power Station Installed
Capacity
(MW)
Survival
power
Auxiliary
Power
Diesel
Generator
Capacity
Synchronis
-ing
Facility
GUJARAT
Ukai (Hy) 4 x 75 100 KW 250 KW 500 kVA Yes
Ukai LBCH 2 x 2.5 5 KW 20 KW 50 KW Yes
Kadana (Hy) 4 x 60 7 KW 200 / 250
KW
500 kVA Yes
Ukai (Th) 2 x 120
+ 1 x 200
+ 2 x 210
1.447
MW
4.5/ 8MW - Yes
Sikka (Th) 2 x 120 500 KW 12 MW 500 KW Yes
Dhuvaran (Th) 1 x 27
+ 4x63.5
+ 2x140
500 KW 5 MW 500 KW Yes
Gandhinagar 2 x 120
+ 3 x 210
175/350
KW P.U
7.2/10.7
MW P.U
500 kVA
D.G.set
Yes
Utran 3 x 15 - - - -
Wanakbori 7 x 210 0.8 MW 13 MW
P.U
3x400 KW Yes
Panandro(KLTPS) 2 x70+2x75 360 KW 4.5 MW 1280 KW &
500 KW
Yes
KLTPS-4 75 300KW 3.5MW 1200KW No
SLPP Phase-II(U-3&4) 2 x 125 - 12MW 750kVA -
A.E.Co.
Stn. C(Thermal) 2 x 30 250 kVA 9 MW 1x500 kVA Yes
Stn.D,E,F(Thermal) 120+ 2x110 (1x125+3x500)
kVA
Yes
GT(Gas) 3x33 - - 500kVA Yes
CLPIPL 3x138+1x241 1 MW 2 MW 3000 kVA Yes
ESSAR 3x110+1x185 - - - Yes
GIPCL(Gas)
Stage-I 3 x 32+1x49 1.5 MW 2 MW 141 KW Yes
Stage-II 1x104+1x56 1x500 kVA Yes
GSEG 2X52+1X52 600 KW 2.2 MW 2x625 kVA -
APL, Mundra 4x330+3x660 5MW 56MW 6x750 kVA Yes
MADHYA PRADESH
Amarkantak 2x120+1x210 135kW
MW
36 MW 750 kVA Yes
Satpura 5 x 62.5
+ 1x200
+ 3x210
800 KW 85 MW 150 KVA +
2x500
kVA+2x500
KVA
Yes
Birsinghpur 4 x210+
1x500
3900
KW
105MW 2x1000+1X
600 kVA
Yes
Jaypee Bina
1x250
Power Station Installed
Capacity
Surviva
l power
Auxiliary
Power
Diesel
Generator
Synchronis
ing
Recovery Procedure for Western Region-Dec 2013 102
(MW) Capacity Facility
Indira Sagar 8 x 125 - - 2 x 1.0 MVA -
MAHARASHTRA
Koradi 4 x 115 + 1x
200 + 2x210
1.44
MW
80 MW 2 x 312 kVA +
3x376 kVA
Yes
Khaperkheda 4 x 210 147 KW 19 MW 2 x 500 kVA Yes
Chandrapur 4 x 210
+ 3 x 500
312 KW 39.2 MW 2x 500 kVA +
2 X 376 kVA
Yes
Bhusawal 1 x 58 +
2 x 210
500 KW 23 KW 2 x 250 kVA Yes
Parli 2 x 30
+ 3 x 210
536 KW 31.8 MW 1x87 kVA +
2x312 kVA
2X375 kVA
Yes
Nasik 2 x 140
+ 3x210
1200
KW
54.5 MW 1 x 212 kVA
1x250 kVA
2x412 kVA
Yes
Uran 4 x 60 +
4x108 +
2x120
- 500 KW Nil Yes
Koyna I &II 4 x 65 +
4x75
3 KW 1.055 MW 2 MVA
350 Ampere-
hours(AH).
Yes
Koyna III 4 x 80 - 515 KW Battery set Yes
Koyna IV 4 x 250 - - - -
Ghatghar 2x125 - - 1x1250kVA Yes
TATA POWER
Trombay –4 1 x 150 400 KW 8 MW 1x200 KVA
1x500 KVA
Yes
Trombay-5&6 2 x 500 2000
KVA
40 MW 2 x 1500 KVA Yes
Trombay –
7A&7B
1 x 120 +
1 x 60
200
KVA
200 KVA 1 x 2.5 MW Yes
BSES
Dahanu
2x250 1.5 MW 30 MW for
first unit and
40MW for
both units
2x750 kVA Yes
JSW CPP(JSW) TPP 1x300
CHHATTISGARH
Korba(E)-II 4 x 40=160 381.7
kW
4 MW 1x1.5MW(3.3
kV)at PH-I
Manual
Korba(E)-III 2x120=240 50 kW 5.318 MW Manual
Korba(E)-Extn 2x250=500 25MW per
unit
3x750kVA(1-
for each unit
& 1-set kept
as stand-by)
Yes
Power Station Installed
Capacity
Surviva
-l power
Auxiliary
Power
Diesel
Generator
Synchronis
-ing
Recovery Procedure for Western Region-Dec 2013 103
(MW) Capacity Facility
Korba(W) 4 x 210=840 400 kW 4x16 MW 4x 500kVA Auto/manua
l
Hasdeo Bango 3 x 40=120 80 kW 3x500 KVA 250 kVA Manual
N.T.P.C.
Korba STPS 3 x 200
+ 4 x 500
4.94
KW
18 MW p.u
for 200
MW set, 40
MW p.u for
500 MWset
3 x 320kVA
+4x750kVA
Yes
VSTPS-I 6 x 210 15 MW 20 MW/unit 6x500kVA Yes
VSTPS-II 2 x 500
--
40 MW
/unit.
3x1200kVA Yes
VSTPS-III 2x500 -- 40MW/unit. -- Yes
Sipat I 3x660 -- -- Yes
Sipat-II 2x500 -- 40mw/unit -- Yes
Kawas–GT
4 x 106
1.2 MW
1 MW /unit
2700 KW
Yes
Kawas-ST 2 x 116 7 MW /unit
Gandhar –GT 3 x 144.3 1.2 MW 1 MW /unit 2975 KW Yes
Gandhar-ST 224.9 3.2MW 8 MW
N.P.C.
TAPS(1&2) 2 x 160 2 to 3
MW
10 MW/unit 3 x 800
KW(each)
Yes
KAPS(1&2) 2 x 220 5 to 6
MW
14 MW/unit 3 x 2.25
MW(each)
Yes
TAPS(3&4) 2x540 …… ……. 4x2.97
MW(each)
SSP
RBPH and CHPH 6x200+5x50 ------ ------- 2x1000kVA Yes
IPPs
CGPL *3x830 -- Yes
LANCO 2x300 --
JINDAL 4x250 --
*As on 30-11-12
Annexure-III
IMPORTANT SUB-STATIONS PROVIDED WITH SYNCHRONISING FACILITIES
GUJARAT
All 400kV substations and generating stations. In addition to that 220kV Navsari, Gondal,
Ranavav, Jambua, Achhalia, Karamsad, Ranasan, Limbdi and Vav substations also have
synchronizing facilities.
MADHYA PRADESH
Recovery Procedure for Western Region-Dec 2013 104
400kV : Indore, Sarni, Bhopal, Nagda & Bina.
220kV : Amarkantak, Jabalpur, Itarsi, Sarni, , Bansagar, Tons & Birsinghpur
132kV : Amarkantak, Jabalpur, Bargi, Pench, Gandhisagar,Ujjain,Bansagar Hydro stage-(II ),
(III) and (IV).
CHHATTISGARH
400kV : Bhilai, Korba(W)
220kV : Korba(W), Korba(E), Barsoor
132kV : Korba(E)
MAHARASHTRA*
Sub-station Synchronizing facility is available on following feeders Remarks
Koradi All 400kV feeders
On 220kV side of 400/220kV ICT
Ambazari All 220kV feeders Syn. Facility not
tried since long.
Amravati On 132kV Ambazari I & II
On 132kV Paras I & II
Syn. Facility not
in use since long.
Paras On 132kV Amravati I &II
On 132kV Malkapur I & II
Bhusawal I 132kV Bhusawal 2 circuit-I, II & III
132kV Malkapur circuit I & II
132kV Pachora circuit I & II
Bhusawal II All 400kV feeders
220kV Chalisgaon Circuit I & II
Chalisgaon 220kV Bhusawal circuit I & II
220kV Bableshwar single circuit
132kV Manmad circuit I & II
132kV Pachora circuit I & II
Pachora 132kV Chalisgaon circuit I & II
132kV Bhusawal circuit I & II
Chandrapur All 400kV feeders except 400/220kV ICT
220kV Warora circuit I, 220kV B.C & T.B.C
Sub-station Synchronizing facility is available on following feeders Remarks
Parli-I 132kV Parli circuit I & II
132kV Parbhani single circuit
132kV Nanded circuit I & II
Parli-II All 400kV feeders
400/220kV ICT
220kV Pusad
Not in working
condition
Parli-III 220kV Parli-2 circuit II, III & IV
Eldari 132kV Malegaon feedrs
132kV Jintur feeders
Lonikhand All 400kV feeders
400/220kV ICT
Bableshwar All 400kV feeders
400/220kV ICT-1
Recovery Procedure for Western Region-Dec 2013 105
400kV TBC & BC
Nagar 132kV Beed feeder
Koyna I & II 220kV Kandalgaon circuit I & II
Karad 400kV TBC
Solapur-I 132kV Ujjain I & II
110kV Pandharpur I & II
Solapur-II 220kV Karad circuit I & II
220kV Parli circuit I & II
220kV side of ICT I & II
Bhatgar 132kV Vir
132kV Phursungi
Kolhapur-2 220kV Belgaon I & II
Nasik All 220kV feeders
132kV Manmad circuit I & II
Khaperkheda All 220kV feeders by way of synchronising trolley
*Details of synchronizing facilities available at 400
kV Padghe,Nagothane,Kharghar,Kharghar,NewKoyna,
Dabhol,Akola,Chakan,Jaigad and 220 kV
Ghatghar substations are to be furnished by MSETCL.
Powergrid /
NTPC /
NPC/NCA
At all 400kV sub-station (viz., Korba, Vindhyachal,
Sipat. Jabalpur, Bhadravati, Itarsi, Khandwa, Bina,
Gwalior, Wardha, Seoni, Bhatapara, Raigarh, Dehgam,
Raipur, Satna, Jhanor&Sipat.
At 220kV Kawas, Jhanor, KAPP, TAPS,SSP)
IPPs At 400 kV APL-Mundra,Sami,JPL-Tamnar,LANCO-
Pathadi&Jaigad
To be confirmed
by the respective
IPPs/SLDCs
***
Annexure-IV (a)
DETAILS OF TRACTION SUB-STATIONS AND THEIR CONTRACTED MAXIMUM
LOAD IN RESPECT OF CENTRAL/WESTERN RAILWAY.
DC Traction
Sr.No. Name of the traction sub-
station(TSS)/Feeding
point(FP)
Contracted Maximum load
in MVA
TATA Power
1 CST,Mumbai 10
2 Igatpuri 12
Recovery Procedure for Western Region-Dec 2013 106
3 Mahim 22
4 Vikhroli 7
5 Mahalakshmi 14
6 Badlapur 62
7 Cotton green 3
8 Mankhurd 25
9 Sion 25
10 Andheri 11
11 Borivali 16.5
Maharashtra
1 Chorpuri 2
2 Igatpuri 12
3 Thakurli 10
4 Virar 1
5 Ambernath 2
6 Kalwa 11
7 Panvel 3
8 Parsik 10
9 Vasai Road 5
10 Seawood(Dharave) 5
ACTraction
Maharashtra
1. Igatpuri FP N/A
2 Nasik FP N/A
3 Manmad FP N/A
4 Chalisgaon FP N/A
5 Pachora FP N/A
6 Bhusawal FP N/A
7 Lasalgaon 7
8 Pimperlhed 7
9 Malkapur 10
10 Jalamb 10
11 Akola 10
12 Murtizapur 10
13 Wardha 5
Sr.No. Name of the traction sub-
station(TSS)/Feeding
point(FP)
Contracted Maximum load
in MVA
14 Warora 2
15 Hinganghat 5
16 Vivekand Nagar 5
17 Butibori 5
18 Dhamangaon 15
19 Badnera 18
20 Katol 2
21 Kalmeshwar 2
22 Palghar 15
23 Gholvad 10
Recovery Procedure for Western Region-Dec 2013 107
24 Nandurbar 10
25 Nardana 6
26 Dharangaon 6
27 Vasai Road (AC) 9
28 Kanhan 10
29 Bhandra Road 8
30 Amgaon 8
31 Kachawni 8
32 Bhadi 20
33 Wirur 6
34 Panvel 9
35 Kharbo 9
36 Wirur 6
Madhya Pradesh *
1 Hetampur 20
2 Gwalior 24
3 Datia 24
4 Bassi 24
5 Bina 35
6 GulabGanj 20
7 Sukhisewaniyan 22
8 Powerkheda 22.5
9 Obaidullagang 21
10 Harda 17
11 Sehore 9.97
12 Talvadiya 12
13 Khirkiya 10
14 Kala Akhar 13
15 Pandhurna 23
16 Betul 22
17 Ghoradongri 12
18 Multai 14
19 Dongargon 17
20 Burhanpur 15
21 Makronia 20
22 Karhiya Bhandoli 26
23 Bamania 21.97
Sr.No. Name of the traction sub-
station(TSS)/Feeding
point(FP)
Contracted Maximum load
in MVA
24 Ratlam 13.97
25 Nagda 16.97
26 Naikheri 11.97
27 Maksi 10
28 Mohammedkhera 10.97
29 Lalitpur 12
30 Anuppur 22.5
31 Nowrajbad 30.5
32 Mazgaon Phatak 23
33 Suwasra 15
Recovery Procedure for Western Region-Dec 2013 108
*MPAKVNL traction substations have also been included in the above list
(for Madhya Pradesh).
Chhattisgarh
1 Dilmili 6.5
2 Kumhorsodra 6.3
3 Kawaragaon 6.5
4 Gidam 7.7
5 Bhansi 7.0
6 Raigarh 16.0
7 Kharsia 9.00
8 Champa 18.0
9 Korba 12.5
10 Akaltara 12.0
11 Bilaspur 21.5
12 Belghana 12.5
13 Pendra Road 24.0
14 Udalkachar 14.5
15 BSPR 7.5
16 Bhatapara 17.5
17 Raipur (Urkura) 17.0
18 Bhilai 15.0
19 Rajnandgaon 12.5
20 Paniajob 16.0
Gujarat
1 Atul 16
2 Bhestan 18.50
3 Madhi 7.00
4 Navapur 8.00
5 Bharuch 17.00
6 Makarpura 18.98
7 Mehmadabad 10.00
8 Anand 9.50
9 Samlaya 12.00
10 Godhra 15.94
11 Gandhinagar 5.00
12 Dahod 21.00
Annex-IV (b)
Details of Power Supply to Railway Traction - Format
S.No Name
of the traction
substati
on
Source
of supply
Neutral section Kms. 132/25kV
Transformer capacity
Contract
Demand (MVA)
Average
demand (MVA)
Emergency
Min.Req. (MVA)
Rail
way Divi
sion
Connected
Phase (R-Y, Y-B,
B-R)
West/ South
East/ North
Recovery Procedure for Western Region-Dec 2013 109
***
Annex-IV(c)
Recovery Procedure for Western Region-Dec 2013 110
Annex-IV (d)
Grid Supply Arrangements of SEBs to Western Railway TSS(AC SECTION)
To NDLS
LEGEND:
:Transformer
:Traction sub-station(TSS)
:SEB's Grid sub-station
:400kV Transmission line
:220 kV Transmission line
:132 kV Transmission line
:110 kV Transmission line
: 66 kV Transmission line
Source:Traction Distribution Data Book prepared by Energy Management Cell,Railway Board,New Delhi
v
Thuria
Linkheda
MeghNagar
Derol
KhachRoad
Morwani
Chhayapuri
VadodVatva
Kim
Lakhodra
Virar N/S
VadodaraGothaj
Gandhi-Nagar
Khatg
aon
Ahaln
er
Udhna
SuratK
ikakui R
d.
PSO
Chal T
han
Nandurb
ar
Jalg
aon
Amalsad
Karambele
Vangaon
Vasai Rd.
Borivali
Shivpura
Kalisindh
Jabri
Bhopal
Naikheri
Ratadia
Nagda
Dewas Indore
Asoj
To Godhra
Chandrapura
220 kV
Godhra
Samlaya
Dahod
Nagda
Ratlam
Anand
Ode
Maksi
Maksi
Ujjain
Sajapur
Panwari
Asta
Bhopal
From
400 kV Itarsi
Sujalpur132 kV
From Ujjain
Sehore
Mohd. Kheda
Sehore
To Indore
From Ujjain
220kV
MangalyagaonJaspura
Dewas
Ratlam
MeghNagarBamania
Wanakbori(TPS)
Ranasan
Chiloda
Talod
Vatwa
Mehmedabad
Mehmedabad
Thasra
Nadiad
Godhra
Dahod
220 kV Jambuva
Makerpura
Karamsad
Bharuch
Bharuch
AnkaleswarAcchalia
Ukai(H)Ukai(T)Vav
From Asoj(400kV)
From Kakrapar
From Navsari
Karjan
Haldarwa220 kV
66 kV
Madhi Navapur
Singarh
From Ukai(H)
Nandurbar
Nandurbar Nardana
Nardana
Patunga
Dondaicha
SS
P
Kh
an
dw
a
Ba
ble
sw
ar
Bhusawal
Jalgaon
Dharangaon
Dharangaon
From Ukai
66 kV
Surat
Udhna
Bhestan
Valsad
Atul
Vapi
Borivali
Padghe
Bhestan
Atul
NavsariFrom Vav
220kV
TAPS
Dhule
Gholvad
Dahanu Rd.
Palghar Palghar
NallasoparaPadghe
Boisar
To MIDC
Wada
Kamba
Kolshet
100kV
Vasai Rd.(EHV)
110kV MSEB
UG Cable
Vasai Rd
Borivali RS(TATA)
110kV MSEB
UG Cable
Borivali
To Church-Gate
MA
DH
YA
PR
AD
ES
HG
UJA
RA
TM
AH
AR
AS
HT
RA
TA
TA
Recovery Procedure for Western Region-Dec 2013 111
Annexure-V
Power Supply Arrangement for Traction substation connected with Chhatisgarh,Maharashtra-grid system of Nagpur Division:
(South-East Central Railway)
Acronyms:
SP : Sectioning & Paralleling Post
TSS: Traction Substation
GSS: Grid Substation
SS: Sub-sectioning Post
To Nagpur
Source:Traction Distribution Data Book - prepared by Energy Management Cell,Railway Board,New Delhi
Rasmara SP
132/22kV
Raj-Nandangaon
TSS
MUN SP
132/25 kV
PJB TSS
Salekasa
SP
132/25 kV
AmgaonTSS
Gondia SP
132/25 kV
Kachewani
TSS
Tumsar
Road SP
220/25 kV
Bhandara
Road(BRD) TSS
Tharsa SP
132/25 kV
Kanhan
TSS
Itwari SP
To Howrah
132 kV Raj-
Nandangaon
GSS, Chattisgarh
132 kV Bhilai GSS,
Chattisgarh
132 kV Balaghat GSS,
MadhyaPradesh
132kV Dongargarh
GSS,Chattisgarh
132 kV
Amgaon SS
132 kV
Gondia SS
132 kV
Madgal GSS
220/132kV BRD
GSS,Maharashtra
220/132 kV Kanhan
GSS,
Maharashtra
220 kV
Khaparkheda
Bus,Maharashtra
Chattis
garh
Zone
Mahara
shtr
a Z
one
Recovery Procedure for Western Region-Dec 2013 112
List of Bus/Tertiary Reactors:
Sr.No Station Name No of reactor X Capacity(MVAr) Total MVAr
Powergrid
1 Bhachhau 1x63 63
2 Bhadravati 1x50* 50
3 BILASPUR 765kV (L/Rs of Ranchi Line) 1x240 240
4 BILASPUR(765 1x240 240
5 Bina 1x63 63
6 Birsinghpur 1x50 50
7 Damoh 1x63 63
8 Dehgam 1x63+1x125 188
9 Dhule 1x80 80
10 Gwalior 1x50 50
11 Itarasi 3x50 150
12 Jabalpur 1x63 63
13 Jabalpur 2x25 50
14 Khandwa 1x125 125
15 Kolhapur(mah) 1x80 80
16 Kolhapur(PG) 1x50* 50
17 Mahan(ESSAR) 1x80 80
18 Mhapusa 1x50* 50
19 Navsari(GIS) 1x63 63
20 Parli 1X63* 63
21 Pune(PG) 1x63* 63
22 PUNE(PG)(L/Rs of A’bad Lines) 2X50 100
23 PUNE(PG)(L/Rs of PARLI Lines) 2X50 100
24 Raigarh 1x63* 63
25 Raipur 1x80* 80
26 Rajgarh(PG) 1x125 125
27 Satna 1x50 50
28 Satna(765kV) 1x240 240
29 SATNA 765kV (L/Rs of SASAN Line) 1x240 240
30 Seoni (L/Rs of Wardha and Bina Line) 2x50 100
31 Seoni(765 kV) 1x240 240
32 Solapur(PG) 1X63+1x50 113
33 Sujalpur 1X63 63
34 Wardha(PG) 1x50 50
35 Wardha(PG) - L/Rs of Wardha-Raipur Line 2X63 126
36 Wardha(PG) 1x50 50
Total 3664
Gujarat
1 Amreli 1x50@ 50
Recovery Procedure for Western Region-Dec 2013 113
2 Asoj 1x50 50
3 Chorania 1x50 50
4 Hadala 1x50 50
5 Jetpur 1x50 50
6 Kansari 1x50 50
7 Kasor 1x50+1x125 175
8 Mundra(APL) 1x80+1x81 161
9 Sami(APL) 1x50 50
10 Soja 1x50+1x80 130
11 Vadavi 1x50 50
12 Varsana 1x50 50
Total 916
Madhya Pradesh
1 Bhopal 2x25 50
2 Bina 1x50+2X25 100
3 Nagda 2x25+2x50 150
4 Satpura 1x63+2x25 113
Total 413
Maharashtra
1 Bableshwar 2x80 160
2 Bhusawal 1x50 50
3 Dhule 2x50 100
4 Karad 1x80 80
5 Kharghar 1x80 80
6 Koradi 1x50 50
7 Lonikhand 1x50 50
8 Nagothane 1x80 80
9 Padghe 1x80 80
10 Parli 1x50 50
11 Parli 3x30 90
Total 780
NTPC+IPPS
1 Vindhyachal 1x63 63
2 Jhanor 1x50 50
3 Sipat 1x240 240
4 TAMNAR(JPL) 1X125 125
5 GMR-EMCO 1X50 50
Total 528
*As Reported in WR Reactive Power Document 2012
***
Annexure-VI
Recovery Procedure for Western Region-Dec 2013 114
LINE CHARGING GUIDELINES
DURING RESTORATION
1. All the CBs of all the lines, ICTs, Reactors and other equipments has to be opened first
before starting any action.
2. It must be ensured that the line to be charged is free from any fault i.e faulty line shall
not be charged.
3. Before charging, it must be ensured that communication is available between both ends
and all protections are in service and no protection is by-passed.
4. During restoration, lines of lower voltage levels should be given first priority.
5. The line should be charged from the end with higher fault level so that the the voltage
rise will be less in the charging end as well as in the open end. It may be kept in mind that
the new fault level of the station during disturbed condition may be very low compared to
that of the healthy system because of tripping/isolation of generators and lines.
6. If two buses have almost same S.C level (3-phase) and neither is a generating station,
the line should be charged from the bus with lower voltage.
7. In case one bus is completely dead, charging of line should be done from the other end
and the breaker at the dead bus end should be closed after that.
8. At the charging end, ensure that the voltage do not exceed 410kV (as per charging
instructions related to particular line). Following voltage control measures must be
utilized in full.
• Bus reactors are to be taken into service (in case of low fault level condition, the
fall of voltage may be very high)
• Charging end generators must operate at reduced voltage (less than 1 p.u) and in
lagging p.f mode
• In case of high frequency, the same should be controlled first.
• Taking loads into service
7. At the synchronising end, control of standing phase angle (SPA) to less than 20o would
help in minimising jerk or sudden rush of power leading to further emergency. For
reduction of SPA, the following measures are needed to be taken up.
(i) Reduce at those generators which are sensitive to the SPA.
(ii) Shed loads at selected buses.
(iii) Simultaneous backing down of generation and shedding of load.
Recovery Procedure for Western Region-Dec 2013 115
(iv) Increase of generation at the sensitive buses. The recommended practice for
synchronizing lines is always through check synchronization relay which
normally is set for 35o above which breaker closing is not permitted. For most of
the lines, SPA < 35 o would suffice. However, in case of lines inter connecting
two major generating stations (Ex. 400kV Vindhyachal-Korba S/C line) it is
prudent to limit the SPA to around 20 degree. However, for the sake of ready
reference on the SPA control and sensitivity, measures to control SPA upto
20degrees have been provided. The measures such as generation reduction, load
shedding etc., suggested for SPA control need not be exercised for upto 35 degrees.
8. Open end voltage should not exceed the voltage level at which O/V protection operates
(generally 110%) of nominal voltage. The open end voltage could be controlled by
reducing the voltage at the charging end. The end with as lower voltage would be ideal
for charging as this minimises the rise of voltage at the open end.
9. If the open end voltage is too high, line charging VARs would increase and it may be
difficult for the charging end to sustain the voltage increase. Ensure adequate voltage
control measures at the charging end to contain high open end voltage. Keep the
charging end voltage as low as possible. It would be also be advantageous to charge all
the transformers at the charging end (to act as bus reactors).
10. While back charging long 400kV lines, the problem of ferro-resonance may occur.
Hence, adequate measures such as taking bus/tertiary reactors in to service and most
importantly some load on the transformer shall be taken.
11. One end is generating station end.
When charging from generating stations during restoration, following a grid disturbance,
care should be taken to ensure that sufficient generation is available and/or connections
with other stations at the charging end to absorb the (leading VARs) reactive power
without difficulty. Before charging, ensure by addition of load preferably or through
excitation control, that these generators are operating at lagging p.f. In case, the
generators are already operating at leading p.f., defer line charging temporarily. Also
ensure that, the generator EHV bus voltages are kept low around 0.9 per unit or even less
by excitation control to ensure less open end voltage rise. The line should be
synchronized preferably at the generating station end.This would help in
a) Checking the healthiness of the line i.e., if the line holds, it will indicate there is no
fault on the line since the line was in “hold” condition.
b) Control of SPA
c) Control of voltage difference
12. Line Reactor is available at one end.
In case, line reactor is available at only one end, it is preferable
a) to charge the line from the end without reactor and synchronize at the end with
reactor.
Recovery Procedure for Western Region-Dec 2013 116
b) If the line is to be opened, open from the end where line reactor is available.
While charging two islands, it is preferable to charge and synchronise at the generating
stations ends. At least, synchronising end must be a generating station.In addition,
frequency difference should also be checked (0.2 Hz-0.5 Hz.). This would avoid sudden
jerk. Further it is advisable to charge at the end with maximum generation level.
***
Recovery Procedure for Western Region-Dec 2013 117
Annexure-VII
RESTORATION OF TPC SYSTEM AFTER COMPLETE SHUTDOWN.
(Black Start Procedure-Operating Instructions)
A–1.0 General Guidelines :
The guide lines given below should be followed prior to restoration of TPC system
after complete shut down:
1) All the stations should inspect their 220 KV/110 KV switchyards and faulty equipment,
if any, should be isolated.
2) All the stations should clear their HT buses and open LT breakers of the transformers
including those of Reactors/capacitors if they have not tripped. 220 KV Bus section
breakers at Trombay (B.S.III and IV breakers) need not be opened out. Please note that
no isolator is to be opened while “clearing” the bus.
3) All the breakers on that LT bus from which station auxiliary supply is to be resumed
should be opened out.
4) Other LT breakers (ABCBs) should be opened only if the compressed air pressure and
voltage levels of station battery are satisfactory. These breakers should be opened after
establishing station auxiliary supply.
5) Hydro stations should start initially one set for supplying station auxiliaries independent
of source from the system.
6) Thermal stations should be ready to resume auxiliaries as soon as supply is made
available.
7) Receiving stations should be ready to resume supply as soon as the same is made
available.
8) Auto reclosures on all transmission lines are to be made inoperative.
9) All the system operations should be carried out only in consultation with LD.
10) Voltage levels should be closely monitored and controlled after every switching
operation by taking suitable measures like, charging ICTs/ transformers, resumption of
load etc. in consultation with LD.
11) Synchronism should be always checked before taking any line into service during the
process of restoration.
12) Generating stations shall keep LD updated about availability of generation capacity at
every stage. Receiving stations to carry out load resumption in small increment as per
Recovery Procedure for Western Region-Dec 2013 118
feeder priority list in consultation with LD. Updated priority list of feeders should be
readily available with the control room staff at the receiving stations.
13) Hydro generating units will be put on governor control, underfrequency load shedding
schemes (discrete and frequency trend relays) will normally be kept in service at
receiving stations. Receiving stations should closely monitor the frequency variations
after resumption of every feeder during the process of restoration.
14) Test charging of suspected faulty line/ equipment will not be carried out till system
stabilizes and interconnection is established with MSETCL.
15) Trombay units 5, 6 & 8 even if they remain on house load, cannot be brought on line as
dead bus closing facility is not available for these units. Hence, priority must be to
establish supply at 220 KV Trombay bus so that units can be synchronised as early as
possible.
A-2.0 RESTORATION :
The initiation of restoration will depend upon the system condition just after
shutdown. The probable considerations in the order are given below:
A) System restoration from Hydro.
B) MSETCL System has not collapsed and is ready to supply power at any of the 110/220
Kv interconnecting tie points, only auxiliary power, restricted power or total
requirement.
SYSTEM RESTORATION FROM BHIRA OLD POWER HOUSE
A1: Bhira Generating Station:
Case I: At 46.5 HZ, Set no 2 or 5 will go on house load.
At 45.0 HZ, the breakers of 110 KV Bhira-Davdi, Bhira- Khopoli line no 2, 220 KV
Bhira-Dharavi line no.7 & 8 will trip by the operation of 'hydro islanding' scheme. All
25 MW sets in service prior to system shutdown would remain on line in synchronism
with each other on 110 KV bus. 220 KV bus will remain charged through 110/220 KV
ICTs. GT-7 will remain back-charged supplying BPSU auxiliaries. Operation Engineer
at Bhira will confirm that:
1) Set no.2 or 5 has come on house load operation and is supplying station auxiliaries.
2) BPSU 11KV generator breaker has tripped and the unit is being shutdown.
3) All the equipment parameters are within the acceptable limits.
Recovery Procedure for Western Region-Dec 2013 119
4) Governors of all the machines are on speed control mode and the frequency
is within 49.5-50.5 Hz.
5) Voltage Regulators of all the machines are in service and 110 KV bus voltage is
maintained around 85 KV.
Case II: If Bhira has not islanded and has complete station shutdown
Start DG set and restore power supply to Set No. 2/5 auxiliaries & start Set No. 2/5.
Resume auxiliary supply of other sets.
Start other available Sets and synchronise on 110 KV bus.
With this, Bhira station would be ready to extend supply to Khopoli.
A2: Khopoli Generating Station:
LD will inform Khopoli and advice Bhira to charge Bhira-Khopoli line no.2.
Khopoli on observing voltage on the line will take the line in service. Charge DT 5 & 7
and resume auxiliary supply. Start 24MW Unit no 7, 8 and 9. Monitor forebay level.
Khopoli will charge Khopoli-Davdi line, Davdi will take the line in service.
Davdi will charge Bhira -Davdi line, Bhira will check synchronism and take the
line in service.
A3: Bhivpuri Generating Station:
LD will inform Bhivpuri and advice Khopoli to charge Khopoli-Bhivpuri line. Bhivpuri
on observing voltage on the line will take the line in service. Charge Power
Transformer no 1 & 2 and resume auxiliary supply. Start 24MW Unit no 9, 10 and 11.
Start old set no 1 & 4.
1. With this, all the three hydro stations will be in synchronism with each other and
ready to extend auxiliary supply to Trombay and other receiving stations.
2. Khopoli in consultation with LD and after informing Mankhurd and Chembur will
charge 110 KV Khopoli-Mankhurd, 110 KV Khopoli-Chembur line. Khopoli will also
bring all available Units on line and according to available capacity, arrange for
discharge from Lonavla/ Walwhan.
Recovery Procedure for Western Region-Dec 2013 120
3. Bhivpuri will Inform Ambernath and in consultation with LD charge 110 KV Bhivpuri-
Ambernath line 1.
Take UFR and FTR relays in service with following settings.
UFR Settings
Carnac - 48.6 HZ FTR settings
Parel - 48.6 HZ Borivli – 49.9 HZ, 0.1 HZ/Sec
Mahalaxmi - 48.8 HZ Parel – 49.0 HZ, 0.5 HZ/Sec
Dharavi - 48.8 HZ Dharavi – 49.9 HZ, 0.2 HZ/Sec
Chembur - 49.0 HZ Salsette – 49.0 HZ, 0.5 HZ/Sec
Vikhroli - 49.0 HZ Saki – 49.9 HZ, 0.4 HZ/Sec
Salsette - 49.2 HZ
Saki - 49.2 HZ
Borivli - 49.4 HZ
Malad - 49.4 HZ
Versova - 49.4 HZ
A4: Chembur:
Chembur will observe voltage on 110 KV Khopoli-Chembur line, take the line into service
Charge Power transformer no 3, 4 & 5 and restore auxiliary supply. Transmission division
will resume supply to Panvel camp from 110 KV Khopoli-Chembur line. Chembur after
informing Trombay - A will charge 110 KV Trombay-Chembur line 3.
A5: Trombay:
1. Trombay „A‟ will observe voltage on Trombay- Chembur line 3 and take the line into
service charging 110 KV bus. Trombay will charge DT3, DT4, DT5 and DT6 and restore
auxiliary supply. Trombay „A‟ will inform Trombay „B‟ and charge ICT4.
2. Trombay „B‟ will take ICT4 into service charging 220 KV B.S.I, III and V. Trombay „B‟,
„C‟,7 & 8 will charge ST5, ST6, ST7 & ST8 and proceed for resumption of auxiliaries
and Unit start up. Trombay control rooms will consult LD before taking equipments of
higher capacity (1MW and above) in service.
3. Trombay station A operation engineer in consultation with station B control engineer will
charge ICT – 5.
4. Trombay station B control engineer will observe voltage and close 220 KV breaker of
ICT- 5 thus charging 220 KV bus II, IV & VI.
5. Trombay „A‟ in consultation with LD and after informing Carnac, Parel, & Dharavi will
charge, Trombay-Carnac 2, Trombay-Carnac 3, Trombay-Parel 1, &Trombay – Dharavi 1
Recovery Procedure for Western Region-Dec 2013 121
A6: Mankhurd:
1. Observe voltage on 110 KV Khopoli-Mankhurd, take the line into service. Charge
Power transformer no 1 & 2 and restore auxiliary supply.
2. Mankhurd will charge 110 KV Parel-Mankhurd line.
A7: Parel:
1. Observe voltage on 110 KV Parel-Mankhurd line and Trombay – Parel line no 1, take the
lines into service. Charge Power transformer no 2, 4, 5, 6, 7, 8 and 9 and restore auxiliary
supply. Resume load as per priority in consultation with LD.
A8: Carnac :
1. Observe voltage on 110 KV Trombay – Carnac line no 2 & 3 and take the lines into
service. Charge Power transformer no 3, 7 and restore auxiliary supply.
2. Back charge Power transformer no 4 and charge 145 KV GIS. Charge Power Transformer
no 8.
3. Charge 33KV BS II from Transformer no 7 and close 33KV BS I-II breaker. Take both
33KV reactors in service to control voltages if required. Resume load as per priority in
consultation with LD.
A9: Dharavi:
1. Observe voltage on 110 KV Trombay-Dharavi 1 and take it into service thus charging 110
KV bus.
2. Charge distribution transformers DT1, 2, 3, 4, 5, 6, 11 & 12. Also Back Charge ICT 7, 8 &
9 for controlling voltages if required. Resume station auxiliaries and resume load as per
priority in consultation with LD.
3. Dharavi in consultation with LD and after informing Vikhroli will charge, Dharavi-
Vikhroli line
A:10 Vikhroli : 1. Observe voltage on 110 KV Dharavi-Vikhroli line and take it into service charging 110
KV bus.
2. Take transformer 1, 2 & 3 into service. Resume station auxiliaries.
3. Resume BMC feeders and other loads as per priority in consultation with LD.
Recovery Procedure for Western Region-Dec 2013 122
4. Inform Salsette and charge 110 KV Salsette-Vikhroli line.
A:11 Salsette:
.1 Observe voltage on Salsette-Vikhroli line and take it into service charging 110 KV bus.
Resume auxiliary supply.
.2 Back Charge ICTs 1/2/3 and then charge 220 KV GIS bus.
.3 Inform Borivli and charge 220 KV Salsette-Borivli line 1.
.4 Inform BMC, Saki & Kolshet and charge 110 KV Salsette-BMC, Salsette-Saki 3 and
Salsette-Kolshet lines. Resume load as per priority in consultation with LD.
A:12 At Ambernath, Kalyan, Chola:
.1 Ambernath will observe voltage on 110 KV Bhivpuri-Ambernath line1 and take the
line into service charging 110 KV bus. Resume auxiliaries. Inform OFA and charge
110 KV Ambernath-Kalyan line 1. Ask OFA to resume supply.
.2 Kalyan will observe voltage on 110 KV Ambernath-Kalyan line no.1 and take the line
into service charging 110 KV bus. Resume station auxiliaries. Resume Railway load
in consultation with LD. If available Hydro generation at Bhira and Bhivpuri is more
than 200MW then inform Chola and charge 110 KV Chola-Kalyan line 1. Chola will
observe voltage and take the line into service thereby charging the 110 KV bus. Chola
will resume auxiliary supply. Resume load in consultation with LD. Kalyan will inform
LD & Salsette and charge 110 KV Kalyan-Kalwa-Salsette line no. 1 & 2.
.3 Salsette will observe voltage and take Kalyan- Kalwa-Salsette line-1 & 2 into service.
A:13 Saki, Kolshet and BMC:
.1 Observe voltage on 110 KV Salsette-Saki 3, Salsette-Kolshet and Salsette-BMC lines
and take these lines into service at respective stations charging their respective 110 KV
buses.
.2 Resume auxiliaries at Saki, Kolshet & BMC.
.3 Resume pumping load at BMC and other loads as per priority in consultation with LD.
Recovery Procedure for Western Region-Dec 2013 123
A:14 Borivli, Malad and Versova:
.1 Take 220 KV Salsette-Borivli line 1 in service charging 220 KV GIS bus.
.2 Take ICTs 1/2/3 in service charging 110 KV bus.
.3 Charge Power Transformer no 1, 2 , 3 & 7
.4 Resume station auxiliaries. Resume load as per priority in consultation with LD.
.5 Charge 110 KV Borivli-Malad line 1. Charge Malad 110 KV bus and take Power
Transformer no 1/ 2 / 3 in service
.6 Resume auxiliaries at Malad.
.7 Charge 110 KV Malad-Versova line 1 and Power Transformer 1. Resume auxiliary
supply at Versova.
.8 Resume load as per priority in consultation with LD.
.9 Charge 22 KV Industries feeder no. 1 and extend auxiliary supply to MSETCL Borivli
with specific instruction that MSETCL should not parallel the supply with any other
source.
A:15 At Trombay :
.1 After auxiliary supply is extended to Trombay unit- 7A, unit will be brought on line
and further restoration will be done simultaneously from hydro stations and Trombay
gas turbine unit.
.2 Trombay unit 7 operation enginer will synchronise unit 7A on 220 KV bus V by
closing 220KV breaker no. 1.
.3 Trombay unit 7 operation engineer will check synchronism & close unit 7A 220KV
breaker no. 2.
.4 Trombay A will resume load as per priority in consultation with LD.
Recovery Procedure for Western Region-Dec 2013 124
A:16 Transmission lines :
.1 Trombay „A‟ will inform Parel and charge 110 KV Trombay-Parel lines 2 & 4. Parel
will check voltage and take the lines into service.
.2 Trombay „A‟ will inform Chembur and charge 110 KV Trombay-Chembur line no.1/
Transformer no.1.
.3 Chembur will observe voltage and take Trombay- Chembur line no. 1/ transformer 1
into service and extend supply to RCF for essential auxiliaries.
.4 Trombay „A‟ will inform Dharavi and charge 110 KV Trombay- Dharavi line no. 2.
Dharavi will observe voltage and take the line into service.
.5 Trombay „A‟ will inform BARC and charge 110 KV BARC line no. 3 & ask BARC to
take the line into service and restore essential load.
.6 Borivli will charge 110 KV Borivli- Malad line no.2 and Malad- Versova line no.2 and
take them into service.
.7 Bhivpuri will inform Ambernath and charge 110 KV Bhivpuri- Ambernath line 2.
.8 Ambernath will observe voltage and take Bhivpuri- Ambernath line 2 into service.
.9 Ambernath will inform Kalyan and charge 110 KV Ambernath- Kalyan line 2.
.10 Kalyan will observe voltage and take Ambernath- Kalyan 2 into service.
.11 Salsette will inform Dharavi and charge 110 KV Salsette- Dharavi line.
.12 Dharavi on observing voltage will take Salsette- Dharavi line into service.
.13 Salsette will inform Saki and charge 110 KV Salsette- Saki line no. 4.
.14 Saki on observing voltage will take Salsette- Saki line no. 4 into service.
.15 Carnac after informing BEST will charge 110 KV Carnac- Grant Road and Backbay no
1 cable. BEST to resume load in consultation with LD.
.16 Parel will inform Mahalaxmi and charge 110 KV Parel- Mahalaxmi-2 cable.
Recovery Procedure for Western Region-Dec 2013 125
.17 Mahalaxmi will check voltage and take Parel-Mahalaxmi-2 line into service. Charge
transformer 1 & 3. Resume station auxiliaries. Resume load as per priority in
consultation with LD.
.18 Kolshet will inform BMC and charge 110 KV Kolshet- BMC line.
.19 BMC will check voltage and take Kolshet-BMC line into service.
.20 Trombay „C‟ will inform Carnac and charge 220 KV Trombay- Carnac line no. 5.
.21 Carnac will observe voltage on Trombay- Carnac 5 and take the line and ICT- 5 into
service.
.22 Trombay „C‟ will inform Salsette and charge 220 KV Trombay- Salsette line no. 1.
.23 Trombay ‟C‟ will inform Dharavi and charge 220 KV Trombay- Dharavi line no. 5.
.24 Salsette on observing voltage on 220 KV Trombay- Salsette line no. 1 will check
synchronism and take the line into service.
.25 Dharavi on observing voltage of 220 KV Trombay-Dharavi line no.5 will check
synchronism and take the line in service. Take ICT no 7, 8, & 9 in service.
.26 Davdi will inform Lavasa and charge Davdi-Lavasa line no 1 with specific instruction
that Lavasa should not parallel the supply with any other source.
.27 Lavasa to take the line in service and Resume load as per priority in consultation with
LD.
.28 The following 220/ 110 KV lines will be taken into service as per the voltage levels.
220 KV Trombay-Carnac line no. 6/ ICT- 6.
220 KV Trombay-Dharavi line no. 6.
220 KV Trombay-Salsette line no. 2.
220 KV Salsette- Borivli line no. 2
110 KV Parel-Grant Road cable.
110 KV Parel-Mahalaxmi- 1 cable
110 KV Dharavi-Mahalaxmi cable
110 KV Trombay-BARC-4
Recovery Procedure for Western Region-Dec 2013 126
110 KV Trombay-Chembur-2 cable
110 KV Chola-Kalyan line no 2
110 KV Trombay-HPCL-3 & 4 cables
110 KV Mahalaxmi – W. Rly 1 & 2 cables
110 KV Dharavi – W. Rly 1 & 2 cables
110 KV Borivli– W. Rly 1 & 2 cables
110 KV Carnac-Backbay no 2 cable
220 KV Dharavi-Backbay cable
110 KV Carnac- Parel cable
A:17 HYDRO
Bhira:
.1 Bhira will charge 220 KV Bhira-Dharavi line no.7 with 85 KV voltage on 110KV Bus.
Minimum 5 sets are required prior to charging the line.
.2 Dharavi will take the line in service.
.3 Bhira will start BPSU if frequency is stable. BPSU load will be picked up in steps of
10MW keeping watch on frequency. Other Hydro generators will vary load as per
frequency. If required generation can be varied manually.
Note:
1. When Hydro stations and Trombay unit- 7A are operating in parallel, loads at
receiving stations will be restored as per generation availability.
2. Bhira units 1 to 6 and Bhivpuri units 9, 10 & 11 will be kept on “Governor
control” to regulate the islanded TPC system frequency.
3. Khopoli to regulate duct line discharge in consultation with LD.
A:18 TROMBAY .1 Unit no.7 operation engineer will keep “speed load changer” in service as unit would
be supplying isolated system load.
.2 Unit 7 operation engineer will control voltage after every stage by adjusting AVR set
point.
.3 Unit 5, 6, 7B and 8 will be synchronized as and when it is made available.
Note:
.1 Stable load on Trombay Unit 7A should not exceed 100 MW. Unit.7A parameters
(voltage, MW, Mvar and current) should be closely monitored.
Recovery Procedure for Western Region-Dec 2013 127
.2 Unit 7A should be loaded maximum up to 100 MW capacity only. Margin of 25/
40 MW should be kept for frequency regulation.
.3 Receiving stations not to resume load without LD‟s consent as limited power is
available. Any unauthorized load pick up can result in tripping of the unit on under
frequency protection.
.4 After system with Unit 7A is stabilized at reasonable load, Trombay will start CW
pumps and high capacity motors one by one. Accordingly, loads at receiving
stations will have to be relieved to maintain total load on the unit at around 100
MW.
A:19 Interconnection with MSETCL and R-infra:
.1 Synchronisation with MSETCL will be done at Salsette on 220KV Kalwa-Salsette line
if MSETCL system is stable. TPC system will be interconnected with MSETCL system
at remaining tie points, one by one.
.2 TPC-R-infra interconnection will be established only after TPC-MSETCL systems are
interconnected or one of the 500 MW units is on line.
RESTORATION OF TPC SYSTEM FROM MSETCL SYSTEM
In case Bhira, Bhivpuri and Khopoli have total shutdown along with collapse of entire system
and if MSETCL is in a position to assist TPC at least up to 50/60 MW from one of the
interconnecting tie points, LD will proceed as follows:
It must be ensured from MSETCL that the 220 KV voltage is in the range of 200-230 KV and
frequency is between 49.0 and 51.0 Hz.
B-1.0 Restoration of TPC System from MSETCL-Trombay 220 KV Tie Point
1. LD will confirm with Trombay stations „B‟ , „C‟ , 7 & 8 that 220 KV bus is cleared. (220
KV Bus section breakers on main bus III and IV need not be opened.
2. LD will inform Trombay stations „B‟ , „C‟ , 7 & 8 and in consultation with LD(Kalwa)
advise MSETCL-Trombay to give permissive for closing and charging 220 KV Tata-
MSETCL-Trombay tie lines 1 and 2.
3. Trombay Station „B‟ will close 220 KV tie I breaker at MSETCL Trombay end and check
that voltage has appeared. He would confirm that synchronising selector switch is on
Recovery Procedure for Western Region-Dec 2013 128
“Auto” position and then close tie 1 breaker to charge 220 KV bus I, III and V. In a
similar way, he will charge 220 KV bus II, IV and VI from 220 KV tie line 2.
4. LD will inform Trombay Station „A‟ and request MSETCL-Trombay to charge ICTs 2 &
3. He will advise Trombay Station „A‟ to observe voltage and take 110KV group breaker
into service.
5. LD will advise Trombay Station „B‟, „C‟, 7 & 8 to resume essential station auxiliaries upto
1 MW for each unit.
6. Trombay unit 7A operation engineer will synchronize unit 7A on 220 KV bus V by closing
breaker no.1.
7. LD will inform Trombay Station „A‟ and advise Trombay Station „B‟ to charge ICT no 4
and 5. Trombay „A‟ will take the ICTs into service.
8. LD will advise Trombay Station „A‟ to charge 110 KV bus, charge DT 3 and 4 and resume
station auxiliary supply for essential auxiliaries upto 1 MW.
9. LD will inform Parel & Chembur and advise Trombay Station „A‟ to charge 110 KV
Trombay-Parel line no. 1 & Trombay-Chembur line no. 3.
10. Chembur will observe voltage on the line & take the line into service. Charge Power
transformer no 3, 4 & 5 and restore auxiliary supply.
11. LD will inform Khopoli and advise Chembur to charge 110 KV Khopoli-Chembur line.
12. Transmission division will resume supply to Panvel camp from 110 KV Khopoli-Chembur
line.
13. LD will advise Khopoli to observe voltage on 110 KV Khopoli-Chembur line and charge
110 KV bus, resume station auxiliaries, synchronise all sets. Khopoli to regulate duct line
discharge in consultation with LD, monitor forebay level.
14. LD will advise Parel to take the line into service, resume station auxiliaries, and charge 110
KV Parel-Mankhurd line. Parel will charge Mankhurd-Khopoli line after informing
Khopoli.
15. Khopoli to observe voltage on 110 KV Khopoli- Mankhurd line and take the line in
service. Khopoli to charge 110 KV Bhira-Khopoli line no 2 and Khopoli-Davdi line after
informing Bhira & Davdi.
Recovery Procedure for Western Region-Dec 2013 129
16. Bhira will take Bhira-Khopoli line no 2 in service. Davdi will take Khopoli-Davdi line in
service. Davdi to charge 110 KV Bhira- Davdi line line after informing Bhira. Bhira to
charge 110 KV bus, resume station auxiliaries and synchronise all sets. Bhira will extend
auxiliary supply to BPSU by charging ICT 1 & 2.
17. Davdi will inform Lavasa and charge Davdi-Lavasa line no 1 with specific instruction that
Lavasa should not parallel the supply with any other source.
18. LD will inform Bhivpuri and advise Khopoli to charge 110 KV Khopoli-Bhivpuri line.
19. LD will advise Bhivpuri to observe voltage on the line, charge 110 KV bus from Khopoli-
Bhivpuri line, resume station auxiliaries and synchronise all sets.
20. LD will ask Trombay „C‟ to charge 220 KV Trombay-Salsette line no.1.
21. Salsette on observing voltage will take 220 KV Trombay-Salsette line no.1 in service.
22. Salsette will follow steps given in A:11 and extend supply to Borivli, Saki, Kolshet &
BMC.
23. Saki, Kolshet & BMC will resume auxiliaries and will restore supply as per section A:13.
24. Borivli, Malad & Versova will follow steps as per section A:14 to resume auxiliaries and
will restore supply in consultation with LD.
25. LD will advise Trombay Station „A‟ to charge 110 KV Trombay-Dharavi line no. 1 & 2.
26. Dharavi to take Trombay- Dharavi line 1 & 2 into service, resume station auxiliaries and
charge one feeder to Railways and restore 4/5 MW load.
27. LD will inform Vikhroli and ask Dharavi to charge 110 KV Dharavi – Vikhroli line.
Vikhroli will follow steps A:10 to resume auxiliaries and will restore supply in
consultation with LD.
28. LD will inform Parel and advise Trombay Station „A‟ to charge 110 KV Trombay-Parel
lines 2 and 4. He will advise Parel to observe voltage on the lines and take them into
service.
Recovery Procedure for Western Region-Dec 2013 130
29. Parel in consultation with LD and after informing Mahalaxmi will charge 110 KV Parel-
Mahalaxmi line 2. Trombay „A‟ after informing Carnac and in consultation with LD will
charge 110 KV Trombay-Carnac lines 2 & 3. Carnac will then proceed as per section A:8.
Mahalaxmi will take the line into service, resume station auxiliaries and restore supply in
consultation with LD.
30. LD will inform Ambernath and advise Bhivpuri to charge 110 KV Bhivpuri-Ambernath
line no.1 & 2.
31. LD will advise Ambernath to observe voltage on the lines, charge 110 KV bus through
Bhivpuri-Ambernath lines, resume station auxiliaries.
32. LD will inform Kalyan and advise Ambernath to charge 110 KV Ambernath-Kalyan lines
1& 2. He will advise Kalyan to observe voltage on the lines and take them into service.
Ambernath in consultation with LD will ask OFA to resume supply from 110 KV
Ambernath-Kalyan line 1 or 2.
33. LD will advise Kalyan to charge 110 KV Chola-Kalyan lines 1 & 2. Chola will check for
voltage, take the lines into service and restore essential auxiliary supply.
34. Trombay „C‟ will charge 220 KV Trombay-Dharavi line no.5.
35. Dharavi will observe voltage on Trombay-Dharavi line no.5 and take it in service on 220
KV GIS bus and take all the ICTs in service.
36. Bhira will charge 220 KV Bhira-Dharavi line no.7 with 85 KV voltage on 110KV Bus.
Minimum 5 sets are required prior to charging the line.
37. Dharavi will take the line in service.
38. Bhira will start BPSU if frequency is stable. BPSU load will be picked up in steps of
10MW keeping watch on frequency. Other Hydro generators will vary load as per
frequency. If required generation can be varied manually.
39. Dharavi will inform Vikhroli and will charge 110 KV Dharavi-Vikhroli line.
40. Vikhroli on observing voltage will take Dharavi-Vikhroli line in service and restore
auxiliaries.
41. Vikhroli will inform Salsette and charge 110 KV Salsette-Vikhroli line.
Recovery Procedure for Western Region-Dec 2013 131
42. Salsette on observing voltage will take Salsette-Vikhroli line in service.
43. Loads at all stations are to be restored as per availability of TPC‟s generation and
assistance from MSETCL.
44. Trombay 5, 6, 7B and 8 will resume Auxiliaries and proceed for startup activities.
45. LD will inform R-infra Aarey and advise Borivli to charge 220 KV Borivli-Aarey line no
1.
46. R-infra Aarey to extend Auxiliary supply to Dahanu Units and restore load in consultation
with LD.
47. Restore remaining network as per section A:16
C-1.0 Restoring TPC System from MSETCL Kalwa-220 KV Tie Point :
1. LD will inform Salsette and in consultation with LD (Kalwa) request MSETCL Kalwa to
charge 220 KV Kalwa-Salsette line No.3 & 4.
2. Salsette will observe voltage on the lines and take them into service. Salsette will charge
ICT no 1, 2 & 3. Salsette will resume station auxiliaries.
3. LD will confirm from Trombay Station „B‟, „C‟ 7 and 8 that 220 KV bus is cleared. (220
KV Bus section breakers on main bus III and IV need not be opened).
4. LD will inform Trombay `C‟ & advise Salsette to charge 220KV Trombay-Salsette line no
1 & 2.
5. Trombay `C‟ to observe voltage and take the lines in service. Trombay B, C, 7 & 8 to
charge ST 5, 6, 7 & 8 and resume station auxiliaries up to 1MW. Trombay control rooms
to consult LD for starting auxiliaries above 1MW.
6. LD will inform Trombay A and advise Trombay B to charge ICT no 4 and 5. Trombay A
to observe voltage and take the ICTs in service.
Recovery Procedure for Western Region-Dec 2013 132
7. LD will inform Kalyan & Salsette and in consultation with LD (Kalwa), request MSETCL-
Kalwa to charge 110 KV Kalwa-Kalyan, 110 KV Kalwa-Kalyan-Salsette line no 1 & 2
lines.
8. LD will advise Kalyan to observe voltage and take Kalwa-Kalyan & Kalwa-Kalyan-
Salsette line no 2 into service.
9. LD will advise Salsette to observe voltage and take Kalwa-Kalyan-Salsette line no 1 & 2
into service.
10. LD will inform Kalyan to charge 110 KV Chola-Kalyan line no. 1 & 2. Chola will observe
voltage, take the lines into service and resume essential auxiliaries.
11. LD will inform Ambernath and advise Kalyan to charge 110 KV Ambernath-Kalyan line
no 1 & 2.
12. Ambernath to observe voltage and take the lines in service. Charge Power Transformer no
1, 2 & 4. Resume station auxiliaries. Inform OFA to resume supply.
13. LD will inform Bhivpuri and advise Ambernath to charge 110 KV Bhivpuri-Ambernath
line no1 & 2.
14. Bhivpuri to observe voltage and take the lines in service. Charge Power Transformer no 1
& 2. Resume station auxiliaries. Start & Synchronise all the Units. Charge Khopoli-
Bhivpuri line after informing Khopoli.
15. Khopoli will observe voltage on the line, charge 110 KV bus through Khopoli – Bhivpuri
line, Charge Distribution Transformer no 5 & 7. Resume station auxiliaries. Start &
Synchronize all the Units.
16. . Khopoli to charge 110 KV Bhira-Khopoli line no 2 and Khopoli-Davdi line after
informing Bhira & Davdi. Bhira will take Bhira-Khopoli line no 2 in service. Charge 110
KV bus, resume station auxiliaries and synchronise all sets. Bhira will extend auxiliary
supply to BPSU by charging ICT 1.
17. Davdi will take Khopoli-Davdi line in service. Davdi will inform Lavasa and charge
Davdi-Lavasa line no 1 with specific instruction that Lavasa should not parallel the supply
with any other source.
18. LD will inform Dharavi and advise Salsette to charge 110 KV Salsette-Dharavi line.
Recovery Procedure for Western Region-Dec 2013 133
19. LD will advise Dharavi to observe voltage on the line, charge 110 KV bus through
Salsette-Dharavi line, resume station auxiliary supply.
20. LD will inform Trombay and advise Dharavi to charge 110 KV Trombay-Dharavi line
No.1 and 2.
21. LD will advise Trombay Station „A‟ to observe voltage on the lines, take the lines into
service.
22. Trombay will bring unit 7A on line and synchronise the same on 220 KV bus V by closing
220KV breaker no.1
23. LD will inform Carnac, Parel and ask Trombay „A‟ to charge 110 KV Trombay-Carnac 2
& 3, 110 KV Trombay-Parel 1 2 and 4 lines.
24. Parel on observing voltage will charge 110 KV bus & resume station auxiliaries and after
informing Mahalaxmi will charge 110 KV Parel-Mahalaxmi line 2. Parel will charge
Railway feeders in consultation with LD. Carnac will then proceed as per Section A:8 and
Mahalaxmi will check voltage and take Parel-Mahalaxmi-2 line into service. Charge
transformer 1 & 3. Resume station auxiliaries. Resume load as per priority in consultation
with LD.
25. LD will inform Khopoli and advise Chembur to charge 110 KV Khopoli-Chembur line.
26. Khopoli to observe voltage on 110 KV Khopoli-Chembur line and take the line in service.
27. LD will advise Parel to charge and take 110 KV Parel-Mankhurd line in service. Parel will
charge Khopoli – Mankhurd line after informing Khopoli.
28. LD will inform BMC, Saki & Kolshet and advise Salsette to charge 110 KV Salsette-
BMC, Salsette-Saki 3 and Salsette-Kolshet lines. Kolshet, Saki, BMC and Borivli, Malad,
Versova R/S will follow steps A:13 to A:14 and Resume load as per priority in
consultation with LD.
29. Trombay „C‟ will charge 220 KV Trombay-Dharavi line no.5.
30. Dharavi will observe voltage on Trombay-Dharavi line no.5 and take it in service on 220
KV GIS bus and take all the ICTs in service.
31. Bhira will charge 220 KV Bhira-Dharavi line no.7 with 85 KV voltage on 110KV Bus.
Minimum 5 sets are required prior to charging the line.
Recovery Procedure for Western Region-Dec 2013 134
32. Dharavi will take the line in service.
33. Bhira will start BPSU if frequency is stable. BPSU load will be picked up in steps of
10MW keeping watch on frequency. Other Hydro generators will vary load as per
frequency. If required generation can be varied manually.
34. Loads at all stations is to be restored as per availability of TPC‟s generation and assistance
from MSETCL.
35. Trombay 5, 6, 7B and 8 will resume Auxiliaries and proceed for startup activities.
36. LD will inform R-infra Aarey and advise Borivli to charge 220 KV Borivli-Aarey line no
1.
37. R-infra Aarey to extend Auxiliary supply to Dahanu Units and restore load in consultation
with LD.
38. Restore remaining network as per section A:16
Loads at all stations will be restored as per availability of TPC’s generation and
assistance from MSETCL.
***
Recovery Procedure for Western Region-Dec 2013 135
Recovery Procedure for Western Region-Dec 2013 136
ANNEX-VIII
(Tables-I to VIII)
MONITORING PERFORMANCE
OF
RESTORATION PLANS
Recovery Procedure for Western Region-Dec 2013 137
Table-I
PERFORMANCE OF ISLANDS IN RESTORATION (Post disturbance analysis)
Sl.
No.
Successful
formation
of
conceived
island
Y/N
(1)
Reasons
for
failure
(2)
Formation of islands not conceived / designed
(3)
Names of
Gen.Stations
in the
islands
220/132kV
load buses
Total
generation
.in the
island
Total load in the
island
Table-I (Contd.)
Sl.
No.
List of
power
station(s)
availed
start up
from this
island
(4)
Start up
path
used
(5)
Any
constraints
in start up
path
*
(6)
Problems
faced by
generators
extending
start up
power
(7)
Time of
synchronization of
this island with other
islands
(8)
Island Time
* Note: Over voltage, phase angle matching (SPA), communication/telemetry, E/S equipment
problems, hunting/oscillations, synchronization problems, protection problems etc.
Recovery Procedure for Western Region-Dec 2013 138
Table-I (Contd.)
Sl. No. Specify
synchronizing
location
(9)
Is
synchronizing
location pre-
specified
Yes / No
(10)
Problems in synchronization
(11)
Remarks
(12)
SPA HV Frequency
matching
Note: One format for each island is required.
Table-II
EXTENDING START UP POWER TO THERMAL PLANTS FROM BLACK STARTED
HYDRO / GAS UNITS
(Restoration plans & post disturbance analysis)
Sl.
No.
Name of
power
station
black
started
Power
station
availing
start up
power.
Description of auxiliaries Ramp &
Response rate of
black started unit
(w.r.to the largest
auxiliary motor)
MW/Min &
MW/Hz.
Essential
for start up
(a)
Non
essential for
start up (b)
Common
station
loads
(c)
Note: 3: Description of Auxiliary
Name of load Quantum (MW) Type of drive Starting current
Amps.
ID Fan IM
FD Fan SM
BFP
Note 4: Largest motor (IM) to be started first with minimum of 2 minutes gap between starting
the next motor
Note:- (1) Auxiliary loads to be listed in descending order of capacity (MW)
(2) Details to be available with both power station.
Recovery Procedure for Western Region-Dec 2013 139
Recovery Procedure for Western Region-Dec 2013 140
Tabl
e-IV
PER
FOR
MA
NC
E O
F BL
AC
K S
TAR
TED
UN
ITS
(Res
tora
tion
plan
s & p
ost d
istur
banc
e ana
lysis
)
Gen
erat
i
ng u
nit
Rem
arks
for
devi
atio
ns/c
onst
rain
ts
Cap
abili
ties t
o isl
and
on h
ouse
load
Act
ual
perf
orm
ance
of is
land
ing
on C
onst
rain
ts/
Rem
arks
-1-5
-6-7
-8
Hot
star
tup
War
m
star
tup
Col
d
star
tup
Hot
star
tup
War
m
star
tup
Col
d
star
tup
Hot
star
tup
War
m
star
tup
Col
d
star
tup
Not
e:
1) A
ll tim
e to
be m
entio
ned
in h
h:m
m
2) C
l.3, C
l.4 an
d Cl
.8 to
be f
illed
up
as p
er b
lack
star
t man
ual f
or th
erm
al g
ener
ator
s
-3-4
Sr.N
o.Ti
me r
equi
red
for
sync
hron
izat
ion
(Hrs
) *
-2
Act
ual t
ime s
tart
up
pow
er
was
ava
ilabl
e (H
rs)
Act
ual t
ime o
f
sync
hron
izat
ion
(Hrs
)
Recovery Procedure for Western Region-Dec 2013 141
Table – V
PLANT LOADING
(Post Disturbance analysis) Load pick up (corresponding to freq change of 0.5Hz) may be reported as under . Momentary
voltage drop, if exceeds 20% should be reported under remarks.
S.No. Plant Rating (MW) Load pick up Remarks **
MW Percentage
** Remarks on the method of assessment to be indicated as under:
1. Design/Manufacture‟s specifications
2. Tested
3. Stability load
4. Estimated
5. No information. Table – VI
Performance of Black start facilities (Post Disturbance Analysis)
Sr
No
Power station Capacity
of D.G
set
(KVA)
Time taken
for black
start
(Minutes)
Time taken for
extending
power to the
next
bus (Min.)
Remarks/ Constraints
1.
2.
3.
4.
5.
6.
7.
8.
9.
10
Recovery Procedure for Western Region-Dec 2013 142
Table-VII
Start up power supply to important power stations (Post disturbance analysis)
Sr
No.
Power
Station
Start up
power
source
Start up
path used
Time at
which start
up power is
available
Is the start
up path pre-
planned
Constraints Remarks
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
Note: Example for restoration following grid disturbance on 30.07.2002 is enclosed.
Recovery Procedure for Western Region-Dec 2013 143
Table-VII-(Example)
Performance of Black start facilities on 30/7/2002
Sr
No
Power station Capacity
of D.G
set
(KVA)
Time taken
for black
start
(Minutes)
Time taken for
extending
power to the
next
bus (Min.)
Remarks/ Constraints
1. Gandhisagar(H)
5 x 23 MW
100 KVA 2 9 After 41 minutes start up power to Satpura
power stations was extended. Voltage and
MW hunting observed along the 132 kV
start up path to Satpura.
2. Pench (H)
2x80MW
250 KVA 44 54 Start up power extended to Satpura
Power station through 132 kV Pench-
Seoni-Chhinwara-Satpura path. High
frequency problem and voltage hunting
observed. Start up power could not be
extended to Koradi power station of
Maharashtra through 132 kV Pench-
Kanhan line due to excessive voltage
hunting.
3. Bargi (H)
2x45 MW
250
KVA
9 9 Power extended up to Jabalpur. Due to high
voltage problem power supply could not be
extended to Amarkantak. Voltage hunting
also observed when 220kV Amarkantak –
Jabalpur Circuit I is charged.
4. Tons (H)
3x45 MW
250 KVA 16 16 Power supply extended to Satna over 220kV
Tons-Satna line. The unit at Tons tripped 3
times due to tripping of transformer at Satna
on overfluxing.
5. Birsingpur (H)
1x20 MW
220 volt.
Battery
49 - The unit tripped and due to fault in CB
power supply could not be extended further
to Birsingpur TPS.
6. Bango (H)
3x40MW
250 KVA 9 49 Power supply extended to Korba (E) and
Korba (W) power stations. Voltage hunting
reported.
7. Koyna Stage-I
4x70 MW
2000
KVA
39 54 Breaker problem at Kandalgaon S/S delayed
start up power supply to Uran. Due to high
voltage problem start up power could not be
extended to Koyna Stage-IV.
8. Ukai (H)
4x75 MW
500
KVA
62 79 Start up power extended to Ukai TPS
9. Kawas (Gas)
3x106 + 2x110
MW
2700
KVA
14 15 Start up power extended to Navsari 220kV
unit –1B which was black started tripped at
21:21 hrs due to restoration of more load at
Navsari. ESSAR & Kawas power stations
were synchronised at 2113 hrs. and start up
power to Tarapur APS given at 2113 hrs.
10
(a)
Jhanor (Gas)
3x144+ 1x225
MW
3120
KVA
- - The units survived on house load but
tripped on charging of 220kV Jhanor –
Haldurwa line.
(b)
-do- -do- 201 201 Hunting of DG observed while black
starting. Difficulty faced in extending
supply to Halderwa due to breaker problem
at Halderwa end
Recovery Procedure for Western Region-Dec 2013 144
Table-VII (example) cont…
Start up power supply to important power stations
Sr
No.
Power Station Start up
power source
Start up path used Time at which
start up power
is available
Is the start
up path
pre-
planned
1. Uran Koyna I & II 220kV Koyna-Kandalgaon-Khargar-
Uran
22.5 Y
2. Nasik Koyna 220kV-Uran-Apta-Kalwa-Taps –Nasik 23.57 Y
3. Chandrapur SR supply 400kV Bhadravati-Chandrapur 21.00 Y
4. Koradi SR supply 220 kV Chandrapur –Warora-Wardha-
Koradi
21.28 Y
5. Khaperkheda SR supply 220kV Koradi-Khaperkheda 21.40 Y
6. Bhusawal SR supply 132kV Koradi-Ambazari-Amaravati-
Akola-Paras-Malkapur-Bhusawal
22.40 Y
7. Parli SR supply 220 Kv Wardha-Pusad-Parli 23.30 Y
8. Tarapur Kawas 220kV Kawas-Navsari-Tarapur 21.13 Y
9. Satpura Gandhisagar 132kV Gandhisagar-Ujjain-Shujalpur-
Shajapur-Bhopal-Itarsi-Satpura
20.52 Y
10. Amarkantak NR supply 132kV –Vindhyachal-Waidhan-
Amarkantak
23.10 Y
11. Birsingpur NR supply 220kV Amarkantak-Birsingpur 00.04 Y
12. Korba (E) Bango (H) 132kV Korba (E)-Bango 21.00 Y
13. Korba (W) Bango (H) 220 kV Korba (E)-Korba (W) 21.05/21.37 Y
14. Ukai (Th) Ukai (H) 220 kV Ukai (H)-Ukai (Th) 21.30 Y
15. Wanakbori GIPCL 132kV GIPCL – Nandesari-Asoj
(132kV)-Asoj (220kV)-Wanakbori
20.55 Y
16. Gandhinagar A.E Co. 132kV AE Co. –Sabarmati-Ranasan-
Gandhinagar
21.30 Y
17. Kakrapar Kawas/Essar
Island
220kV Kawas-Navsari-Vav-Kakrapar 23.59 Y
18. Dhuvaran A.E Co. (Gas) 132kV Watva-Dhuvaran - Y
Recovery Procedure for Western Region,Dec 2013 145
Tabl
e-VI
II
Time
Prev
ious
Day
To-d
ay%
Resto
rati
on
Prev
ious
Day
To-d
ay%
Resto
rati
on
Prev
ious
Day
To-d
ay%
Resto
rati
on
Prev
ious
Day
To-d
ay%
Resto
rati
on
Note:
*To b
e com
puted
as pe
r ow
gene
ratio
n +IS
GS dr
awal.
% R
estor
ation
= (T
oday
‟s De
mand
) / (P
reviou
s day
‟s De
mand
)
**M
ay be
disp
layed
on V
DUs t
hrou
gh S
CADA
F
orm
at fo
r Rep
ortin
g Deg
ree o
f Res
tora
tion*
*
Cat
ered
Dem
and*
GUJA
RAT
CHHA
TTIS
GARH
MAD
HYA
PRAD
ESH
MAH
ARAS
HTRA
WR
Recovery Procedure for Western Region,Dec 2013 146
Annex-IX(i)
Report on the black start of Indira Sagar HPS (unit#5) conducted on 22nd
May,
2011. A proposal for black-start mock exercise was put-forth in the 419
th Operational Co-ordination Committee
Meeting of WR held on 12th January,2011 and an island comprising two units at ISP, block loads at 220/132
kV Neemuch S/S being radially fed through 400/220 kV Nagda S/S was proposed. In view of the concerns of
SLDC, MPPTCL for the high voltage conditions at Nagda in the absence of any reactive support, an
alternative proposal for forming an island with radial load at Jetpura (220/132/33 kV) S/S fed from a black
started unit at ISP through 400/220 kV Indore S/S was made which was finalized.
A detailed procedure for the mock exercise was prepared and finalized in consultation with all concerned on
11th May, 2011. A display for SCADA was prepared for monitoring all the S/S during the mock drill on a
single screen and all SLDCs were advised to get that picture copied to their respective servers for
simultaneous observation.
The black start exercise for Indira Sagar HPS was planned on 22nd
May,2011(Sunday) in consultation with all
concerned.22nd
May,2011 being a Sunday alternative supply to the loads fed from Jetpura 132 kV bus could
be ensured with-out any major constraint. All 33 kV feeders emanating from 220/132/33 kV Jetpura S/S
were identified to be fed from the islanded unit at ISP.
A presentation was made at Indore 400/220 kV substation on 20th May,2011in presence of teams from
WRLDC, SLDC, Jabalpur and 400/220 kV Indore S/S. A second presentation was made the next day (i.e. on
21st May, 2011) at ISP in presence of identified executives from ISP and teams from WRLDC and SLDC,
MPPTCL. Based on the few comments/inputs received during the above two presentations slight
modification was incorporated in the procedure and a final procedure was released and circulated to all
concerned by the evening of 21st May,2011.
A. Preparatory exercises for black start exercise of Indira Sagar HEP (shifting of feeders to
appropriate bus with bus coupler closed):
1. At 220/132/33 kV Jetpura S/S. (Please refer to Fig. 1):
a) After ensuring alternative supply to the loads fed from132 kV Jetpura bus(132 kV NZ-
1&2,Ujjain 1&2,Depalpur1&2 ) these feeders along with the 40 MVA, 132/33 kV transformer
and 160 MVA,220/132 kV ICT-II were tripped from both ends.
b) Then 63 MVA 132/33 kV transformer,160 MVA,220/132 kV ICT-I,220 kV Indore-Jetpura-II
were kept on 220 kV Main Bus-I and all other feeders and ICTs were shifted to the other bus and
opened followed by opening of the 220 kV bus coupler(B/C) at Jetpura.
2. At 400/220 kV Indore S/S.(Please refer to Fig. 2):
a) 220 kV Indore-Jetpura-II and LV side of 315 MVA,400/220 kV ICT-I were kept on 220 kV
Bus-I and other feeders were shifted to 220 kV bus-II at Indore.
b) 400kV Indore-ISP-II and HV side of 315 MVA ,400/220kV ICT-I were kept on 400 kV Bus-I
and all other ICTs/feeders were shifted to 400 kV Bus-II at Indore.
c) Bus-coupler(B/C)kept closed on both 400kV and 220 kV sides.
3. At 400 kV Indira Sagar(ISP) substation.(Please refer to Fig. 3):
a) Unit #5, Unit #6 and 400 kV ISP-Indore-II were kept on 400 kV Main bus-B and all other
feeders and units were shifted to the other bus i.e. 400 kV Main bus-A.Unit #6 was kept as a
stand by to be used for the mock drill in case of failure of unit #5.
b) 400 kV bus coupler (B/C) at ISP was kept closed.
Recovery Procedure for Western Region,Dec 2013 147
The above mentioned operations were completed by 08:45 hrs on 22nd May, 2011.Then the following
switching operations were done at Indore S/S.
a) 220 kV B/C at Indore was opened at 09:14 hrs.
b) 400 kV B/C at Indore was opened at 09:15hrs.
Immediately after opening the B/Cs the corresponding B/C-isolators were opened so as to rule out any
chance of re-striking on account of difference in voltages across the B/C during the is-landed operation.
B. Stage-I : Formation of is-land by separating out the identified subsystem -
1. Unit #5 at ISP was started after a change in its droop setting so as to operate the unit between a wider
frequency range (45-55 hz) and synchronised at 09:33 hrs. Flow on the 400kV ISP bus coupler was
closely observed.
2. The load at Jetpura and generation of ISP unit #5 were adjusted so as to make the flow on the B/C at
ISP closed to zero MW.
3. Then the B/C at ISP was opened followed by opening of both-side isolators at 10:12:48 hrs after
getting a code from WRLDC.
The is-land separated out at 10:12:48 hrs and 347ms and operated independently with frequency varying
widely. Since there was no primary response (governor action), the mechanical power input to the generator
turbine was controlled manually to match the electrical load to stabilize the frequency around 50 hz. But
frequency kept on fluctuating before the unit tripped when frequency touched 45 hz at 10:13:58 hrs (as per
the SOE data retrieved from WRLDC SCADA). Since the sub-system did not survive, the 400 kV circuit
breaker (CB) of ISP-Indore-II was opened from ISP end at 10:41 hrs.
C. Black-starting of unit #5 at ISP and building up of the is-land with the radial load at Jetpura being
fed through 400 kV Indore S/S:
The CBs of all the identified feeders/ICTs to be charged from the black-started unit were opened from
both ends by 10:43 hrs as informed by 400/220 kV Indore S/S. Then the CB of 400 kV ISP-Indor-II was
closed at Indore end along with the 50 MVAR line reactor(L/R) at Indore in line. It was decided to start the
unit #5 at ISP and charge the 400 kV dead bus at a reduced voltage level and gradually build up the voltage
as the sub-system stabilized. Then the following operations were performed to black start unit #5 at ISP and
gradually build up the is-land.
1. Start-up power to unit #5 at ISP was cut-off by tripping incomer at 11 kV switch-gears at 10:56 hrs. The
DG set started automatically within 10 seconds feeding start-up (auxiliary) power to unit #5.
2. Unit #5 was started at 11:20 hrs with a reduced terminal voltage (4kV against the rated voltage of 11kV)
at the 11/400kV GT (generator transformer) primary and generator circuit breaker was closed, charging
the 400 kV dead bus (Main Bus-B) at ISP at 11:20 hrs. The voltage observed at 400 kV ISP Main Bus-B
was around 160 kV(approximately).
3. Then 400 kV ISP-Indore-II was charged by closing the CB from ISP end at 11:34 hrs. This resulted in
charging of 400 bus-I at Indore along with the 50 MVAR L/R at Indore. The voltage observed at Indore
400 kV bus-I was around 150 kV which was insufficient for charging the 400/220kV ICT-I at Indore.
Hence the generator terminal voltage was increased so as to achieve 200-210 kV at 400 kV Indore bus-I.
4. Then the 400/220 kV Indore ICT-I was charged at 11:48 hrs by closing the HV side CB followed by
charging of 220 kV bus-I at 11:50 hrs by closing the LV side CB.
5. Then 220 kV Indore-Jetpura-II was charged from Indore end at 11:51 hrs followed by charging of 220
kV main bus-I at Jetpura at 11:52 hrs.
6. Then 220/132 kV ICT-I at Jetpura was charged at 11:53 hrs and 132 kV Jetpura bus was charged at
11:54 hrs, followed by charging of 63 MVA, 132/33 kV transformer at Jetpura at 11:55 hrs. Then 33 kV
Jetpura bus was charged at 11:55 hrs.
Recovery Procedure for Western Region,Dec 2013 148
7. Generator terminal voltage at ISP was gradually increased and a voltage of around 370kV at Indore bus-I
was achieved at 12:10 hrs. Generator turbine speed was gradually increased to reach a high frequency
before addition of any load at Jetpura. A frequency of 52 hz for the is-land was achieved at 12:14 hrs.
8. Then radial load was added gradually at Jetpura by charging the identified 33 kV feeders. The first load
(33 kV BPCL feeder) added was 0.7 MW (approximately) at 12:15 hrs causing the frequency to dip to
51.89 Hz. Subsequently 33 kV Ramaphosphate, Dhaturia, Sanwer and Dharampuri feeders were
connected at 12:18 hrs, 12:20 hrs, 12:30 hrs and12:43 hrs respectively as informed by Indore S/S. The
load was thus increased in steps and generator output was adjusted accordingly to maintain frequency
between 50-51hz. At 12:58 hrs the unit was catering to a load of 12.01 MW(approximately) at 50.9 hz as
per the data observed at ISP.
D. Synchronisation of the is-land with rest of grid by closing the 400 kV B/C at Indore:
After successfully operating the is-landed subsystem for almost one hour, preparation was made to
synchronise the is-land with rest of the grid. It was planned earlier to synchronise the is-land with rest of the
N-E-W grid at 400 kV Indore S/S since synchronising facility was not available with the 400 kV bus-coupler
at ISP.
1. The generator output was adjusted to bring down the frequency close to that of the N-E-W grid.
2. The bus voltage at 400 kV Main Bus-I (part of island) was 381 kV while that of the bus-II(part of main
grid) was close to 420 kV at 13:00 hrs. Hence the generator terminal voltage was gradually increased to
increase the voltage level at Indore bus-I. A voltage close to 420 kV at Indore 400 kV main bus-I was
achieved by 13:11 hrs.
3. The voltage magnitudes, phase sequences and frequencies of 400 kV bus-I and bus-II at Indore were
closely monitored with help of the synchronising trolley at Indore S/S and the bus-coupler was check-
synchronised at 13:12:37 hrs(as per WRLDC SOE data) when the N-E-W frequency was 49.92 hz.
4. Unit #5 at ISP experienced mild jerk and tripped immediately (at 13:12:38 hrs-as per WRLDC SOE data)
on excitation failure alarm.
5. 220 kV Indore B/C was closed at 13:25 hrs. Normalisation of all arrangements made at different
locations were completed by 14:36 hrs as per the information received from 400/220 kV Indore S/S.
E. Sequence of Events for the Black Start Exercise is summarized below:
Sl. No. Time in
hrs
Event
1. 10:12:48 Subsystem successfully created with radial load of 16-18MW at Jetpura.
2. 10:13:58 The island collapsed when frequency fell below 45 hz during manual control
of generation of unit #5 at ISP.
3. 11:20 Unit # 5 of Indira Sagar HEP self-started through station D.G. supply and
dead 400 kV Main Bus -B at ISP was charged at a reduced voltage level.
4. 11:34 400kV ISP-Indore-II was charged from ISP along with 50 MVAR L/R at
Indore. This caused simultaneous charging of 400 kV Indore bus-I
5. 11:48 400/220 kV Indore ICT-I was charged from 400 kV side.
6. 11:50 220 kV bus-I at Indore was charged.
7. 11:51 220 kV Indore-Jetpura-II was charged from Indore end
8. 11:52 220 kV main bus-I at Jetpura was charged.
9. 11:53 160 MVA,220/132 kV ICT-I at Jetpura was charged.
10. 11:54 132 kV bus at Jetpura was charged.
11. 11:55 63 MVA,132/33 kV transformer at Jetpura charged along with 33 kV bus.
12. 12:10 Terminal voltage at ISP increased so as to achieve 370 kV at 400 kV bus-I at
Indore.
13. 12:15 33 kV BPCL feeder was switched on from Jetpura.
14. 12:18 33 kV Ramaphosphate feeder was switched on from Jetpura.
15. 12:20 33 kV Dhaturia feeder was switched on from Jetpura.
16. 12:30 33 kV Sanwer feeder was switched on from Jetpura.
Recovery Procedure for Western Region,Dec 2013 149
17. 12:43 33 kV Dharampuri feeder was switched on from Jetpura.
18. 13:12:37 Check-synchronisation of 400 kV B/C at Indore causing synchronisation of
the is-land with N-E-W grid.
19. 13:12:38 Unit #5 at ISP tripped on jerk with excitation failure alarm.
20. 14:36 All intermediate arrangements were normalised as per the information
received from Indore s/s.
F. Issues that needed further improvement / investigation:
1. Primary response is mandatory for a unit while separating out from the rest of the grid that survives
to operate in is-landed mode. The same was absent at ISP causing collapse of the is-land within
seventy seconds from separation while attempting to stabilize the subsystem through manual control
of the generation. It was understood from ISP that it was not possible to operate the unit under speed
control mode under normal operation. Necessary modifications may be made to ensure that this is
possible under normal mode of operation.
2. Even 15 minutes after opening the 400 kV bus-coupler at ISP voltage of around 200 kV was
appearing on 400kV Main Bus-B at ISP though it was zero immediately after the unit tripped at
10:15:06 hrs. Surprisingly Indore bus-I was also showing similar value (200 kV approximately) at its
end. Though it was assumed to be an instrument error, the voltage became zero only after opening
the CB of ISP-Indore-II from ISP end. This required further investigation.
3. Though the check-synchronisation at 400 kV Indore B/C was done with due diligence and care, the
unit experienced perceptible jerk and tripped on excitation failure alarm (after successfully running
in is-landed mode for around one hour).Thus the healthiness of the synchronising trolley at 400/220
kV Indore(MP),S/S may be checked and rectified.
4. Although the black-start exercise was smooth, the time taken to start restoration of loads after black-
out was close to 2 hrs(10:13:58 hrs to 12:15hrs). This would need to be further reduced to the range
of 30 minutes maximum. One reason for the delay was energization of 400 kV transmission system
at reduced voltage (160 kV). The voltage was gradually built up just before restoring loads at 33 kV.
One of the reasons for energization at low voltage was the apprehension of tripping of 400 kV line
on high voltage as experienced during a similar exercise in 2006. At that time the 50 MVAR L/R at
Indore was not available and energization was attempted at 400 kV. Restoration time can be reduced
if the network is energized in the range of 360-370 kV.
G. Some interesting facts observed during the mock drill (As per WRLDC SCADA data):
1. Maximum load fed in islanded subsystem: 12.69 MW [13:12hrs]
2. Maximum frequency of the subsystem: 53.39Hz [12:12hrs]
3. Minimum frequency of the subsystem: 49.17 Hz [12:10hrs]
4. Maximum voltage of subsystem recoded at 400 kV Indore bus-I: 420kV [13:11hrs]
5. Minimum voltage of subsystem recorded at 400 kV Indore bus-I: 194kV [11:51 hrs]
6. Island created by opening of bus coupler at ISP survived for 70 seconds with 16-17 MW load
(approximately) of Jetpura S/S.
7. This island collapsed during manual control of governor while frequency varied widely and fell
below the 45 Hz at 10:13:58 hrs and 442 ms.
8. Duration of complete load interruption at Jetpura for blackstart exercise: 121 minutes [10:13:58 hrs
to 12:15 hrs].
9. Time taken by the generator to start from DG set after the grid supply (11kV incomer) was
disconnected: 24 minutes [10:56hrs to11:20hrs].
10. The 400/220 kV Indore substation engineers could synchronize the island with main grid within 16
minutes of receiving instruction for check-synchronization from WRLDC.
11. Speed Governor Droop setting of ISP Unit-5 was changed from 5% to 10 % during the black start
mock exercise.
Recovery Procedure for Western Region,Dec 2013 150
12. The black start exercise (starting the unit from DG set, charging 400 kV dead bus and feeders,
extending power to feed radial load and re-synchronisation of the island with main grid) was
completed in 1 hr and 52 minutes [11:20 hrs to 13:12 hrs].
H. Few graphical plots during the is-landed operation:
47.00
48.00
49.00
50.00
51.00
52.00
53.00
54.00
9:00
:00
9:30
:00
10:0
0:00
10:3
0:00
11:0
0:00
11:3
0:00
12:0
0:00
12:3
0:00
13:0
0:00
13:3
0:00
14:0
0:00
Indore220_Bus-I_Frq(Hz)
ISP_400 BusA_Frq(Hz)
Fre
qu
en
cy(H
z)
Grid Frequency
Is-land Frequency
Is-landed operation
of ISP unit #5
Time(hh:mm:ss)
Total duration of 220 kV bus dead at
Jetpura on account of mock exercise
was from 10:15 to 11:52 [1hr & 27mins]
13:12:37 hrs:
Subsystem was
synchronized with
the main grid
through 400 kV B/C
at Indore.
10:12:48 hrs :
400 kV ISP B/C
opened creating
the is-land.The is-
land collapsed at
10:13:58 hrs
At 12:15 the first load (0.7MW
approx.)connected on 33 kV
Jetpura bus
Indore_Bus-I_Voltage(400kV)
10
110
210
310
410
9:00
:00
9:30
:00
10:0
0:00
10:3
0:00
11:0
0:00
11:3
0:00
12:0
0:00
12:3
0:00
13:0
0:00
13:3
0:00
14:0
0:00
10:13:58 hrs : The is-
land collapsed due to
tripping of unit # 5.
Vo
ltag
e(k
V)
Time(hh:mm:ss)
13:12:37hrs :
400 kV Indore
bus-coupler
check-
synchronised.
Recovery Procedure for Western Region,Dec 2013 151
LEGEND:
400 kV :
220 kV :
132 kV :
33 kV :
Transformer:
Depalpur-I&IIUjjain-I&IINorth Zone-I&II
63 MVA,132/33 kV BBL make transformer
40 MVA,132/33 kV TELK make transformer
BP
CL
Sa
nwer
Dh
atu
ria
Ram
a P
hos
pha
te
Dh
ara
mpu
ri
160 MVA,220/132 kV Jetpura ICT-II(AREVA make)
160 MVA,220/132 kV Jetpura ICT-I(CGL make)
Ujjain-IIndore-I Indore-II
Ra
dia
l L
oa
d t
o b
e f
ed
fro
m t
he
bla
ck
sta
rte
d u
nit
B/C220kV Main Bus-I220kV Main Bus-II
Ujjain-II
Fig. 1: Jetpura 220/132/33 kV S/S
Jetpura-II
80 kms(Approx.)
Fig. 2: Indore (400/220 kV) S/S
400/220 kV Indore ICT-II,III&IV 400/220 kV Indore ICT-I
Indira Sagar-I
Indira Sagar-II
400kV B/C
400kV Bus-I400kV Bus-II
Nagda
220kV Bus-I220kV Bus-II
220kV B/C
Jetpura-I
(220 kV Feeders to Ujjain,Dewas,Pithampur,Indore SZ,Badnagar,Barwaha)
30 Kms(Approx.)
ItarsiAsoj
LEGEND:
400 kV :
220 kV :
132 kV :
33 kV :
Transformer:
Jetpura-II
80 kms(Approx.)
Indore (400/220 kV) S/S
400/220 kV
Indore ICT-II,III&IV 400/220 kV Indore ICT-I400kV B/C
400kV Bus-I400kV Bus-II
220kV Bus-I220kV Bus-II
220kV B/C
Jetpura-I
(220 kV Feeders to
Ujjain,Dewas,
Pithampur,Indore
SZ,Badnagar,Barwaha)
STEP- 3:
a) 400/220 kV ICT-I,220 kV Jetpura-II to be kept on
220 kV bus -I.
b)400 kV Indira Sagar-Indore-II to be kept on 400 kV
bus-I
c) All other feeders/ICTs to be shifted to bus-II
d)B/Cs continue to remain closed.
30 Kms(Approx.)
kms(Approx.)
Fig. 3: Indira Sagar (400/220 kV)
Indore-II
Indira Sagar-II
400kV B/C
400kV Main Bus-A
Unit #5
400kV Main Bus-B
80 Kms(Approx.)
(All units except unit # 5 and unit # 6 were kept on Main Bus-A)
Unit #2 Unit #1Unit #8
Indore-I
Nagda Satpura
LEGEND:
400 kV :
220 kV :
132 kV :
33 kV :
Transformer:
Generator:
Indira Sagar (400/220 kV) S/S
Indore-II
400kV B/C
400kV Main Bus-A
Unit #5
400kV Main Bus-B
STEP- 4:
a) 125 mW unit #5 and Indore-II feeders to be kept
on Main Bus-B.
b) All other feeders/ICTs to be shifted to bus-II.
c) 400 kV B/C continues to remain closed.
80 Kms(Approx.)
Unit #6
Recovery Procedure for Western Region,Dec 2013 152
Annex-IX(ii)
Black-Start mock drill at Bargi Hydel Power station A mock black-start exercise for Bargi HPS unit was carried out on 10th February, 2012. SLDC Jabalpur is pleased to place on record the cooperation, assistance and efforts made by engineers from Bargi Hydel Power Station, MP Power Transmission Company, 132 kV Lakhnadaun substation, Generating Control Centre and East DISCOM Control Centre during the mock drill of black start. This black start exercise involved two major stages: Stage-I: Creating an islanded subsystem by separating out unit #2 (45 MW) at Bargi HPS along with radial load at 132/33 kV Lakhnadaun s/s fed through 132 KV bus #1 of bargi HPS, followed by operation of the created island around the Bargi unit for some time.
Stage-II : Creating a blackout in the islanded subsystem created with one unit (45 MW unit #2) of Bargi and radial load at 132/33 kV Lakhnadaun s/s, start of one unit at Bargi, charging of one dead 132 KV bus at Bargi, charging 132 kV Bargi-Lakhnadaun line, islanded operation of the Bargi HPS unit with radial load at Lakhnadaun s/s followed by synchronising this island at Bargi HPS. Bargi is the nearest Hydel power station to Jabalpur. Capacity of the plant is 2x45 MW = 90 MW. Bargi HPS is interconnected with Jabalpur 220 KV sub-station through 132 KV D/C line and to Lakhnadaun 132 KV S/s through 132 KV S/C line. One 132/33 KV 40 MVA transformer at Lakhnadaun S/s feeds consumer load through 5 Nos. 33 KV feeders. The Black Start Mock Drill was proposed to be conducted after creating island at 132 KV Lakhnadaun S/s with Unit No.2 of Bargi HPS. Lakhnadaun 132 KV S/s is having two 132 KV buses - one Main and one Auxiliary bus, 1x40 MVA 132/33 KV transformer and two 132 kV lines viz, 132 KV Lakhnadaun-Seoni S/C & 132 KV Lakhnadaun-Bargi S/C. The maximum loading of about 28 MW was recorded in morning hours on 40 MVA transformer in February 2012 . The loading of each feeder at 33 KV system at 132 KV Lakhnadaun S/s was recorded at 10:30 Hrs on 10th February 2012 as detailed below:
SNo. Name of the feeder Load
1. Jhabua Power Ltd 0
2. Bhimgarh 160 Amp/8MW
3. Lakhnadaun 130 Amp/6 MW
4. Ghansaur 144 Amp/7 MW
5. Dhooma 83 Amp/4 MW
Total load on 40 MVA transformer
~ 25 MW
Prior to start of black start mock exercise it was ensured that 132 KV Lakhnadaun S/s is fed from 132 KV Bargi HPS as well as 132 KV Seoni S/s and all 33 KV feeders shall also be in
charged position. It was also ensured that both 132 KV Bargi-Jabalpur feeders, Unit # 1 & 20 MVA station X-mer are kept on 132 KV Main bus-II, 132 KV bus-coupler in closed position at this stage and Unit # 2 and 132 KV Bargi-Lakhnadaun feeder on 132 KV Main bus-I. This scheme has ensured availability of Unit No.1 at Bargi HPS with 132 KV Jabalpur S/s through Bus-II during mock drill.
Recovery Procedure for Western Region,Dec 2013 153
The complete black start mock exercise has been conducted at Bargi HPS between 10:25 Hrs to 11.42 Hrs on 10th February 2012. The procedure followed is detailed below :
(1) Islanding of 132 KV Lakhnadaun S/s WITH Unit No. 2 (45 mw) at Bargi HPS 1. The droop setting of Generator under Black Start Mock Drill was 5%.
2. Generation on 45 MW unit #2 at Bargi HPS adjusted equal to load on 132/33 kV 40 MVA transformer (~27 MW) at 10:35 Hrs.
Recovery Procedure for Western Region,Dec 2013 154
3. Breaker of 132 KV Lakhnadaun-Seoni line opened at Lakhnadaun s/s at 10:38 Hrs. After ensuring Generator output is equal to load connected at 132 KV Lakhnadaun s/s, 132 kV bus-coupler breaker opened at Bargi HPS at 10:45 Hrs on issue of instruction by SLDC forming an island around are fed from 132 kV Lakhnadaun s/s. This exercise was done as bus coupler ammeter at Bargi was found not showing correct reading.
4. The generator output adjusted to match the load. However, the frequency variation from 44.5 Hz to 52.2 Hz has been observed in the islanded system fed from Bargi Unit #2 (45 MW) before getting stabilized. The primary response of the governor was observed and found working. The islanded system with about 25 MW load was run for about 7 minutes.
(2) Blackout in the area fed through 132 KV Lakhnadaun : 1. After stabilizing the island for few minutes, Unit No.# 2 was hand tripped at 10: 52 hrs after
hand tripping of 0.4 kV incomer (auxiliary supply). This has created black out in the area fed from Lakhnadaun S/s.
2. The breakers of 33 KV breakers of 132 KV Lakhnadaun S/s alongwith breaker of 132 KV
Lakhnadaun-Bargi, 40 MVA Transformer (both ends) hand tripped. Similarly 132 KV Bargi-Lakhnadaun breaker has been hand tripped at Bargi HPS.
(3) Black Start Operation : The black-start activities of machine No. 2 at Bargi HPS have been carried out as given below : 1. As soon as Unit No.2 is tripped and black out occurred, the D.G. set should start automatically.
As the auto start up facility is not available with DG set at Bargi HPS, the same has been started manually at 10:55 Hrs.
1. 0.4 kV supply extended to unit bus to start essential auxiliaries and essential auxiliaries of Unit
No. 2 taken into service. 2. SLDC issued instruction at 10:58 Hrs to start Unit No 2. Unit rolling started at 11:00 Hrs. and
132 KV Bus #1 charged at 110 kV at 11:05 Hrs. 3. 132 KV Bargi-Lakhnadaun line charged at 11:07 hrs from Bargi end and Lakhnadaun end at
11:08 Hrs. 4. Breaker of 40 MVA 132/33 kV transformer at Lakhnadaun closed at 11:08 Hrs and voltage of
132 Kv bus at Lakhnadaun adjusted to 126 kV by raising generator voltage at Bargi. The frequency of Unit #2 has been set At 50.5 Hz. At this stage R-Phase bus PT fuse has got blown out which got replaced at about 11:15 Hrs.
5. As per instruction of SLDC, 33 KV Lakhnadaun line charged at 132 KV Lakhnadaun s/s at
11:15 Hrs with load of about 4 MW. Then at 11:16 Hrs 33 kV Ghansore line taken on load. The frequency in the islanded area was 50.2 Hz. Then other 33 kV lines at Laknadaun s/s also closed. The load in the islanded area after black start was as below :
The primary response of governor has maintained the frequency in the islanded area close to 50.0 Hz. The islanded portion operated for about 25 minutes without any difficulty.
1. The islanded portion check-synchronized with the NEW grid by closing 132 kV Bus coupler at Bargi HPS at 11:40 Hrs.
Time Consumer load at Lakhnadaun s/s.
11:17 11 MW
11:18 14 MW
11:22 18 MW
11:24 18 MW 50.0 Hz, 130 kV
Recovery Procedure for Western Region,Dec 2013 155
Fig 2. Plot of frequency and Unit-2 generation at Bargi HPS which was part of the island during
black start exercise.
Fig 3. Plot of Bus 132 kV -1 Voltage at Bargi HPS which was part of the island during black start
exercise
Observations and analysis of the exercise : The results of black start exercise of Bargi HPS has been quite satisfactory. The restoration of the supply to Lakhnadaun area post black out took about 23 minutes which could have been reduced to 16 minutes if the bus PT fuse did not blow out at Bargi. The restoration of the system within this short time without any abnormal behavior of voltage, frequency and other electrical parameters will help in restoration process in real time.
The graphical plots in Fig. 2 & 3 based on the achieved data at SLDC indicate various observations made during the exercise. The subsystem in island condition operated for almost 7
Recovery Procedure for Western Region,Dec 2013 156
minutes pre-black out (10:45 Hrs to 10:52 Hrs) 25 minutes after black start (11:15 hrs to 11:40 Hrs). The frequency of the island remained close to 50.0 Hz, which shows that the unit is perfectly working in free governor mode.
The DG set at Bargi HPS do not have auto start facility and thus started manually. MPPGCL may explore the possibility of installing auto start facility so that the DG set start automatically in real time under black out conditions.
The capabilities of the generator that got tested during black start exercise include the capability to start from a DG set, to regulate the active and reactive power output so as to operate the island at reduced standards of frequency and voltage, to operate under partial loading condition without losing stability, primary response of the generator, healthiness of synchronisation facility etc. The transmission capability that were put to test include the ability of switch gear to charge dead bus, healthiness of bus breakers, flexibility available in protection systems in terms of operating at other than normal settings for a short period.
Other observations that need immediate attention by MPPGCL are described hereunder :
(1) After opening of bus coupler at 10:38 Hrs at Bargi HPS, 48 Volt charger tripped and as 48 VDC battery is in bad condition the telemetry become out till battery charger put back into service at about 11:06. Thus vital data for this period is not available. The 48 VDC battery therefore need to be replaced within the shortest possible time. The cause of tripping of 48 V charger also need to be investigated by MPPGCL.
(2) The hunting of Generator output (Unit 2) also observed in GT control panel and as telemetry transducer inputs are extended from the same control panel, the hunting also recorded in SLDC SCADA system. The hunting to the extent +22 to -24 MW observed though the generation and frequency was stable. This also need to be investigated and corrective measures should be taken by MPPGCL.
(3) The ampere meter on 132 kV Bus coupler panel at Bargi HPS was showing 130 Ampere current irrespective of load and even when both buses were isolated by opening bus coupler, the meter continued showing 130 Amp current. The ampere meter need to be recalibrated/replaced. Conclusion: Black out in power grid is a worst kind of contingency and brings unpleasant situations when it occurs. Since the power systems worldwide are evolving both in size and complexity, the conventionally adopted recovery procedures requires constant review, upgradation, test and validation. The black start exercises assume vital importance for any large interconnected power system since they do not only testify the existing restoration facilities but also prepare the system operators to restore the power system in a shortest possible time by identifying deficiencies and suggesting scopes for improvement.
Recovery Procedure for Western Region,Dec 2013 157
Annex-IX(iii)
MOCK BLACKSTART OPERATION AT SSP ON 8TH APRIL 2012
• A mock self start exercise for SSPPL was carried out on 8th April 2012 .
• Exercise involved creation of island that involved SSP Unit-2 ,SSP-Asoj S/C line ,Asoj 400/220
ICT-1 ,220KV Asoj-Wagodia line and loads at Wagodia.
Fig : 11KV AND BELOW SLD OF SSP PLANT THEIR OPERATION DURING BLACK START
11KV Switch Yard(S/Y) is GIS at SSP.
2 no of 13.8KV/11KV STR (station transformer) are there in total which are connected from LV side
of GT(Generator Transformer). STR-1 is connected from GT-1 and STR-2 is connected from GT-4.
2 no of SST- (station service transformer) from 11KV Bus-A supplies to 415 KV SSB (station
service bus).
SSB-A supplies to station and unit auxiliary of unit 1, unit 2 and unit 3 .Whereas SSB-B supplies to
unit 4,unit 5 and unit 6.
So to conduct the mock black-start and islanding operation with unit 2 and 3, B/C of 11KV bus and
so as of SSB were opened.
Unit 6 was running as per schedule and it got auxiliary supplies from STR-2
During first stage of mock exercise unit 2 was started with supply from STR-1 .But after the system
was completely blackout, unit -2 started taking auxiliary supplies from DG set-2.
Recovery Procedure for Western Region,Dec 2013 158
With this type of circuit connection Unit-1,2,3 forms a group and Unit-4,5,6 forms another. So at a
time any of the units from 1,2 or 3 can be used for islanding operation with any of the unit 4,5 or 6
continuing normal operation with grid.
Brief details of Mock-Exercise as per activities observed at SSP end.
1. 8:55Hrs to 9:05Hrs -Bus changeover at SSP . GT-2,GT-3 and 400KV Asoj line is kept on Bus A.
Remaining lines and Units were connected to Bus B.400KV SSP-Dhule-1 and 400 KV SSP-
Rajgarh-1 were out during that time to control High voltage.
2. 9:10Hrs SAT-1 is made off and load was taken on SAT-2.Bus coupler of 11KV bus is off and Dam-
1 feeder also made off.
3. 10:00Hrs Unit-2 was put in FGMO mode and so as Unit -3 at 10:05 Hrs.
4. 10:45Hrs start command was given to Unit-2 and unit synchronised at 10:52 Hrs. Generation on
Unit-2 was 80MW and it was absorbing 20MVAR.Guide vane position was 4.4. Freq was 50.01HZ .
At that time Unit-6 was also running as per schedule and there was a flow of around 190MW on
400KV SSP-Asoj S/C line.
5. 11:10Hrs 400 kV Bus Coupler(B/C) at SSP was opened isolating Bus-A and Bus -B . So Asoj line
flow was reduced to 78MW as it was connected to Bus -A with only generation from Unit-2.Bus-A
voltage was 414MW and freq was 49.89HZ.
6. Bus changeover at 400KV Asoj and 220KV Asoj was already done and at 11:14Hrs 220KV Asoj
Bus coupler was opened.
7. Now the only element that connects this island grid to NEW grid was Bus Coupler at 400KV Asoj.
As informed by SLDC Gotri ,Wagodia Load was around 42 MW .So from 11:19 Hrs generation
reduction at Unit-2 started to make flow on Asoj B/C close to ‘0’ MW.
8. 11:21 Hrs Unit -2 generation was 60MW and -13MVAR . At 11:22Hrs Excitation of Unit-2 was kept
on MEC(manual excitaion) to control voltage manually. Generator Terminal Voltage was 13.5KV to
13.8KV.
9. 11:24 Hrs Unit -2 generation was 65 MW and -37 MVAR. Voltage at SSP was 410KV and at Asoj
412KV. Freq was 49.88HZ.Generation was reduced even further and at 11:26 Hrs it was 56MW, -
35 MVAR. 400KV SSP-Asoj line flow was 52 MW.
10. 11:28 Hrs after confirmation from SLDC and with WRLDC code bus coupler at 400KV Asoj was
opened. Generation was 40MW and Voltage of SSP Bus-A was 412 KV. Before opening of B/C
frequency was 49.76HZ, but after opening of B/C system was completely islanded from NEW grid
and freq was varying between 48.5HZ to 51.8HZ.
11. Oscillation was also observed on voltage and Guiding Vane position of unit-2. At 11:34 Hrs Asoj
line flow was fluctuating between 38MW to 42 MW. Voltage at SSP was between 372KV to 404KV.
12. As Unit-3 was kept as standby machine in case of failure of Unit-2 at 11:41 Hrs GTCB-3 was
opened and at 11:43Hrs Unit-2 was normally stopped causing blackout of island. GTCB-2 also out
on under freqency. So before complete black out system sustained Islanded operation from
11:28Hrs to 11:43Hrs.
13. As per previously planned DG was not kept on automatic mode to start after sensing 0 voltage. At
11:48 Hrs DG-2 stared energizing SSB(system service bus for Unit 1,2,3).
14. SSP-Asoj line was still in service causing a residual voltage around 42KV . At 11:48Hrs SSP-Asoj
line CB was opened from SSP end.
15. At 11:53 Hrs Under frequency relay for Unit-2 was bypassed.12:00Hrs GTCB for Unit-2 closed and
at 12:02 Unit-2 started again. Excitation put on to manual mode. Generator Terminal Voltage was
Recovery Procedure for Western Region,Dec 2013 159
set on 11KV. At 12:07 GCB was closed charging Bus-A at SSP. Bus Voltage was 328 KV and
frequency was 49.2HZ.
16. Voltage was increased gradually and 12:09Hrs voltage was 394KV,freq was 48.77. G/V position
was varying between1.8 to 2.8.
17. 12:11Hrs 400KV SSP-Asoj line was charged with L/R at Asoj end,but at 12:12Hrs Asoj line tripped
on High Voltage on both stage 1 and stage 2 HV setting.
18. 12:18Hrs another attempt was made to charge Asoj line,but line didn't hold and tripped again.
19. 12:21Hrs voltage was further reduced to 369KV at SSP end and Asoj line was charged at 12:27Hrs
,so as 400KV Bus-1 at Asoj
20. 12:29Hrs 500MVA 400KV/220KV ICT-1 at Asoj charged and so as 220KV bus-1 at 220KV Asoj.
Frequency at that time was around 49.8HZ.
21. 12:34Hrs 220/66KV ICT was charged at Wagodia and load increment started. At the same time
there was 1.23 MW flow on Asoj line . freq was varying between 48.6 HZ to 50.3HZ.
22. Load increment stared at Wagodia so was generation of Unit-2. At 12:39Hrs Unit-2 load was 7MW
and flow on Asoj Line was 3.24MW. Freq was varying between 47.73HZ to 51.3HZ and voltage
was between 360KV to 390KV.
23. 12:45Hrs Unit-2 load 10MW,Line load 8MW. Generator terminal voltage was varying between12.2
to 13.4KV although excitation was on MEC mode. Guiding vane variation was between 1.6 to 3.6
and vibration of upper bracket was 115microns.
24. 12:49Hrs Unit-2 load 14MW ,line load 10.7MW.Freq :48.7HZ- 50.58HZ.
25. 12:52Hrs Unit-2 Load was 24MW.At 12:53 Hrs it increased up to 31MW and line load was 26MW.
26. 12:55Hrs frequency was between 47.26HZ to 50.75HZ with 33 MW generations.
27. 12:58 Hrs generation of Unit -2 was varying between 39MW to 42 MW. Asoj line loading was
around 38 MW.
28. Although there was gradual increment in load with little time delays no significant stability was seen
in frequency, voltage, Guiding vane. Voltage was varying between 370KV to 421KV and
Frequency variation was between 46.6HZ to 51.9HZ.
29. As per SSP this variation was due to less loading on generator and SLDC was not able to provide
further radial loads .
30. So it was advised to stop the machine as synchronization with new grid at such large range of
fluctuation in frequency and voltage is a threat to generator with such a large inertia.
31. At 13:25Hrs Unit -2 was stopped by emergency push button.
32. Before shut down of unit the system operated on islanded mode from 12:34Hrs to 13:25Hrs.
33. At 13:32 Hrs B/C at SSP was closed and it was connected to NEW grid.
Recovery Procedure for Western Region,Dec 2013 160
Annex-IX(iv)
REPORT OF MOCK BLACK START EXERCISE OF BANGO HYDEL
POWER STATION OF CSPGCL ON 25.08.2012 Details of Bango HPS
1) Unit Capacity: - 3 x 40 MW
2) Commissioning Year: - U#1 - 21.03.94, U#2 - 21.11.94 and U#3 - 11.01.95
3) Type of Turbine: FRANCIS, Vertical position supplied by M/s BHEL.
4) Water Source: Hasdeo River.
5) DG Set Capacity: 250 KVA.
Network for Black Start Drill at Bango HPS consisted of: -
1) 132 KV Bus No.1 at Bango HPS.
2) 132 KV Bango- Jamnipali Circuit no. 2 (Line length- 45 Km.)
3) 132 KV Bus at Jamnipali s/s.
4) 132 KV Jamnipali- Korba East Circuit no. 1(Line length - 10.36 Km.)
5) 132 KV FAR BUS at 132 KV Korba East station.
6) 40 MVA transformer (132/33 KV) No. 2 feeding supply to 33 KV, Phutkapahar, Industrial and
Rajgamar feeders.
Brief Detail of Mock Exercise
Following Pre Mock drill activities were done before Mock Drill.
(A) At Korba East 132 KV S/s
The 132 KV Korba East has two main buses namely NEAR BUS & FAR BUS.Following feeders and
transformers were shifted to 132 KV NEAR BUS:-
a) 220KV/132 KV ICT No. 01 at 132 KV end.
b) 220KV/ 132 KV ICT No. 02 at 132 KV end.
Recovery Procedure for Western Region,Dec 2013 161
c) 132/33 KV 20 MVA transformer
d) 132/33 KV 40 MVA transformer No. 01.
e) 132 KV Korba- Mopka circuit No. 01.
f) 132 KV Korba -Mopka circuit No. 02.
g) 132/33 KV 6.5 MVA station transformer
h) 132 KV Korba -Champa circuit No. 01.
i) 132 KV Korba- Champa circuit No. 02.
j) 132 KV Korba -Jamnipali circuit No. 02.
Further following feeders and transformers were kept on FAR BUS:-
a) 132 KV Korba - Jamnipali Circuit No.01.
b) 132/33 KV, 40 MVA, Transformer no.2, feeding to 33 KV: Phutkapahar, Industrial Load,
Rajgamar feeders.
(B) At Jamnipali 132 KV S/s
132 KV Jamnipali has only one bus as such so complete shut down of bus was necessary for Mock drill. The
following lines were disconnected from 132 KV Jamnipali Bus:
a) Jamnipali- Vandana Pooling substation at 12:30 hrs.
b) 40 MVA, 132/33 KV Transformer no.2 at 12:55 hrs
c) Supply to Gevra 132 KV Bus also made off from the tapping of Jamnipali-Bango circuit No. 2 at
12:30 hrs.
C) At Bango 132 KV S/s
At 132 KV Bango Hydel power stations, all units and feeders were shifted on main bus No. 2 except
generator No. 3 and Jamnipali feeder No. 2 and then bus coupler also made off .There was no interruption of
supply from Bango Station to 132 KV Manendragarh, 132 KV Bishrampur, VESPL Pooling station and 132
KV Gevra.
a) 12:25 Hrs :- 132 KV Korba East-Jamnipali circuit no.1 switched off
b) 12:30 Hrs :- 33 KV feeders Rajgamar, Industrial & Phutka Pahar switched off.
c) 12:31 Hrs :- 33 KV bus coupler at KEB made off.
d) 12:32 Hrs :- 132 KV breakers of 40 MVA transformers No. 2 at KEB made off.
e) 12:35 Hrs :- 132 KV bus coupler at KEB made off.
f) 12:50 Hrs :- 132/33 KV, transformers no.1 hand tripped from both sides at Jamnipali
g) 12:55 Hrs :- 132/33 KV, transformers no.2 hand tripped from both sides at Jamnipali
h) 12:54 Hrs :- Bango Bus coupler opened.
i) 12:55 Hrs :- 132 KV KEB-Jamnipali circuit No. 2 made off from Jamnipali end.
j) 12:58 Hrs :- 132KV Jamnipali-Bango circuit No.2 hand tripped at Jamnipali s/s.
Recovery Procedure for Western Region,Dec 2013 162
BLACK START MOCK DRILL EXERCISE SEQUENCE
Sl.No. Time Activity for Mock Drill
1 13:26 Hrs 250 KVA, DG set was started at Bango PS for black start
2 13:27 Hrs 0.4KV Station bus at Bango HPS was charged.
3 13:48 Hrs Rolling of unit no. 3 started.
4 14:00 Hrs Speed came to 187 RPM. Field breaker was made ON and voltage built up to 11 KV.
5 14.02 Hrs Generator breaker of unit no. 3 made ON and bus-1 was charged of Jamnipali made
ON.
6 14:04 Hrs 132KV Bango-Jamnipali line breaker made „ON‟ at Jamnipali S/s
7 14:09 Hrs Supply extended to Korba East 132 KV sub station by charging 132 KV Jamnipali-
Korba East line No. 1.
8 14:12 Hrs 132/33 KV, 40 MVA transformer was charged from both sides & 4 MW Load was
taken immediately Load on the unit has been gradually increased.
9 14:40Hrs About 8 MW load was taken. The voltage & frequency of generator were controlled
at Bango HPS with telephonic assistance from Electrical Control Room of Korba
East 132 KV S/s.
10 14:48 Hrs After stabilizing the parameter at 132 KV FAR BUS, the Bango HPS Machine was
synchronized with 132 KV system at through NEAR BUS by switching ON the Bus
Coupler breaker from ECR at PH-I.
From the above it can be seen that the power from Bango HPS was extended to nearest Jamnipali s/s in 37
minutes and to nearest Thermal Power station of KEB in 43 minutes. Synchronising with the rest of the
system at KEB was done in 01 Hrs and 22 minutes time, successfully.
The voltage of Jamnipali S/s, frequency of FAR BUS at Korba East and loading on 132 KV, KEB-Jamnipali
circuit no.1 are given under:-
VOLTAGE AT 132KV JAMNIPALI BUS DURING MOCK DRILL
100.00
105.00
110.00
115.00
120.00
125.00
130.00
135.00
140.00
145.00
14:0
5
14:0
6
14:0
7
14:0
8
14:1
0
14:1
2
14:1
3
14:1
4
14:1
5
14:1
7
14:1
8
14:2
0
14:2
1
14:2
3
14:2
4
14:2
4
14:2
5
14:2
7
14:2
7
14:2
8
14:3
0
14:3
2
14:3
4
14:3
4
14:3
5
14:3
6
14:3
7
14:3
8
14:4
0
14:4
0
14:4
2
14:4
3
14:4
4
14:4
5
14:4
6
14:4
7
14:4
8
14:4
9
VO
LT
AG
E K
V
Recovery Procedure for Western Region,Dec 2013 163
The above mock drill has been successful with the active participation of Engineers of all three companies.
However there were certain difficulties faced at different stations a few of them are given under:-
a) The RTU of Bango HPS needs to be brought to service. This will be very helpful in studying the
lapses and thus improving performance.
b) 132 KV Jamnipali substations having only one bus, mock drill is only possible by taking the
complete shut down of bus. Some measures like bus splitting or possibility of another bus may be
explored. Possibilities of re-establishing of old circuit of 132 KV Korba-Bango may overcome
many difficulties during mock trial and will certainly reduce
FREQUENCY AT FAR BUS OF 132KV KEB DURING MOCK DRILL (HZ)
48.50
48.70
48.90
49.10
49.30
49.50
49.70
49.90
50.10
50.30
50.50
50.70
50.90
51.10
51.30
51.50
51.70
51.90
52.10
52.30
14:0
4
14:0
5
14:0
6
14:1
0
14:1
1
14:1
4
14:1
5
14:1
8
14:2
0
14:2
2
14:2
3
14:2
4
14:2
5
14:2
6
14:2
8
14:2
9
14:3
0
14:3
1
14:3
3
14:3
5
14:3
6
14:3
8
14:3
9
14:4
0
14:4
4
14:4
7
14:4
9
FR
EQ
UE
NC
Y H
Z
LOADING ON 132 KV KEB-JAMNIPALI LINE NO.1
AT KEB END DURING MOCK DRILL
syn with system
-10.00-9.00-8.00-7.00-6.00-5.00-4.00-3.00-2.00-1.000.001.002.003.004.005.006.007.008.009.00
10.0011.0012.0013.0014.0015.0016.0017.0018.0019.0020.0021.0022.00
LO
AD
MW
Load MW -0.75 -3.15 -5.10 -5.40 -5.70 -6.60 -7.05 -7.95 -7.50 -7.95 -7.95 -7.95 -7.95 -7.95 20.70 20.25 19.05
14:05:15 14:22:50 14:24:02 14:25:14 14:26:26 14:29:38 14:35:50 14:39:14 14:42:38 14:43:14 14:46:14 14:46:25 14:47:42 14:47:49 14:49:14 14:49:26 14:50:28
Recovery Procedure for Western Region,Dec 2013 164
c) Many steps involving isolation of many feeders at 132KV Jamnipali Bus, in turn will enormously
help in actual black start condition. The telemetry of this station was also not available to SCADA
due to shut down of Bus.
d) Auto synchronising facility of D.G. Set at Bango HPS may reduce few valuable minutes in
renovation process.
e) A more stable voice and data communication system needs to be built at Bango HPS as difficulty
was observed in contacting engineers at Bango HPS over Mobile, BSNL as well as PLCC
communications.
Recovery Procedure for Western Region,Dec 2013 165
Annex-IX(v)
BLACK-START MOCK DRILL AT PENCH HYDEL POWER STATION
A mock black-start exercise for Pench HPS unit was carried out on 12th October, 2012. SLDC Jabalpur is pleased to place on record the cooperation, assistance and efforts made by engineers from Pench Hydel Power Station, MPPGCL, MP Power Transmission Company, 132 kV Lakhnadaun substation, Generating Control Centre and East DISCOM Control Centre during the mock drill of black start. This black start exercise involved two major stages:
a) Stage-I : Creating an islanded subsystem by separating out unit #2 (80 MW) at Pench HPS along
with radial load at 132/33 kV Lakhnadaun s/s fed through 132 KV bus #1 of Pench HPS, followed
by operation of the created island around the Pench unit for some time.
b) Stage-II : Creating a blackout in the islanded subsystem created with one unit (80 MW unit #2) of
Pench and radial load at 132/33 kV Lakhnadaun s/s, start of one unit at Pench, charging of one
dead 132 KV bus-I at Pench, charging 132 kV Pench-Seoni-Lakhnadaun line, islanded operation
of the Pench HPS unit with radial load at Lakhnadaun s/s followed by synchronising this island at
Pench HPS.
Pench Hydel Project is interstate project of Madhya Pradesh and Maharashtra having 2x80 MW capacity. Share of Maharashtra in Pench Hydel is 1/3rd (53 MW) and share of MP is 2/3rd (107 MW). Pench HPS is connected with Seoni 132 KV S/s through 132 KV D/c line and to Maharashtra through 132 KV Pench-Kanhan and 132 KV Pench-Mansar line.
The Pench Hydel Generation is mainly fed to 132 KV Seoni S/s through 132 KV Pench-Seoni lines. Further 132 KV S/s Seoni is connected to EHV sub-station at Balaghat, Lakhnadaun, Nainpur & Seoni I & II through 132 KV lines..The load of 132 KV Lakhnadaun S/s has been made radial to Pench HPS by opening of 132 KV breaker of Lakhnadaun-Bargi line and shifting 132 KV Lakhnadaun-Seoni and Seoni-Pench-I on 132 KV Auxiliary Bus at 132 KV Seoni S/s. At Lakhnadaun sub-station there are (40 MVA + 20 MVA) 132/33 KV X-mers supplying 33 KV loads to consumers. A single line diagram indicating black start arrangement for Pench HPS is also enclosed.
The loading of each feeder at 33 KV system at 132 KV Lakhnadaun S/s was recorded at 10:00 Hrs
on 12th October 2012 as detailed below-
SNo. Name of the
feeder
Load
1. Bhimgarh 52 Amp/2.8 MW
2. Lakhnadaun 48 Amp/2.4 MW
3. Ghansaur 112 Amp/5.6 MW
4. Dhooma 20 Amp/1 MW
Total load on 40 MVA transformer ~ 12 MW
Prior to start of black start mock exercise it was ensured that 132 KV Lakhnadaun S/s is fed from
132 KV Pench HPS as well as 132 KV Seoni S/s and all 33 KV feeders kept in charged position.
It was also ensured that both 132 KV Pench-Seoni line II, 132 KV Pench-Kanhan, 132 KV Pench-
Mansar, Unit # 1 & 20 MVA station X-mer are kept on 132 KV Main bus-II, 132 KV bus-coupler in
Recovery Procedure for Western Region,Dec 2013 166
closed position at this stage and Unit # 1 and 132 KV Pench-Seoni-II feeder on 132 KV Main bus-
II. This scheme has ensured availability of Unit No.1 at Pench HPS with 132 KV Seoni S/s through
Bus-II during mock drill.
It was decided that at Seoni 132KV S/s, Bus-Coupler breaker shall be kept ON for charging of
132KV Aux Bus and Aux Bus isolator of 132KV Pench-Seoni Ckt-I and 132KV Seoni-Lakhnadaun
Ckt shall be closed at Seoni S/s. The Zone-II DPR setting of 132 KV Pench-Seoni line at Pench
HPS FROM 300 M Sec. to 200 M. Sec, as Auxiliary Bus has been used at Seoni S/s to extend
dgeneration to Lakhnadaun S/s.
Recovery Procedure for Western Region,Dec 2013 167
The complete black start mock exercise has been conducted at Pench HPS between 10:00 Hrs to
11.35 Hrs on 12th October 2012. The procedure followed is detailed below:
(1) Islanding of 132 KV Lakhnadaun S/s WITH Unit No. 2 (80 mw) at Pench HPS
1. The droop setting of Generator under Black Start Mock Drill was set at 4 %.
2. Generation on 80 MW unit #2 at Pench HPS adjusted equal to load on 132/33 kV 40 MVA
transformer (~17 MW) at 10:35 Hrs.
3. Main Breaker of 132 KV Pench-Seoni I line, 132 KV Seoni-Lakhnadaun line opened at
Seoni s/s at 10:30 Hrs. After ensuring Generator output is equal to load connected at 132 KV
Lakhnadaun s/s to shift the line to Auxiliary Bus at Seoni 132 KV S/s. The 132 kV bus-coupler
breaker opened at Pench HPS at 10:40 Hrs on issue of instruction by SLDC forming an island
around area fed from 132 kV Lakhnadaun s/s with unit No.1 of Pench HPS.
4. The generator output adjusted to match the load. However, the frequency variation from
48.5 Hz to 51.2 Hz has been observed in the islanded system fed from Pench Unit #2 (80 MW)
before getting stabilized. The primary response of the governor was observed and found working.
The islanded system with about 14 MW load was run for about 10 minutes.
(2) Blackout in the area fed through 132 KV Lakhnadaun :
1. After stabilizing the island for few minutes, Pench Unit No # 2 was hand tripped at 10: 50
hrs by hand tripping of 0.4 kV incomer (auxiliary supply). However the unit did not trip, then 132 KV
Generator Breaker opened, the generator output became zero but turbine did not trip. The same
tripped by operating Turbine Emergency Trip button. This has created black out in the area fed
from Lakhnadaun S/s.
2. The 33 KV breakers at 132 KV Lakhnadaun S/s alongwith breaker of 132 KV Lakhnadaun-
Seoni-Pench line, 40 MVA Transformer (both ends) hand tripped. Similarly 132 KV Pench –Seoni I
breaker has been hand tripped at Pench HPS.
(3) Black Start Operation : The black-start activities of machine No. 2 at Pench HPS have
been carried out as given below :
1. As soon as Pench Unit No.2 is tripped and black out occurred, the D.G. set should start
automatically. As the auto start up facility is not available with DG set at Pench HPS, the same has
been started manually at 10:53 Hrs.
2. Supply to RTU at Pench is also interrupted hence the data communication is also interrupted.
Supply to RTU normalized within a few minutes and data communication normalized.
3. 0.4 kV supply extended to unit bus to start essential auxiliaries of Unit No. 2 taken into service.
4. SLDC issued instruction at 10:54 Hrs to start Unit No 2. Unit rolling started at 10:55 Hrs. and
132 KV Bus #1 charged at 90 kV at 11:00 Hrs.
Recovery Procedure for Western Region,Dec 2013 168
5. 132 KV Pench-Seoni-Lakhnadaun line charged at 11:03 hrs from Pench end and Lakhnadaun
end at 11:04 Hrs.
6. Breaker of 40 MVA 132/33 kV transformer at Lakhnadaun closed at 11:04 Hrs and voltage of
132 Kv bus at Lakhnadaun adjusted to 133 kV by raising generator voltage at Pench.
7. As per instruction of SLDC, 33 KV Dhuma feeder made ON at 11.05 Hrs and gradually other
33 KV feeders i.e. 33 KV Lakhnadaun, 33 KV Bhimgarh, 33 KV Ghansour made on at 11.09 hrs,
11.11 hrs, 11.12 hrs, respectively. Gradually load also increased upto 14 MW at 11.20 hrs. Load in
islanded portion was automatically maintained smoothly by governor operation in between 49.3 Hz
to 51.2 Hz frequency. The load in the islanded area after black start was as below :
Time Consumer load at Lakhnadaun s/s.
1111:05 2 MW
1111:09 5 MW
1111:11 9 MW
1111:12 14 MW 50.0 Hz, 130 kV
The primary response of governor has maintained the frequency in the islanded area close to 50.0
Hz. The islanded portion operated for about 20 minutes without any difficulty.
8. The islanded portion check-synchronized with the NEW grid by closing 132 kV Bus coupler at
Pench HPS at 11:25 Hrs.
Fig 2. Plot of frequency and Unit-2 generation at Pench HPS which was part of the island during
black start exercise.
PERFORMANCE DURING BLACK START
45
46
47
48
49
50
51
52
53
54
55
10:0
0,0
3
10:0
2,3
3
10:0
5,0
3
10:0
7,3
3
10:1
0,0
3
10:1
2,3
3
10:1
5,0
3
10:1
7,3
3
10:2
0,0
3
10:2
2,3
3
10:2
5,0
3
10:2
7,3
3
10:3
0,0
3
10:3
2,3
3
10:3
5,0
3
10:3
7,3
3
10:4
0,0
3
10:4
2,3
3
10:4
5,0
3
10:4
7,3
3
10:5
0,0
3
10:5
2,3
3
10:5
5,0
3
10:5
7,3
3
11:0
0,0
3
11:0
2,3
3
11:0
5,0
3
11:0
7,3
3
11:1
0,0
3
11:1
2,3
3
11:1
5,0
3
11:1
7,3
3
11:2
0,0
3
11:2
2,3
3
11:2
5,0
3
11:2
7,3
3
11:3
0,0
3
11:3
2,3
3
11:3
5,0
3
TIME
FR
EQ
(H
Z)
0
5
10
15
20
25
30
35
40
45
50
55
60
65
70
75
80
MW
FRQ MW
Turbine did
not trip
Blackout
Turnbine
H/T
IslandingBlack Start
Synchronised with NEW Grid
Load stabilised
Recovery Procedure for Western Region,Dec 2013 169
Fig 3. Plot of Bus 132 kV -1 Voltage at Pench HPS which was part of the island during black start
exercise
Observations and analysis of the exercise : The results of black start exercise of Pench HPS
has been quite satisfactory. The restoration of the supply to Lakhnadaun area post black out took
about 15 minutes. The restoration of the system within this short time without any abnormal
behavior of voltage, frequency and other electrical parameters will help in restoration process in
real time.
The graphical plots in Fig. 2 & 3 based on the achieved data at SLDC indicate various
observations made during the exercise. The subsystem in island condition operated for almost 10
minutes pre-black out (10:40 Hrs to 10:50 Hrs) 15 minutes after black start (11:15 hrs to 11:25
Hrs). The frequency of the island remained close to 50.0 Hz, which shows that the unit is perfectly
working in free governor mode.
The unit did not trip on removing 0.4 KV station supply. Moreover on opening of 132 KV generator
breaker the turbine did not trip and speed overshoot. The same need to be investigated and
remedial measures need to be taken by MPPGCL.
The DG set at Pench HPS do not have auto start facility and thus had to start manually. MPPGCL
may explore the possibility of installing auto start facility so that the DG set start automatically in
real time under black out conditions.
The capabilities of the generator that got tested during black start exercise include the capability to
start from a DG set, to regulate the active and reactive power output so as to operate the island at
Voltage of Bus #1 at Pench Hydel Power Station during Black Start
0
20
40
60
80
100
120
140
160
10:0
0,03
10:0
3,03
10:0
6,03
10:0
9,03
10:1
2,03
10:1
5,03
10:1
8,03
10:2
1,03
10:2
4,03
10:2
7,03
10:3
0,03
10:3
3,03
10:3
6,03
10:3
9,03
10:4
2,03
10:4
5,03
10:4
8,03
10:5
1,03
10:5
4,03
10:5
7,03
11:0
0,03
11:0
3,03
11:0
6,03
11:0
9,03
11:1
2,03
11:1
5,03
11:1
8,03
11:2
1,03
11:2
4,03
11:2
7,03
11:3
0,03
11:3
3,03
11:3
6,03
Time
KV
Recovery Procedure for Western Region,Dec 2013 170
reduced standards of frequency and voltage, to operate under partial loading condition without
losing stability, primary response of the generator, healthiness of synchronisation facility etc. The
transmission capability that were put to test include the ability of switch gear to charge dead bus,
healthiness of bus breakers, flexibility available in protection systems in terms of operating at other
than normal settings for a short period.
Conclusion: Black out in power grid is a worst kind of contingency and brings unpleasant situations when it occurs. Since the power systems worldwide are evolving both in size and complexity, the conventionally adopted recovery procedures requires constant review, upgradation, test and validation. The black start exercises assume vital importance for any large interconnected power system since they do not only testify the existing restoration facilities but also prepare the system operators to restore the power system in a shortest possible time by identifying deficiencies and suggesting scopes for improvement.
Recovery Procedure for Western Region,Dec 2013 171
Annex-IX(vi)
Black Start Mockdrill at CCPP VATVA
Date
28-11-2012
Recovery Procedure for Western Region,Dec 2013 172
31 415 v HRSG-2 MCC breaker ON 07:16:48 01:41:57
32 GTG-2 synchronised –HOUSE LOAD 07:27:14 01:52:23
33 Switch ON 11KV UAT-2 07:28:01 01:53:10
Time 05:34 Hrs.
DG Set Details
Make : Kirlosker
Capacity : 500 KVA, Voltage : 415 V
Fuel Tank Capacity 1000 LTR
Starter with 24 V Battery , Two Cells 0f 12 Volts
Sr. no Black Start with DG SET Time Response
time
1 UT-3 11KV breaker OFF 05:34:43
2 Switch OFF 11 KV UAT-2 05:34:44
3 Switch OFF 11 KV SST-2 05:34:44
4 Switch OFF 415 v UAT-2 incomer 05:34:44
5 415 v Unit bus coupler ON 05:34:44
6 Switch OFF 415 v SST-2 incomer 05:34:44
7 415 v Station bus coupler ON 05:34:44
8 UT-1 11KV breaker OFF 05:34:51 00:00:00
9 Switch OFF 11KV UAT-1 05:34:52 00:00:01
10 Switch OFF 415 v UAT-1 incomer 05:34:52 00:00:01
11 Switch OFF 11 KV ST-1 05:34:55 00:00:04
12 Switch OFF 11 KV SST-1 05:34:55 00:00:04
13 Switch OFF 415 v SST-1 incomer 05:34:55 00:00:04
14 GT-1 DC EOP ON 05:35:02 00:00:11
15 GT-2 DC EOP ON 05:35:03 00:00:12
16 ST DC EOP ON 05:35:06 00:00:15
17 Switch OFF 11 KV ST-2 05:35:11 00:00:20
18 Switch OFF 3.3 KV ST-2 05:35:11 00:00:20
19 415 v HRSG-1 MCC breaker OFF 05:35:24 00:00:33
20 415 v CWPH MCC breaker OFF 05:35:29 00:00:38
21 415 v HRSG-2 MCC breaker OFF 05:35:30 00:00:39
22 415 v MCC-1 breaker OFF 05:35:35 00:00:44
23 415 v MCC-2 breaker OFF 05:35:36 00:00:45
24 415 v MCC-4 breaker OFF 05:35:39 00:00:48
25 415 v DG incomer breaker ON 05:35:51 00:01:00
26 Unit bus tie breaker ON
27 Station bus tie breaker ON
28 Check DG set Amps. Loading.(Safe limit is 680 amps) 480 A
29 Start ACW-C, Close all opened vent. Check DG SET loading 05:38:30 00:03:39
30 415 v MCC-2 breaker ON 06:33:28 00:58:37
Recovery Procedure for Western Region,Dec 2013 173
34 Switch ON 11KV SST-2 07:28:05 01:53:14
35 Switch ON 11KV ST-2 07:28:08 01:53:17
36 415 v DG incomer OFF and 415 v UAT-2 ON 07:28:37 01:53:46
37 Station tie breaker OFF and 415 v SST-2 ON 07:29:08 01:54:17
38 415 v CWPH MCC breaker ON 07:29:23 01:54:32
39 415 v HRSG-1 MCC breaker ON 07:29:27 01:54:36
40 415 v MCC-4 breaker ON 07:29:33 01:54:42
41 415 v MCC-1 breaker ON 07:29:37 01:54:46
42 UT-3 11KV breaker synchronised with 66K system 07:30:44 01:55:53
43 UT-1 11KV breaker ON - 07:31:13 01:56:22
44 Switch ON 11KV ST-1 07:31:19 01:56:28
45 Switch ON 11KV SST-1 07:31:23 01:56:32
46 Switch ON 11KV UAT-1 07:31:27 01:56:36
47 Switch ON 415 v UAT-1 incomer & bus coupler OFF 07:32:17 01:57:26
48 Switch ON 415 v SST-1 incomer & bus coupler OFF 07:32:43 01:57:52
49 Switch ON 3.3 KV ST-1 07:32:52 01:58:01
50 Switch ON 3.3KV ST-2 07:32:58 01:58:07
Annexure-X
Ready Reckoner on Reactive Power Management
Recovery Procedure for Western Region,Dec 2013 174
1. Change in voltage at a bus
∆ V = ∆Q .
V Fault Level of the Bus
Units: ∆ V & V (kV), ∆ Q (MVAR), Fault Level (MVA)
2. Fault contribution at HT bus of Unit Transformer:
Sl. No. Unit Size(MW) Type 3 Φ MVA Contribution
1 60 Hydro 280
2 120 Thermal 490
3 210 Thermal 735
4 500 Thermal 1800
Thumb Rule: Short circuit level contribution of a generating unit is 3-4 times its MVA
rating.
3. Line Charging MVAR:
(Source: CEA: Manual on Transmission Planning Criterion, 2013)
4. Line Current
Sl.No. Voltage Level
(kV)
Ampere/MVA
1 132 4.4
2 220 2.6
3 400 1.4
5. Voltage rise at receiving end of uncompensated line
Sl. No. Voltage
Level (kV) Conductor Type
Line Charging MVAR/100
km/circuit
1 132 Panther 5
2 220 Zebra 13.5
3 400 Twin Moose 55.5
4 400 Quad Moose 74
5 400 Quad Bersimis 74.6
6 765 at 400 Triple Snow Bird 65.6
6 765 Quad Bersimis 291
Sl. No. Voltage
Level(kV)
Conductor
Type
(Single circuit)
Voltage Rise
(kV) per 100km
1 132 Panther 0.75
Recovery Procedure for Western Region,Dec 2013 175
S
6. Rated breaking Current Capability of Switch Gear
(Source: CEA: Manual on Transmission Planning Criterion, 2013)
7. MW vs Current (ampere)
Sl. No. Voltage Level (kV) MW
1 400 =2/3 * current (amp)
2 220 =1/3 * current (amp)
3 132 =1/4 * current (amp)
8. Impact of 1000 amp flow on a 100 km Long 400 kV Line (p.f.=1)
a) I2 X loss -100 MVAR
b) I2 R loss -10 MW
c) Potential drop (Vs-Vr) -3.3 kV
9. Line Equivalent of a Transformer:
Conductor Type
500 MVA
Transformer is
equivalent to
transmission
line (in km)
315 MVA
Transformer is
equivalent to
transmission line
(in km)
250 MVA
Transformer is
equivalent to
transmission line
(in km)
765 KV Quad
Bersimis
559 887 1117
400 kV Quad
Bersimis
153 242 305
400 kV Quad Moose 159 253 319
400 kV Triple
Snowbird
145 230 290
400 kV Twin Moose 120 191 241
220 kV Zebra 30 48 61
***
ACKNOWLEDGEMENT
2 220 Zebra 1.5
3 400 Twin Moose 3
Sl. No. Voltage Level (kV) Kilo ampere
1 765 40/50
2 400 50/63
3 220 31.5/40
4 132 25/31.5
Recovery Procedure for Western Region,Dec 2013 176
We do thankfully acknowledge the various inputs given by the W.R constituents, IPPs and all other
utilities for preparing this document. The sharing of experience of the Engineers from the
constituents of Western region had greatly helped in bringing out this document that would serve
the practical needs while restoring the grid. This document is intended to be useful for the operating
personnel during restoration of the Western Regional grid. We look forward to enrich this document
with the experience of W.R constituents from time to time.
***
Bibliography:
Recovery Procedure for Western Region,Dec 2013 177
1. M. M. Adibi: Power System Restoration Methodologies and Implementation strategies,
IEEE Press.
2. Central Electricity Regulatory Commission: Indian Electricity Grid Code-May2010.
3. Black Strart Restoration Procedure of Southern Region.
4. System Restoration Procedures of Northern Region.
5. Black Strart and Restoration Procedure of NER grid.
6. Black Start facility start-up power and Restoration Procedure for Eastern Regional Grid.
***