RATUA FOUNDATION, ASSOCIATION DE MELE AND SHaRM PIKININI ECOLE FOUNDATION WITH STUART FRIEND and OTHERS
Rebuild of Suango Mele Primary School Block 2
Suango Mele Primary School classroom block following Cyclone PAM – March 2015
Report dated: 25 October 2015
Prepared by : SHaRM Pikinini Ecole Foundation for Ministry of Education
PO Box 128, Port Vila, Vanuatu
Ph: (+678) 7788224
Email. [email protected]
Website :www.sharmfoundation.com
mailto:[email protected]
-
================================================================
Final Reporting
Post-Pam April 2015
A working group of Ratua Foundation, Cyrille Mainguy and for Association de Mele and SHaRM Pikinini Ecole Foundation met post-PAM with the School Board, School Headmaster and Executive for the School as to how we could jointly assist Suango Mele Primary School with reconstruction on the school buildings damaged by Cyclone PAM. A plan was formulated for the reconstruction subject to fundraising by the various groups involved.
Following is a plan and layout of the School and identification of the School Block 2 consisting of four large classrooms, the subject of this report.
Proposed site plan of rebuilding programme for Suango Mele Primary School
-
Rebuild
The combined team working with the Project Manager for Suango Mele Primary School, Cyrille Mainguy, Consulting Engineer and Project Management, were fortunate via Stuart Friend (Sunny Coast Board Room) to secure the services of a team of four kiwi builders from New Zealand to undertake the re-roofing for Block 2 free of charge to this part of the Project.
This work commenced on 15th August with the Kiwi team coordinated by Andy Ross being Mark Leppard, Phil Pointon and Todd Berriman from the Hawkes Bay in New Zealand who, during their stay, completed the re-roofing ready for the local builders under Foster Rakom to continue with the finishing building required to refurbish the four classrooms. This project was also extremely fortunate to have input from Volunteer Vanuatu whose contingent of workers arrived daily to paint, repair and assist with the refurbishment of all four classrooms.
The school Block 2 suffered extensive damage in Cyclone PAM and required not only a large contingent of labourers to undertake the work but also funding to bring the classrooms back to serviceable use by the school.
Cyrille Mainguy, as project manager for Suango was overseeing the work and inspections plus reporting back to the Ministry during the course of the reconstruction.
Kiwi team of builders undertaking the work which commenced on 15th
August 2015
-
School reroofing in progress 15th August 2015
Roof on and wetting the roof ceremony on 21st August 2015
Progress as at 30th August 2015
-
Work that has been completed to repair the 4 classrooms included:
Completely new colour steel iron replacement from BlueScope Lysaght
New trusses constructed and stronger reinforcing of the roofing system has been achieved
Repair to exterior cement walls and interior damage where roofing was torn from the structure
Plastering of all damage and two end walls of building plastered and painted
Painting of all fascias and trims once re-roofed – green
Painting of total exterior of the building - white
Refurbishment or replacement of window loovres and glass and replaced and repaired where required
Lockable doors fitted to all rooms
New steps built and cemented for access to all classrooms
Mesh inserted on soffit to provide security and air flow
Interiors of all classrooms repainted totally in white
Blackboards and pin boards repainted and reinstalled
Classrooms cleaned ready for re-use
Refurbishing work Completed on 25th September 2015
The construction rebuild for Block 2 at Suango Mele Primary School was completed in stages with the classes moving back into their permanent classes from their temporary tent classrooms as and when the volunteer teams finished the work. The Project Manager/Engineer inspected the buildings on or about 25th September 2015.
Mele builders continuing the repair work on Block 2
-
COSTINGS
Final cost for the total rebuild was :
Details Donor Cost in Vatu
Materials purchased PVH Ratua / Association de Mele
1,176,719
BlueScope Lysaght – purchase of 52 sheets Trimdeck and Flashings and accessories
BlueScope 625,170
Guttering and Water Tanks - supplied by Intraco
Intraco donation
Washers and Screws - roofing washers and screws
Frank Hallbauer &
Graham Beaumont
33,000
84,850
Materials for finishing and exterior finishing, cement, mesh plus paint including loovres and glass
SHaRM 228,109
Wages – foreman and 3 labourers SHaRM
Association de Mele
35,350
146,400
Total cost of the Rebuild – 4 Classrooms – Block 2
2,329,598 VT
Completed classroom Block 2 and Headmasters House taken September 2015
-
FURTHER WORK TO BE CONSIDERED BY THE PROJECT TEAM OR SOUGHT BY OTHER DONORS
These classrooms will require:
Electricity run to the classrooms in Block 2
Guttering connected to the water tanks for additional water supply (2 large tanks – now provided and guttering which had been funded by Intraco)
Extra cupboards and white boards and shelving (supplied by SHaRM)
Additional chairs and desks to all four classrooms (supplied by SHaRM)
Teaching resources (to be supplied by SHaRM)
Storm shutters made and to be installed on all windows
Landscaping and repair to ground outside of classrooms including verandah reinstallation.
INSPECTION AND SIGN OFF BY CYRILLE MAINGUY, PROJECT MANAGER FOR SUANGO
Working with Cyrille Mainguy, Project Manager on all the rebuilding at Suango, Cyrille has been reporting throughout the rebuild of Block 2 and providing interim technical reports following inspections.
Cyrille will provide this report to the Ministry of Education, following his further final inspection of Block 2 and upon approval of this report.
……………………………………………………………………..
For and on behalf of the Combined Group assisting Suango Mele Primary Rebuild Per: Stephanie (Steph) Neilson
Dated 25 October 2015
(Attached)
1. Photos of the Block2- before and during the rebuilding 2. Excell Spreadsheet of payments 3. Final evidence of rebuild payment receipts 4. Acknowledgements
-
Photo March 2015 following PAM
Classroom after PAM evidencing damage March 15
Kiwi and Mele Builders reconstructing roof trusses August 2015
-
CyrilleMainguy and Headmaster Peter Jerome with donors for Block 2 Frank Hallbauer and Graham Beaumont
School children inspecting their refurbished classrooms – September 2015
-
Costing for Block 2 = 625,170 VT
-
Acknowledgements:
Cyrille Mainguy, Consulting Engineer and Project Management for project managing the rebuild
Ratua Foundation
Association de Mele
BlueScope Lysaght
Frank Hallbauer and Graham Beaumont
Volunteer Vanuatu and their teams of volunteers
The Beach Bar
Stuart Friend and Deb Friend
Kiwi Building Team from New Zealand – Andy Ross, Mark Leppard, Phil Pointon and Todd Berriman
Foster Rakom and team of builders from Mele – Henry, Mark and WooWo
SHaRM Pikinini Ecole Foundation
Intraco - for supply of spouting and water tanks for Block 2
Port Vila Hardware
Wilco Limited
School Board and Committee assisting during the rebuilding of Block 2
School Mamas for supplying meals during the rebuilding process
===================