Vault 9 Project Update9th September 2009
Paul Pointon – Site Project Delivery Manager
LLW Repository Ltd
Date: 11/03/2009 2
Overview of Presentation
• Vault 9 Design• Current Status
Date: 11/03/2009 3
Vault 9Vault 9 Design
Date: 11/03/2009 4
Plan Overview Scheme
ANDY – Can you insert the base site plan that you are using to show the new material facility plan – Showing the Current infrastructure
Date: 11/03/2009 5
Proposed Development
Vault 9 Liner Details
Date: 11/03/2009 7
Vault 9Current Status
Date: 11/03/2009 8
Bulk Excavation – 100% Complete
Date: 11/03/2009 9
Rail Deliveries – Aggregate, Reinforcement & Ancillaries
Date: 11/03/2009 10
Rail Deliveries – Port of Workington
Date: 11/03/2009 11
Rail Deliveries – Millom Main Line Loading
Date: 11/03/2009 12
West Outer Wall Construction - 95% Complete
Date: 11/03/2009 13
Secant Pile Wall – 100% Complete
Date: 11/03/2009 14
BES Bottom Layer - 80% Complete
Date: 11/03/2009 15
Geomembrane, Geotextile & Drainage Layer – 45% Complete
Date: 11/03/2009 16
Vault 9 Floor Slab - 22% Complete
Date: 11/03/2009 17
West Inner Wall - 60% Complete
Date: 11/03/2009 18
Partial Handover – 21st July 2009
Date: 11/03/2009 19
Delivery Schedule
• Partial Turnover to Operations – July 2009
• Operational Safety Case Approved
• First HHISO –July 2009• Contract Completion –
January 2010
Date: 11/03/2009 20
Vault 9Questions