S.No Item Specifications Qty Unit Unit Rate Total Rate 1.1 Providing flooring in vitrified ceramic tiles 24" x 24", Ivory Plain, inclusive of finishing of joints in pigmented white cement, rubbing down of edges and cleaning of finished tile work. (Bell / Euro / Naveen / Nitco) Asian premium quality.. 52 Sq.ft. 1.2 door/ fixed glazing of 12" in cement mortar 1:4 complete with cutting & joint filling and round molding & polishing of granite edges - Steps to be done in case required with black granite / granite 8 Sq.ft. 1.3 Chequered Tiles for outside area Max upto 24 sqft (to be done only upon written confirmation by Project team) 24 Sq.ft. 2.1 False Ceiling Providing and Fixing 12 mm Armstrong board suspended false ceiling on metallic grid in line and level,, GI intermediate channel (sub frames) of size 45mm and 0.5mm thk with two flange of 15mm each at 1200 mm center to center, GI hanger of size 25mm, 0.5mm thk at 1200mm center to center distance, joint filling & finishing with proper scraping inclusive of all material and labour as instructed by Site Incharge and directed. 48 Sq.ft. 3.1 Painting Overall servicing and greasing plus providing and applying of 3 coats of Burgandy enamel paint to existing shutter from both side 185 Sq.ft. 3.2 Shutter Servicing &Greasing Overall servicing and greasing. 1 Sq ft 4.1 Fixed Glazing Providing and fixing external fixed glazing of 8 mm Saint gobain, Modi, AIS or equivalent cleared class with 2.25" x 2.25" aluminum sections anodized - champagne bronze color on all 4 side 40 Sq.ft. 4.2 Main Door Providing and fixing in position 7' x 3' aluminum glass door with anodized - champagne bronze color comprising of 3.25" X 3.25" Vertical & horizontal member with 8 mm Modifloat / Saint Gobain or equivalent clear glass, heavy duty floor spring of ENOX / Hemco / Everite / Hyper make or equivalent, sealant filling between inside the aluminum sections, Door to have 1" Dia, 12" long D- shape steel handle Ozone/enox/Ebco make. The top & Bottom members to be secured with rubber weather strip. There will not be any center member. Space (if any )above the door would be closed with ACP 21 Sq.ft. COST Flooring (only in ATM lobby): Vitrified Tiles

Upload: pushpakbhawgati27

Post on 13-Sep-2015

212 views

Category:

Documents


0 download

DESCRIPTION

Rate Matrial

TRANSCRIPT

  • S.No Item SpecificationsQty Unit Unit Rate Total Rate

    1.1

    Providing flooring in vitrified ceramic tiles 24" x

    24", Ivory Plain, inclusive of finishing of joints in

    pigmented white cement, rubbing down of edges

    and cleaning of finished tile work. (Bell / Euro /

    Naveen / Nitco) Asian premium quality.. 52 Sq.ft.

    1.2

    Jet Black Granite slab 18-24 mm thick below main

    door/ fixed glazing of 12" in cement mortar 1:4

    complete with cutting & joint filling and round

    molding & polishing of granite edges - Steps to be

    done in case required with black granite / granite 8 Sq.ft.

    1.3

    Chequered Tiles for outside area Max upto 24 sqft

    (to be done only upon written confirmation by

    Project team) 24 Sq.ft.

    2.1 False Ceiling

    Providing and Fixing 12 mm Armstrong board

    suspended false ceiling on metallic grid in line and

    level,, GI intermediate channel (sub frames) of size

    45mm and 0.5mm thk with two flange of 15mm

    each at 1200 mm center to center, GI hanger of size

    25mm, 0.5mm thk at 1200mm center to center

    distance, joint filling & finishing with proper

    scraping inclusive of all material and labour as

    instructed by Site Incharge and directed. 48 Sq.ft.

    3.1 Painting

    Overall servicing and greasing plus providing and

    applying of 3 coats of Burgandy enamel paint to

    existing shutter from both side 185 Sq.ft.

    3.2

    Shutter

    Servicing

    &Greasing Overall servicing and greasing. 1 Sq ft

    4.1 Fixed Glazing

    Providing and fixing external fixed glazing of 8 mm

    Saint gobain, Modi, AIS or equivalent cleared class

    with 2.25" x 2.25" aluminum sections anodized -

    champagne bronze color on all 4 side 40 Sq.ft.

    4.2 Main Door

    Providing and fixing in position 7' x 3' aluminum

    glass door with anodized - champagne bronze color

    comprising of 3.25" X 3.25" Vertical & horizontal

    member with 8 mm Modifloat / Saint Gobain or

    equivalent clear glass, heavy duty floor spring of

    ENOX / Hemco / Everite / Hyper make or

    equivalent, sealant filling between inside the

    aluminum sections, Door to have 1" Dia, 12" long D-

    shape steel handle Ozone/enox/Ebco make. The top

    & Bottom members to be secured with rubber

    weather strip. There will not be any center member.

    Space (if any )above the door would be closed with

    ACP 21 Sq.ft.

    COST

    Flooring (only

    in ATM lobby):

    Vitrified Tiles

  • 5.1 Paneling

    2" x 2" Aluminium box section with 3mm

    aluminum Composite panel with a 2'x2' framework

    on the backside with spacing not exceeding 600mm

    Clading to be done on side wall of ATM room till 1 feet - Shutter boxing is also of the same ACP color -

    Color is IVORY and ACP make to be specified 215 Sq.ft.

    5.2 Partition

    2" X 2" Alu Section with 2X2 feet frame, 3 mm ACP

    including 7' X 2' door. 1 ATM slot to be made.

    Provision for the 2nd ATM to be kept. The framing

    to be done accordingly - 3mm ACP groving to be

    filled with black silica - from backside to be covered

    with 6mm ply 80 Sq.ft.

    5.3 Shelf for IDU

    Providing and fixing a 2 wooden shelf of size 24" x

    30" comprising of 18mm thick marine ply with

    ACP on top, and all the exposed sides of 18mm

    thickness of the ply, bottom with 3 coats of 1st grade

    enamel paint wire manager ( circular slot ) for

    passing cables, resting on strong metal L section

    frame - one at the height of 30" and second will be

    at 48" from floor level 1 Nos.

    5.4 Air Louvers

    P and F 4 powder coated aluminum louvers of Ivory colour complete as directed. Louvers to have

    collar on all the four sides. 2 Sq.ft.

    6.1

    Fire

    extinguishers

    ABC Type - fire extinguisher to be provided - 2KG -

    to be installed in customer lobby only 1 No.

    6.2

    Dustbin

    (grouted on the

    ground)

    Silver colour powder coaring / Perforated Bin, Size

    3 ft high and 12 inch in diameter, Ms perforated

    powder coated Rubber gasket on the floor end of the

    bin, Bin grounded on the floor 1 No.

    6.3 Door Mat

    Providing footmat / doormat of size 36" X 24" -

    Color has to be Burgandy 1 No.

    6.4 Grouting ATM grouted with 4 holes 1 No.

    6.5

    Cheque Drop

    Box (to be

    grouted) Bank Specific Design - to be grouted 1 No.

    A3 Poster frame of Size 12 X 17, Acrylic Sandwich made of 4mm + 3mm thick Imported Clear Acrylic

    (Mitsubishi ) with extra 1 clear border all around the A3 Size = 14 X 19 X 2 Pcs, Front Panel- 4mm thick imported clear cast grade Acrylic - polished/

    buffed on all 4 sides, Back Panel - 3mm thick

    imported clear cast grade Acrylic - polished/ buffed

    on all 4 sides

    Spacer Bolts - 9 mm diameter X 0.75 Long stainless steel finish spacer screw- 4 numbers, has to be

    absolutely transparent and will not turn foggy or

    yellowish for 3 years if used indoors.6.6 Poster Frame 2 Nos.

  • 7.1

    Single phase

    electrical of

    distribution

    board

    Power Distribution Box will have the following

    items - 63 Amps - Isolator 1nos; 32 Amps - DP MCB - 2nos (1 for AC & 1 for UPS) ; 16 Amps - SP

    MCB - 6 nos ; Anchor make 5/15 Switch / Socket -

    8nos; Additional 5/15 Switch / Socket - 2 nos for

    UPS Input & Output; Metal Clad plug Socket - 4 nos.

    (2 for Stabilizer input & output and 2 for ACs)

    Timer 2 Nos (1 for AC & 1 For Signage 1 No.

    7.2

    ATM Power

    points

    2 Nos. of Electrical points (5/15 amps) in back

    room (on UPS power) - Just behind the ATM

    machine 2 Set

    7.3

    ATM Network

    Points

    2 Nos. of Network (I/O Port) in back room - Just

    behind the ATM machine, one end connected in IO

    port (behind the machine) and 2nd end to be lay till

    Wooden self - alteast of 5 mtr 2 Nos.

    7.4 LAN Cable

    5 mtr LAN CABLE (1 straight and 1 cross), crimped

    at both ends 2 Nos.

    7.5

    Lighting

    Fixtures

    2 nos of 2 0" x 2' 0" mirror optic fixtures (Philips / wipro/Edison or equivalent), ONE IN RAW POWER

    & ONE IN UPS POWER. 2 X 18W CFL to be used in

    each fixture 2 Nos.

    7.6 Porch Light

    2 x 11W PL Spot lights, fixture with lamps of make

    GE,Philips, Wipro, Opelite, Crompton, Clipsal, Bajaj 2 Nos.

    7.7

    v-sat cable

    laying &

    conducting

    v-sat cable laying & conducting from the entrance

    of the shop till IDU 8 Rmt

    7.8

    Tube light -

    Back room

    Providing & fixing Philips / Wipro or equivalent

    TUBE lights for BACK ROOM 1 No.

    7.9 Earthing Earthing including wiring from Earth pit to DB 1 No.

    8 Signage

    Bank Specefic Design (8' * 3' LED Type 24 Watts 3M

    Vinyl make(Cable should be conducted upto DB) As

    per manual with 5 yr 3M Warrantey 24 Sq.ft.

    10

    Total Pole for

    Lollypop

    10 ft clear height from floor level, 3 feet need to dig

    in floor/road - total height of the pole will be alteast

    13 feet (NEED BASIS) nos 1

    11 Main Cabling 6 sq mm or equivalent 15 Rmt

    12 Stickers

    1 set of Push & Pull sticker in metal and 1 poster

    frame sticker - as per bank specification 1 Set

    17.1

    Supply of split

    type 1 Tr Split

    ACs (3star) Airconditioners

    , comprising

    indoor unit &

    outdoor unit &

    4m of Copper

    Piping Make: Godrej/Voltas/Blue Star 2 No

    17.2

    Installation &

    Commissioning

    of AC's 2 No

    9 Lollypop

    2' * 2' LED 3M Vinyl with 1' * 1' cube light as per

    Bank Design (Cable shuld be conducted upto DB)

    Warranty:5 years by 3M nos 1

  • 17.3

    3 KVA

    Stabilizer 1 No

    18.1

    Trenching /

    Zari NEED BASIS RMT 1

    18.2 Demolition Demolition (NEED BASIS) Nos 1

    18.3 PCC PCC (NEED BASIS) sqft 1

    Note:-

    1-- Taxes and Govt, levies charged extra.

    2--Payment as oer progress of work.

    Work will start immediately against confirm order.

    Total